How electricity works in Suriname.
Suriname electricity 2026: state utility EBS as single buyer, EAS regulation, Afobaka hydro, block tariffs in SRD, rooftop solar netting and the first utility-scale solar tenders.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Surinamese dollar (SRD) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Suriname energy at a glance.
Key figures for households in Suriname. Each one links to its source on the full overview below.
Electricity price.
2.27 SRD per kWh for households, including taxes. Figures for Nov 2024.
Household use.
4,540 kWh a year for a typical household. Figures for 2024.
Renewable share.
52.9% of electricity from renewable sources. Figures for 2024.
Selling back to the grid.
Can homes export electricity? Yes. Details are in the export section below.
Four things to check in Suriname.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Suriname below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Suriname requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Suriname.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Suriname, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Suriname, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Suriname.
The energy market in Suriname, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 9 October 2026.
On this page22 sections
Suriname’s power sector is organised under two laws of 2016: the Electricity Act (Elektriciteitswet 2016) and the Energy Authority Suriname Act. The state-owned N.V. Energiebedrijven Suriname (EBS) generates, transmits, distributes and sells electricity, and the Electricity Act makes it the single buyer for the national grid. The Energie Autoriteit Suriname (EAS), operational since the fourth quarter of 2020, supervises the sector, prepares the Electricity Sector Plan (ESP) and advises government. Tariffs themselves are set by the government by state decree, not by the regulator.
There is no single national grid. EBS runs several separate systems: EPAR, which serves Paramaribo and the surrounding districts and carries most of the load; ENIC around Nieuw Nickerie in the west; and smaller district systems such as Albina, Moengo, Coronie and Wageningen. More than a hundred interior villages are supplied by small diesel sets run by the ministry responsible for energy rather than EBS. Most electricity comes from the 189 MW Afobaka hydropower station and heavy-fuel-oil plants owned by EBS and by Staatsolie Power Company Suriname (SPCS).
Households pay a fixed monthly charge plus a rising block tariff per kWh. Prices have been heavily subsidised. Large tariff increases from March 2024 and monthly adjustments for fuel and the exchange rate have narrowed, but not closed, the gap between cost and price. Customers may install solar panels or small wind turbines for their own use and offset exported energy against their consumption. EBS is preparing the country’s first competitive tenders for utility-scale solar.
Energy snapshot.
Headline figures for electricity in Suriname. Each shows its data year and links to its source.
- Population639,850 peopleSource 12025
- Households140,367 householdsSource 232012
- Average household size3.83 people/householdSource 232012
- Electricity use per household4,540 kWh/yrSource 172024
- Household price (SRD)2.27 SRD/kWhSource 17Nov 2024
- Household price (EUR)0.054 EUR/kWhSource 6Nov 2024
- Renewable electricity share52.9%Source 42024
- Solar capacity0.036 GWSource 52025
- Wind capacityNot identified from a reliable public source.
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Single buyer
- Homes can export to the grid
- Yes
- Home equipment in grid services
- No
- Regulator
- Energie Autoriteit Suriname (EAS); tariffs set by government state decree
- System operator
- N.V. Energiebedrijven Suriname (EBS), which operates the EPAR, ENIC and district grids
- Distribution networks
- Single state-owned utility (EBS) for all grid-connected customers; interior villages supplied by government-run diesel systems
- Currency
- Surinamese dollar (SRD)
- Voltage and frequency
- 127 V single-phase / 220 V two- and three-phase, 60 Hz
Electricity prices in Suriname.
- Household price (SRD)
- 2.27 SRD/kWh (Nov 2024)Source 17Average tariff per kWh paid by all household customers in November 2024 (EAS table 25), against an average supply cost of SRD 4.05/kWh. Includes the fixed charge spread over consumption. For consumption from December 2024, the published household energy rates are SRD 1.971 (0–400 kWh/month), 2.850 (401–900), 3.330 (901–1,500) and 4.680 (above 1,500), plus a fixed charge of SRD 211.78 a month for a single-phase connection (EBS). No VAT is shown separately on the published tariff.
- Household price (EUR)
- 0.054 EUR/kWh (Nov 2024)Source 6Derived: SRD 2.27/kWh divided by SRD 42.2065 per euro, the midpoint of the Central Bank of Suriname’s weighted average giral buying (41.816) and selling (42.597) euro rates on 9 October 2026. The Surinamese dollar has depreciated sharply since 2024, so this converts a 2024 tariff at a 2026 rate.
- Typical annual electricity bill
- 11,490 SRD/yr (Dec 2024 tariffs)Source 7Derived illustration: a single-phase household using 4,540 kWh a year (about 378 kWh a month, all in the first block at SRD 1.971/kWh) plus the SRD 211.78 monthly fixed charge, giving about SRD 957 a month. This excludes any subject subsidy and later monthly fuel and exchange-rate adjustments. About €272 at the October 2026 central-bank rate.
Household electricity in Suriname has long been priced well below cost. EAS reports that in November 2024 households paid an average of SRD 2.27 per kWh while the average cost of supply was SRD 4.05, a gap of about 44%. Single-phase households, who are 58% of household connections, paid the least (SRD 1.88). Small business customers paid more than cost (about SRD 5.34), cross-subsidising households.
Reform since 2024
State Decree 2024 no. 41 raised tariffs from 1 March 2024. Household energy rates rose by 40%, followed by 7% increases every two months, and the top block above 1,500 kWh moved to a market-based rate. The decree also introduced a fuel clause, adjusted at the start of each quarter, and linked tariffs to the central bank’s average US dollar selling rate. Under a later agreement between government and the trade unions, the kWh rate is now set monthly, based on the previous month’s weighted average exchange rate and Staatsolie’s fuel price. The first household block rose from SRD 1.47 in October 2024 to SRD 1.97 in December 2024.
Why costs are high
Cost depends heavily on rainfall. When the Brokopondo reservoir is low, EBS has to run more heavy-fuel-oil generation. EAS puts the cost of thermal energy at an average of about US 16 cents per kWh, against about US 2 cents for hydro. Government budgeted SRD 800 million for electricity subsidy in 2024 but spent SRD 3.996 billion. EAS attributes the overrun to persistent drought, rising consumption and exchange-rate movements.
Connection charges
A new single-phase household connection (1×25 A, 3 kVA) costs SRD 5,000. Larger connections are priced at actual cost, and EBS may also require a deposit based on connected capacity. EAS is funded by a levy of SRD 0.01 per kWh on the electricity tariff.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | All grid-connected households pay the EBS household tariff set by state decree: a monthly fixed charge by connection type (SRD 211.78 single-phase, 293.97 two-phase, 349.13 three-phase) plus a rising block charge per kWh. For consumption from December 2024 the blocks are SRD 1.971 (0–400 kWh/month), 2.850 (401–900), 3.330 (901–1,500) and 4.680 above 1,500 kWh. The minimum bill is the fixed charge. |
| Other | Yes | Subject subsidy: under the subsidy decree, households received a fixed monthly discount by consumption band. From March 2024 this was SRD 85 for up to 150 kWh, rising to SRD 400 for 501–900 kWh a month (EAS). Social and religious organisations registered with EAS as vulnerable customers receive a 50% discount on their monthly bill. |
| Prepayment | Unknown | State Decree 2024 no. 41 provides for prepaid electricity for household and non-household customers (ESP Strategic Plan). No public information on availability from EBS was identified. |
| Time-of-use | Limited | Only large non-household and high-voltage customers have separate high and low energy rates (SRD 2.664 and 1.785/kWh from March 2024). Households have no time-of-use option. The ESP recommends introducing time-of-use tariffs. |
| Dynamic | No | There is no wholesale market or spot-linked retail price. Energy rates are adjusted periodically for fuel prices and the central-bank exchange rate. |
Household prices compared with neighbouring countries (EUR per kWh).
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- 4,540 kWh/yr (2024)Source 17Derived: 712,262 MWh of household consumption on EBS networks from January to November 2024, divided by an average of 171,144 household connections over those months (4,162 kWh), then multiplied by 12/11 to give a yearly figure. All figures are EBS data published by EAS. This is per household connection.
- Average daily use per household
- 12.4 kWh/day (2024)Source 17Derived: 4,540 kWh a year per household connection divided by 365.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- Not identified from a reliable public source.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- 1.5 % of households (2012)Source 23Census 8: main cooking fuel was propane gas for 82.3% of households, wood or charcoal for 11.4% and electricity for 1.5%.
An average EBS household connection used about 380 kWh a month in 2024, high for the region. Household consumption rose through the second half of the year, from 61,484 MWh in July to 71,649 MWh in November 2024. Households account for about 89% of EBS connections and 53% of EBS sales (EAS, November 2024).
Cooling is the main reason for high and rising demand. EAS names economic growth, increasing electrification and higher temperatures that require more cooling, while dry seasons reduce hydro output. Cooking is mostly done with propane gas, which EBS distributes through its subsidiary OGANE.
Because households pay low rates in the first block (up to 400 kWh a month), the price signal for efficiency is weak. The ESP notes that most refrigerators and freezers in use are of standard efficiency and that no solar water heaters have been adopted.
Housing and households.
- Dwellings
- 134,329 dwellings (2012)Source 23Occupied dwellings (woonverblijven) in Census 8.
- Owner-occupied
- 67.7% (2012)Source 23Dwellings owned by a household member (90,985). A further 0.8% were hire-purchase (huurkoop), and 14.6% were classed as “other”.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- 84.5% (2012)Source 23Self-contained private dwellings (zelfstandig woonverblijf – privé woning), 113,512 of 134,329.
- Apartments and flats
- Not identified from a reliable public source.
- Urban population
- 65.8% (2025)Source 2
Most Surinamese live in detached, self-contained houses, usually on their own plot, and about two-thirds of dwellings are owner-occupied. Population is concentrated on the coastal strip around Paramaribo, Wanica and Commewijne, which is served by the EPAR grid. In 2012, 111,699 dwellings were lit by electricity directly from EBS, 8,143 from government-run systems and 4,330 through a neighbour’s connection.
The interior is home to Indigenous and Maroon communities, mostly reached by river or air. Their villages are supplied by small diesel generators that run for 4 to 6 hours a day. The ministry responsible for energy owns these systems and provides the service free of charge. Detached houses with their own roofs make rooftop solar physically straightforward, but the low first-block tariff limits the savings.
How the grid works in Suriname.
- TransmissionN.V. Energiebedrijven Suriname (EBS)
- DistributionSingle state-owned utility (EBS) for all grid-connected customers; interior villages supplied by government-run diesel systems
- MeteringEBS
- Supply1 or more retail suppliers
Physically, Suriname’s grid is a set of islands. EPAR is by far the largest system, with about 488 MW of installed capacity in 2023: Afobaka hydro (189 MW), the SPCS heavy-fuel-oil plant (96 MW), and EBS’s DPP1 (73 MW) and DPP2 (130 MW) diesel and heavy-fuel-oil plants in Paramaribo. EPAR peaked at about 250 MW in 2023 and served about 171,000 customers. ENIC in Nickerie has a 25.6 MW thermal plant and a 2 MW solar-battery hybrid plant. Six smaller district systems run mainly on diesel and heavy fuel oil, some with solar hybrids such as the 500 kW plant at Pokigron.
Afobaka’s output depends on the Brokopondo reservoir. Its effective capacity fell from 138 MW in 2022–23 to 93 MW in 2024 during drought, forcing more oil-fired generation. In 2023, transmission losses on EPAR were about 5.7% and technical losses in distribution about 6.5% (ESP Strategic Plan).
Commercially, power flows through one buyer. SPCS, a subsidiary of the state oil company Staatsolie, produces about three-quarters of Suriname’s electricity and sells most of it to EBS under power purchase agreements. EBS adds its own generation and sells to all grid-connected customers at state-decreed tariffs. Government covers the shortfall with subsidy. The Rosebel gold mine is supplied from the EPAR high-voltage network under separate arrangements with the government.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry responsible for energy (Ministry of Natural Resources at the time of the 2025 ESP) | Sets energy policy and runs rural village electrification through its Dienst Electrificatie Voorziening (DEV). Electricity tariffs are fixed by state decree. |
| Regulator | Energie Autoriteit Suriname (EAS) | Independent supervisory body under the 2016 EAS Act. It prepares the Electricity Sector Plan, supervises compliance with the Electricity Act and IPP tenders, publishes quarterly supply statistics, issues the Grid Code and regulatory accounting rules, and administers the vulnerable-customer discount. It cannot set tariffs itself. |
| System operator | N.V. Energiebedrijven Suriname (EBS) | Wholly state-owned. EBS dispatches and operates the EPAR and ENIC grids and the district systems, owns most transmission (161 kV and 33 kV, with a new 110 kV line under construction) and all distribution, and is the legal single buyer and retailer. Its general terms describe separate internal units for buyer and supplier (Koper & Leverancier) and network operator (Netbeheerder). |
| DSO | EBS (network operator unit) | The only distributor for grid-connected customers. It connects customers, installs and owns meters, reads them monthly and approves self-generator connections. |
| Supplier | EBS | Sole retail supplier. IPPs may not sell directly to end customers under the Electricity Act. |
| Metering | EBS | EBS decides on the meter type, owns the meter and reads it monthly by billing cycle. Customers can also submit readings by SMS, phone or the MyAccount portal. |
Compared with the UK system.
| UK concept | Suriname equivalent | How it works |
|---|---|---|
| DNO | EBS (network operator) | One state utility owns and runs all distribution networks for grid-connected customers, in several separate systems (EPAR, ENIC and district grids). There are no regional network companies. |
| National Grid/NESO | EBS (transmission and dispatch) | EBS owns most 161 kV and 33 kV transmission and dispatches generation from its own plants, SPCS and the Afobaka hydro plant. There is no independent system operator and no interconnected national grid. EPAR and ENIC are separate. |
| MPAN | Aansluitnummer (connection number) | Every EBS connection has an aansluitnummer, used to report meter readings, request bills and transfer or cancel a connection. It identifies the connection, not the person. EBS publishes no fixed national format like the MPAN. |
| MPRN | No equivalent identified | EBS also handles gas connections and distributes propane through its subsidiary OGANE. No separate national gas supply-point identifier was identified. |
| Meter operator | EBS | Meters are installed, owned and maintained by EBS. There is no competitive metering market. |
| Supplier | EBS (single retailer) | Households cannot switch supplier. EBS bills every grid-connected customer at government-set tariffs. |
| Smart-meter infrastructure | None identified | There is no DCC-style communications network or national smart-meter programme. Meters are read monthly, and self-generators must allow EBS to read generation and consumption data online where they have internet access. |
How a supply point is identified.
000482917
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Aansluitnummer |
| Who issues it? | N.V. Energiebedrijven Suriname (EBS) |
| Format | A numeric connection number assigned by EBS. EBS’s own example (“Rek 000123456”, for requesting a bill by SMS) shows nine digits with leading zeros. A separate klantnummer (customer number) identifies the account holder. |
| Length | 9 digits in EBS’s published example; no formal specification published |
| Stays with the property when you switch supplier? | Yes |
| Where to find it | On the EBS bill and in the EBS MyAccount portal. Customers need it to submit meter readings and request bills. |
| Electronic access | Customers can view open bills without logging in by entering the connection number on the EBS website, or log in to MyAccount with the connection and customer numbers. Meter readings can be sent by SMS to 1222 in the format “Meter [aansluitnummer] [reading] [day] [month]”, or by phone (175). |
| Third-party access | No regulated third-party data access exists. Self-generators must give EBS written consent to read generation and consumption data over the internet, or on site where there is no internet connection. |
| Who keeps the register | EBS customer and connection database. No independent registry or data hub exists. |
| Register scope | National |
An EBS connection is identified by two numbers. The aansluitnummer belongs to the physical connection and meter. The klantnummer belongs to the customer. EBS uses the connection number for routine self-service, such as SMS meter readings and bill requests, and asks for both numbers for phone and MyAccount access.
The connection stays with the property. When a home is sold or let to a new occupant, the customer asks for an overschrijving (transfer). The connection stays live and only the account holder changes. The new occupant provides proof of title (a mortgage extract from GLIS no older than 30 days, a purchase agreement or a deed of sale), valid ID and a recent photo of the meter showing the meter number and reading. Tenants also sign a bank authorisation and a liability declaration. There must be no unpaid bills, and EBS sets a deposit based on the connected capacity.
A cancellation (opzegging) closes the connection permanently. EBS removes the meter, or cuts the supply at the pole if it cannot reach the meter, and asks for the connection or customer number. A connection that has been inactive for more than a year needs a control inspection (controlekeuring) before it is reconnected.
Meters are read monthly. Each connection has a cycle code that fixes the reading day (between the 2nd and 22nd of the month) and the bill date (12th, 18th, 22nd or 28th). Where readers cannot get access, EBS asks customers to submit the reading themselves. For digital meters, customers read register 1.8.0 in kWh and ignore decimals.
Because EBS is the only distributor, supplier and meter owner, there is no national registry or switching process. The connection number is administered entirely within EBS’s own customer system. The interior village systems run by the ministry are outside it.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Yes |
| Net metering | Yes |
| Net billing | Limited |
| How exported electricity is paid | Exported kWh are netted against consumption under EBS’s self-generator terms, with surplus carried forward monthly and reset to zero at the annual settlement. A 2021 tariff decree specifies a feed-back rate of 115% of the customer’s energy rate, but EBS had not updated its 2018 terms as of May 2024. |
| Who can export? | Any EBS customer generating renewable electricity, mainly for their own use. EBS accepts solar PV and wind turbines. |
| Is there a size limit? | EBS currently accepts systems up to 63 A without further study. Larger applications need an EBS grid analysis, and the customer pays for any reinforcement. Under the Electricity Act, exports are credited only up to the customer’s total annual consumption. |
| How is surplus handled? | Under EBS’s terms, monthly surplus kWh are carried to the next bill. At the annual settlement, in the first month of the new financial year, any remaining surplus is reset to 0 kWh without payment. |
| What meter is used? | A bidirectional meter supplied, owned and maintained by EBS. The customer must allow EBS to read generation and consumption data remotely where internet access exists. |
| Are the rules final? | No. EBS describes its arrangements as provisional until EAS sets technical requirements, connection costs and compensation in the Electricity Sector Plan. The 2025 ESP proposes a feed-in tariff based on avoided generation cost and a cap on distributed generation. |
Connecting a home system.
- Choose an installer from EBS’s list of recognised installers.
- The installer submits the self-generator application (digital or paper) with a power of attorney and the system design.
- The inspection body (keuringsinstantie) checks that the design meets EBS’s requirements and reports in writing. For systems above 63 A, EBS also studies the effect on the grid.
- EBS sets the capacity that may be connected and issues a quote for connection costs, including any grid reinforcement.
- After the installation passes inspection, the customer signs the feed-back agreement and pays the costs. EBS installs a bidirectional meter and monitors the connection to the grid.
The Electricity Act 2016 allows customers to generate renewable electricity for their own use and to feed surplus into the national grid, to be offset against what they take from it. EBS implements this through its general and connection terms for self-generators (Algemene- en Aansluitvoorwaarden voor Zelfopwekkers) of April 2018. A customer must use an EBS-recognised installer, and an independent inspection body set up by state decree checks the design and the installation.
On paper there are two compensation rules. EBS’s terms use kWh netting, with surplus carried forward each month and written off at the end of the financial year. The Tariff Methodologies and Subsidy State Decree (no. 88 of 2021) provides for net billing at 115% of the customer’s energy rate, and EAS’s March 2024 tariff summary repeats this. The ESP Strategic Plan noted in 2025 that EBS had not yet updated its terms. Anyone installing should confirm with EBS which method will apply.
Because household energy rates have been far below cost, exports and self-consumption have been worth little to most homes. The 2024 tariff reforms raise the value of each kWh, especially for homes using more than 900 kWh a month.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity (utility-scale solar or wind) | Licence required. Under Article 21 of the Electricity Act, new utility-scale solar and wind capacity must be procured by EBS through a public tender. The winning bidder is granted a licence to build, operate and maintain the plant (Art. 21(4)) and signs a PPA with EBS (Art. 21(5)). | Government under the Electricity Act 2016; tender run by EBS and supervised by EAS | New fossil-fuel and hydropower capacity is reserved for state-owned companies. Bidding procedures were being finalised by state decree for the first 10 MW solar tender. |
| Generate for own use (rooftop solar, small wind) | No generation licence. Requires an EBS self-generator agreement, a recognised installer and an inspection certificate. Systems above 63 A need an EBS grid study. | EBS; inspection body (keuringsinstantie) | Renewable sources only. |
| Store electricity | No specific licensing regime for batteries was identified. Batteries behind the meter are treated as part of the customer installation, and EBS terms cover only renewable generation linked to the grid. | — | The ESP expansion plan includes 3 MW of battery storage for EPAR by 2044. Tender documents consider solar-plus-storage products. |
| Export to the grid | Permitted for self-generators under the EBS feed-back agreement, credited up to annual consumption. IPPs export only under a PPA with EBS. | EBS | See export section. |
| Sell or supply to end customers | Not permitted for private producers. EBS is the single buyer and retailer, and IPPs cannot sell directly to final customers. | Electricity Act 2016 | The state may buy electricity itself and supply energy-intensive companies on special terms (Art. 10(3)). |
| Aggregate or operate a virtual power plant | No legal framework. Aggregation is not recognised. | — | No aggregator role exists in the Electricity Act. |
| Wholesale trading | No wholesale market. Power is bought bilaterally by EBS under PPAs. | — | SPCS and EBS generation is dispatched by EBS. |
| Balancing and grid services | Provided by EBS and contracted generators. There is no market for third-party balancing or ancillary services. | EBS | — |
| Remote control of customer assets | No framework. EBS terms give it only a right to read self-generator data and to require disconnection for safety. | EBS | — |
Suriname’s licensing is simple because almost everything sits with the state. The Electricity Act names EBS as the electricity company, single buyer and retailer, and reserves fossil-fuel and hydro generation for state-owned companies. Private investment enters through two routes: rooftop and small-scale renewable self-generation under EBS’s terms, and utility-scale solar or wind won in a competitive tender, which brings a production licence and a PPA with EBS.
The first tender, prepared with Inter-American Development Bank support (programme SU-L1055), is designed as 10 MW of solar PV split into two 5 MW projects in 2026. It is part of an ESP target of 50 MW of solar by 2026. EAS supervises the process. In September 2026 it introduced a standard pre-screening of unsolicited generation proposals against set criteria.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Balancing / reserves | No | — | No | EBS. Reserves come from EBS’s own thermal units and SPCS under PPAs. There is no open procurement of balancing or frequency services. |
| Demand response | No | — | No | No demand-response scheme was identified. Time-of-day rates apply only to large customers. |
There are no flexibility or capacity markets in Suriname, and no legal role for aggregators. The system’s flexibility comes from the Afobaka reservoir, which can store more than a year of inflows, and from EBS’s and SPCS’s oil-fired engines.
EAS has called for reliability standards, reserve-capacity requirements and performance monitoring to be written into regulation after supply problems in 2026. The ESP’s tariff recommendations, including time-of-use energy rates and a feed-in tariff based on avoided cost, are the first steps that would give distributed resources a price signal.
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | No smart-meter programme identified |
| Reading interval | Monthly manual reading |
| Meter owner | EBS |
| Reading | Monthly by billing cycle; customer self-reading by SMS, phone or web |
| Self-generators | Bidirectional meter; remote data reading with consent |
| Prepayment | Provided for by State Decree 2024 no. 41; availability not confirmed |
EBS reads meters monthly by billing cycle. Customers can also submit readings themselves by SMS to 1222, by phone on 175, on the website or through MyAccount. Some meters are digital and display OBIS register 1.8.0. No programme for remote-read smart meters or a central data system was identified.
The ESP’s Energy Information Management System is a regulator-side data platform for sector indicators such as outages, losses and generation, not customer metering.
Renewable electricity.
Electricity generation mix (2024).
- Hydropower: 51.7%
- Oil: 46%
- Gas: 1.1%
- Solar: 0.6%
- Bioenergy: 0.6%
- Renewable electricity share
- 52.9% (2024)Source 4Share of generation (Ember via Our World in Data): hydropower 51.72%, solar 0.57% and bioenergy 0.57%. EAS data for EBS and SPCS generation from January to November 2024 give a lower hydro share of about 47.5% (849,706 of 1,789,605 MWh), reflecting drought at the Brokopondo reservoir. Suriname has no electricity imports.
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- 23.3 MW (2025)Source 5Derived: 35.817 MW (2025) minus 12.552 MW (2024), IRENA data via Our World in Data.
- Hydropower (Afobaka)
- 189 MW (2023)Source 20Six Kaplan units. Effective capacity was 93 MW in 2024 because of low reservoir levels.
- Solar PV
- 35.8 MW (2025)Source 5
- Wind
- Not identified from a reliable public source.
Targets.
- More than 35% of electricity generation from renewable sources by 2030 (Nationally Determined Contribution, cited in the 2025 ESP).
- 50 MW of solar PV by 2026 under the ESP and Generation Expansion Plan, starting with a 10 MW tender.
- EPAR 20-year expansion plan to 2044: 1,301 MW of new capacity, including 396 MW of solar, 840 MW of simple- and combined-cycle gas plant, 62 MW of engines and 3 MW of batteries.
- Government expects solar to provide 25% of generation by 2040 (ESP Strategic Plan).
Hydropower has long made Suriname’s electricity comparatively low-carbon. Afobaka is owned and operated by SPCS (ESP Strategic Plan). In wet years it supplies most of EPAR’s energy (63% in 2023), but recent droughts have cut its output and pushed oil-fired generation close to half of the total.
Solar has started to grow from a very small base. Early projects include a 5 MW plant built in 2014 for the Rosebel gold mine, hybrid solar-diesel systems in Nickerie, Coronie, Atjoni and Pokigron, and solar mini-grids for interior villages supported by the IDB and the EU. The coastal strip yields about 4.1 kWh per kWp a day, modest by tropical standards because of cloud cover.
Offshore oil and gas development (the US$10.5 billion Block 58 project) is expected to drive up demand. The 2025 ESP plans to use natural gas as a transition fuel alongside more solar.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
Storage plays a small role in planning so far. Consultants preparing the renewable tenders described EPAR as an energy-constrained rather than capacity-constrained system: the Afobaka reservoir lets it meet the evening peak with relative ease. Batteries are therefore considered mainly for peak shaving and as part of combined solar-plus-storage products, rather than for price arbitrage.
Storage projects.
- Bryan Overeem hybrid solar PV–battery plant (Nickerie): 2 MW solar plant with battery storage supplying the ENIC system.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| N.V. Energiebedrijven Suriname (EBS) | 100% of grid-connected retail customers (about 193,500 connections, Nov 2024) | No | Limited | No | Yes |
EBS is the only retail supplier. In November 2024 it had 172,318 household connections, 17,753 non-household connections and 3,482 large customers (EAS). Households cannot choose another supplier or a renewable tariff. Suriname has been approved for I-REC renewable energy certificate issuance, which large buyers can use to document renewable supply.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Energie Autoriteit Suriname (EAS) | Regulator | Energy sector regulator and planner | Publishes the Electricity Sector Plan, quarterly supply statistics, tariff information, the Grid Code and regulatory accounting rules. |
| N.V. Energiebedrijven Suriname (EBS) | Distribution | State utility: generation, transmission, distribution and supply | Handles connections, tariffs, self-generator applications and the installer list. |
| Staatsolie Power Company Suriname (SPCS) | Government | Largest generator (Afobaka hydro and thermal plant) | Produces about three-quarters of Suriname’s electricity and sells it to EBS. |
| Algemeen Bureau voor de Statistiek (ABS) | Government | National statistics office | Census data on households, dwellings and cooking fuel. Census 9 fieldwork took place from late 2024. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Grid connection | Surinamese Grid Code (2026) | EAS | Published by EAS in 2026. The ESP describes the planning and operation codes for connecting generating units and customer installations. |
| Self-generation | EBS Algemene- en Aansluitvoorwaarden voor Zelfopwekkers (4 April 2018) | EBS | Covers application, inspection, coupling through an automatic circuit breaker, metering, netting and disconnection. |
| Installation inspection | Inspection certificate from the keuringsinstantie | Inspection body established by state decree | Inspects customer and generation installations before connection, and again after a dormant period of more than a year. |
| Installer recognition | EBS list of recognised installers | EBS | New connections and self-generator applications must go through a recognised installer. |
| Inverters / anti-islanding | No national product standard identified | — | EBS approves the design case by case through the inspection body. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| EBS self-generator approval | Yes | National | Application through a recognised installer, design check, inspection certificate, connection quote and signed feed-back agreement. |
| Grid impact study | Limited | National | Required for systems above 63 A. The applicant pays any reinforcement costs. |
| Generation licence | Limited | National | Only for licensed producers selling to EBS, normally via the Article 21 tender. |
| Building permission for rooftop PV | Unknown | Local | No specific rule for rooftop solar was identified. |
For a household, the main hurdle is EBS approval. The installer prepares the application and design, the inspection body checks it, and EBS replaces the meter before the system may be coupled. EBS monitors the coupling and can disconnect a system that is altered or enlarged without approval.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Net metering for self-generators | Active | Net metering | Exported renewable electricity is offset against consumption with monthly carry-forward and an annual reset. A decree also refers to a feed-back rate of 115% of the energy rate. | — |
| Subject subsidy for household electricity | Active | Consumption subsidy | Fixed monthly discounts for households by consumption band (SRD 85–400 from March 2024), being phased down as tariffs move towards cost. | Since 2021 (amended 2023 and 2024) |
| Vulnerable-customer discount | Active | Bill discount | 50% discount on the monthly electricity bill for social and religious organisations approved by EAS. | — |
Data and connectivity.
- Fixed broadband
- 18.8 fixed subscriptions per 100 people (2024)Source 3
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
Fixed broadband reached 18.75 subscriptions per 100 people in 2024. EBS’s self-generator terms already assume that generation and consumption data can be read over the customer’s internet connection, with on-site reading as the fallback.
Grid conditions.
- National peak demand
- 0.25 GW (2023)Source 20EPAR system only. ENIC peaked at 16 MW and the rural district systems together at about 5.4 MW.
- Annual electricity demand
- 1.464 TWh (2023)Source 20Net energy injected into the EPAR system, including supply to the Rosebel gold mine (about 220 GWh a year on average from 2019 to 2023).
- Generation capacity
- 0.488 GW (2023)Source 20EPAR only: Afobaka 189 MW, DPP2 130 MW, SPCS thermal 96 MW, DPP1 73 MW. ENIC adds 27.6 MW.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
Supply is tight. EAS said in August 2026 that rising demand from economic growth, electrification and cooling, combined with lower hydro output in dry periods, amounted to a structural energy crisis. It called for the Electricity Sector Plan to be turned into binding reliability standards, reserve-capacity requirements and maintenance obligations.
EBS is building a 110 kV line from the 5e Rijweg substation to a new substation (OSD2) at Toevluchtweg, reported 70% complete in February 2025, and a line from Paramaribo to Albina.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Monthly tariff indexation | Current | Since late 2024 | Household energy rates are adjusted monthly for the central-bank exchange rate and Staatsolie’s fuel price, following State Decree 2024 no. 41 and a government–union agreement. |
| Electricity Sector Plan 2025 | Current | May 2025 | Strategic, technical and regulatory plans covering demand forecasts, expansion of EPAR and ENIC, rural electrification, tariff methodology, single-buyer procedures and a feed-in tariff method for distributed generation. |
| Grid Code and regulatory accounting rules | Current | 2026 | Published by EAS in June 2026. |
| First utility-scale solar tender | Upcoming | 2026 | 10 MW of solar PV in two 5 MW projects, procured by EBS under Article 21 with EAS oversight, toward a 50 MW solar target. |
| Feed-in tariff for distributed generation | Upcoming | Not scheduled | The ESP recommends a feed-in tariff based on avoided generation cost and a cap on distributed generation. EBS terms remain provisional until then. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Low | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | Medium | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | Medium | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Low | Net metering exists, but solar capacity was only about 36 MW in 2025 (IRENA). There is no count of rooftop systems, and subsidised first-block tariffs limit savings. |
| Distributed energy market | Low | A single-buyer model with no private retail sales. Self-generation is allowed only for renewables mainly for own use, under provisional EBS terms. |
| Grid flexibility market | Low | No wholesale, balancing or demand-response markets, and no aggregator role. |
| Energy storage adoption | Low | Only one small hybrid solar-battery plant identified. The expansion plan includes 3 MW of batteries by 2044. |
| Renewable growth environment | Medium | Solar capacity nearly tripled in 2025 (IRENA). A 50 MW solar target and the first tenders are planned, but the hydro share fell in drought years. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 24 sources
- Population, total – Suriname (SP.POP.TOTL). World Bank, 2025. accessed 9 October 2026.
- Urban population (% of total population) – Suriname. World Bank, 2025. accessed 9 October 2026.
- Fixed broadband subscriptions (per 100 people) – Suriname. World Bank, 2024. accessed 9 October 2026.
- Share of electricity production by source – Suriname (Ember). Our World in Data / Ember, 2024. accessed 9 October 2026.
- Installed solar PV capacity – Suriname (IRENA). Our World in Data / IRENA, 2025. accessed 9 October 2026.
- Dagelijkse publicaties – gewogen gemiddelde wisselkoersen. Centrale Bank van Suriname, 2026. accessed 9 October 2026.
- Stroomtarieven. N.V. Energiebedrijven Suriname, 2024. accessed 9 October 2026.
- Zelf opwekken en terugleveren. N.V. Energiebedrijven Suriname. accessed 9 October 2026.
- Algemene- en Aansluitvoorwaarden van de N.V. EBS voor Zelfopwekkers. N.V. Energiebedrijven Suriname, 2018. accessed 9 October 2026.
- Aansluitingen aanvragen. N.V. Energiebedrijven Suriname. accessed 9 October 2026.
- Opzegging & overschrijving. N.V. Energiebedrijven Suriname. accessed 9 October 2026.
- Meterstand doorgeven. N.V. Energiebedrijven Suriname. accessed 9 October 2026.
- Rekening bekijken / opvragen. N.V. Energiebedrijven Suriname. accessed 9 October 2026.
- Nieuws – voortgang 110 kV transmissielijn. N.V. Energiebedrijven Suriname, 2025. accessed 9 October 2026.
- Energie Autoriteit Suriname – kwetsbare afnemers en tarieven. Energie Autoriteit Suriname. accessed 9 October 2026.
- Publicaties (Electricity Act, ESP, Grid Code, tariff decrees). Energie Autoriteit Suriname. accessed 9 October 2026.
- Status Elektriciteitsvoorziening in Suriname, januari–november 2024. Energie Autoriteit Suriname, 2025. accessed 9 October 2026.
- Energiecrisis onderstreept noodzaak van structurele regulering en uitvoering Elektriciteit Sector Plan. Energie Autoriteit Suriname, 2026. accessed 9 October 2026.
- EAS wil meer inzicht in voorstellen voor uitbreiding van elektriciteitsvoorziening. Energie Autoriteit Suriname, 2026. accessed 9 October 2026.
- Electricity Sector Plan – Vol. I Strategic Plan. Energie Autoriteit Suriname (prepared by Castalia), 2025. accessed 9 October 2026.
- Overview of the Suriname Electricity Sector Plan (ESP). Energie Autoriteit Suriname, 2025. accessed 9 October 2026.
- Consulting Services to Support Renewable Energy (RE) Tenders in Suriname (SU-L1055). Energie Autoriteit Suriname / MRC Consultants and PSR, 2026. accessed 9 October 2026.
- Census 8 (2012) Volume 3 – Huishoudens, Gezinnen en Woonverblijven. Algemeen Bureau voor de Statistiek Suriname, 2012. accessed 9 October 2026.
- Census 9. Algemeen Bureau voor de Statistiek Suriname, 2024. accessed 9 October 2026.
Questions about energy in Suriname.
For consumption from December 2024, EBS charges households SRD 1.971 per kWh for the first 400 kWh a month, rising to SRD 4.680 above 1,500 kWh, plus a fixed charge from SRD 211.78 a month. In November 2024 households paid an average of SRD 2.27 per kWh, against a supply cost of SRD 4.05 (EAS). Rates are now adjusted monthly for fuel and exchange rates.
No. EBS is the single buyer and retailer for all grid-connected customers under the Electricity Act 2016.
Yes. Customers can connect renewable systems up to 63 A, or larger after an EBS grid study, through a recognised installer. Exports are offset against consumption, with surplus carried forward monthly and written off at the annual settlement. A tariff decree also provides for 115% of the energy rate, so check the current method with EBS.
The EBS aansluitnummer (connection number). It identifies the physical connection, stays with the property when ownership changes, and is used for meter readings and bills. A separate klantnummer identifies the customer.
The Energie Autoriteit Suriname (EAS) supervises the sector and prepares the Electricity Sector Plan. Tariffs are set by the government by state decree.
About 53% in 2024, almost all from the Afobaka hydropower station (Ember). Drought has reduced hydro output, and oil-fired plants supply most of the rest.