How electricity works in Sweden.
Sweden electricity market 2026: Ei, Svenska kraftnät, bidding zones SE1–SE4, ~170 DSOs, anläggnings-ID, smart meters, solar export, grön teknik tax reduction.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Swedish krona (SEK) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Sweden energy at a glance.
Key figures for households in Sweden. Each one links to its source on the full overview below.
Electricity price.
2.992 SEK per kWh for households, including taxes. Figures for 2025-H2.
Household use.
8,284 kWh a year for a typical household. Figures for 2024.
Renewable share.
71% of electricity from renewable sources. Figures for 2025.
Selling back to the grid.
Can homes export electricity? Yes. Details are in the export section below.
Four things to check in Sweden.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Sweden below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Sweden requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Sweden.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Sweden, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Sweden, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Sweden.
The energy market in Sweden, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 1 October 2026.
On this page22 sections
Sweden has a fully liberalised electricity market. Households choose their electricity supplier (elhandelsföretag) freely, while the local network company (elnätsföretag) that owns the wires is a regulated monopoly. The Swedish Energy Markets Inspectorate (Energimarknadsinspektionen, Ei) regulates network tariffs and market rules, and the state utility Svenska kraftnät owns and operates the national transmission grid (stamnätet) and is the system operator. The country is divided into four bidding zones, SE1 (Luleå) in the far north to SE4 (Malmö) in the south, and wholesale prices can differ sharply between them.
The power system is almost entirely fossil-free. In 2025 Sweden generated about 169.5 TWh: 68 TWh of hydropower, 45 TWh of nuclear, 39 TWh of wind, 12 TWh from combined heat and power (mainly biomass and waste) and 4.4 TWh of solar. Sweden is a large net exporter, with interconnectors to Norway, Finland, Denmark, Germany, Poland and Lithuania.
A household bill has three parts: the network charge, the supplier’s energy price and taxes. Energy tax on electricity was cut to 36.0 öre/kWh (excluding VAT) for 2026, from 43.9 öre in 2025, and 25% VAT applies on top. Rooftop solar is supported mainly through the grön teknik tax reduction (15% for solar, 50% for home batteries and EV chargers), while the 60 öre/kWh tax reduction for exported micro-production was abolished from 1 January 2026.
Energy snapshot.
Headline figures for electricity in Sweden. Each shows its data year and links to its source.
- Population10,605,500 peopleSource 131 Dec 2025
- Households5,002,600 householdsSource 231 Dec 2025
- Average household size2.11 people/householdSource 231 Dec 2025
- Electricity use per household8,284 kWh/yrSource 82024
- Household price (SEK)2.992 SEK/kWhSource 52025-H2
- Household price (EUR)0.271 EUR/kWhSource 52025-H2
- Renewable electricity share71%Source 82025
- Solar capacity5.541 GWSource 8end 2025
- Wind capacity18.3 GWSource 8end 2025
- Energy storage capacity0.37 GWSource 10July 2024
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Fully liberalised
- Homes can export to the grid
- Yes
- Home equipment in grid services
- Yes
- Regulator
- Energimarknadsinspektionen (Ei)
- System operator
- Svenska kraftnät (Affärsverket svenska kraftnät)
- Distribution networks
- More than 170 network companies; Vattenfall Eldistribution, E.ON Energidistribution and Ellevio own most of the regional grid and many local grids, the rest are mainly municipal or cooperative
- Currency
- Swedish krona (SEK)
- Voltage and frequency
- 230 V / 50 Hz
Electricity prices in Sweden.
- Household price (SEK)
- 2.992 SEK/kWh (2025-H2)Source 5Eurostat average household price, all taxes and levies included, consumption band 2,500–4,999 kWh/yr. Prices vary by bidding zone and network area.
- Household price (EUR)
- 0.271 EUR/kWh (2025-H2)Source 5Eurostat’s own EUR figure for the same series (band DC, all taxes included); no separate currency conversion applied. EU average for the same semester: EUR 0.2896/kWh.
- Typical annual electricity bill
- 5,465 SEK/yr (2024)Source 10Total annual electricity cost for an apartment in bidding zone SE3 using 2,000 kWh on a variable contract: SEK 1,927 for electricity (including VAT), SEK 1,970 network charges and SEK 1,568 tax and VAT. An electrically heated detached house using 20,000 kWh pays many times more.
Household price trend (SEK per kWh).Source 5
| 2019-H1 | 2.1385 SEK/kWh |
|---|---|
| 2019-H2 | 2.1866 SEK/kWh |
| 2020-H1 | 2.0407 SEK/kWh |
| 2020-H2 | 2.0803 SEK/kWh |
| 2021-H1 | 2.1419 SEK/kWh |
| 2021-H2 | 2.6465 SEK/kWh |
| 2022-H1 | 2.3871 SEK/kWh |
| 2022-H2 | 2.9533 SEK/kWh |
| 2023-H1 | 3.0177 SEK/kWh |
| 2023-H2 | 2.5342 SEK/kWh |
| 2024-H1 | 2.7726 SEK/kWh |
| 2024-H2 | 2.6967 SEK/kWh |
| 2025-H1 | 2.9445 SEK/kWh |
| 2025-H2 | 2.992 SEK/kWh |
What a bill is made of
Swedish households receive two separate charges, sometimes on one combined invoice: the network charge from the local network company and the energy charge from the chosen supplier. Energy tax (energiskatt) is collected through the network invoice. For 2026 it is 36.0 öre/kWh before VAT, down from 43.9 öre in 2025; households and service businesses in designated municipalities in the north (mainly in Norrbotten, Västerbotten and Jämtland) get a reduction of 9.6 öre/kWh. VAT of 25% applies to the whole bill.
Energiföretagen’s series for an electrically heated house on a variable contract shows how the split shifts with the spot price. In January 2026 the network charge was 46.0 öre/kWh, the supplier price 60.3 öre and taxes 71.6 öre, a total of 177.9 öre/kWh, with tax and VAT making up 40%. In January 2025, when spot prices were higher, the same customer paid 230.5 öre/kWh.
Regional differences
Prices differ in two ways. The wholesale price depends on the bidding zone: SE1 and SE2 in the north have surplus hydro and wind and usually much lower prices than SE3 and especially SE4, which depend more on imports and continental price levels. In 2024 the average day-ahead price was about EUR 27/MWh in SE1 and SE2, EUR 38.7/MWh in SE3 and EUR 53.6/MWh in SE4. Network charges vary by network company, as each of the roughly 170 companies sets its own tariff within a revenue cap set by Ei for each four-year regulatory period.
Network tariff design
Ei’s regulation EIFS 2022:1 would have required every network company to introduce demand-based (effekt) tariffs by 1 January 2027. After public criticism that they were hard for customers to understand, the government instructed Ei in March 2026 to repeal the regulation by 30 June 2026 and to propose a new, clearer model for demand charges by 12 April 2027. Some companies have since dropped their demand charges; others keep them.
Trend
Eurostat’s household price rose from about SEK 2.14/kWh in 2019 to a peak of SEK 3.02/kWh in the first half of 2023 and was SEK 2.99/kWh in the second half of 2025, slightly below the EU average in euro terms. The 2026 energy tax cut lowers bills by about 9.9 öre/kWh including VAT.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Variable | Yes | Variable (rörligt) contracts priced on the monthly average spot price in the customer’s bidding zone plus a supplier margin are the most common contract. 58.5% of households had a variable contract in December 2024 and SCB data published by Energiföretagen show 70% of contracts were variable-price in January 2026. |
| Dynamic | Yes | Hourly-price (timpris) contracts, and quarter-hour pricing since the day-ahead market moved to 15-minute periods on 1 October 2025, pass the spot price through for each period. 13.6% of customers had an hourly price contract in December 2024. They require the meter to report hourly or quarter-hourly values, which all modern Swedish meters do. |
| Fixed | Yes | Fixed-price contracts of one to three years are offered by most suppliers but have lost popularity since the 2022 energy crisis: 10% of customers in December 2024. |
| Regulated | No | There is no regulated retail price or price cap. A customer who does not choose a supplier, for example after moving, is placed on an assigned contract (anvisat avtal) with a supplier chosen by the network company; 7.8% of customers were on one in December 2024. These are usually more expensive than other contracts. |
| Time-of-use | Limited | Time-of-use pricing appears mainly in network tariffs rather than supplier contracts. Some network companies charge higher rates on winter weekdays or use demand (effekt) charges based on peak hourly use; 17 network companies applied demand tariffs for households in January 2024 and Ellevio introduced one for all house customers on 1 January 2025. |
Household prices compared with neighbouring countries (EUR per kWh).
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- 8,284 kWh/yr (2024)Source 8Derived: 36,950 GWh used in detached houses (24,592 GWh) and apartments in multi-dwelling buildings (12,358 GWh), divided by 4,460,455 electricity subscriptions in those dwellings (SCB data in Energiföretagen’s Energiåret 2025). Detached houses averaged about 11,700 kWh and apartments about 5,200 kWh. The figure is high by European standards because many houses are heated with electricity or heat pumps. Holiday homes are excluded.
- Average daily use per household
- 22.7 kWh/day (2024)Source 8Derived from the 8,284 kWh/yr average per detached-house and apartment subscription (÷ 365).
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 12,750 kWh/person/yr (2024)Source 8Derived: total national electricity use of 135 TWh in 2024 (all sectors, including losses) divided by the population at the end of 2024 (about 10,587,700, SCB). Residential use alone was about 40 TWh.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- 806,521 plug-in cars (end 2025)Source 26432,709 battery electric and 373,812 plug-in hybrid cars, 16% of the car fleet. Plug-in cars were about 61% of new registrations in 2025.
- Electric cooking
- Not identified from a reliable public source.
Swedish homes use a lot of electricity because electricity is a common heating source outside the district-heating networks. In 2024 detached houses used 24.6 TWh across 2.1 million subscriptions, apartments in multi-dwelling buildings 12.4 TWh across 2.4 million subscriptions, and holiday homes 3.2 TWh. Most apartment blocks are heated by district heating, so apartment electricity use is mainly appliances and lighting; detached houses typically use direct electric heating, electric boilers or, increasingly, ground-source, air-to-water or air-to-air heat pumps.
Consumption peaks in winter. The national peak hour of winter 2025/26 was 24,800 MWh/h on 12 January 2026 between 08:00 and 09:00, higher than the mild previous winter but below earlier cold winters. Household demand is very temperature-sensitive, and the network and capacity problems in SE3 and SE4 are greatest during cold spells.
Electric cars are spreading fast, with 16% of the car fleet plug-in at the end of 2025 and the highest share in Stockholm County (about 30%). Home charging is common for house owners and is supported by the 50% grön teknik tax reduction on charging points.
Housing and households.
- Dwellings
- 5,291,493 dwellings (31 Dec 2025)Source 3
- Owner-occupied
- 36.6% (31 Dec 2025)Source 3Dwellings held with freehold ownership (äganderätt), mostly detached houses. A further 24.0% are tenant-owned cooperative flats (bostadsrätt), which function much like owner-occupation.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- 41% (31 Dec 2025)Source 3Share of dwellings in one- and two-dwelling buildings (småhus). 90% of these are freehold.
- Apartments and flats
- 52% (31 Dec 2025)Source 3Share of dwellings in multi-dwelling buildings; 58% of these are rented and 42% cooperative. A further 6% are special housing (student, elderly) and 1% other.
- Urban population
- 88 % of population (2023)Source 4Population living in urban areas (tätorter, 200+ inhabitants). Including small localities (småorter) the figure is 90%.
The housing stock divides into two worlds that matter for energy. About 2.1 million detached and semi-detached houses are mostly owner-occupied, have their own electricity supply and roof, and are where nearly all rooftop solar, home batteries and heat pumps are installed. About 2.8 million flats in multi-dwelling buildings are split between rental flats (hyresrätt) and tenant-owned cooperative flats (bostadsrätt), where the housing cooperative (bostadsrättsförening) owns the building and roof.
In 2025, 38% of households lived in an owned detached house, 29% in a rented flat and 21% in a cooperative flat. Stockholm County is the exception: there, cooperative flats are the most common form. For multi-dwelling buildings, solar and charging investments are decided by the landlord or the cooperative’s board, and shared installations are often connected behind a single building connection.
How the grid works in Sweden.
- TransmissionSvenska kraftnät
- DistributionMore than 170 network companies; Vattenfall Eldistribution, E.ON Energidistribution and Ellevio own most of the regional grid and many local grids, the rest are mainly municipal or cooperative
- MeteringLocal network company, No central data hub (Ediel messaging)
- Supply5 or more retail suppliers
Physical flow
Svenska kraftnät’s transmission grid runs at 400 kV and 220 kV, with about 15,500 km of overhead line and 1,500 km of cable. Much of the generation is hydropower in the north (SE1 and SE2) and nuclear in SE3, while most consumption is in the south, so large north–south flows cross four "cuts" that define the bidding zones. Regional grids (mainly 40–130 kV), owned largely by Vattenfall Eldistribution, E.ON and Ellevio, carry power to local grids, which step down through 10–20 kV networks to the 400/230 V low-voltage grid. 5.6 million electricity users are connected at low voltage, and 74% of the 596,000 km network is underground cable.
Interconnectors link SE1 and SE2 with Norway and Finland, SE3 with Norway, Finland (Fenno-Skan) and Denmark (Konti-Skan), and SE4 with Denmark, Germany (Baltic Cable), Poland (SwePol) and Lithuania (NordBalt). Sweden is part of the Nordic synchronous area, together with Norway, Finland and eastern Denmark.
Commercial flow
Generators and suppliers trade on the day-ahead and intraday markets or bilaterally. Every supplier must be, or have a contract with, a balance responsible party (balansansvarig), which takes financial responsibility for imbalances settled by eSett in 15-minute periods. Svenska kraftnät balances the system in real time through frequency reserves (FCR, FFR, aFRR and mFRR) and the mFRR energy activation market. Network companies pay Svenska kraftnät transmission charges and recover their own costs through tariffs within Ei’s revenue cap.
Retail and data exchange
The supplier holds the customer relationship for energy, but the network company is the hub of the data flow: it registers which supplier serves each supply point, collects the meter readings, and sends hourly or quarter-hourly values to the supplier and the balance responsible party via Ediel. Customers pay the network company separately unless their supplier offers combined billing. A central data hub (elmarknadshubb) was planned for years but put on hold; the current government assignment is to propose a central data management tool for the existing market model.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry of Climate and Enterprise (Klimat- och näringslivsdepartementet) | Sets energy policy and legislation (Electricity Act 1997:857) and issues government assignments to Ei, Svenska kraftnät and the Swedish Energy Agency (Energimyndigheten), which handles statistics, energy policy analysis and support schemes. |
| Regulator | Energimarknadsinspektionen (Ei) | Grants network concessions, sets four-year revenue caps for network companies, issues regulations on metering, tariffs and customer information, supervises the retail market and runs the price comparison site Elpriskollen. |
| Regulator | Elsäkerhetsverket | National Electrical Safety Board: registers electrical installation companies, authorises electricians and enforces electrical safety rules, including for solar and battery installations. |
| TSO | Svenska kraftnät | State-owned transmission system operator. Owns the 400 kV and 220 kV transmission grid and the interconnectors, is the system balancing authority, procures frequency reserves and runs Ediel, the electronic messaging standard used between market parties. |
| DSO | Vattenfall Eldistribution | Part of the state-owned Vattenfall group. One of the three companies that own most of the regional grid, and a large local network owner across many parts of the country. |
| DSO | E.ON Energidistribution | Regional and local network owner, particularly in southern Sweden including Skåne, and in parts of central and northern Sweden. |
| DSO | Ellevio | Privately owned network company serving about 964,000 customers, including Stockholm and large areas of west and central Sweden; it also owns regional grid. |
| DSO | Municipal and cooperative network companies | The remaining 160-plus local network companies are mostly municipally owned (for example Göteborg Energi, Mälarenergi, Tekniska verken, Skellefteå Kraft, Jämtkraft) or small cooperatives, each with a geographically defined area concession. |
| Supplier | Electricity suppliers (elhandelsföretag) | About 140 suppliers report offers to Elpriskollen. The three largest had about 47% of customers at the end of 2024. Suppliers must be balance responsible themselves or have an agreement with a balance responsible party. |
| Metering | Local network company | The network company owns the meter, collects meter readings and reports them to the supplier, the balance responsible party and settlement. There is no separate competitive meter operator role. |
| Data hub / registry | No central data hub (Ediel messaging) | Each network company keeps its own register of supply points and sends switching, master data and meter values to suppliers via Ediel messages. A planned central hub was put on hold in 2020; Ei and Svenska kraftnät were asked in September 2025 to propose a central data tool, reporting by 30 September 2026. |
| Settlement | eSett | Nordic imbalance settlement company owned by the Swedish, Finnish, Norwegian and Danish TSOs; settles balance responsible parties’ imbalances in 15-minute periods. |
| Exchange | Nord Pool and other NEMOs | Day-ahead (15-minute products since 1 October 2025) and intraday trading for the four Swedish bidding zones, coupled with the rest of Europe. |
| Flexibility market | Local flexibility markets (sthlmflex, Effekthandel Väst, Skåne) | Network companies and Svenska kraftnät buy local capacity relief in Stockholm, Gothenburg and Skåne through market platforms; Ei regards these markets as still at an early stage. |
Compared with the UK system.
| UK concept | Sweden equivalent | How it works |
|---|---|---|
| DNO | Elnätsföretag (network company) | More than 170 network companies, each holding an area concession from Ei for a defined local network. Unlike Great Britain’s 14 regions, areas range from whole regions to a single town. Three companies also own most of the regional (40–130 kV) grid. |
| National Grid/NESO | Svenska kraftnät | One state body both owns the transmission grid and operates the system, including balancing and reserve procurement. There is no separate transmission owner. |
| MPAN | Anläggnings-ID (GSRN) with områdes-ID | An 18-digit number created by the network company from a GS1 prefix beginning 735999, plus a three-letter metering grid area code. Both are printed on the network invoice and needed to switch supplier. |
| MPRN | Gas: separate anläggnings-ID | Very few Swedish homes have mains gas (only parts of the south-west and Stockholm’s town gas network). Where they do, the gas network company assigns its own installation ID in the same way. |
| Meter operator | Network company (mätansvar) | The local network company is responsible for metering by law: it installs, owns and reads the meter. Customers and suppliers cannot appoint a different meter operator. |
| Supplier | Elhandelsföretag | Competitive suppliers, no licence or price cap. Switching is free, and the network company must be notified by the new supplier; customers who make no choice get an assigned contract. |
| Smart-meter infrastructure | Network-company AMR/AMI systems | No national communications network like DCC. Each network company runs its own meter collection system (radio mesh, power-line or mobile) and reports data via Ediel. All meters on supplies up to 63 A had to meet the 2025 functional requirements, including a customer HAN port. |
How a supply point is identified.
735999123456789018, områdes-ID ABC (fictional)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Anläggnings-ID (GSRN) |
| Who issues it? | The local network company (elnätsföretag), using a GS1 company prefix it receives from GS1 Sweden |
| Format | GS1 Global Service Relation Number: industry prefix 735999, a three-digit code unique to the network company (together the GS1 company prefix 735999XXX), a serial number chosen by the network company, and a final check digit. It is used together with a three-letter områdes-ID identifying the metering grid area. |
| Length | 18 digits (plus a separate 3-letter områdes-ID) |
| Stays with the property when you switch supplier? | Yes |
| Where to find it | Printed on the network company’s invoice and shown in the network company’s customer portal (Mina sidor). Supplier invoices and contracts often repeat it. The områdes-ID is on the same invoice. |
| Electronic access | The customer can log in to the network company’s portal to see the ID and meter values. Between companies, the ID is the key in Ediel messages for supplier switching, moves, master data and meter values; Svenska kraftnät administers the Ediel standard and assigns Ediel IDs to market parties. |
| Third-party access | There is no public look-up. A new supplier, aggregator or energy service company gets the ID from the customer or, with the customer’s power of attorney (fullmakt), from the network company. Installers need it when notifying a solar or battery installation to the network company. |
| Who keeps the register | Each network company keeps the register of supply points in its own area; there is no national central register. GS1 Sweden only allocates the number prefixes and does not record the individual IDs. |
| Register scope | Per DSO |
What the anläggnings-ID identifies
The anläggnings-ID identifies the point where a customer is connected to the network and where electricity is metered, not the meter itself. When the meter is replaced, the ID stays the same, and it stays with the property when occupants or suppliers change. A home that also produces electricity normally keeps the same supply point for import and export, and the network company records production at the same installation; separate production IDs are used for some larger plants. Svenska kraftnät and the Nordic reserve markets use the same 18-digit GS1 numbers to identify generation units.
How the number is built
GS1 Sweden gives every Swedish network company a GS1 company prefix starting 735999, followed by three digits unique to that company. The network company then numbers its own installations and adds a check digit calculated with the standard GS1 modulo-10 method, so systems can catch typing errors. Because all Swedish numbers share the 735999 prefix, people sometimes quote only the remaining digits on the phone. The three-letter områdes-ID (nätområdes-ID) shows which metering grid area the installation belongs to and, together with the anläggnings-ID, forms a unique identification for switching.
How switching and moving work
To switch supplier, the customer gives the new supplier their personal identity number, address, the start date, anläggnings-ID and områdes-ID. The new supplier notifies the network company through Ediel that it takes over from the chosen date; the network company confirms, reports meter readings at the switch, and informs the previous supplier. When someone moves in without choosing a supplier, the network company assigns one (anvisat avtal).
Who holds the register
Because there is no central hub, the authoritative record of each supply point, its supplier and its meter values sits in the network company’s own systems. This decentralised model is why Sweden has spent years on plans for a central data hub, comparable to Elhub in Norway or Datahub in Denmark. The current assignment to Ei and Svenska kraftnät is to propose a central data management tool for the existing market model.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Yes |
| Net metering | No |
| Net billing | No |
| How exported electricity is paid | Supplier-set price for surplus electricity (usually linked to the spot price) plus a small statutory network benefit payment (nätnytta) from the network company; no tax reduction for export from 2026 |
| Is there net metering? | No. Import and export are metered separately. Exported electricity is sold to a supplier and does not offset imported kilowatt-hours, so imported kWh still carry network charges, energy tax and VAT. |
| Do microproducers pay to connect or feed in? | Under the Electricity Act, a customer with a main fuse of at most 63 A whose production can feed in at no more than 43.5 kW pays no fee for feeding in electricity, and no separate fee for connecting the production unit at an existing supply point within the existing subscription capacity. |
| What else is paid for exported electricity? | The network company must pay compensation for the value the production brings to its network (reduced losses and reduced charges to the higher-voltage grid). In practice this is a few öre per kWh and varies by network company. |
| Is the 60 öre/kWh tax reduction still available? | No. The tax reduction for micro-production of renewable electricity (60 öre/kWh, up to 30,000 kWh and SEK 18,000 a year) was abolished from 1 January 2026; electricity fed in after 31 December 2025 does not qualify. |
| Is income from selling surplus electricity taxed? | Sales are declared as income from a private residence, but a standard deduction of SEK 40,000 a year per residence is applied first, so most households pay no tax on it. |
| Which technical rules apply? | Inverters must meet the EU Requirements for Generators (RfG) as supplemented by Ei’s regulation EIFS 2018:2; production units from 0.8 kW are Type A. Energiföretagen’s ALP handbook and SS-EN 50549-1 set out how network companies apply the requirements on the low-voltage grid. |
| Is plug-in (balcony) solar allowed? | No. Elsäkerhetsverket decided in 2022 that solar panels connected through an ordinary plug do not meet Swedish electrical safety requirements and banned their sale, and reaffirmed this in 2026. A small system must be permanently installed by a registered electrical installation company and notified to the network company. |
Connecting a home system.
- Choose an electrical installation company registered with Elsäkerhetsverket for electrical production installations; private individuals may not do the electrical work themselves.
- The installer sends a pre-notification (föranmälan) to the local network company before work starts, giving the anläggnings-ID, inverter data and planned capacity.
- The network company checks whether the connection, fuse size and meter are adequate and gives installation consent (installationsmedgivande); meter changes or network reinforcement are handled at this stage.
- The installer installs and commissions the system and sends a completion notice (färdiganmälan); the system may only be put into operation once the network company accepts it.
- The household signs a contract with an electricity supplier to buy its surplus (not necessarily the same supplier as for import).
- The network company registers production at the supply point and starts reporting the exported quarter-hourly or hourly values to the buyer of the surplus.
Households can export surplus electricity and be paid for it, but Sweden has never had net metering. Export is priced in the market: suppliers that buy surplus electricity typically pay the spot price for the hour or month, sometimes with a small premium or deduction, and the network company adds its network benefit payment. With the 60 öre/kWh tax reduction gone from 2026, the value of exported electricity has fallen sharply, which makes self-consumption, batteries and smart control more important than export.
The connection process runs through the local network company and is carried out by the installer. Small systems on an existing house connection usually need no reinforcement, but the network company can require a larger fuse, a meter change or export limits where the local low-voltage grid is weak. Production is metered by the same meter as import, which records exported energy separately.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity | No licence to generate. Connection needs an agreement with the network company. Large plants need environmental permits under the Environmental Code and, for wind power, municipal approval; household solar needs neither. | Network company; county administrative board (länsstyrelsen) and municipality for large plants | All production must be covered by a balance responsible party, normally the supplier that buys the output. |
| Store electricity | No licence. Batteries connect under the same rules as production. Network companies are generally not allowed to own storage except in limited cases set out in the Electricity Act. | Ei; network company | Large battery parks have been notified to or permitted by county administrative boards; 130 parks were approved in 2021–2025. |
| Export to the grid | No licence. Requires notification and acceptance by the network company (föranmälan and färdiganmälan) and a contract with a buyer for the surplus. | Network company | Free feed-in for customers with fuses up to 63 A and up to 43.5 kW of feed-in capacity. |
| Supply (sell) electricity to consumers | No supply licence. A supplier must be balance responsible or contract with a balance responsible party, use Ediel, and report its offers for customers using up to 100,000 kWh/yr to Elpriskollen (EIFS 2020:4). | Ei (supervision); Svenska kraftnät (balance agreement) | Consumer contracts are also covered by the Electricity Act’s customer protection rules and the Swedish Consumer Agency. |
| Distribute electricity (build or operate networks) | Network concession (nätkoncession) needed for power lines, either for a line or for an area. Internal networks within a property, and some other networks listed in Ordinance 2007:215, are exempt (IKN). | Ei | Network companies may not trade or produce electricity (legal unbundling) and are subject to revenue caps. |
| Aggregate (aggregation services) | No licence. Since 1 June 2023 the Electricity Act sets rules for aggregation service providers; they must notify the customer’s network company before providing the service, and suppliers may not impose unreasonable fees or conditions on customers who use one. | Ei | Independent aggregators do not need the customer’s supplier’s consent. |
| Trade wholesale electricity | No energy licence. Market participants need balance responsibility or a BRP contract and must register under REMIT. | Ei (REMIT); Finansinspektionen for financial instruments | Day-ahead and intraday trading through NEMOs such as Nord Pool. |
| Balancing and frequency reserves | No licence. Become a balancing service provider (BSP) by signing Svenska kraftnät’s BSP agreement and pre-qualifying each reserve unit or aggregated group. | Svenska kraftnät | Minimum bids: 0.1 MW for FCR-N and FCR-D, 0.5 MW for FFR, 1 MW for aFRR and mFRR (capacity and energy activation). |
| Local flexibility services | No licence. Register on the platform used by the network company (for example the sthlmflex market in Stockholm) and meet its metering and dispatch requirements. | Network companies; Svenska kraftnät | Markets are local and project-based; requirements differ between platforms. |
| Remote control of household assets (VPP) | No specific licence. A provider that pools and controls home batteries, heat pumps or chargers operates as an aggregator or BSP and needs the customer’s agreement and, for reserves, Svenska kraftnät pre-qualification. | Svenska kraftnät; Ei | Skatteverket confirmed in July 2024 that using a home battery partly for reserves or price arbitrage does not remove the right to the grön teknik tax reduction, provided it also stores self-produced electricity. |
| Electrical installation work | Only an electrical installation company registered with Elsäkerhetsverket, working under its self-control programme with an authorised electrician, may install solar or battery systems. | Elsäkerhetsverket | Check a company with Elsäkerhetsverket’s "Kolla elföretaget" service; the business type must include electrical production installations. |
Sweden regulates networks heavily but competitive activities lightly. The Electricity Act’s main licence is the network concession: nobody may build or use a power line without one, unless it falls under an exemption such as an internal network within a property. Generation, storage, supply, trading and aggregation need no licence, but they are bound by market agreements: balance responsibility with Svenska kraftnät, Ediel messaging, the BSP agreement for reserves, and Ei’s information and customer protection rules.
For households, the practical requirements are electrical safety and network notification. The installation must be carried out by a registered electrical installation company, the network company must accept it before it is put into operation, and a buyer must be contracted for any surplus.
Flexibility and grid services.
Aggregation of home equipment: Yes
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| FCR-N (normal frequency containment) | Yes | 0.1 MW | Yes | Svenska kraftnät. Symmetrical up and down regulation within 49.9–50.1 Hz, procured daily. Aggregated household batteries and other small units take part through balancing service providers. |
| FCR-D up / FCR-D down (disturbance) | Yes | 0.1 MW | Yes | Svenska kraftnät. Activated between 49.9 and 49.5 Hz (up) or 50.1 and 50.5 Hz (down), with at least 20 minutes’ endurance. Batteries have become a major source of these reserves. |
| FFR (fast frequency reserve) | Yes | 0.5 MW | Yes | Svenska kraftnät. Very fast upward response (0.7–1.3 seconds) when system inertia is low, mainly in summer. |
| aFRR (automatic frequency restoration) | Yes | 1 MW | Yes | Svenska kraftnät. Automatic activation on frequency deviations, with full activation within 5 minutes and one hour of endurance. |
| mFRR capacity and energy activation | Yes | 1 MW | Yes | Svenska kraftnät. Svenska kraftnät runs a daily national mFRR capacity market; the Nordic energy activation market has cleared in 15-minute periods since 4 March 2025, with 12.5-minute full activation. |
| Day-ahead and intraday (implicit flexibility) | Yes | — | Yes | Nord Pool and other NEMOs. 15-minute day-ahead products since 1 October 2025. Households reach this market through hourly or quarter-hourly price contracts and smart control of heating, charging and batteries. |
| Local flexibility markets | Developing | — | Yes | Network companies (Ellevio, Vattenfall Eldistribution, E.ON, Göteborg Energi) and Svenska kraftnät. Projects such as sthlmflex in Stockholm, Effekthandel Väst in Gothenburg (since 2022) and markets in Skåne buy capacity relief in congested areas. Ei found them still at an early stage in its 2023 and 2025 reviews. |
Sweden is one of Europe’s most open markets for small flexible assets. Svenska kraftnät’s frequency containment reserves accept bids from 0.1 MW and allow aggregation of many small units, even across different balance responsible parties. Home batteries, EV chargers and heat pumps are pooled by aggregators and balancing service providers into FCR bids, and batteries have quickly taken a large share of FCR-D. Reserve prices have fallen as battery capacity has grown, so revenues are increasingly combined with spot-price arbitrage and peak shaving.
Since 1 June 2023 the Electricity Act has given independent aggregators a legal footing. They must notify the customer’s network company before providing their service, and suppliers may not penalise customers who use them. The EU network code on demand response, still being finalised, is expected to standardise local flexibility procurement by network companies.
Flexibility and aggregation platforms.
| Platform or aggregator | What it does |
|---|---|
| Svenska kraftnät reserve markets and Mimer | Svenska kraftnät publishes reserve volumes and prices on Mimer; bids are submitted through the BSP agreement and Nordic market systems. |
| sthlmflex | Local flexibility market for the Stockholm region involving Ellevio, Vattenfall Eldistribution and Svenska kraftnät. |
| Effekthandel Väst | Local flexibility market in the Gothenburg area, established in 2022. |
| Elpriskollen | Ei’s price comparison site for supply contracts, including hourly price contracts used by flexible customers. |
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | Second-generation rollout: all meters on supplies up to 63 A had to meet seven new functional requirements by 1 January 2025; other meters by 1 January 2030 |
| Reading interval | At least hourly by law; quarter-hourly for producers and increasingly for consumers as settlement moved to 15 minutes |
| Responsible party | Local network company (mätansvar); the customer cannot choose another meter operator |
| First generation | Monthly remote reading required for all customers from 1 July 2009 |
| Second generation deadline | 1 January 2025 for meters at supplies with fuses up to 63 A |
| Customer interface | HAN port on the meter giving near-real-time data to the customer’s own equipment |
| Other required functions | Extended measured quantities (voltage, current, active and reactive power both ways), remote reading, outage registration and hourly registration |
| Data access | Through the network company’s customer portal; third parties with the customer’s consent; data sent to suppliers via Ediel |
Sweden was among the first countries to make remote meter reading universal. Rules adopted in 2003 required monthly meter readings for all customers from July 2009, which led network companies to install remotely read meters almost everywhere. In 2012 customers on supplies up to 63 A gained the right to hourly metering at no extra cost if they chose an hourly price contract.
Because first-generation meters were reaching the end of their life and lacked newer functions, the government adopted seven functional requirements in 2018. They include an open customer interface (HAN port), more measured quantities, remote reading, outage alarms and registration of active energy every hour, with quarter-hour registration for producers. Meters at supplies up to 63 A had to comply by 1 January 2025. With imbalance settlement and the day-ahead market now running in 15-minute periods, the remaining hourly values are divided into quarter-hours where meters do not yet report 15-minute data.
The meters remain the network company’s assets, and their cost is included in the network revenue cap. There is no national communications system: each company runs its own data collection by radio, power-line communication or mobile network.
Renewable electricity.
Electricity generation mix (2025).
- Hydropower: 40.1%
- Nuclear: 26.5%
- Wind: 23%
- Combined heat and power (mainly biomass and waste): 7.1%
- Solar: 2.6%
- Condensing and other thermal: 0.6%
- Renewable electricity share
- 71% (2025)Source 8Derived: hydro (68 TWh) + wind (39 TWh) + solar (4.4 TWh) + biofuel-fired CHP (8.9 TWh) out of 169.5 TWh total generation. Waste-fired CHP (2.1 TWh) is excluded although part of it is biogenic. Nuclear supplies a further 26.5%, so electricity generation is about 99% fossil-free. Eurostat’s RES-E indicator, which compares renewable generation with gross consumption, was 89.2% in 2025 because Sweden exports much of its output.
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- 0.7 GW (2025)Source 9Increase in installed solar capacity from 1 January 2025 to 1 January 2026, rounded; Svenska kraftnät notes solar figures include estimates. 21,600 new grid-connected installations were added in 2025, 7% more than the year before.
- Hydropower
- 16.3 GW (end 2025)Source 8
- Wind
- 18.3 GW (end 2025)Source 8
- Nuclear
- 7.012 GW (end 2025)Source 8
- Solar PV
- 5.541 GW (end 2025)Source 8
- CHP (district heating and industry)
- 4.872 GW (end 2025)Source 83,288 MW in district heating plus 1,584 MW in industry.
Targets.
- 100% fossil-free electricity production by 2040 (energy policy goal changed by the Riksdag on 20 June 2023 from 100% renewable).
- EU 2030 renewable energy and climate targets apply; Sweden already has one of the highest renewable shares in the EU.
Hydropower and nuclear have been the backbone of Swedish electricity since the 1980s, and wind power has grown to match them: installed wind capacity overtook hydro in 2024 and reached 18.3 GW at the end of 2025. Wind supplied 39 TWh in 2025. Investment has stalled, though: turbine orders in 2025 were just under 30 MW, the weakest year on record, and Green Power Sweden expects expansion to stop after the projects under construction are finished in 2027.
Solar is small but growing. Capacity reached 5.5 GW at the end of 2025 across about 314,600 grid-connected installations, but growth in the number of installations slowed to 7% in 2025, which the Swedish Energy Agency attributes to the weaker economy and reduced support for small producers. Large solar parks are now driving capacity growth, with the largest so far, 100 MW, commissioned in 2025. Most solar capacity is in SE3 and SE4.
Combined heat and power plants in district heating networks and industry, fuelled mainly by biomass and waste, supply about 12 TWh of electricity, mostly in winter when it is needed most.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- 0.37 GW (July 2024)Source 10Estimated operational battery capacity; more than 1,400 MW was under construction and more than 8,300 MW planned at that time. County administrative boards approved 130 battery parks totalling about 5 GW and 9.4 GWh in 2021–2025.
Battery storage has grown rapidly since 2022, driven by revenues from Svenska kraftnät’s frequency reserves, especially FCR-D. Ei estimated about 370 MW of batteries in operation in July 2024, and Green Power Sweden’s survey shows 130 battery parks with about 5 GW and 9.4 GWh approved by county administrative boards in 2021–2025. As reserve prices fall with more batteries, owners are combining reserve income with spot-price trading and network services.
Home batteries are supported by the grön teknik tax reduction of 50% of labour and material costs. Since July 2024 Skatteverket has accepted that a battery may be used partly for reserves or price arbitrage as long as it is connected to a home renewable installation and partly stores self-produced electricity. The end of the export tax reduction in 2026 has also made storing solar electricity for self-use more attractive.
Storage projects.
- Storen and Isbillen Power Reserve (Neoen): Grid-scale batteries in Ragunda, Jämtland: Storen (52 MW/52 MWh) opened in 2024 and Isbillen (93.9 MW/93.9 MWh) was built nearby.
- Pumped and reservoir hydro: Sweden’s large hydro reservoirs act as seasonal storage and provide much of the system’s flexibility, but there is little dedicated pumped storage.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Vattenfall | — | Yes | No | Yes | Yes |
| E.ON | — | Yes | No | Yes | Yes |
| Fortum | — | Yes | No | Yes | Yes |
| Tibber | — | Yes | No | Yes | Yes |
| Göteborg Energi | — | Yes | No | Yes | Yes |
About 140 suppliers report offers to Ei’s Elpriskollen, but some only sell in their home region or bidding zone. The three largest suppliers had a combined 47% of customers at the end of 2024. About 9.3% of customers switched supplier in 2024 and a further 14.3% renegotiated their contract.
Smart meters belong to the network company, not the supplier, so every supplier can offer hourly or quarter-hourly prices to any customer. Most large suppliers buy surplus solar electricity at prices tied to the spot price; terms vary and should be compared, especially since the export tax reduction ended in 2026. Market shares of individual suppliers are not published officially.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Energimyndigheten (Swedish Energy Agency) | Government | National energy agency | Official energy statistics, including solar and wind statistics, guarantees of origin and energy policy analysis. |
| Energimarknadsinspektionen (Ei) | Regulator | Energy market regulator | Network tariffs, revenue caps, metering rules, consumer rules and Elpriskollen. |
| Elsäkerhetsverket | Regulator | Electrical safety authority | Registers installation companies and sets the safety rules for solar, batteries and chargers. |
| Svenska kraftnät | Transmission | TSO and system operator | Transmission grid, bidding zones, reserves, Ediel and power balance reports. |
| Energiföretagen Sverige | Distribution | Trade association for energy companies | Represents network companies, suppliers and producers; publishes connection handbooks (ALP, AMP) and annual statistics. |
| Svensk Solenergi | Solar | Solar industry association | Industry body for solar companies and installers. |
| Green Power Sweden | Renewable Energy | Wind, solar and storage association (formerly Svensk Vindenergi) | Quarterly statistics on wind, solar and battery projects and the battery park survey. |
| Energimarknadsbyrån | Consumer | Consumer advice on energy contracts | Independent advice for households on supply contracts, network charges and complaints. |
| eSett | Market | Nordic imbalance settlement | Settles imbalances for Swedish balance responsible parties. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Generator connection requirements | EU RfG (Regulation 2016/631) + EIFS 2018:2 | European Commission; Ei | Ei’s regulation sets the Swedish general requirements and type thresholds; Type A covers units from 0.8 kW up to 1.5 MW, including household inverters. |
| Grid connection (low voltage) | SS-EN 50549-1 | SIS / CENELEC | Requirements for generating plants connected in parallel to the low-voltage distribution network (up to Type B); current version 2019 with A1:2024. |
| Network company guidance | ALP handbook (Anslutning av elproduktion till lågspänningsnätet) | Energiföretagen Sverige | Industry guidance used by network companies for connecting production to the low-voltage grid; the AMP handbook covers medium voltage. |
| Inverter settings | Rikta rätt | Energiföretagen Sverige | Manufacturers apply to Energiföretagen’s Rikta rätt with a declaration that a Type A inverter (0.8 kW–1,500 kW) meets RfG, EIFS 2018:2, Swedish protection settings based on SS-EN 50549-1 and the ALP handbook (2025 form). |
| Installer registration | Elsäkerhetslagen (2016:732) registration and self-control programme | Elsäkerhetsverket | Solar and battery installation is electrical installation work that only registered companies with the business type for electrical production installations may carry out. |
| Smart meters | Ordinance 1999:716 functional requirements | Government; Ei | Seven functional requirements including HAN port, remote reading, outage registration and hourly registration; mandatory for meters up to 63 A from 1 January 2025. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Building permit (bygglov) for rooftop solar | Limited | Local | Not needed for panels mounted on an existing roof or façade that follow the building’s shape, on any building type, unless the building or area is especially valuable or near areas of national interest for total defence. Tilted-up panels, and many systems in protected areas, need a permit from the municipality. |
| Network company notification | Yes | National | The installer must send a pre-notification before work and a completion notice afterwards; the system may only be operated after the network company’s acceptance. |
| Registered electrical installer | Yes | National | Electrical work on solar and batteries must be carried out by a company registered with Elsäkerhetsverket. |
| Plug-in (balcony) solar | No | National | Not permitted: Elsäkerhetsverket banned sales of plug-in solar panels in 2022 and reaffirmed its position in 2026. |
| Environmental permit or notification for large parks | Limited | Regional | Ground-mounted solar and battery parks are handled by county administrative boards (consultation, notification or permit depending on size and site) and may also need a building permit. |
Since 2018 the Planning and Building Act has exempted most roof- and façade-mounted solar panels from building permits, provided they follow the building’s shape and the building or area is not especially valuable. Municipalities may still require a permit in detailed plans for protected areas, and panels mounted at an angle to the roof always need one.
The main steps for a household are therefore electrical and network-related rather than planning: hire a registered electrical installation company, let it notify the network company, and wait for the network company’s acceptance before switching on.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Grön teknik tax reduction | Active | Tax reduction (deducted on invoice) | 15% of labour and material costs for grid-connected solar PV (20% for work before 1 July 2025), 50% for storage of self-produced electricity and 50% for EV charging points, up to SEK 50,000 per person per year. Applies to the buyer’s own home; the installer deducts it on the invoice and claims it from Skatteverket. | Since 1 January 2021 (solar rate 15% since 1 July 2025) |
| Tax reduction for micro-production of renewable electricity | Closed | Export payment (tax reduction) | 60 öre per kWh fed into the grid, up to 30,000 kWh and SEK 18,000 a year, for supplies with fuses up to 100 A. Electricity fed in after 31 December 2025 does not qualify. | Until 31 December 2025 |
| Network benefit compensation (nätnytta) | Active | Export payment | Statutory payment from the network company for reduced losses and reduced charges to the higher-voltage grid; typically a few öre per kWh exported. | — |
| Free feed-in for microproducers | Active | Fee exemption | Customers with fuses up to 63 A and up to 43.5 kW feed-in pay no fee for feeding in or for connecting the production unit within their existing capacity. | — |
| SEK 40,000 standard deduction on sales of surplus electricity | Active | Tax treatment | Income from selling surplus electricity from a private residence is reduced by a standard deduction of SEK 40,000 a year per residence before tax. | — |
Data and connectivity.
- Fixed broadband
- 98 % of households and businesses with 1 Gbit/s available (1 Oct 2025)Source 2788% in sparsely populated areas. 86% have fixed broadband in the building and about 61% subscribe.
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
Fibre is widely available, so home energy devices, inverters and batteries can usually be connected over the household’s broadband. Network companies collect meter data over their own radio mesh, power-line communication or mobile networks.
The HAN port on second-generation meters gives the customer a local, near-real-time data stream. Third-party readers plugged into it are widely used by energy apps and battery and charger controllers to follow consumption and manage peaks, without having to go through the network company’s data systems.
Grid conditions.
- National peak demand
- 24.8 GW (winter 2025/26)Source 924,800 MWh/h on 12 January 2026, 08:00–09:00. The previous mild winter peaked at 22,470 MWh/h.
- Annual electricity demand
- 135 TWh (2024)Source 8Total electricity use including network losses.
- Generation capacity
- 54.3 GW (end 2025)Source 8SE1 8.7 GW, SE2 17.1 GW, SE3 20.2 GW, SE4 8.3 GW.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
The main constraint is geographic. Production is concentrated in the north and in SE3’s nuclear plants, while demand is concentrated in the south. Transmission limits between the zones often split prices: in 2024 SE4 averaged about twice the SE1/SE2 price. Svenska kraftnät introduced flow-based capacity calculation in 2024, which has probably increased price differences between bidding zones.
In winter 2025/26 Svenska kraftnät judged that the power balance at the peak hour was maintained with good margins. However, network capacity for new connections is a growing problem in parts of SE3 and SE4 and around large cities, where network companies report long queues for large connections. Household solar connections are rarely refused, but export limits or meter and fuse upgrades can be required where the local grid is weak.
Grid and capacity maps.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Energy tax on electricity cut to 36.0 öre/kWh | Current | 1 January 2026 | Down from 43.9 öre/kWh in 2025, excluding VAT. Customers in designated northern municipalities get a 9.6 öre/kWh reduction. |
| Micro-production tax reduction abolished | Current | 1 January 2026 | The 60 öre/kWh tax reduction for exported renewable electricity ended for electricity fed in after 31 December 2025. |
| Grön teknik rate for solar cut to 15% | Current | 1 July 2025 | The tax reduction for solar installation was lowered from 20% to 15%; batteries and EV chargers remain at 50%. |
| 15-minute day-ahead market | Current | 1 October 2025 | The European day-ahead market moved to 15-minute products, following 15-minute imbalance settlement and the 15-minute mFRR energy activation market (March 2025). |
| Mandatory demand tariffs dropped | Current | Government decision March 2026; repeal by 30 June 2026 | The government instructed Ei to repeal EIFS 2022:1, which would have required network companies to introduce demand-based tariffs by 1 January 2027. |
| New model for network demand charges | Upcoming | Proposal due 12 April 2027 | Ei must propose a transparent, non-discriminatory design for demand charges that customers can understand and act on. |
| Central data management tool for the electricity market | Upcoming | Proposal due 30 September 2026 | Ei and Svenska kraftnät were asked in September 2025 to propose a central tool to improve access to market data, including cost, timetable and ownership. The old data hub assignment was ended. |
| Supplier of last resort to replace assigned contracts | Upcoming | Proposed in SOU 2025:47 (no date set) | The Electricity Market Inquiry proposed abolishing assigned contracts; customers moving home would have to choose a supplier, and a supplier of last resort would be appointed in each network area. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Medium | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | High | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | High | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Medium | About 314,600 grid-connected solar installations at the end of 2025, roughly one for every 16 households, but growth slowed to 7% in 2025 after support was cut. |
| Distributed energy market | Medium | 5.5 GW of solar, fast-growing battery capacity and 806,521 plug-in cars, set against a system dominated by large hydro, nuclear and wind plants. |
| Grid flexibility market | High | Frequency reserves open to aggregated units from 0.1 MW, legal rules for independent aggregators since June 2023, 15-minute markets and local flexibility markets in Stockholm, Gothenburg and Skåne. |
| Energy storage adoption | Medium | About 370 MW of batteries operating in mid-2024 with more than 1,400 MW under construction and 5 GW approved in 2021–2025; home batteries supported by a 50% tax reduction. |
| Renewable growth environment | Medium | 1.4 GW of wind commissioned in 2025 and about 0.7 GW of solar added, but wind orders fell to under 30 MW in 2025 and expansion is expected to stop after 2027. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 33 sources
- Befolkningsstatistik helåret 2025. Statistics Sweden (SCB), 2026. accessed 1 October 2026.
- Hushållens boende 2025. Statistics Sweden (SCB), 2026. accessed 1 October 2026.
- Bostadsbeståndet 2025-12-31. Statistics Sweden (SCB), 2026. accessed 1 October 2026.
- Tätorter och småorter 2023. Statistics Sweden (SCB), 2023. accessed 1 October 2026.
- Electricity prices for household consumers – bi-annual data (nrg_pc_204). Eurostat, 2025-H2. accessed 1 October 2026.
- Share of energy from renewable sources (nrg_ind_ren), RES-E. Eurostat, 2025. accessed 1 October 2026.
- Skatt på el. Skatteverket, 2026. accessed 1 October 2026.
- Energiåret 2025. Energiföretagen Sverige, 2026. accessed 1 October 2026.
- Kraftbalansen på den svenska elmarknaden, rapport vår 2026. Svenska kraftnät, 2026. accessed 1 October 2026.
- Sweden’s electricity and natural gas market 2024 (Ei R2025:19). Energimarknadsinspektionen, 2025. accessed 1 October 2026.
- Smart meters in Sweden – lessons learned and new regulations (CIRED 2018). Energimarknadsinspektionen, 2018. accessed 1 October 2026.
- Svar på skriftlig fråga: Nya elmätare. Sveriges riksdag. accessed 1 October 2026.
- Grön teknik. Skatteverket, 2026. accessed 1 October 2026.
- Mikroproduktion av förnybar el – privatbostad. Skatteverket, 2026. accessed 1 October 2026.
- Prop. 2024/25:109 Förändrade skattesubventioner för solceller och mikroproduktion av el. Sveriges riksdag, 2025. accessed 1 October 2026.
- Uppdrag till Ei och Svenska kraftnät att ta fram förslag till ett centralt datahanteringsverktyg för elmarknaden (KN2025/01781). Regeringen / Energimarknadsinspektionen, 2025. accessed 1 October 2026.
- Uppdrag till Energimarknadsinspektionen att upphäva föreskrifter och lämna förslag om en ny utformning av effektavgifterna. Regeringen, 2026. accessed 1 October 2026.
- Identify and label electrical installations (GSRN). GS1 Sweden. accessed 1 October 2026.
- What is a GS1 code?. Svenska kraftnät. accessed 1 October 2026.
- Ordlista el och energi (anläggnings-ID, områdes-ID). Varberg Energi. accessed 1 October 2026.
- Ellag (1997:857). Sveriges riksdag. accessed 1 October 2026.
- Overview of the requirements for reserves (updated 24 March 2025). Svenska kraftnät, 2025. accessed 1 October 2026.
- Kvartalsstatistik fjärde kvartalet 2025. Green Power Sweden, 2026. accessed 1 October 2026.
- Batteriparksstatus 2025. Green Power Sweden, 2026. accessed 1 October 2026.
- Solcellsboomen kyls av – tillväxten rasar (citing Energimyndigheten). Börskollen, 2026. accessed 1 October 2026.
- Laddbara personbilar ökar – en av sex går att ladda. Trafikanalys, 2026. accessed 1 October 2026.
- Utbredd tillgång till snabbt bredband i Sverige – användningen kan öka. Post- och telestyrelsen (PTS), 2026. accessed 1 October 2026.
- Ändra fasad eller tak (solfångare och solcellspaneler). Boverket. accessed 1 October 2026.
- Vem får installera solceller?. Elsäkerhetsverket. accessed 1 October 2026.
- Solceller på balkongen ger 2 200 kronor lägre elräkning. Dagens PS, 2026. accessed 1 October 2026.
- EIFS 2018:2 – Ei:s föreskrifter om krav som gäller för nätanslutning av generatorer. Energimarknadsinspektionen (via lagen.nu). accessed 1 October 2026.
- SOU 2025:47 Spänning i tillvaron – hur säkrar vi vår framtida elförsörjning?. Sveriges riksdag / Regeringskansliet, 2025. accessed 1 October 2026.
- Vårändringsbudget för 2023 (FiU21) – energipolitiskt mål 100 procent fossilfri elproduktion. Sveriges riksdag, 2023. accessed 1 October 2026.
Questions about energy in Sweden.
Eurostat put the average household price at SEK 2.99/kWh (EUR 0.27) including all taxes in the second half of 2025. The price depends on the bidding zone, the network company and the contract. Energy tax for 2026 is 36.0 öre/kWh plus 25% VAT, and an apartment in SE3 using 2,000 kWh paid about SEK 5,465 in total in 2024.
The anläggnings-ID: an 18-digit GS1 number (GSRN) beginning 735999 that the local network company assigns to each supply point, used together with a three-letter områdes-ID. Both are printed on the network invoice and are needed to switch supplier.
Yes. You sell surplus electricity to a supplier, usually at a spot-linked price, and receive a small network benefit payment from your network company. There is no net metering, and the 60 öre/kWh tax reduction for exported electricity ended on 1 January 2026.
The grön teknik tax reduction covers 15% of labour and material costs for solar PV and 50% for home batteries and EV charging points, up to SEK 50,000 per person per year. The installer deducts it directly on the invoice.
They are Sweden’s four electricity bidding zones, from Luleå in the north (SE1) to Malmö in the south (SE4). Wholesale prices are set separately for each zone and are usually lowest in the north, where hydro and wind exceed local demand.
Usually not. Panels that follow the shape of the roof or façade are exempt from building permits unless the building or area is especially valuable. Tilted-up panels need a permit. The installation must be done by a registered electrical installation company and notified to the network company.
Your local network company. It owns, installs and reads the meter. Since 1 January 2025 meters on supplies up to 63 A must meet new functional requirements, including a HAN port that lets you connect your own equipment for real-time data.
Not yet. A planned hub was put on hold in 2020. In September 2025 the government asked Ei and Svenska kraftnät to propose a central data management tool, reporting by 30 September 2026. Until then each network company keeps its own customer and meter register.