How electricity works in Finland.
Finland electricity market 2026: Energiavirasto, Fingrid, 77 DSOs, Fingrid Datahub and 18-digit GSRN, 15-minute metering, solar netting, prices and licensing.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Euro (EUR) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Finland energy at a glance.
Key figures for households in Finland. Each one links to its source on the full overview below.
Electricity price.
0.225 EUR per kWh for households, including taxes. Figures for 2025-H2.
Household use.
7,791 kWh a year for a typical household. Figures for 2024.
Renewable share.
57% of electricity from renewable sources. Figures for 2025.
Selling back to the grid.
Can homes export electricity? Yes. Details are in the export section below.
Four things to check in Finland.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Finland below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Finland requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Finland.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Finland, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Finland, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Finland.
The energy market in Finland, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 1 October 2026.
On this page22 sections
Finland has a fully liberalised electricity market. Households choose their electricity retailer (sähkönmyyjä) freely, while the local distribution system operator (jakeluverkonhaltija) that owns the wires and the meter is a regulated monopoly. The Energy Authority (Energiavirasto) regulates network pricing methods and supervises the market. Fingrid Oyj, majority-owned by the State, owns and operates the national transmission grid (kantaverkko). Mainland Finland is a single bidding zone (FI) in the Nordic market. Since February 2022, all retail market data has run through Datahub, a central data exchange operated by Fingrid’s subsidiary Fingrid Datahub Oy.
Electricity generation is almost entirely fossil-free. Energiateollisuus (Finnish Energy) preliminary statistics for 2025 show 79 TWh of domestic generation: nuclear 39.6%, wind 27.9%, hydro 15.6% and biomass 11.3%, with solar at 1.2%. Consumption was 85 TWh, and net imports covered the difference. Wind capacity reached 9.4 GW at the end of 2025 and has overtaken hydro as the second-largest source after nuclear, helped by the Olkiluoto 3 reactor, commissioned in April 2023.
A household bill has three parts: the retailer’s energy price, the distribution charge, and taxes (electricity tax and 25.5% VAT). Rooftop solar owners can sell their surplus to a retailer at spot-linked prices. Since 1 January 2023, consumption and production at sites of up to 100 kVA have been netted within each metering period. Finland has no feed-in tariff for small producers. Support comes mainly through the household tax deduction for installation labour.
Energy snapshot.
Headline figures for electricity in Finland. Each shows its data year and links to its source.
- Population5,652,881 peopleSource 131 Dec 2025
- Households2,869,879 household-dwelling unitsSource 2end 2025
- Average household size1.92 people/householdSource 2end 2025
- Electricity use per household7,791 kWh/yrSource 32024
- Household price (EUR)0.225 EUR/kWhSource 72025-H2
- Renewable electricity share57%Source 82025
- Solar capacity1.6 GWSource 10end 2025
- Wind capacity9.433 GWSource 8end 2025
- Energy storage capacity1.05 GWSource 11Feb 2026
- Smart-meter share99%Source 92025
- Market structure
- Fully liberalised
- Homes can export to the grid
- Yes
- Home equipment in grid services
- Yes
- Regulator
- Energiavirasto (Energy Authority)
- System operator
- Fingrid Oyj
- Distribution networks
- 77 distribution system operators with local monopoly licences, from Caruna (about 746,000 customers) and Elenia (443,200) to small municipal and cooperative companies, plus 9 high-voltage-only DSOs
- Currency
- Euro (EUR)
- Voltage and frequency
- 230 V / 50 Hz
Electricity prices in Finland.
- Household price (EUR)
- 0.225 EUR/kWh (2025-H2)Source 7Eurostat average household price, all taxes and levies included, consumption band 2,500–4,999 kWh/yr.
- Typical annual electricity bill
- 1,012 EUR/yr (2025)Source 9Derived: the Energy Authority’s average price of 20.23 c/kWh for a typical household using 5,000 kWh a year (network charges 6.84 c, energy and supply margin 6.96 c, taxes 6.44 c) multiplied by 5,000 kWh. Fixed monthly network and retail fees are included in the average unit price.
Household price trend (EUR per kWh).Source 7
| 2019-H1 | 0.1734 EUR/kWh |
|---|---|
| 2019-H2 | 0.1783 EUR/kWh |
| 2020-H1 | 0.174 EUR/kWh |
| 2020-H2 | 0.1773 EUR/kWh |
| 2021-H1 | 0.1767 EUR/kWh |
| 2021-H2 | 0.184 EUR/kWh |
| 2022-H1 | 0.1934 EUR/kWh |
| 2022-H2 | 0.2474 EUR/kWh |
| 2023-H1 | 0.2557 EUR/kWh |
| 2023-H2 | 0.2403 EUR/kWh |
| 2024-H1 | 0.2489 EUR/kWh |
| 2024-H2 | 0.2319 EUR/kWh |
| 2025-H1 | 0.2276 EUR/kWh |
| 2025-H2 | 0.2254 EUR/kWh |
What a bill is made of
Finnish households usually receive two bills: one from the retailer for energy and one from the local DSO for the network service (sähkönsiirto). The DSO also collects electricity tax and the security-of-supply fee. For households, electricity tax class I is 2.24 c/kWh before VAT. The security-of-supply fee (huoltovarmuusmaksu) rose from 0.013 c/kWh to 0.085 c/kWh on 1 April 2026. VAT of 25.5% applies to the energy price, the network charge and the taxes. Industry, heat pumps and electric boilers in district heating, and professional greenhouses pay class II, at 0.05 c/kWh.
For a typical household using 5,000 kWh, the Energy Authority puts the 2025 average at 20.23 c/kWh: 6.84 c network, 6.96 c energy and supply margin, and 6.44 c taxes. Energiateollisuus, using Statistics Finland data, shows that for a larger household using 5,000–15,000 kWh in September 2025 the energy component was 37% of the bill, the network charge 30% and taxes 33%.
Network charges
DSOs set their own tariffs. The Energy Authority does not approve prices in advance. It confirms the methods used to calculate each operator’s reasonable return for four-year regulatory periods (2024–2027 and 2028–2031) and can order excess profits to be returned. The law limits network price rises to 8% in any rolling 12-month period. In January 2026, average distribution charges for a household using 5,000 kWh were 1.8% higher than a year earlier. Charges differ between DSOs, as each sets its own tariffs within the regulated return.
Trend
Eurostat’s household price rose from about EUR 0.17/kWh before 2022 to a peak of EUR 0.256/kWh in the first half of 2023, then eased to EUR 0.225/kWh in the second half of 2025, well below the EU average. Wholesale prices in 2025 were lower than before the energy crisis, but more volatile. The Energy Authority calculated an average daily spread of EUR 89.57/MWh between the highest and lowest hourly prices, which makes exchange-price contracts and flexible consumption more valuable.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Fixed | Yes | Fixed-term, fixed-price contracts, most often for one or two years, are the most common type: about 42% of retail customers at the end of 2025. |
| Variable | Yes | Open-ended (toistaiseksi voimassa oleva) contracts, which the customer can end with two weeks’ notice, made up about 24% of customers at the end of 2025. |
| Dynamic | Yes | Exchange-price (pörssisähkö) contracts pass through the Finnish day-ahead price plus a fixed margin. About 34% of customers had one at the end of 2025. Since 1 June 2023, retailers with more than 200,000 customers, and all suppliers of last resort, must offer them. Every nationwide retailer does. The day-ahead market has used 15-minute periods since 1 October 2025. |
| Time-of-use | Yes | Time-of-use pricing appears mainly in distribution tariffs. Many DSOs offer day/night (aikasiirto) and seasonal (kausisiirto) products alongside a flat general tariff. Oulun Energia’s 2026 network price list, for example, charges 2.69 c/kWh by day and 1.63 c/kWh at night, including VAT. Some retailers sell "consumption-effect" products that combine a fixed price with a time-dependent element. The Energy Authority’s comparison tool lists them as a separate category. |
| Regulated | No | There are no regulated retail tariffs: retailers set prices freely, and no authority approves them. Retailers with supplier-of-last-resort status must report their prices for small customers to the Energy Authority’s comparison tool and may not offer only dynamic contracts. |
| Prepayment | No | Prepayment meters are not used. Most customers are billed monthly or every two months on actual metered consumption. |
Household prices compared with neighbouring countries (EUR per kWh).
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- 7,791 kWh/yr (2024)Source 3Derived: 22,290 GWh of electricity used by households in 2024 (Statistics Finland, Energy consumption in households, all end uses including space heating, saunas and hot water) divided by 2,860,961 household-dwelling units at the end of 2024. Electrically heated detached houses use far more than this, flats far less.
- Average daily use per household
- 21.3 kWh/day (2024)Source 3Derived from 7,791 kWh/yr per household-dwelling unit (÷ 365).
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 15,037 kWh/person/yr (2025)Source 8Derived: total electricity consumption of 85 TWh in 2025 (all sectors, preliminary) divided by the population of 5,652,881 at the end of 2025. Industry used 42% of the total; housing and agriculture 28%.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- 351,744 plug-in cars (end 2025)Source 36164,705 battery electric and 187,039 plug-in hybrid cars in traffic use (Traficom data compiled by Technology Industries of Finland). Battery electric cars accounted for 43% of fleet renewal in 2025.
- Electric cooking
- Not identified from a reliable public source.
Household electricity use in Finland is driven by heating and the cold climate. Statistics Finland counts 22.3 TWh of household electricity use in 2024, including space heating, sauna stoves and hot water as well as appliances. Of 1.16 million detached and semi-detached houses in 2025, 493,673 (42.5%) listed electricity as their main heating source, more than any other source. Wood, oil and ground-source heat pumps account for most of the rest. Most blocks of flats are on district heating, so electricity use in flats is mainly lighting, appliances and the building’s sauna.
National demand peaks on cold winter mornings. Peak load in winter 2025–26 was 15.6 GW, in January 2026, although the Energy Authority notes that 933 MW of this came from electric boilers running on cheap windy-day power rather than from scarcity. Electric heating, hot-water storage and sauna heating make many Finnish houses well suited to load shifting, and many DSOs offer day/night and seasonal network tariffs that reward it.
Electric cars are growing quickly from a low base: 351,744 plug-in cars were in use at the end of 2025. The tax benefit for plug-in hybrid company cars ended at the end of 2025, and battery electric cars are expected to become the most common powertrain in new registrations in 2026.
Housing and households.
- Dwellings
- 3,261,390 dwellings (2025)Source 4All dwellings, including those not permanently occupied.
- Owner-occupied
- 61% (end 2022)Source 6Share of households living in owner-occupied dwellings (about 1.73 million). Flats are usually owned through shares in a housing company (asunto-osakeyhtiö), which owns the building and roof.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- 50% (end 2025)Source 2Derived: share of household-dwelling units living in one- and two-dwelling houses (1,056,590; 36.8%) plus terraced houses (378,827; 13.2%).
- Apartments and flats
- 48.6% (end 2025)Source 2Derived: 1,394,699 household-dwelling units in blocks of flats out of 2,869,879. 1.4% live in other buildings.
- Urban population
- 74.5 % of population (2025)Source 38World Bank estimate (degree-of-urbanisation method). National definitions give different figures.
Finland’s housing splits into two groups that matter for energy. About 1.06 million households live in one- and two-dwelling houses, mostly owner-occupied, with their own connection and roof and often electric or heat-pump heating. These are where most rooftop solar, home batteries and smart heating control are installed: about 6,500 small houses added solar in 2025, after about 10,000 in 2024 and 30,000 in 2023. Nearly half of households live in blocks of flats, almost all owned through housing companies or rented. There, any solar plant or charging infrastructure is a decision for the housing company’s board and general meeting.
Since 2023, a housing company can share solar output among its flats through an energy community. Datahub performs compensation calculations (hyvityslaskenta) that allocate production to each apartment’s accounting point. The Energy Authority counted 307 energy communities with 6,200 consumption places in distribution grids at the end of 2025, almost double the number of places a year earlier.
How the grid works in Finland.
- TransmissionFingrid Oyj
- Distribution77 distribution system operators with local monopoly licences, from Caruna (about 746,000 customers) and Elenia (443,200) to small municipal and cooperative companies, plus 9 high-voltage-only DSOs
- MeteringFingrid Datahub Oy, Local DSO
- Supply5 or more retail suppliers
Physical flow
Fingrid’s transmission grid carries power from nuclear plants, hydro stations and fast-growing wind farms, concentrated in Ostrobothnia, to consumption that is increasingly concentrated in southern Finland. The Energy Authority reports about 6,100 km of 400 kV, 1,000 km of 220 kV and 17,600 km of 110 kV lines in Finland, and 156,300 km of medium-voltage (1–70 kV) and 263,400 km of low-voltage (0.4 kV) distribution network. DSOs have been required to make their networks weather-proof: storm or snow outages may last no longer than 6 hours in zoned areas and 36 hours elsewhere, with deadlines to the end of 2028, or 2036 for rural operators with large investment programmes. This has driven extensive underground cabling.
Finland is part of the Nordic synchronous area. Interconnectors link it to northern Sweden (SE1), including the third AC line, Aurora Line, commissioned in late 2025; to central Sweden (SE3, 1,200 MW); to Estonia via Estlink 1 and 2 (1,016 MW); and to northern Norway (NO4). Imports from Russia, once up to 1,400 MW, have been suspended since May 2022.
Commercial flow
Generators and retailers trade on the day-ahead and intraday markets or bilaterally. Every retailer must be, or have a contract with, a balance responsible party, which is settled for imbalances by eSett. Fingrid balances the system in real time through FCR, FFR, aFRR (connected to the European PICASSO platform since 26 March 2025) and the Nordic mFRR energy activation market (automated 15-minute balancing since 4 March 2025). Mainland Finland is a single bidding zone, so internal congestion is handled by countertrade.
Retail and data exchange
Datahub is the hub of retail processes. The DSO registers each accounting point and its GSRN and uploads metering data. Retailers register contracts, and switching, moving and billing data flow through Datahub. Customers can log in to the Datahub customer portal with strong electronic identification to see their contracts and consumption, and can authorise third parties. Combined billing of supply and distribution is not mandatory: in 2025 Parliament rejected proposed provisions on it.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry of Economic Affairs and Employment (TEM) | Prepares energy legislation, including the Electricity Market Act (588/2013) and its decrees on metering and settlement, and runs energy aid and the fossil-free flexibility support now being prepared. |
| Regulator | Energiavirasto (Energy Authority) | Grants distribution network licences, confirms the network pricing methods for each regulatory period, approves Fingrid’s terms under EU network codes, supervises retail and wholesale markets (including REMIT), procures strategic reserves and runs the official price comparison site sahkonhinta.fi. |
| Regulator | Tukes (Finnish Safety and Chemicals Agency) | Electrical safety authority. Keeps the register of electrical contractors and their operating rights and supervises compliance with the Electrical Safety Act (1135/2016), including for solar and battery installations. |
| TSO | Fingrid Oyj | Owns and operates the national transmission grid and the interconnectors and is the system operator for mainland Finland. It procures frequency reserves and is responsible for the balance. After a 2026 share transaction, the State of Finland owns 59.50% of the shares and holds 81.49% of the votes. |
| Data hub / registry | Fingrid Datahub Oy | Operates Datahub, the central information exchange for the retail market, live since 21 February 2022. It holds the master data for about 3.9 million accounting points, their contracts and their metering time series. Retailers and DSOs have been required to use it by law since a 2019 amendment to the Electricity Market Act. |
| DSO | Caruna | Largest DSO, with about 746,000 customers in southern, south-western and western Finland, Joensuu and Koillismaa (about 20% of Finnish distribution) and about 90,000 km of network. Owned by KKR, Ontario Teachers’ Pension Plan, AMF and Elo. |
| DSO | Elenia | Second-largest DSO, supplying 443,200 end users through about 77,400 km of network in more than 100 cities and municipalities. |
| DSO | Helen Sähköverkko | Network company for Helsinki, part of the Helen group. It is replacing meters with 15-minute models, a programme it must finish by the end of 2028. |
| DSO | Other local DSOs | The remaining operators include Järvi-Suomen Energia and the network companies of Oulun Energia, Turku Energia and Vaasan Sähkö. Each has an exclusive licensed area. DSOs that distribute 200 GWh or more a year at 0.4 kV must be legally unbundled from supply and generation: 36 met that threshold in 2025, and 54 were unbundled in total. |
| Supplier | Electricity retailers (sähkönmyyjät) | 49 retailers supplied households and small businesses at the end of 2025. The three largest held 44% of metering points. No licence is required, but each must have balance responsibility arrangements in an open supply chain ending with Fingrid. |
| Metering | Local DSO | The DSO owns, installs and reads the meter and sends validated metering data to Datahub. There is no competitive meter operator role. |
| Settlement | eSett | Nordic imbalance settlement company owned by the Finnish, Swedish, Norwegian and Danish TSOs. It settles balance responsible parties in 15-minute periods and runs the central compensation settlement for independent aggregators in aFRR. |
| Exchange | Nord Pool and other NEMOs | Day-ahead (15-minute products since 1 October 2025) and intraday trading for the Finnish bidding zone, coupled with the rest of Europe. |
| Flexibility market | Fingrid reserve markets | Annual and hourly markets for FCR-N and FCR-D, plus FFR, aFRR and mFRR. Aggregated and independently aggregated resources are allowed in most products. |
Compared with the UK system.
| UK concept | Finland equivalent | How it works |
|---|---|---|
| DNO | Jakeluverkonhaltija (DSO) | 77 DSOs, each holding a network licence from Energiavirasto for an exclusive geographical area. Areas range from the large national groups Caruna and Elenia to single towns. There is no fixed regional map like the 14 GB licence areas. |
| National Grid/NESO | Fingrid | One company owns the transmission grid and operates the system, including balancing and reserve procurement. Since 1 January 2026 the law has also allowed regional DSOs to build and run high-voltage distribution networks up to 400 kV. |
| MPAN | Käyttöpaikkatunnus (GSRN) | An 18-digit GS1 number that the DSO creates for each accounting point, beginning with the DSO’s GS1 company prefix (country code 64). It is printed on bills and is the key used in Datahub for switching and data. |
| MPRN | Gas: no household equivalent in common use | Gas plays a small role in Finnish homes: distribution networks took only 17.6% of gas delivered from the transmission grid in 2025. Where a home is connected, the local gas network operator identifies the site in its own systems. |
| Meter operator | DSO | By law the DSO is responsible for metering: it owns the meter, reads it remotely and delivers the data to Datahub. Customers and retailers cannot appoint another meter operator. |
| Supplier | Sähkönmyyjä (retailer) | Competitive retailers with no supply licence or price cap. The new retailer arranges a switch through Datahub, and each DSO area has a supplier of last resort for small customers. |
| Smart-meter infrastructure | DSO AMR systems + Fingrid Datahub | There is no national communications company like DCC. Each DSO runs its own meter reading system, and all metering time series go to the national Datahub, where customers and authorised third parties can see them. |
How a supply point is identified.
643001234567890127 (fictional)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Käyttöpaikkatunnus (GSRN) |
| Who issues it? | The local DSO, using the GS1 company prefix it orders from GS1 Finland Oy |
| Format | GS1 Global Service Relation Number: the DSO’s GS1 company prefix (7–11 digits, starting with Finland’s GS1 country code 64; in practice usually 643…), a service reference number that the DSO assigns freely, and a final check digit calculated with the GS1 modulo-10 method. The number carries no information about the site itself. |
| Length | 18 digits |
| Stays with the property when you switch supplier? | Yes |
| Where to find it | Printed on the DSO’s network invoice and connection or network contract confirmation, and usually on the retailer’s bill. It is also shown in the Datahub customer portal and the DSO’s online service. |
| Electronic access | Customers log in to the Datahub customer portal through Suomi.fi strong authentication and can see their accounting points, contracts and 15-minute or hourly metering time series, and download them as CSV. There is currently no API for consumers. Retailers, DSOs and registered service providers exchange data with Datahub electronically, using the GSRN as the key. |
| Third-party access | There is no public look-up. Parties with a contract for the accounting point see its data. Other service providers, such as energy reporting or smart-control companies, need the customer’s authorisation in the Datahub portal, valid for up to two years. Customers can also authorise retailers to see their data in order to make offers. |
| Who keeps the register | Fingrid Datahub Oy holds the national register of accounting points (about 3.9 million) and their metering data. Each DSO creates and maintains the records for its own area, and GS1 Finland allocates only the company prefixes. |
| Register scope | National |
What the GSRN identifies
The käyttöpaikkatunnus identifies an accounting point (käyttöpaikka): the point where a customer’s consumption, and any production, is metered and settled. It does not identify the meter. Replacing the meter, changing the metering method, a change of retailer or occupant, or even the sale of the network to another DSO does not change the number. Fingrid Datahub’s rules require each GSRN to remain valid for the whole life of the metering point, and Datahub does not allow an existing identifier to be edited. Usually there is one accounting point per address or flat. Temporary sites, such as construction sites, can be closed and recreated.
How the number is built
Every market party in Datahub orders a GS1 company prefix from GS1 Finland. Finland’s country code is 64, and the prefix can be 7 to 11 digits long. A DSO that chooses a 9-digit prefix has 8 digits free for its own numbering, enough for 100 million identifiers. The DSO builds each GSRN by adding its own service reference number and a check digit. Datahub validates that the identifier begins with the DSO’s prefix, is not a duplicate and has a correct check digit. Production units and border metering points get GSRNs too, while metering areas use EIC Y codes issued by Fingrid and market parties use GLN codes.
Switching and moving
A customer switching retailer gives the new retailer their details and usually the GSRN. The new retailer registers the contract in Datahub, which handles the change and informs the DSO and the old retailer. Moving house works the same way: the new occupant makes a contract for the accounting point at the new address. Because Datahub holds contracts and metering data centrally, the DSO, the old retailer and the new retailer all work from the same record.
Why it matters for solar and batteries
A home solar system normally stays on the same accounting point and GSRN. The DSO records the production in Datahub, the meter measures both import and export, and netting within each metering period is calculated centrally. Installers and aggregators need the GSRN for connection notifications to the DSO, for authorisations in Datahub and, for reserve market participation, to identify the site to Fingrid.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Yes |
| Net metering | Limited |
| Net billing | No |
| How exported electricity is paid | Surplus sold to a retailer at a contract price, usually the hourly or 15-minute Finnish spot price minus a small margin; consumption and production are first netted within each metering period for sites up to 100 kVA |
| Is there net metering? | Only within each metering period. Since 1 January 2023, under a government decree on electricity settlement and metering, consumption and production at sites of up to 100 kVA are netted within each metering period, originally the hour and now moving to 15 minutes as meters are replaced. Network charges and electricity tax apply only to the net import in each period. Surplus left after netting is sold to a retailer, and there is no carry-over of credits between periods or months. |
| What do small producers pay to connect? | For small-scale generation up to 2 MVA, the connection fee may cover only the direct costs of connection, not the cost of reinforcing the existing network. Annual network charges collected from a generator connected to the distribution network may not exceed 0.07 c/kWh. |
| Must a retailer buy my surplus? | No. Retailers have no obligation to buy small producers’ surplus, but most offer purchase contracts priced on the spot price minus a margin of roughly 0–0.3 c/kWh. Most require an electricity supply contract as well, though a few retailers buy from non-customers. |
| Do I pay electricity tax on what I produce? | Producers with a plant of at most 100 kVA are exempt from electricity tax registration and reporting, so self-consumed solar electricity is not taxed. Larger plants up to 800,000 kWh a year register but report only annually. |
| Which technical rules apply? | DSOs apply SFS-EN 50549-1, Energiateollisuus network recommendation YA 9:23 on connecting small-scale production and storage, Fingrid’s VJV2024 requirements for generating units of 0.8 kW and above, and SJV2024 for storage of 0.8 kW and above. Plants below 50 kVA may use interface protection integrated in the inverter. Larger plants need separate interface protection. |
| Is plug-in (balcony) solar allowed? | No. The Finnish electrical installation standard, based on the international model, prohibits connecting a generator such as a solar panel and inverter to the grid through a plug. A grid-connected system must be permanently installed by a registered contractor and notified to the DSO. |
Connecting a home system.
- Ask the local DSO what maximum generation capacity the existing connection (main fuse size) allows, and check with the municipal building control whether a notification or building permit is needed.
- Have the system installed by an electrical contractor registered with Tukes with operating right A or A (sj); an L (equipment repair) right is not enough.
- The contractor carries out the commissioning inspection and measurements and gives the owner the inspection report and documentation.
- Send the DSO the small-scale production notification (Energiateollisuus pientuotannon yleistietolomake, or the DSO’s own form) with inverter and capacity details. The DSO grants commissioning permission and, where needed, a connection amendment agreement.
- Sign a contract with a retailer to buy the surplus. Most require the household to buy its electricity from them too. Electricity may not be fed into the grid without a buyer.
- The DSO registers the production in Datahub. Netting of consumption and production in each metering period then applies, and exported 15-minute values go to the retailer for payment.
Households can export and be paid, but Finland has never had a feed-in tariff for rooftop solar or annual net metering. The main benefit of solar is self-consumption: every kilowatt-hour used on site avoids the energy price, the network energy charge, electricity tax and VAT, whereas exported energy earns only the spot price, which is often low or negative on sunny, windy summer days. Netting within each metering period means that production during a period offsets consumption in the same period before anything counts as export.
The process runs through the DSO and the installer. The DSO has a legal duty to connect plants that meet the technical requirements in its area. For typical house systems on an existing three-phase connection, the main checks are fuse size and protection settings. For larger systems, and for battery storage, the DSO may require more detailed studies, and Fingrid’s VJV2024 and SJV2024 compliance must be documented.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity | No generation licence. Connection needs an agreement with the network operator and compliance with VJV2024. Large plants need land-use planning and permits; household solar needs at most municipal building-control procedures. | DSO or Fingrid (connection); municipality (building control, zoning) | Plants up to 100 kVA are exempt from electricity tax registration. All production must sit in a balance, normally that of the retailer buying the output. |
| Store electricity | No licence. Storage has been treated as a competitive market activity under amendments to the Electricity Market Act in force since 1 June 2023. Storage units of 0.8 kW and above must meet Fingrid’s SJV2024 requirements. Since 2025, storage at power plants can share the plant’s connection line. | Energiavirasto; DSO or Fingrid | Fingrid has stopped new grid-scale storage connections in southern Finland until about 2029; projects over 5 MW must apply to Fingrid. |
| Export to the grid | No licence. Requires notification to and permission from the DSO, a commissioning inspection by a registered electrical contractor, and a contract with a buyer for the surplus. | DSO | Netting within the metering period for sites up to 100 kVA; connection fees for generation up to 2 MVA are limited to direct costs. |
| Supply (sell) electricity to consumers | No supply licence. A retailer must have balance responsibility arrangements (an open supply chain to Fingrid), register as a party in Datahub, and follow consumer contract rules. Retailers with more than 200,000 customers must offer dynamic-price contracts. | Energiavirasto (supervision); Fingrid (balance agreements); Competition and Consumer Authority (consumer protection) | Prices for customers using under 100,000 kWh a year may be published on the Energy Authority’s comparison tool; suppliers of last resort must report them. |
| Distribute electricity (build or operate networks) | Network licence (sähköverkkolupa) from Energiavirasto for an exclusive area. Since June 2023, DSOs need the authority’s permission to carry on businesses other than network operation and may not provide EV charging services. | Energiavirasto | Legal unbundling is required for DSOs distributing 200 GWh or more a year at 0.4 kV; separate management rules apply from 50,000 customers. |
| Aggregate (aggregation services) | No licence. The Electricity Market Act defines aggregation and independent aggregation (amendment 497/2023, in force 1 June 2023). In Fingrid’s reserve markets an aggregator acts as a balancing service provider, either with contracts with the resource’s retailer and BRP or as an independent aggregator without them. | Fingrid; Energiavirasto | Independent aggregation is allowed in FCR-N, FCR-D, FFR and aFRR, but not yet in mFRR, day-ahead or intraday. A government decree on the compensation model is being prepared. |
| Trade wholesale electricity | No energy trading licence. Participants need balance responsibility or a BRP contract and must register under REMIT with Energiavirasto. | Energiavirasto (REMIT) | Day-ahead and intraday trading through NEMOs such as Nord Pool. |
| Balancing and frequency reserves | No licence. Sign Fingrid’s balancing service provider agreement and prequalify each resource or aggregated group (no prequalification test for mFRR). | Fingrid | Minimum bids: 0.1 MW for FCR-N; 1 MW for FCR-D, FFR, aFRR and mFRR. |
| Remote control of household assets (VPP) | No specific licence. A provider that controls home batteries, heating or chargers acts as an aggregator or BSP and needs the customer’s agreement and, to see consumption data, a Datahub authorisation. Market-based load control of loads connected to the DSO’s smart meter (section 65 b of the Electricity Market Act) is being phased in between September 2026 and June 2027. | Fingrid; DSO; Energiavirasto | Customers will be able to choose a demand response service that controls meter-connected loads according to the electricity price. |
| Electrical installation work | Grid-connected solar and battery installation is electrical work that only an electrical contractor registered with Tukes and holding operating right A or A (sj) may do, with a commissioning inspection before use. | Tukes | Operating rights can be checked in Tukes’ register of operators; owners may order a voluntary verification inspection. |
Finland licenses networks but leaves competitive activities largely unlicensed. Building or operating a distribution network needs a network licence from the Energy Authority. Generation, storage, supply, trading and aggregation do not, but they depend on market agreements: balance responsibility and Datahub registration for retailers, and Fingrid’s balancing service provider agreement and prequalification for reserves. They must also follow the technical requirements set by Fingrid and the DSOs.
For households the practical requirements are electrical safety and DSO notification. The installer must be a Tukes-registered contractor with the right operating rights, the DSO must give commissioning permission, and a buyer must be contracted for any surplus.
Flexibility and grid services.
Aggregation of home equipment: Yes
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| FCR-N (normal frequency containment) | Yes | 0.1 MW | Yes | Fingrid. Symmetrical regulation within 49.9–50.1 Hz, procured in a yearly market and a daily hourly market (bids by 18:30 for the next day). Independent aggregation has been allowed since 1 January 2018. |
| FCR-D up / FCR-D down (disturbance) | Yes | 1 MW | Yes | Fingrid. Responds to disturbances beyond the normal band, within 49.5–50.5 Hz; yearly and hourly markets. Independent aggregation has been allowed since 1 January 2017. |
| FFR (fast frequency reserve) | Yes | 1 MW | Yes | Fingrid. Very fast frequency response product. Independent aggregation allowed since 12 May 2020. |
| aFRR (automatic frequency restoration) | Yes | 1 MW | Yes | Fingrid. Capacity procured in the common Nordic market. Energy has been activated through the European PICASSO platform since 26 March 2025. Independent aggregation has been allowed since 5 June 2025, with financial transfers to the resource’s BRP settled centrally by eSett at the Finnish day-ahead price. |
| mFRR capacity and energy activation | Yes | 1 MW | Limited | Fingrid. Common mFRR capacity market with Sweden and Denmark since November 2024, and automated Nordic energy activation in 15-minute periods since 4 March 2025. Aggregation is possible within one transmission area and through contractual BSPs, but independent aggregation is not yet allowed. |
| Day-ahead and intraday (implicit flexibility) | Yes | — | Limited | Nord Pool and other NEMOs. Households reach this market through exchange-price contracts (34% of customers) and smart control of heating, water heaters, EV charging and batteries. Independent aggregation is not yet possible in these markets. |
| Strategic reserve | Restricted | — | Unknown | Energiavirasto. The capacity reserve is open to generation and demand flexibility, but no capacity has been held since July 2022 because adequacy assessments showed no need. |
| DSO flexibility services | Developing | — | Unknown | Distribution system operators. DSOs must consider demand response, storage and other flexibility as alternatives to network expansion in their development plans, and the 2024–2031 regulation methods include a separate flexibility incentive. Market-based procurement is still at an early stage. |
Finland has one of Europe’s most open reserve markets for small resources. Fingrid accepts FCR-N bids from 0.1 MW. Aggregation from several balances is allowed in all products, and independent aggregators, who need no agreement with the customer’s retailer, can take part in FCR-N, FCR-D, FFR and, since June 2025, aFRR. Aggregated resources can be generation, consumption or storage. The Energy Authority notes that new flexible demand, such as electric boilers and energy storage, has entered the market and helps smooth wholesale price fluctuations.
For households, the most widespread form of flexibility is implicit: about a third of customers are on exchange-price contracts and shift heating, hot water and charging to cheap periods, often automatically. The Electricity Market Act amendment of 2025 adds market-based load control of meter-connected loads, being phased in between 1 September 2026 and 1 June 2027. The Ministry is also preparing a support scheme for fossil-free flexibility under the EU General Block Exemption Regulation.
Flexibility and aggregation platforms.
| Platform or aggregator | What it does |
|---|---|
| Fingrid reserve markets | Product terms, prequalification and aggregation models for FCR, FFR, aFRR and mFRR. |
| Fingrid open data | Reserve prices and volumes, production and consumption, and Datahub-based statistics on consumption and small-scale production. |
| Datahub customer portal | Where customers see metering data and authorise service providers, including flexibility and energy reporting companies. |
| Sähkönhinta.fi | The Energy Authority’s official comparison tool for supply contracts, including exchange-price and consumption-effect products. |
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | First generation complete (over 99% of customers); second-generation 15-minute meters being installed, all metering to be 15-minute by the end of 2028 |
| Reading interval | 15 minutes for new meters (imbalance settlement and day-ahead market are 15-minute); hourly values on older meters until replaced |
| Responsible party | The local DSO; customers cannot choose another meter operator |
| First generation | Hourly remote-read meters; legislation required hourly-based meter reading by the end of 2013 |
| Coverage | More than 99% of customers have a smart meter (Energy Authority, 2025) |
| Second generation deadline | 15-minute metering at all sites by the end of 2028 |
| Data platform | All metering time series delivered to Fingrid Datahub; customers access them through the Datahub portal and DSO services |
| Load control | Market-based control of loads connected to the meter, chosen by the customer, is being phased in between September 2026 and June 2027 |
Finland was one of the first countries to make hourly metering universal. Legislation required hourly-based meter reading by the end of 2013, so DSOs installed remote-read meters almost everywhere, and by the time Datahub went live in 2022 the Energy Authority counted more than 99% of customers with a smart meter. Hourly data made exchange-price contracts possible for all households, and their share rose to about a third after the 2022 energy crisis.
The second rollout is driven by the EU move to a 15-minute imbalance settlement period and the 15-minute day-ahead market, introduced on 1 October 2025. DSOs are replacing meters with models that record and transmit quarter-hour data daily. Elenia, Helen Sähköverkko and Oulun Energia, for example, run programmes due to finish by 2028 at the latest. Until a site’s meter is replaced, its hourly values are used in settlement.
Meters remain the DSO’s assets, and their cost is recovered through regulated network charges. There is no national meter communications network. Each DSO chooses its own communications technology (Oulun Energia, for example, is moving to mobile IoT) and delivers validated data to Datahub, which makes it available to the customer’s retailer and to authorised third parties.
Renewable electricity.
Electricity generation mix (2025).
- Nuclear: 39.6%
- Wind: 27.9%
- Hydropower: 15.6%
- Biomass: 11.3%
- Solar: 1.2%
- Waste: 1%
- Natural gas: 1%
- Peat: 0.7%
- Coal: 0.3%
- Oil: 0.2%
- Other: 1.2%
- Renewable electricity share
- 57% (2025)Source 8Share of domestic electricity generation from renewables (preliminary). Including nuclear, 96% of generation was carbon-dioxide neutral. Eurostat’s RES-E indicator, which compares renewable generation with gross electricity consumption, was 56.6% for 2025.
- Home solar
- 108,000 household self-generation contracts (end 2025)Source 9Households with a network service contract for partial self-generation, out of 121,900 customers in total. Small-scale photovoltaic capacity (units up to 1 MVA) connected to distribution grids was 1,249.5 MW.
- Solar added each year
- 0.35 GW (2025)Source 10Preliminary. Small-scale capacity grew by 138 MW (12%), and industrial-scale capacity more than tripled to 326 MW. Only about 6,500 small houses installed solar in 2025, down from about 30,000 in 2023.
- Nuclear
- 4.4 GW (end 2025)Source 9
- Wind
- 9.433 GW (end 2025)Source 8
- Hydropower
- 3.2 GW (end 2025)Source 9
- Biofuels
- 2.6 GW (end 2025)Source 9
- Solar PV
- 1.6 GW (end 2025)Source 10
- Fossil and peat (coal, gas, oil, peat)
- 5 GW (end 2025)Source 9Derived sum: coal 0.8, gas 1.7, petroleum 1.3 and peat 1.2 GW. Much of this is reserve or rarely used capacity.
Targets.
- At least 62% renewable energy in final energy consumption by 2030 (updated National Energy and Climate Plan, submitted 28 June 2024).
- Carbon neutrality by 2035 under the Climate Act (423/2022), in force since 1 July 2022.
- Use of coal for electricity and heat banned from 1 May 2029, with limited security-of-supply exceptions.
Finland’s electricity has moved from fossil fuels to nuclear and wind in little more than a decade. In 2010 coal, gas and peat produced more than a third of the electricity Finland used; in 2025 they produced about 2% of domestic generation. Olkiluoto 3, commissioned in April 2023, lifted nuclear capacity to 4.4 GW. Wind power is built on a fully commercial basis, especially in the Ostrobothnian provinces, and its output rose 9% in 2025 to 22.1 TWh.
Hydropower provides about 3.2 GW of flexible capacity, and biomass, mainly black liquor and other wood fuels from the forest industry, is burned in combined heat and power plants. Solar is small but growing. Total capacity reached about 1.6 GW in 2025, and growth has shifted from rooftops to industrial-scale ground-mounted plants. The rapid growth of weather-dependent output has brought negative-price hours and increased the value of storage, electric boilers and other flexible demand.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- 0.98 GW (Feb 2026)Source 11261 reported storage systems. 57% of storage power comes from systems over 10 MW. About 1,800 MW more had connection agreements with Fingrid by September 2025.
Battery storage has grown fast in Finland because of the reserve markets and price volatility. Fingrid estimated connected storage at about 1,050 MW in February 2026, more than a gigawatt within a few years. Most capacity comes from systems over 10 MW, but by number 85% of storage systems are under 2 MW. Around half of the systems are south of the Tampere–Lahti–Lappeenranta line.
For households, batteries are mainly used to increase solar self-consumption and to shift heating and charging loads under exchange-price contracts. Small batteries can earn reserve market income through aggregators, mostly in FCR-N. Grid-scale storage now competes for scarce connection capacity in the south, and Fingrid has prioritised growth in household and industrial demand there.
Storage projects.
- Fingrid storage connection pipeline: Fingrid has received storage connection requests totalling over 30,000 MW, about twice Finland’s peak consumption. New grid storage connections in southern Finland are on hold until the Hikiä–Toivila reinforcement is completed in 2029, while several thousand megawatts of capacity remain available in Ostrobothnia and the north.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Helen | — | Yes | Limited | Yes | Yes |
| Fortum | — | Unknown | Unknown | Yes | Yes |
| Vattenfall | — | Unknown | Unknown | Yes | Yes |
| Oomi | — | Unknown | Unknown | Yes | Yes |
| Väre | — | Unknown | Unknown | Yes | Yes |
49 retailers served households and small businesses at the end of 2025. The three largest held 44% of metering points, and eight retailers had more than 5% of the market by energy volume after several mergers. Individual market shares are not published officially. About 12.8% of households switched retailer in 2025, a figure that includes switches caused by mergers. Most retailers belong to the same group as a local DSO or are owned by DSOs, but they must operate separately from the network business.
Smart meters belong to the DSO, not the retailer, so any retailer can offer exchange-price or quarter-hour products to any customer with a suitable meter. All nationwide retailers offer exchange-price contracts. Surplus purchase terms differ in margin, monthly fees and whether a supply contract is required, so they are worth comparing. The figures quoted here come from a 2024 private comparison and may have changed.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Ministry of Economic Affairs and Employment (TEM) | Government | Energy policy and legislation | Prepares amendments to the Electricity Market Act, the metering decree, energy aid and the flexibility support scheme. |
| Energiavirasto (Energy Authority) | Regulator | Energy regulator | Network licences, pricing methods, market supervision, statistics on small-scale production and the price comparison tool. |
| Tukes | Regulator | Electrical safety authority | Registers electrical contractors; the place to check whether an installer may install solar or batteries. |
| Fingrid | Transmission | Transmission system operator | Grid and storage connection rules (VJV2024, SJV2024), reserve markets and open data. |
| Fingrid Datahub | Market | Central retail market data hub | National register of accounting points and metering data; customer portal and third-party authorisations. |
| Caruna | Distribution | Largest DSO | Publishes technical requirements for small-scale production and storage connected to its network. |
| Elenia | Distribution | Second-largest DSO | Small-scale production commissioning process and second-generation meter rollout. |
| eSett | Market | Nordic imbalance settlement | Settles balance responsible parties and independent aggregation compensation in 15-minute periods. |
| Energiateollisuus (Finnish Energy) | Renewable Energy | Energy industry association | Annual electricity statistics and network recommendations such as YA 9:23 on connecting small-scale production and storage. |
| Suomen Uusiutuvat ry | Renewable Energy | Renewable energy industry association | Statistics and policy work on wind, industrial-scale solar and storage. |
| Sähkönhinta.fi | Consumer | Official price comparison tool | Run by the Energy Authority under the Act on the Comparison Tool for Electricity Supply Contracts (498/2023). |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Grid connection (small-scale) | Energiateollisuus network recommendation YA 9:23 | Energiateollisuus | Connecting small-scale production and electricity storage to the distribution network, including protection settings (version of 2 June 2025 referenced by Caruna). |
| Generator requirements | VJV2024 (Voimalaitosten järjestelmätekniset vaatimukset) | Fingrid | National implementation of the EU Requirements for Generators. Applies to generating units of 0.8 kW and above. |
| Storage requirements | SJV2024 (Sähkövarastojen järjestelmätekniset vaatimukset) | Fingrid | Technical requirements for electricity storage of 0.8 kW and above, including home batteries. |
| Inverters and interface protection | SFS-EN 50549-1:2019 | SFS / CENELEC | Plants under 50 kVA may use protection integrated in the inverter; 50 kVA and above need a separate interface protection system. |
| Electrical installation | SFS 6000 series (including SFS 6000-5-52 for cabling) | SESKO / SFS | National low-voltage installation standard; it prohibits plug-in connection of generators to the grid. |
| Installer accreditation | Electrical contractor operating right A or A (sj) | Tukes (Electrical Safety Act 1135/2016) | Required for grid-connected solar installations; an L (equipment repair) right is not sufficient. A commissioning inspection and report are mandatory. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Building permit or notification for rooftop solar | Limited | Local | Set by each municipality’s building ordinance under the Building Act in force since 2025. Panels that significantly affect the townscape or environment need at least a building permit; many municipalities exempt ordinary rooftop panels or require only a notification to building control. |
| DSO commissioning permission | Yes | Local | The DSO must receive the small-scale production notification and give permission before the system is connected in parallel with the grid. |
| Commissioning inspection by electrical contractor | Yes | National | Under the Electrical Safety Act, the installing contractor inspects and measures the installation and gives the owner the inspection report. |
| Contract with a buyer for surplus | Yes | National | Electricity may not be fed into the grid without a buyer. Retailers are not obliged to buy. |
| Electricity tax registration | No | National | Not required for plants of at most 100 kVA; larger small producers register with the Tax Administration and report annually. |
| Protected or heritage buildings | Limited | Mixed | Protected or culturally valuable buildings may need separate approval from the municipality or heritage authorities. |
Permitting for household solar is light, but it is split between three bodies: the municipality for the building, the DSO for the grid connection, and the registered electrical contractor for electrical safety. Because building ordinances are municipal, the same rooftop system may need a permit in one municipality and only a notification in another. Checking with building control before buying is the standard advice.
For blocks of flats, the investment is a decision for the housing company, and shared use of output among flats is arranged through an energy community with compensation calculated in Datahub.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Household tax deduction (kotitalousvähennys) | Active | Tax credit | 35% of the labour cost of household work bought from a company, which can include installing solar panels or a heat pump at home, up to EUR 1,600 per person a year after a EUR 150 deductible. Equipment is not covered. | Tax years 2025–2026 |
| Temporary increase of the household tax deduction | Scheduled | Tax credit | In its April 2026 spending limits session the government agreed to raise the deduction to 40% and the maximum to EUR 2,100 for tax years 2026 and 2027. A government proposal is before Parliament; the Tax Administration listed it as a proposal, not yet law, in June 2026. | Proposed for 2026–2027 |
| Household deduction for replacing oil heating | Active | Tax credit | Higher deduction of 60% of labour costs, up to EUR 3,500 per person a year, for work to replace oil heating. | Tax years 2025–2026 |
| Electricity tax exemption for small producers | Active | Tax exemption | Plants of up to 100 kVA are exempt from electricity tax registration and reporting, so self-consumed electricity carries no electricity tax. Netting within the metering period also removes tax on imports offset by production in the same period. | — |
| Energy aid for large demonstration projects | Closed | Grant | EUR 48 million call by the Ministry of Economic Affairs and Employment for 2026, for projects over EUR 5 million, prioritising renewable transport fuels and energy storage with significant new technology. Applications closed on 5 August 2026. | 9 Apr – 5 Aug 2026 |
Data and connectivity.
- Fixed broadband
- 36.5 fixed subscriptions per 100 people (2024)Source 39World Bank / ITU indicator. Mobile broadband is widely used instead of fixed lines in Finland.
- 4G coverage
- 96 % of households (≥100 Mbit/s) (Dec 2025)Source 37
- 5G coverage
- 93 % of households (≥100 Mbit/s) (Dec 2025)Source 37
Finland has very high mobile coverage: at the end of 2025, 4G networks offering at least 100 Mbit/s covered 96% of households and 5G networks 93% (Traficom). This supports app-based control of heat pumps, batteries and chargers.
Meter data travels over each DSO’s own networks, increasingly mobile IoT in second-generation rollouts, and reaches retailers and service providers through Datahub rather than directly from the meter. Retailers, DSOs and third parties connect to Datahub through standard electronic messaging, using GLN codes to identify parties and GSRN codes for accounting points.
Grid conditions.
- National peak demand
- 15.6 GW (winter 2025–26)Source 9Reached in January 2026, with domestic generation of 14.3 GW and net imports of 1.2 GW. Energiateollisuus recorded a calendar-2025 peak of 13,681 MW on 4 February 2025.
- Annual electricity demand
- 85 TWh (2025)Source 8Preliminary; up about 2% on 2024. Domestic generation was 79 TWh and net imports 5.6 TWh.
- Generation capacity
- 26.4 GW (end 2025)Source 9Installed capacity. The Energy Authority estimated that only about 11.7 GW would be available in low-wind conditions in winter 2025–26.
- Interconnection
- 4.2 GW (maximum import) (winter 2025–26)Source 9Total maximum import capacity during the winter, from Sweden (SE1, SE3), Estonia and Norway. The Energy Authority gives installed Finland–Sweden capacity as 3,500 MW; the Aurora Line, commissioned in late 2025, added 800 MW of import and 900 MW of export capacity with SE1. The Russian links (1,400 MW) have been out of commercial use since May 2022.
- Curtailment
- Not identified from a reliable public source.
Finland’s grid challenge is geographic. New wind and solar are concentrated in the west and north, while consumption, including electric boilers and new industry, grows mainly in the south. Fingrid is reinforcing north–south transmission and estimates gross capital expenditure of about EUR 2 billion in 2026–2029. Connection requests from storage have far exceeded available capacity in the south. In September 2025 Fingrid extended its stop on new grid storage connections there until 2029.
Security of supply depends on imports during cold, windless periods. Domestic dispatchable capacity is falling as old combined heat and power plants close: two coal-fired and one gas-fired CHP unit (330 MW) closed in 2025, and the Meri-Pori coal plant will close on 1 March 2027. The Energy Authority expects adequacy concerns to grow into the 2030s. The national reliability standard is a loss-of-load expectation of 2.1 hours a year, and no strategic reserve has been procured since 2022.
Grid and capacity maps.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Electricity Market Act amendments (201/2025) | Current | 1 July 2025 | Harmonised the components of distribution tariffs and promoted power-based pricing, capped reasonable connection times for consumers at generally six months, required DSOs to publish available capacity, allowed storage to share power plant connection lines and limited termination fees for fixed-term contracts. |
| 15-minute day-ahead market | Current | 1 October 2025 | The single European day-ahead coupling moved to 15-minute market time units, following 15-minute imbalance settlement (2023) and 15-minute mFRR activation (March 2025). |
| High-voltage grid reform | Current | 1 January 2026 | Lines above 110 kV are no longer automatically transmission grid, and regional DSOs may build and operate high-voltage distribution networks up to 400 kV. |
| Higher security-of-supply fee | Current | 1 April 2026 | The fee collected with electricity tax rose from 0.013 to 0.085 c/kWh (excluding VAT) in both tax classes. |
| Market-based load control via smart meters | Upcoming | 1 September 2026 – 1 June 2027 | Section 65 b of the Electricity Market Act lets customers choose a demand response service that controls loads connected to their meter according to the electricity price. A March 2026 proposal phases the introduction between these dates instead of a single start date. |
| Temporary increase of the household tax deduction | Upcoming | Tax years 2026–2027 (pending Parliament) | Proposed rise from 35% to 40% of labour costs and from EUR 1,600 to EUR 2,100 a year. |
| Support scheme for fossil-free flexibility | Upcoming | Not yet set | Following the Fossil-Free Flexibility Working Group’s May 2025 report, the government announced in May 2026 that it would prepare a support scheme under the EU General Block Exemption Regulation. |
| 15-minute metering at all sites | Upcoming | End of 2028 | DSOs must complete the replacement of hourly meters with 15-minute meters. |
| Next network regulation period | Upcoming | 1 January 2028 | Sixth period ends in 2027; the rate-of-return methods for 2028–2031 are already confirmed but under appeal at the Supreme Administrative Court. |
| Coal ban in energy production | Upcoming | 1 May 2029 | Use of coal for electricity and heat is banned, with exceptions for security of supply approved by the Energy Authority. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Medium | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | High | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | Medium | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | High | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Medium | 108,000 households had self-generation contracts at the end of 2025, about one in 27 households, and small-scale PV reached 1.25 GW. However, new house installations fell to about 6,500 in 2025 from 30,000 in 2023. |
| Distributed energy market | Medium | 1.4 GW of small-scale generation in distribution grids, 307 energy communities and about 1 GW of storage, in a system dominated by nuclear, large hydro and utility wind. |
| Grid flexibility market | High | FCR-N bids from 0.1 MW; independent aggregation allowed in FCR-N, FCR-D, FFR and aFRR; 34% of customers on exchange-price contracts; 15-minute markets and universal smart metering through Datahub. |
| Energy storage adoption | High | About 1,050 MW of electricity storage connected by February 2026, around 7% of winter peak demand, with about 1,800 MW more under connection agreements with Fingrid. |
| Renewable growth environment | High | Wind capacity rose by 1,023 MW to 9.4 GW in 2025 without subsidies, and solar capacity grew 28%; renewables supplied 57% of generation in 2025. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 39 sources
- Väkiluku (population) – 31.12.2025. Statistics Finland (Tilastokeskus), 2026. accessed 1 October 2026.
- Household-dwelling units and dwelling population by number of persons, number of rooms and type of building, 2005–2025 (table 15fh). Statistics Finland, 2026. accessed 1 October 2026.
- Energy consumption in households, 2008–2024 (table 11zs). Statistics Finland, 2025. accessed 1 October 2026.
- Dwellings by type of building, occupancy and year of construction, 2025 (table 15f6). Statistics Finland, 2026. accessed 1 October 2026.
- Number of buildings by regions and by intended use and heat source, 2005–2025 (table 15f7). Statistics Finland, 2026. accessed 1 October 2026.
- Asunnot ja asuinolot 2022 (Dwellings and housing conditions 2022). Statistics Finland, 2023. accessed 1 October 2026.
- Electricity prices for household consumers – bi-annual data (nrg_pc_204). Eurostat, 2025-H2. accessed 1 October 2026.
- Energiavuosi 2025 – Sähkö (preliminary electricity statistics 2025). Energiateollisuus ry (Finnish Energy), 2026. accessed 1 October 2026.
- National Report on electricity and gas markets in 2025 in Finland (Ref. 2333/040800/2026). Energiavirasto (Energy Authority), 2026. accessed 1 October 2026.
- Aurinkosähkön tuotantokapasiteetti kasvoi yli neljänneksen vuonna 2025 – eniten kasvua teollisessa mittaluokassa. Energiavirasto (Energy Authority), 2026. accessed 1 October 2026.
- The combined capacity of electricity storages in Finland now exceeds 1,000 MW. Fingrid, 2026. accessed 1 October 2026.
- Fingrid secures transmission capacity for growth in electricity consumption and new industrial investments – restrictions on new energy storage facility connections continued in southern Finland. Fingrid, 2025. accessed 1 October 2026.
- Aggregation in electricity markets – general information (6/2026). Fingrid, 2026. accessed 1 October 2026.
- Frequency containment reserves (FCR products). Fingrid. accessed 1 October 2026.
- Questions and answers about Datahub. Fingrid Datahub. accessed 1 October 2026.
- Datahub customer portal – Q&A. Fingrid Datahub. accessed 1 October 2026.
- GS1-tunnuksien käyttö sähkön vähittäismarkkinoilla (v1.8). Fingrid Datahub Oy, 2025. accessed 1 October 2026.
- Metering point ID (GSRN). Vaasan Sähkö. accessed 1 October 2026.
- Pientuotannon netotus. Turku Energia Sähköverkot. accessed 1 October 2026.
- Small-scale electricity production. Elenia. accessed 1 October 2026.
- Information on switching to 15-minute metering. Helen Sähköverkko. accessed 1 October 2026.
- Caruna in brief. Caruna. accessed 1 October 2026.
- Elenia Verkko Oyj consolidated financial statements 2025. Elenia, 2026. accessed 1 October 2026.
- Sähkön pientuotannon ja sähkövarastojen tekniset vaatimukset. Caruna, 2025. accessed 1 October 2026.
- Verkkopalveluhinnasto 1.1.2026 alkaen. Oulun Energia, 2026. accessed 1 October 2026.
- Sähkövero (electricity tax). Verohallinto (Finnish Tax Administration), 2026. accessed 1 October 2026.
- Kotitalousvähennyksen määrä. Verohallinto (Finnish Tax Administration), 2026. accessed 1 October 2026.
- Tukihaku avattu energiateknologian suurten demonstraatiohankkeiden investointitukeen. Finnish Government (Valtioneuvosto), 2026. accessed 1 October 2026.
- Lausunnolle lakiehdotus sähkömarkkinalain markkinapohjaisen kuormanohjauksen käyttöönoton porrastuksesta sähkön jakeluverkossa. Finnish Government (Valtioneuvosto), 2026. accessed 1 October 2026.
- Finland sends the EU-required National Energy and Climate Plan to the Commission. Finnish Government (Valtioneuvosto), 2024. accessed 1 October 2026.
- New Climate Change Act into force in July. Ministry of the Environment, 2022. accessed 1 October 2026.
- SESKOn aurinkosähkösuositus 2024. SESKO ry, 2024. accessed 1 October 2026.
- Taloyhtiön aurinko-opas: Aurinkosähköjärjestelmän luvat. Turku University of Applied Sciences (NERC), 2025. accessed 1 October 2026.
- Electricity products and prices. Helen. accessed 1 October 2026.
- Sähkön pientuotannon ostosopimukset vertailussa – nämä yhtiöt ostavat ylijäämäsähköä ilman välityskuluja. VertaaEnsin.fi (via STT Info), 2024. accessed 1 October 2026.
- Sähköisen liikenteen tilannekatsaus Q4/2025. Teknologiateollisuus (Technology Industries of Finland), Traficom data, 2026. accessed 1 October 2026.
- Development of Finnish mobile networks. Traficom, 2026. accessed 1 October 2026.
- Urban population (% of total population) – Finland (SP.URB.TOTL.IN.ZS). World Bank, 2025. accessed 1 October 2026.
- Fixed broadband subscriptions (per 100 people) – Finland (IT.NET.BBND.P2). World Bank / ITU, 2024. accessed 1 October 2026.
Questions about energy in Finland.
Eurostat put the average household price at EUR 0.225/kWh including all taxes in the second half of 2025, well below the EU average of EUR 0.290. The Energy Authority’s 2025 average for a household using 5,000 kWh a year was 20.23 c/kWh: 6.84 c network, 6.96 c energy and 6.44 c taxes. That is about EUR 1,010 a year.
The käyttöpaikkatunnus, an 18-digit GS1 GSRN number that the local DSO creates for each accounting point, beginning with the DSO’s GS1 prefix (country code 64, usually 643…). It stays with the property, is printed on network bills and is the key to the accounting point in Fingrid’s national Datahub.
Yes. You notify your DSO, have the system installed by a Tukes-registered electrical contractor and sign a purchase contract with a retailer, which normally pays the spot price minus a small margin. For sites of up to 100 kVA, consumption and production are first netted within each metering period. There is no feed-in tariff.
Fingrid Oyj, majority-owned by the State, owns and operates the transmission grid and is the system operator. Local distribution is run by 77 licensed DSOs, the largest being Caruna and Elenia, under regulation by the Energy Authority (Energiavirasto).
Yes. More than 99% of customers have remote-read meters, owned and read by their DSO. All metering data goes to Fingrid Datahub, where customers can view it. DSOs are replacing hourly meters with 15-minute meters, a programme due for completion by the end of 2028.
Through an aggregator, yes. Fingrid’s FCR-N reserve accepts bids from 0.1 MW and allows independent aggregation, so many small batteries can be pooled. Batteries can also cut bills under exchange-price contracts by shifting consumption to cheap 15-minute periods.
It depends on the municipality. Many exempt ordinary rooftop panels or require only a notification to building control, while panels that significantly affect the townscape need a building permit. The DSO’s commissioning permission and the contractor’s inspection are always required.