Energy-market overview

How electricity works in Canada.

Canada electricity market 2026: provincial utilities and regulators, IESO and AESO markets, Alberta Site ID, smart meters, net metering, rebates and reforms.

This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Canadian dollar (CAD) where they relate to prices.

Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.

At a glance

Canada energy at a glance.

Key figures for households in Canada. Each one links to its source on the full overview below.

  • Electricity price.

    0.183 CAD per kWh for households, including taxes. Figures for April 2025.

  • Household use.

    10,865 kWh a year for a typical household. Figures for 2021.

  • Renewable share.

    63.9% of electricity from renewable sources. Figures for 2025.

  • Selling back to the grid.

    Can homes export electricity? Yes. Details are in the export section below.

Before you start

Four things to check in Canada.

Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.

  1. Check the local rules.

    Read the connection, export and permission rules for Canada below, and ask your local grid operator if anything is unclear.

  2. Choose a qualified installer.

    Look for an installer listed on an official register, with the certifications Canada requires for the work.

  3. Look at current schemes.

    Check which support schemes are open now. Closed or scheduled schemes are labelled as such.

  4. Talk to your energy supplier.

    Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.

Local detail

Schemes, rules and certifications in Canada.

The full detail sits in the sections below. Each item shows its status and links to the official source.

  • Support schemes.

    Grants, tax relief and export payments in Canada, each labelled Active, Scheduled or Closed.

  • Connection and export.

    How equipment is connected to the grid in Canada, and the steps to export electricity.

  • Standards and certifications.

    The technical standards and installer certifications that apply to energy equipment in Canada.

Full overview

The energy market in Canada, in detail.

Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.

Profile last updated 1 October 2026.

On this page22 sections

Electricity in Canada is a provincial matter. Each province and territory decides how its power system is owned, priced and regulated, so Canada has no single national market, no national regulator for retail electricity and no national supply-point register. The federal government sets environmental rules such as the Clean Electricity Regulations, approves international power lines and electricity exports through the Canada Energy Regulator, and oversees meter accuracy through Measurement Canada.

The result is a patchwork. Québec, British Columbia, Manitoba, Saskatchewan, New Brunswick and Newfoundland and Labrador are served mainly by provincially owned, vertically integrated utilities such as Hydro-Québec, BC Hydro and SaskPower. Ontario has a wholesale market run by the Independent Electricity System Operator (IESO), regulated household prices set by the Ontario Energy Board and dozens of local distribution companies. Alberta has the most liberalised system, with an energy-only wholesale market operated by the Alberta Electric System Operator (AESO) and competitive retail supply.

Canada generates most of its electricity from low-carbon sources: in 2025 renewables supplied 63.9% of generation, led by hydropower at 52.8%, and nuclear a further 13.1%, according to Ember. Household prices vary widely by province. Hydro-Québec’s 2025 comparison of 12 Canadian cities found monthly bills for 1,000 kWh, including taxes, ranging from C$95 in Montréal to C$240 in Calgary.

Energy snapshot.

Headline figures for electricity in Canada. Each shows its data year and links to its source.

  • Population41,798,407 peopleSource 11 July 2026
  • Households14,978,941 private householdsSource 22021
  • Average household size2.4 people/householdSource 22021
  • Electricity use per household10,865 kWh/yrSource 42021
  • Household price (CAD)0.183 CAD/kWhSource 10April 2025
  • Household price (EUR)0.114 EUR/kWhSource 11April 2025
  • Renewable electricity share63.9%Source 122025
  • Solar capacity5.93 GWSource 122025
  • Wind capacity17.7 GWSource 122025
  • Energy storage capacity1 GWSource 13end 2025
  • Smart-meter shareNot identified from a reliable public source.
Market structure
Partially liberalised
Homes can export to the grid
Yes
Home equipment in grid services
Developing
Regulator
Provincial regulators: Ontario Energy Board, Alberta Utilities Commission, Régie de l’énergie (Québec), BC Utilities Commission and others; Canada Energy Regulator for international lines and exports
System operator
Provincial: IESO (Ontario), AESO (Alberta), Hydro-Québec, BC Hydro, SaskPower, Manitoba Hydro, NB Power, Nova Scotia Power and others
Distribution networks
Provincial Crown utilities in most provinces; dozens of local distribution companies in Ontario; wire owners (ATCO, ENMAX, EPCOR, FortisAlberta and municipal utilities) in Alberta
Currency
Canadian dollar (CAD)
Voltage and frequency
120/240 V / 60 Hz

Electricity prices in Canada.

Household price (CAD)
0.183 CAD/kWh (April 2025)Source 10Derived: unweighted average of the monthly bills, including taxes, for 1,000 kWh in 12 Canadian cities (rates in effect 1 April 2025) from Hydro-Québec’s comparison, divided by 1,000. Individual cities ranged from 9.5¢/kWh (Montréal) to 24.0¢/kWh (Calgary). There is no official national average residential price.
Household price (EUR)
0.114 EUR/kWh (April 2025)Source 11Converted from C$0.1834/kWh at the ECB reference rate of 30 September 2026 (EUR 1 = CAD 1.6105).
Typical annual electricity bill
2,201 CAD/yr (April 2025 (annualised))Source 10Derived: unweighted average of the 12 Canadian city bills for 1,000 kWh a month, including taxes (C$183.39 a month), multiplied by 12. Annual bills at this consumption range from about C$1,144 in Montréal to C$2,886 in Calgary.

Household price trend (CAD per kWh).Source 10

0.1390.1520.164Apr 2021Apr 2022Apr 2023Apr 2024Apr 2025
Canada household electricity price, CAD per kWh
Apr 20210.1393 CAD/kWh
Apr 20220.1456 CAD/kWh
Apr 20230.1641 CAD/kWh
Apr 20240.1621 CAD/kWh
Apr 20250.1638 CAD/kWh

Why prices differ so much

Provincial resource endowments drive prices. Provinces with large, long-paid-off hydro fleets – Québec, Manitoba and British Columbia – have the cheapest power: Hydro-Québec’s comparison put the average price for 1,000 kWh a month, before tax, at 8.29¢/kWh in Montréal, 10.53¢ in Winnipeg and 12.60¢ in Vancouver on 1 April 2025. Provinces relying more on fossil generation or with small systems pay more: 17.89¢ in Regina, 19.69¢ in Charlottetown, 20.48¢ in Halifax, and 22.00¢ in Edmonton and 22.90¢ in Calgary, where the bill includes Alberta’s separate transmission and distribution charges.

Taxes and rebates

Sales taxes on electricity depend on the province. The federal GST (5%) or the Harmonized Sales Tax (13–15% in Ontario and Atlantic Canada) applies, and Québec adds its own sales tax. Ontario offsets part of the HST and other costs through the Ontario Electricity Rebate, which gives eligible consumers 23.5% off the subtotal of their bill. With taxes and rebates included, the 1,000 kWh monthly bill on 1 April 2025 was C$95.32 in Montréal, C$134.31 in Vancouver, C$178.99 in Toronto, C$215.02 in Halifax and C$240.49 in Calgary.

Regulated and market prices

In most provinces household prices are set through cost-of-service rate cases before the provincial regulator, and governments sometimes cap increases. Québec’s residential rates rose by 3% on 1 April 2026, in line with the provincial cap on annual increases. In Alberta, energy prices follow the wholesale pool unless the customer is on a fixed contract or the Rate of Last Resort, and wires charges are approved separately by the Alberta Utilities Commission.

Trend

The chart shows the unweighted average price, excluding taxes, for 1,000 kWh a month across the same 12 cities in Hydro-Québec’s comparisons. It rose from 13.9¢/kWh in 2021 to 16.4¢ in 2023, driven mostly by Alberta, where Calgary’s price reached 29.80¢ in 2023 during a period of very high wholesale prices before easing to 22.90¢ in 2025. Prices in hydro provinces rose by roughly inflation over the same period.

Tariff types.

Tariff types.
TariffAvailableDetail
RegulatedYesMost households pay prices approved by a provincial regulator. Hydro-Québec, BC Hydro and other Crown utilities use two-step block tariffs (a cheaper first block, then a higher price). In Ontario the Ontario Energy Board sets Regulated Price Plan prices; from 1 November 2025 these were 9.8¢ off-peak, 15.7¢ mid-peak and 20.3¢ on-peak on time-of-use, or 12.0¢ and 14.2¢ on tiered pricing.
Time-of-useYesTime-of-use is the default for most Ontario households. Ontario also offers an Ultra-Low Overnight plan at 3.9¢/kWh from 11 p.m. to 7 a.m. and 39.1¢/kWh from 4 p.m. to 9 p.m. on weekdays. BC Hydro offers an optional time-of-day rate with a 5¢/kWh overnight discount and a 5¢/kWh surcharge from 4 p.m. to 9 p.m.
DynamicLimitedHydro-Québec’s Rate Flex D charges lower prices for most of the winter but a much higher price during up to 30 announced peak events (maximum 120 hours) between 1 December and 31 March. Fully wholesale-indexed household tariffs exist only in Alberta, where some retailers offer pool-price-linked products.
FixedLimitedFixed-price retail contracts are widely offered in Alberta’s competitive market and are available from licensed retailers in Ontario. Households in other provinces cannot choose a supplier.
VariableLimitedIn Alberta, customers who do not choose a retail contract are on the Rate of Last Resort, a regulated fixed price of about 12¢/kWh (EPCOR 12.01¢) for 1 January 2025 to 31 December 2026, which can change by no more than 10% at each two-year reset. Retailers also offer variable products that follow the wholesale market.
OtherYesNet metering or self-generation credits are offered by every major utility, but rules differ by province: kWh credits in Ontario and Québec, retail-rate credits for small Alberta micro-generators, and a fixed 10¢/kWh payment under BC Hydro’s new self-generation rate.

Household prices compared with neighbouring countries (EUR per kWh).

Household prices including taxes, converted to euros as stated on each country page.

Household electricity use.

Electricity use per household
10,865 kWh/yr (2021)Source 4Derived: average household energy use of 85.4 GJ, of which electricity was 45.8% (39.1 GJ), converted at 1 GJ = 277.8 kWh. Household figures from the 2021 Households and the Environment Survey (provinces only). Electric heating makes use much higher in Québec, Manitoba and Atlantic Canada than in gas-heated Ontario and Alberta.
Average daily use per household
29.8 kWh/day (2021)Source 4Derived: 10,865 kWh a year divided by 365.
Typical household peak demand
Not identified from a reliable public source.
Electricity use per person
14,093 kWh/person/yr (all sectors) (2024)Source 15Total electric power consumption per person, World Bank. Ember puts 2025 demand per capita at 16.1 MWh.
Heat pumps
10 % of households (2021)Source 5Households with a heat pump (air or ground source). 6% used a heat pump as their primary heating system. Shares were highest in New Brunswick (34%), Prince Edward Island (31%), Nova Scotia (28%) and Québec (26%).
Air conditioning
64 % of households (2021)Source 5Households in the provinces with at least one type of air conditioner; 38% had central air conditioning.
Electric vehicles
3.5 % of registered light-duty vehicles (2025)Source 7Zero-emission vehicles (battery-electric and plug-in hybrid) as a share of 25.3 million registered light-duty vehicles. ZEVs were 9.5% of new registrations in 2025, down from 14.6% in 2024 after federal and Québec rebates were paused or reduced.
Electric cooking
Not identified from a reliable public source.

Canadian homes use far more electricity than European homes, mainly because of heating and long winters. In 2021 the average household used 85.4 GJ of energy at home (electricity, natural gas and heating oil only), and electricity made up 45.8% of it, about 10,900 kWh a year. Alberta (121.8 GJ), Saskatchewan, Manitoba and Ontario households used more energy than average.

How homes are heated differs sharply by province, and this shapes electricity demand. In 2021, 51% of households with a primary heating system used a forced-air furnace (usually gas-fired in Ontario and the Prairies), 25% electric baseboard heaters and 6% heat pumps. In Québec, 58% of homes used electric baseboards and a further 7% electric radiant heating, so Québec’s system peaks on the coldest winter mornings and evenings. In Ontario, 75% of homes used forced-air furnaces.

Cooling is also widespread: 64% of households had air conditioning in 2021 and 10% had a heat pump that can provide it. Electric vehicles made up 3.5% of registered light-duty vehicles in 2025, with Québec and British Columbia having the highest adoption, but new ZEV registrations fell by 34.7% in 2025 after incentive pauses.

Housing and households.

Dwellings
16,284,235 private dwellings (2021)Source 214,978,941 of these were occupied by usual residents.
Owner-occupied
66.5 % of households (2021)Source 2The lowest homeownership rate since 2001, down from a peak of 69.0% in 2011.
Private rented
29.2 % of households (2021)Source 2Derived: renter households were 33.1% of all households, and 11.7% of tenant households lived in subsidised housing; the remainder is shown here.
Social or public housing
3.9 % of households (2021)Source 2Derived: 11.7% of the 33.1% of households that rent were in subsidised housing.
Houses
64.3 % of occupied dwellings (2021)Source 2Single-detached 52.6%, semi-detached 5.0%, row houses 6.5%, other single-attached 0.2%. Movable dwellings were a further 1.3%.
Apartments and flats
34.5 % of occupied dwellings (2021)Source 2Apartments in buildings of fewer than five storeys 18.3%, five or more storeys 10.7%, flats in a duplex 5.5%.
Urban population
82.9 % of population (2025)Source 14

Canada’s housing stock is dominated by single-detached houses, which made up 52.6% of occupied dwellings in the 2021 Census. Including semi-detached and row houses, almost two-thirds of households live in a house with its own roof. Apartments are concentrated in the large cities: 30.7% of dwellings in the Toronto area were in buildings of five or more storeys, and 41.3% of Montréal-area dwellings were in low-rise apartment buildings.

Two-thirds of households (66.5%) own their home, the lowest share since 2001. About a third rent, and 11.7% of renting households live in subsidised housing. Ownership matters for rooftop solar and heat pumps because programmes such as Hydro-Québec’s LogisVert solar grant are open only to owners of eligible dwellings.

Housing is highly seasonal in its energy needs. Detached homes in cold provinces often have high winter heating loads, so the switch from gas or oil furnaces to heat pumps is a major driver of future electricity demand, especially in Ontario and the Prairies.

How the grid works in Canada.

  1. TransmissionIndependent Electricity System Operator (IESO), Ontario, Alberta Electric System Operator (AESO), Vertically integrated Crown utilities
  2. DistributionProvincial Crown utilities in most provinces; dozens of local distribution companies in Ontario; wire owners (ATCO, ENMAX, EPCOR, FortisAlberta and municipal utilities) in Alberta
  3. MeteringDistributors and Measurement Canada, IESO Smart Metering Entity (MDM/R), Ontario
  4. Supply8 or more retail suppliers

Physical flow

Canada’s grids run mostly north–south. Provincial systems are linked to neighbouring US states by many interties, while east–west links between provinces are comparatively weak. Québec’s system is not synchronised with the rest of North America and connects to its neighbours through DC links and back-to-back converters. Large hydro stations in northern Québec, Manitoba, British Columbia and Labrador send power over long high-voltage lines (up to 735 kV in Québec) to southern cities, while Ontario relies on nuclear plants at Bruce, Darlington and Pickering for its baseload.

In 2024 Canada exported 36.1 TWh of electricity to the United States and imported 23.5 TWh, according to Statistics Canada. Exports fell by 24.5% because drought cut hydro output in Québec and Manitoba, and British Columbia became a large net importer.

Commercial flow

In Ontario, generators sell into the IESO-administered market, but most of their revenue comes from long-term contracts with the IESO or regulated prices for Ontario Power Generation’s nuclear and hydro output. The difference between market prices and these contract costs is recovered from consumers through the Global Adjustment, which is built into household Regulated Price Plan prices. LDCs bill customers for both energy and delivery.

In Alberta, generators bid into the AESO power pool, retailers buy energy from the pool or through hedges, and wire owners charge for transmission and distribution through the retailer’s bill. Load settlement agents allocate hourly energy to each retailer using site-level meter data under AUC Rule 021.

In Québec, Hydro-Québec’s distribution division buys a fixed-price heritage pool of electricity from its own generation division under provincial law and buys additional supply through tenders, mostly wind. BC Hydro, Manitoba Hydro and SaskPower similarly plan, build and buy generation for their own customers.

Who does what.

Who does what.
RoleOrganisationWhat it does
MinistryNatural Resources Canada (NRCan) and provincial energy ministriesNRCan runs federal energy-efficiency programmes and policy; Environment and Climate Change Canada administers the Clean Electricity Regulations. Provincial ministries (such as Ontario’s Ministry of Energy and Mines or Alberta’s Ministry of Affordability and Utilities) set the rules for their own power systems.
RegulatorProvincial utility regulatorsThe Ontario Energy Board (OEB), Alberta Utilities Commission (AUC), Régie de l’énergie in Québec, BC Utilities Commission (BCUC) and equivalent boards in other provinces approve rates, license market participants and set connection and metering rules. The federal Canada Energy Regulator (CER) regulates international power lines and electricity exports.
System operatorIndependent Electricity System Operator (IESO), OntarioOperates Ontario’s grid and wholesale market. Market Renewal went live on 1 May 2025, introducing a day-ahead market, a single-schedule market and locational marginal prices. The IESO also runs capacity auctions and procurements, Save on Energy programmes and, as the Smart Metering Entity, the province’s central meter data repository.
System operatorAlberta Electric System Operator (AESO)Operates Alberta’s grid and energy-only power pool and acts as load settlement reference for retailers. It is implementing the Restructured Energy Market for mid-2027, which brings locational pricing for generators, a new 30-minute ramping product and higher offer caps.
TSOVertically integrated Crown utilitiesHydro-Québec, BC Hydro, Manitoba Hydro, SaskPower, NB Power and Newfoundland and Labrador Hydro own generation and transmission and operate their own balancing areas. Nova Scotia Power is investor-owned. Hydro One owns most of Ontario’s transmission; AltaLink and ATCO own most of Alberta’s.
DSODistribution utilitiesIn most provinces the Crown utility also distributes power. Ontario has dozens of local distribution companies (LDCs), including Hydro One, Toronto Hydro, Alectra and Hydro Ottawa. Alberta’s wire services providers include ATCO, ENMAX Power, EPCOR, FortisAlberta and municipal utilities such as Lethbridge and Red Deer.
SupplierUtilities and Alberta/Ontario retailersIn most provinces the distribution utility is the only supplier. Alberta has full retail choice, with the Rate of Last Resort as the default. Ontario households can sign with a licensed retailer but most stay on the Regulated Price Plan billed by their LDC.
MeteringDistributors and Measurement CanadaMeters are owned and read by the distributor or wire owner. Measurement Canada, a federal agency, approves meter types and sets accuracy and reverification rules that force utilities to replace meters at the end of their service life.
Data hub / registryIESO Smart Metering Entity (MDM/R), OntarioA central repository receiving hourly data from more than five million Ontario smart meters, adding over 125 million records a day, used by LDCs for billing residential and small business customers. Alberta instead uses distributed site catalogues kept by each wire owner under AUC Rule 021.
ExchangeAESO power pool and IESO day-ahead and real-time marketsOnly Alberta and Ontario have organised wholesale markets. Elsewhere, utilities trade with each other and with US markets bilaterally; Hydro-Québec, BC Hydro (through Powerex) and Manitoba Hydro are large exporters.
Flexibility marketIESO capacity auction and Save on Energy demand responseAggregated demand response competes in Ontario’s annual capacity auction; the 2025 auction secured 1,833 MW for summer 2026 and 1,125 MW for winter 2026–27. Households can join the IESO’s Peak Perks smart-thermostat programme.

Compared with the UK system.

Compared with the UK system.
UK conceptCanada equivalentHow it works
DNOProvincial utility, LDC (Ontario) or wire services provider (Alberta)Distribution is organised province by province. In Québec, British Columbia, Manitoba and Saskatchewan the Crown utility owns the local network. In Ontario each municipality or region is served by a local distribution company licensed by the OEB. In Alberta the wire owner is called a wire services provider (WSP). Customers cannot choose their distributor.
National Grid/NESOIESO, AESO and provincial balancing authoritiesThere is no national grid operator. Each province balances its own system; the IESO (Ontario) and AESO (Alberta) are independent, while elsewhere the Crown utility operates the grid. Reliability standards are set through NERC and its regional entities (NPCC in the east, WECC in the west), as provinces are interconnected with the United States more than with each other.
MPANNo national equivalent; Site ID in AlbertaAlberta’s 13-digit Site ID, assigned by the wire owner, is the closest equivalent: retailers use it to enrol a customer, and load settlement happens at Site ID level. In other provinces a supply point is identified by the utility’s own account and meter numbers, because there is no retail switching to support.
MPRNGas utility account and meter numbersGas distribution is also provincial (for example Enbridge Gas in Ontario, ATCO and Apex in Alberta, Énergir in Québec, FortisBC in British Columbia), and each identifies gas service points with its own account and meter numbers. Alberta’s gas retail market uses site IDs in a similar way to electricity.
Meter operatorDistributor or wire owner, under Measurement Canada rulesThere is no competitive metering market. The distributor owns, installs, reads and replaces the meter, and the meter must be of a type approved by Measurement Canada. Hydro-Québec, for example, is replacing its 4.4 million smart meters from 2027 to meet Measurement Canada requirements.
SupplierThe utility (most provinces); retailer in Alberta and optionally OntarioOnly Alberta has a fully competitive household retail market. Ontario households may sign with a licensed retailer but the default is the OEB’s Regulated Price Plan. In Québec, British Columbia and most other provinces the utility is the sole supplier at a regulated rate.
Smart-meter infrastructureUtility-run AMI networks; Ontario MDM/REach utility runs its own advanced metering network. Ontario is unique in pooling hourly data from all LDCs in a central repository run by the IESO, and all Ontario utilities must offer Green Button data download and authorised third-party sharing.

How a supply point is identified.

0030274819366 (fictional EPCOR site; check digit 6)

Fictional example in the real format.

How a supply point is identified.
QuestionAnswer
What is it called?Site ID (Alberta); no national identifier (Site ID)
Who issues it?The wire services provider (distribution wire owner) for the site, in Alberta. Elsewhere, the distribution utility identifies service by account and meter numbers.
FormatAlberta: four-digit WSP ID + eight-digit site number chosen by the WSP + one check digit. The check digit is the sum of each of the first 12 digits multiplied by its position (1 to 12), divided by nine; the remainder (0–8) is the check digit. WSP IDs include 0010 ATCO, 0020 ENMAX, 0030 EPCOR, 0040 FortisAlberta, 0050 Lethbridge and 0070 Red Deer.
Length13 digits (Alberta Site ID)
Stays with the property when you switch supplier?Yes
Where to find itPrinted on Alberta electricity bills from the retailer or Rate of Last Resort provider, and available from the wire owner. In other provinces customers quote the account number and meter number shown on their utility bill.
Electronic accessIn Alberta, retailers enrol and de-enrol sites, receive daily meter readings and request connections by Site ID through standard electronic transactions defined in AUC Rule 021. In Ontario, consumption is held centrally in the IESO’s MDM/R and customers can download it in Green Button format.
Third-party accessAlberta retailers and load settlement agents receive site data as part of the market processes. In Ontario, Ontario Regulation 633/21 requires utilities to offer Green Button Connect My Data, so customers can authorise third parties such as solar installers or energy apps to receive their data directly.
Who keeps the registerEach Alberta wire services provider keeps a site catalogue of its Site IDs; the AESO assigns retailer IDs and load settlement is done by the load settlement agent for each zone. There is no national register.
Register scopePer DSO

Why Canada has no national supply-point number

Because electricity is provincial and most provinces have a single utility serving households, there has never been a need for a common identifier to support supplier switching. A Hydro-Québec, BC Hydro or SaskPower customer is identified by the utility’s own customer account and contract, and by the serial number of the meter at the address. These numbers are internal to each utility and have no standard format across Canada.

Alberta’s Site ID

Alberta is the exception because households can choose their retailer. AUC Rule 021, the Settlement System Code, defines a 13-digit Site ID that identifies each point of delivery. The first four digits identify the wire services provider, the next eight are chosen by that provider and the final digit is a calculated check digit to catch typing errors. If a different wire owner takes over a site, the first four digits must change. A Site ID is not reused: when a site is removed from the catalogue it can no longer be enrolled.

A retailer uses the Site ID to enrol a customer, and consumption is allocated and settled at Site ID level. Because the Site ID belongs to the point of delivery rather than the customer, a new occupant keeps the same Site ID when moving in and simply enrols it with a retailer of their choice. Micro-generation sites use the same Site ID, and the meter readings for exported energy are sent to the retailer through dedicated transactions.

Ontario

Ontario has retail choice in principle but no standard public identifier equivalent to a Site ID. Each LDC identifies customers by account number and meter, and the IESO’s Meter Data Management/Repository holds hourly consumption for more than five million smart meters. Since 1 November 2023 all Ontario electricity and gas utilities must provide Green Button data, letting customers download their usage or authorise third parties to receive it.

Sending electricity to the grid.

Sending electricity to the grid.
QuestionAnswer
Can homes export electricity?Yes
Net meteringYes
Net billingYes
How exported electricity is paidProvince-specific: kWh credits (Ontario, Québec, Nova Scotia), retail-rate credits for small micro-generators (Alberta) and a fixed 10¢/kWh payment (BC Hydro since 1 July 2026)
OntarioNet metering lets customers offset their own use with renewable generation; surplus credits can be carried forward for up to 12 months. Homeowners who take the Home Renovation Savings solar or battery rebate must size the system for their own use and cannot join net metering.
AlbertaMicro-generation up to 5 MW is allowed if it meets an emissions limit of 418 kg/MWh. Small micro-generators (under 150 kW) are credited monthly at their retail energy rate, or hourly at pool price with a suitable meter; large micro-generators (150 kW and above) are paid the hourly pool price. Credits are administered by the retailer.
QuébecHydro-Québec’s net metering option gives kWh credits for surplus energy injected into the grid. Installations must be approved by Hydro-Québec.
British ColumbiaFrom 1 July 2026 BC Hydro’s Self-Generation Service Rate (RS 2289) pays 10¢/kWh for exports each billing period, for systems sending up to 100 kW per phase. Net metering (RS 1289) has closed to new customers; existing customers can stay for ten years from enrolment, except those who took a BC Hydro solar rebate, who moved to RS 2289.
Nova ScotiaNet-metered exports are credited at the customer’s full electricity rate, and 2022 legislation barred Nova Scotia Power from adding fees that discourage residential solar.

Connecting a home system.

  1. Check the provincial scheme and size limit (for example 5 MW micro-generation in Alberta, 100 kW per phase at BC Hydro).
  2. Hire a licensed electrical contractor; obtain any municipal building permit.
  3. Apply to the distribution utility or wire owner for connection approval before installing (in Alberta, file the micro-generation notice under AUC Rule 024).
  4. Install equipment certified to CSA standards and pass the provincial electrical safety inspection (for example ESA in Ontario).
  5. The utility installs or reprograms a bidirectional meter and enrols the account in net metering or the self-generation rate.

Households in every province can connect rooftop solar and export surplus electricity, but the commercial terms are set province by province and have been moving away from simple kWh banking. British Columbia replaced net metering with a fixed export price in July 2026, and Ontario’s main solar rebate is only available to systems that are not net-metered.

Connection is handled by the local distribution utility, which checks the system size, protection settings and the local feeder before approval. Most utilities require inverters certified to CSA C22.2 No. 107.1 or UL 1741 and compliance with the interconnection standard CSA C22.3 No. 9. Larger systems may need a connection impact assessment and can be asked to pay for network upgrades.

In Alberta the micro-generation framework, set by the Micro-generation Regulation and AUC Rule 024, is the main route for homes and farms; the AUC consulted on revisions to Rule 024 between May and November 2025.

Licensing and approvals.

Requirements depend on the activity. The table sets out what each activity needs and who grants it.

Licensing and approvals.
ActivityLicence or registrationAuthorityNotes
Generate electricity (household / small)No generation licence for net-metered or micro-generation systems; connection approval and electrical permit requiredDistribution utility; provincial electrical safety authority; AUC in AlbertaAlberta micro-generation up to 5 MW is notified under AUC Rule 024 rather than licensed. In Ontario, OEB generation licences are not required for facilities of 500 kW or less.
Generate electricity (utility-scale)Provincial approval: OEB generation licence in Ontario; AUC power plant approval in Alberta; elsewhere sale to the Crown utility under contractOEB, AUC, provincial regulators and environmental assessment bodiesOutside Alberta and Ontario, independent generators generally sell only to the provincial utility through tenders or power purchase agreements.
Store electricityTreated like generation for licensing and market registration where it connects to the transmission or wholesale market; behind-the-meter storage needs only connection approval and inspectionOEB / IESO (Ontario), AUC / AESO (Alberta), local utilityBattery systems in homes must meet the Canadian Electrical Code (Section 64) as adopted by the province.
Export to the gridUtility connection agreement under the provincial net metering or self-generation rulesDistribution utility, under rules approved by the provincial regulatorSize limits differ: up to 5 MW in Alberta; 100 kW per phase at BC Hydro.
Sell / supply to householdsAlberta: registration with the Department of Energy, AESO retailer ID and pool participation, consumer marketing licence and a service agreement with each wire owner. Ontario: OEB retailer licence. Other provinces: no third-party retail permittedAlberta Government, AESO, AUC; OEBIn Québec, British Columbia and most other provinces the Crown utility has an exclusive right to sell to households in its service area.
Aggregate demand response or distributed resourcesMarket participant registration with the IESO to offer aggregated demand response in the capacity auction; no separate aggregator licenceIESO (Ontario); AESO (Alberta)Aggregations of distributed resources cannot yet offer energy into the IESO market; a foundational DER participation model is due by the end of 2026.
Trade / wholesale participationRegistration as a market participant (IESO) or pool participant (AESO), with credit supportIESO; AESOElsewhere, wholesale trading is done by the Crown utilities and their marketing arms, such as Powerex for BC Hydro.
Export electricity outside CanadaFederal authorisation for exports and permits for international power linesCanada Energy RegulatorNot relevant to households; applies to utilities and marketers selling to US markets.
Balancing and ancillary servicesQualification and registration with the system operator for each serviceIESO; AESO; provincial utilitiesIn provinces without a market, the Crown utility provides or contracts these services itself.
Virtual power plant / remote control of assetsNo specific licence; operates through utility or system-operator programmes and customer consentUtility programme rules; IESO for Ontario programmesExamples are BC Hydro’s Peak Saver battery programme, Hydro-Québec’s Hilo and the IESO’s Peak Perks thermostat programme.

Licensing depends entirely on the province. In Ontario the OEB licenses generators, distributors, transmitters and retailers under the Ontario Energy Board Act, and anyone selling into the wholesale market must register with the IESO. In Alberta the AUC approves power plants and transmission, the AESO registers pool participants and retailers, and the provincial government licenses businesses that market electricity to consumers.

In most other provinces there is no competitive market to license. The Crown utility has an exclusive franchise to distribute and sell electricity to households, and independent producers can only sell to it. Households that install solar or batteries do not need a licence anywhere in Canada, but they do need a licensed electrical contractor, an electrical permit and inspection, and the utility’s connection approval.

Flexibility and grid services.

Aggregation of home equipment: Limited

Flexibility and grid services.
Market or serviceAccess for home equipmentMinimum sizeVia an aggregatorDetail
IESO capacity auction (Ontario)Yes—YesIESO. Hourly demand response, including aggregated loads, competes alongside generators and storage for summer and winter capacity obligations. The 2025 auction secured 1,833 MW for summer 2026 and 1,125 MW for winter 2026–27.
IESO energy and operating reserve marketsDeveloping—NoIESO. Storage and large loads can participate directly. Under the Enabling Resources Program, the IESO has committed to a foundational model for dispatchable aggregations of distributed resources by the end of 2026.
AESO energy and ancillary services (Alberta)Restricted—NoAESO. Grid-scale storage and large loads take part in the energy and operating reserve markets. The AESO is studying participation thresholds and aggregation for distributed resources under its DER Roadmap. The Restructured Energy Market from mid-2027 adds a 30-minute ramping product and day-ahead procurement of reserves.
Utility demand response programmesYes—YesHydro-Québec’s Rate Flex D and Hilo, BC Hydro’s Peak Saver and Ontario’s Peak Perks pay or reward households for reducing use or letting devices be controlled during peaks.

Flexibility markets exist mainly in Ontario and Alberta, the two provinces with wholesale markets. Ontario’s capacity auction is the most accessible route for aggregators, and hourly demand response has become a large part of the capacity it buys. Households take part indirectly through utility and IESO programmes rather than by selling directly into the market.

In provinces with a single utility, flexibility is procured through tariffs and utility programmes. Québec’s winter peak is the main focus: Hydro-Québec uses Rate Flex D and Hilo to reduce demand during up to 30 peak events each winter. BC Hydro is using rebates to build a fleet of controllable home batteries.

Aggregated distributed resources offering energy and reserves into wholesale markets is still developing. The IESO plans its first participation model for DER aggregations by the end of 2026, and the AESO is assessing aggregation as part of its DER Roadmap alongside the 2027 market redesign.

Flexibility and aggregation platforms.

Flexibility and aggregation platforms.
Platform or aggregatorWhat it does
Peak Perks (Save on Energy, Ontario)Bring-your-own-thermostat programme: C$75 on enrolment and C$20 for each further year, with adjustments of 2–4 °C up to 10 times between June and September.
Hilo (Hydro-Québec)Hydro-Québec subsidiary that controls smart thermostats and other devices during winter peak events and pays customers for the reduction.
BC Hydro Peak SaverProgramme for enrolled home batteries; since 1 April 2026 the full C$5,000 battery rebate requires Peak Saver enrolment.

Smart meters.

Smart meters.
FactValue
Smart-meter rolloutNear-universal in Ontario, British Columbia and Québec; utility-led, with Hydro-Québec starting a second-generation replacement in 2027
Reading intervalHourly in Ontario; varies by utility elsewhere
OntarioMore than 5 million smart meters sending hourly data to the IESO’s MDM/R
British ColumbiaBC Hydro installed 1.93 million smart meters from 2011; more than 99% of customers have one
QuébecAbout 4.4 million communicating meters, to be replaced over seven years from 2027
Data accessGreen Button Download My Data and Connect My Data mandatory for Ontario utilities since November 2023
Meter approvalMeasurement Canada approves meter types and sets reverification periods

Smart meter roll-outs in Canada were run by individual utilities and provincial governments, not a national programme. Ontario led: the province mandated smart meters and time-of-use pricing in the late 2000s, and the IESO, as Smart Metering Entity, operates a central database that validates hourly readings for all LDCs. This is why time-of-use is the default tariff for Ontario households.

BC Hydro completed its roll-out in the early 2010s and now has smart meters at more than 99% of customers. Hydro-Québec installed its first generation of communicating meters from 2012; it will replace about 4.4 million of them over seven years from 2027 because they are reaching the end of their 15–18-year lifespan and must meet Measurement Canada requirements. Customers in Québec who refuse a communicating meter pay installation and monthly reading fees.

Alberta’s wire owners use a mix of interval and cumulative meters, and readings flow to retailers through standard Rule 021 transactions. Access to data for third parties is most developed in Ontario, where Green Button lets customers authorise apps and installers to receive their usage data.

Renewable electricity.

Electricity generation mix (2025).

  • Hydro: 52.8%
  • Gas: 17.9%
  • Nuclear: 13.1%
  • Wind: 7.9%
  • Coal: 4%
  • Bioenergy: 1.6%
  • Solar: 1.6%
  • Other fossil: 1.2%
Source 12
Renewable electricity share
63.9% (2025)Source 12Hydro 52.8%, wind 7.9%, solar 1.6%, bioenergy 1.6%. Including nuclear (13.1%), low-carbon sources supplied 77.0%. Statistics Canada reported a 63.9% renewable share for 2024.
Home solar
Not identified from a reliable public source.
Solar added each year
57 MW (utility-scale) (2025)Source 13Utility-scale projects in Alberta, British Columbia and Yukon only; behind-the-meter installations are excluded.
Hydro
84.1 GW (2025)Source 12
Wind
17.7 GW (2025)Source 12
Nuclear
12.7 GW (2025)Source 12
Solar
5.93 GW (2025)Source 12
Gas
27.2 GW (2025)Source 12
Battery storage
1 GW (end 2025)Source 13Rounded (“nearly 1 GW”).

Targets.

  • Clean Electricity Regulations (SOR/2024-263): fossil-fuelled generating units must meet an emissions limit of 65 t CO2/GWh from 2035, falling to zero from 2050, with limited use of offset credits.
  • Net-zero electricity grid by 2050 under the federal Clean Electricity Regulations.
  • Provincial procurements: CanREA expects wind and solar in Québec to grow from about 4.5 GW to more than 14 GW, and in British Columbia from about 900 MW to 4 GW, by 2029.

Canada’s electricity has long been dominated by hydropower, which supplied 52.8% of generation in 2025. Québec alone produced about half of Canada’s hydroelectricity in 2024. Nuclear power, almost all of it in Ontario, adds a further 13%, so low-carbon sources supply about 77% of electricity. Fossil generation is concentrated in Alberta, Saskatchewan and Nova Scotia; coal still supplied 4.0% nationally in 2025, mainly in Saskatchewan and Nova Scotia.

Wind is the main new renewable source, with about 18–19 GW installed, led by Ontario, Québec and Alberta. Solar is small by comparison at about 5–6 GW, with most utility-scale capacity in Alberta and Ontario. Growth slowed in 2025, when only 347 MW of wind and 57 MW of utility-scale solar were completed, but large procurements by Hydro-Québec, BC Hydro, the IESO and other utilities are expected to raise wind, solar and storage capacity by a third over the next four years.

Drought matters in a hydro-based system. In 2024 low water reduced hydro output by 3.8%, cutting Québec and Manitoba’s exports and making British Columbia a large net importer.

Energy storage.

Home batteries
Not identified from a reliable public source.
Grid-scale storage
1 GW (end 2025)Source 13CanREA: “nearly 1 GW” after capacity more than doubled in 2025, mostly in Ontario.

Grid-scale battery storage is concentrated in Ontario, where the IESO has contracted batteries to meet rising peak demand and to manage the nuclear refurbishment programme. Canada’s battery capacity more than doubled in 2025 to nearly 1 GW, and CanREA expects it to nearly double again within two years. Alberta has a handful of grid batteries taking part in the AESO energy and reserve markets.

Canada also has large hydro reservoirs that already provide seasonal and daily flexibility, so the case for batteries differs by province. Home batteries are supported by BC Hydro and Ontario’s Home Renovation Savings Program, but no national data on residential installations are published.

The federal Clean Electricity Investment Tax Credit, enacted in March 2026, provides a refundable 15% credit for stationary storage, including for provincial Crown utilities.

Storage projects.

  • Oneida Energy Storage (Ontario): 250 MW / 1,000 MWh battery in Haldimand County, the largest in Canada when it began commercial operation in May 2025; co-owned by Northland Power, Six Nations of the Grand River Development Corporation and partners.
  • IESO E-LT1 storage procurement (Ontario): Long-term contracts awarded by the IESO for new storage. Most of the 502 MW of storage added in Ontario in 2025 came from E-LT1 and bilateral agreements.
  • BC Hydro battery rebates: Up to C$5,000 for home batteries enrolled in Peak Saver, or C$1,500 for batteries paired with solar outside the programme.

Electricity suppliers.

Electricity suppliers.
SupplierMarket shareRenewable tariffTime of useDynamicExport tariff
Hydro-Québec—NoYesLimitedYes
Hydro One—NoYesNoYes
Toronto Hydro—NoYesNoYes
BC Hydro—NoYesNoYes
ENMAX—UnknownUnknownUnknownYes
EPCOR—UnknownUnknownUnknownYes
SaskPower—NoNoNoYes
Nova Scotia Power—NoUnknownNoYes

Which supplier a household has depends almost entirely on where it lives. In Québec, British Columbia, Manitoba, Saskatchewan, New Brunswick and Newfoundland and Labrador the provincial utility is effectively the only option. Nova Scotia Power and Maritime Electric (Prince Edward Island) are investor-owned regulated monopolies.

In Ontario the local distribution company bills customers under the Regulated Price Plan; Hydro One serves much of rural Ontario, and Toronto Hydro, Alectra and Hydro Ottawa serve the largest cities. In Alberta households choose among competing retailers, including ENMAX, EPCOR, Direct Energy and smaller firms, or stay on the Rate of Last Resort.

Key organisations.

Key organisations.
OrganisationCategoryWhat it doesWhy it matters
Natural Resources CanadaGovernmentFederal energy departmentRuns federal home-efficiency programmes (the Greener Homes Loan closed to new applications on 1 October 2025) and publishes energy data.
Canada Energy RegulatorRegulatorFederal regulator for international power lines and exportsPublishes provincial energy profiles and long-term outlooks.
Ontario Energy BoardRegulatorOntario utility regulatorSets Regulated Price Plan prices, licenses market participants and sets distribution connection rules.
Alberta Utilities CommissionRegulatorAlberta utility regulatorApproves wires rates and power plants and owns Rule 021 (settlement) and Rule 024 (micro-generation).
Régie de l’énergieRegulatorQuébec energy regulatorRegulates Hydro-Québec’s distribution and transmission activities.
BC Utilities CommissionRegulatorBritish Columbia utility regulatorApproved BC Hydro’s new self-generation rate and its time-of-day rates.
Independent Electricity System Operator (IESO)MarketOntario system and market operator; Smart Metering EntityRuns the market, capacity auctions, procurements, Save on Energy and the MDM/R.
Alberta Electric System Operator (AESO)MarketAlberta system and market operatorOperates the power pool and is delivering the Restructured Energy Market.
Measurement CanadaMeteringFederal metrology agencyApproves electricity meters and sets accuracy and reverification rules.
Canadian Renewable Energy Association (CanREA)Renewable EnergyWind, solar and storage industry associationPublishes annual installed-capacity data and forecasts.
Energy Storage CanadaStorageStorage industry associationRepresents storage developers and users in provincial market design.
Electricity CanadaDistributionAssociation of Canadian electricity companiesRepresents utilities, including the Crown utilities and Ontario LDCs.
Utilities Consumer Advocate (Alberta)ConsumerAlberta consumer bodyExplains retail choice and the Rate of Last Resort and handles complaints.

Technical standards.

Technical standards.
AreaStandardIssued byNotes
Electrical installationsCSA C22.1:24 Canadian Electrical Code, Part I (26th edition)CSA GroupAdopted by each province, sometimes with amendments (for example the Ontario Electrical Safety Code). Section 64 covers renewable energy and storage systems, with a new subsection for residential storage.
Grid connectionCSA C22.3 No. 9:20 Interconnection of distributed energy resources and electricity supply systemsCSA GroupSecond edition, replacing the 2008 standard. Utilities and provinces reference it for DER interconnection; individual utilities add their own technical requirements.
InvertersCSA C22.2 No. 107.1 / UL 1741CSA Group / ULGrid-connected inverters must be certified by an accredited certification body; utilities typically require utility-interactive certification.
MeteringElectricity and Gas Inspection Act and Measurement Canada specificationsMeasurement CanadaMeters must be of an approved type and reverified or replaced at set intervals.
Settlement and site data (Alberta)AUC Rule 021 Settlement System CodeAlberta Utilities CommissionDefines Site IDs, retailer transactions and meter data standards.
Energy data access (Ontario)Green Button (NAESB REQ.21 ESPI), O. Reg. 633/21Government of Ontario; Green Button AllianceMandatory Download My Data and Connect My Data for Ontario utilities.
Installer accreditationProvincial electrical contractor licensingProvincial safety authorities (e.g. ESA in Ontario, RBQ/CMEQ in Québec)There is no national installer certification scheme; solar and battery wiring must be done or supervised by a licensed electrical contractor. BC Hydro requires Home Performance Contractor Network members for rebates from 1 June 2026.

Permissions.

Permissions.
PermissionRequiredLevelDetail
Utility connection approvalYesRegionalRequired before connecting any grid-tied generation or storage; issued by the distribution utility or wire owner.
Electrical permit and inspectionYesRegionalIssued by the provincial electrical safety authority or delegated municipality.
Building permitLimitedLocalMany municipalities require a building permit for roof-mounted solar, particularly for structural review.
Alberta micro-generation noticeYesRegionalMicro-generators file with the wire owner under AUC Rule 024 and must meet the 418 kg/MWh emissions limit.
Generation licenceNoRegionalNot needed for household systems; required for larger plants in Ontario (OEB) and plant approvals in Alberta (AUC).

Permissions are a provincial and municipal matter. A typical rooftop installation needs the utility’s connection approval, an electrical permit and inspection, and in some municipalities a building permit. Utilities usually want the application before work starts so they can check that the local transformer and feeder can accept the export.

Heritage districts and condominium rules can restrict rooftop installations, and multi-unit buildings often need the owner or condominium board’s consent.

Support schemes, taxes and incentives.

Support schemes, taxes and incentives.
SchemeStatusTypeDetailPeriod
Home Renovation Savings Program (Ontario)ActiveRebateDelivered by Save on Energy and Enbridge Gas. Up to C$10,000 for rooftop solar and battery storage, plus rebates for heat pumps, insulation and other upgrades. Solar systems funded by the rebate must be sized for the home’s own use and cannot be net-metered.From 28 January 2025
LogisVert solar grant (Hydro-Québec)ActiveGrantC$1,000 per installed kW, up to 40% of the cost of buying and installing solar panels, for owners of eligible homes; panels must be installed on or after 30 June 2025 and connected to Hydro-Québec’s grid. Separate LogisVert grants cover heat pumps. No battery grant is offered.Installations from 30 June 2025
BC Hydro solar and battery rebatesActiveRebateUp to C$5,000 for solar panels and up to C$5,000 for batteries enrolled in Peak Saver (C$1,500 for non-enrolled batteries paired with solar, from 1 April 2026). Installers must be Home Performance Contractor Network members from 1 June 2026. Rebate recipients are on the Self-Generation Service Rate.—
BC Hydro Self-Generation Service Rate (RS 2289)ActiveExport payment10¢/kWh for electricity exported, paid each billing period, for systems sending up to 100 kW per phase.From 1 July 2026
Alberta micro-generation creditsActiveNet billingExports from small micro-generators are credited at the retail energy rate; larger micro-generators are paid the hourly pool price.—
Clean Electricity Investment Tax CreditActiveTax creditRefundable 15% credit for low-emitting generation, stationary storage and interprovincial transmission, available to taxable corporations and to provincial Crown, municipal and Indigenous-owned corporations. Not available to households.Enacted 26 March 2026; eligible expenses before 2035
Canada Greener Homes LoanClosedInterest-free loanInterest-free loans of up to C$40,000 for retrofits including solar; closed to new applications on 1 October 2025. Approved loans remain valid.—

Data and connectivity.

Fixed broadband
97.3 % of households with access to 50/10 Mbps unlimited (2024)Source 35Availability, not take-up. Fixed broadband subscriptions were 42.5 per 100 people in 2024 (World Bank).
4G coverage
99.6 % of population covered by LTE (2024)Source 35
5G coverage
Not identified from a reliable public source.

Canada’s population is concentrated in the south, where broadband and LTE coverage are almost universal, but rural, northern and Indigenous communities still have gaps. Smart meters in most provinces use utility-owned radio frequency mesh networks rather than public mobile networks.

Home energy devices mostly connect over home Wi-Fi to cloud platforms. Utility programmes such as Peak Perks, Hilo and Peak Saver control thermostats and batteries through manufacturers’ cloud interfaces, and Ontario’s Green Button gives third parties a standard way to receive meter data.

Grid conditions.

National peak demand
Not identified from a reliable public source.
Annual electricity demand
645.6 TWh (2025)Source 12Statistics Canada reported 503.3 TWh of sales to end users in 2024.
Generation capacity
156 GW (2025)Source 12Derived: Ember clean capacity (123.14 GW) plus fossil capacity (32.85 GW).
Interconnection
Not identified from a reliable public source.
Curtailment
Not identified from a reliable public source.

Grid conditions differ by province. Québec and the Atlantic provinces peak in winter because of electric heating, while Ontario’s system has traditionally peaked in summer but is moving towards winter peaks as heating electrifies. Alberta’s market has seen volatile prices and tight supply in recent winters, which shaped the move to the Rate of Last Resort and the Restructured Energy Market.

Connection queues for large loads and generation have grown quickly in Ontario, Alberta and Québec, driven by industry and electrification. Hydro-sourced exports also swing year to year with water conditions, as shown by the 24.5% fall in exports in 2024.

Grid and capacity maps.

Regulatory changes.

Regulatory changes.
ChangeStatusDateDetail
BC Hydro Self-Generation Service Rate replaces net meteringCurrent1 July 2026Exports are paid at 10¢/kWh each billing period instead of banked kWh credits; net metering is closed to new customers and existing customers transfer after ten years.
Hydro-Québec rate increaseCurrent1 April 2026Residential and farm rates rose 3%; business rates rose 3.8%.
Clean Electricity Investment Tax Credit enactedCurrent26 March 2026Bill C-15 received Royal Assent, making the 15% refundable credit law, including for provincial Crown utilities.
Ontario Market RenewalCurrent1 May 2025The IESO introduced a day-ahead market, a single-schedule market and locational marginal pricing.
Alberta Rate of Last Resort resetUpcoming1 January 2027The 2025–26 Rate of Last Resort (about 12¢/kWh) ends on 31 December 2026; the next two-year price can move by no more than 10%.
IESO foundational DER participation modelUpcomingEnd of 2026Allows dispatchable aggregations of distributed energy resources to take part in IESO-administered markets.
Alberta Restructured Energy MarketUpcomingMid-2027Locational marginal pricing for generators, a 30-minute ramping product, day-ahead reserve procurement and a higher offer cap of C$1,500/MWh in 2027 rising to C$2,000/MWh by 2032; no full day-ahead energy market.
Hydro-Québec meter replacementUpcoming2027–2034Replacement of about 4.4 million smart meters over seven years.
Clean Electricity Regulations take effectUpcoming1 January 2035Emissions limit of 65 t CO2/GWh for covered fossil units from 2035, with offsets allowed up to a limit, falling to zero from 2050.

Market indicators.

Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.

Market indicators.
IndicatorLevelBasis
Electricity costLowLow below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros).
Household electricity useHighLow below 2,500 kWh a year, high at 5,000 kWh or more (average use per household).
Renewable shareHighLow below 30%, high at 60% or more (renewable share of electricity).
Smart-meter adoption—Low below 30%, high at 80% or more (share of meters that are smart).
Home solar adoptionMediumNet metering or export payments in every province and grants in Ontario, Québec and British Columbia, but solar is only about 1.6% of generation and no official national rooftop count is published.
Distributed energy marketMedium10% of households had a heat pump and 64% air conditioning in 2021; ZEVs were 3.5% of registered light-duty vehicles in 2025.
Grid flexibility marketMediumAggregated demand response clears in Ontario’s capacity auction (1,833 MW for summer 2026) and utility programmes exist in several provinces, but DER aggregation in energy markets is still being designed.
Energy storage adoptionMediumGrid batteries more than doubled to nearly 1 GW in 2025, including the 250 MW / 1,000 MWh Oneida project; little data on home batteries.
Renewable growth environmentMediumRenewables already supply about 64% of generation, but only about 1 GW of wind, solar and storage was added in 2025; large procurements are under way in Québec, British Columbia and Ontario.

Sources.

Public sources used for this profile, with the date each was accessed.

Show all 36 sources
  1. Canada's population estimates: Age and gender, 2026. Statistics Canada (The Daily), 2026. accessed 1 October 2026.
  2. Census Profile, 2021 Census of Population (98-401-X2021001). Statistics Canada, 2021. accessed 1 October 2026.
  3. The Daily — To buy or to rent: The housing market continues to be reshaped by several factors as Canadians search for an affordable place to call home. Statistics Canada, 2022. accessed 1 October 2026.
  4. Households and the Environment Survey: Energy use, 2021. Statistics Canada (The Daily), 2024. accessed 1 October 2026.
  5. Air conditioning: More Canadians keep cool, but costs heat up. Statistics Canada (StatsCAN Plus), 2023. accessed 1 October 2026.
  6. The heat is on: How Canadians heat their home during the winter. Statistics Canada (StatsCAN Plus), 2023. accessed 1 October 2026.
  7. A pan-Canadian electric feel. Statistics Canada (StatsCAN Plus), 2026. accessed 1 October 2026.
  8. New motor vehicle registrations, fourth quarter 2025. Statistics Canada (The Daily), 2026. accessed 1 October 2026.
  9. Electricity supply and disposition, 2024. Statistics Canada (The Daily), 2025. accessed 1 October 2026.
  10. Comparison of Electricity Prices in Major North American Cities — Rates in effect April 1, 2025. Hydro-Québec, 2025. accessed 1 October 2026.
  11. Euro foreign exchange reference rates — Canadian dollar. European Central Bank, 2026. accessed 1 October 2026.
  12. Yearly electricity data — Canada. Ember, 2026. accessed 1 October 2026.
  13. The stage is set for the future of Canada’s wind, solar and energy storage industry (2025 installed capacity data). Canadian Renewable Energy Association, 2026. accessed 1 October 2026.
  14. Urban population (% of total population) — Canada. World Bank, 2025. accessed 1 October 2026.
  15. Electric power consumption (kWh per capita) — Canada. World Bank, 2024. accessed 1 October 2026.
  16. AUC Rule 021: Settlement System Code Rules. Alberta Utilities Commission (copy hosted by AESO). accessed 1 October 2026.
  17. Micro-generation. Government of Alberta. accessed 1 October 2026.
  18. Regulated Rate Option to change to the Rate of Last Resort. EPCOR, 2024. accessed 1 October 2026.
  19. Electricity rates — Regulated Price Plan effective November 1, 2025. Hydro Ottawa, 2025. accessed 1 October 2026.
  20. Smart Metering Entity. IESO. accessed 1 October 2026.
  21. IESO Secures Resources via 2025 Capacity Auction. IESO, 2025. accessed 1 October 2026.
  22. ERP Distributed Energy Resources Integration Project. IESO. accessed 1 October 2026.
  23. O. Reg. 633/21: Energy Data. Government of Ontario, 2021. accessed 1 October 2026.
  24. Self-generation rate updates. BC Hydro, 2026. accessed 1 October 2026.
  25. BC Hydro solar, battery, rate and rebate changes. Home Performance Stakeholder Council, 2026. accessed 1 October 2026.
  26. LogisVert — Residential. Hydro-Québec. accessed 1 October 2026.
  27. Smart meter replacement: How to prepare for the visit from our crews. Hydro-Québec. accessed 1 October 2026.
  28. Home Renovation Savings Program. Save on Energy (IESO). accessed 1 October 2026.
  29. Ontario’s solar rebate has a hidden catch. The Atmospheric Fund, 2026. accessed 1 October 2026.
  30. Closed: Canada Greener Homes Loan. Natural Resources Canada. accessed 1 October 2026.
  31. Clean Electricity Regulations (SOR/2024-263). Government of Canada (Justice Laws), 2024. accessed 1 October 2026.
  32. Canada’s 2025 Budget Implementation Bill No. 1 receives Royal Assent. EY Tax News, 2026. accessed 1 October 2026.
  33. Alberta announces details of restructured electricity market. DLA Piper, 2025. accessed 1 October 2026.
  34. Northland Power begins commercial operations at 250 MW / 1,000 MWh BESS project in Ontario. Energy Global, 2025. accessed 1 October 2026.
  35. Canadian Telecommunications Market Report 2025. CRTC, 2025. accessed 1 October 2026.
  36. CSA C22.3 No. 9:20 Interconnection of distributed energy resources and electricity supply systems. Standards Council of Canada, 2020. accessed 1 October 2026.