Energy in Trinidad and Tobago, explained.

How electricity works in Trinidad and Tobago: prices, the grid and local rules. Olmack status: Not yet available. Information last checked 10 October 2026.

Olmack in Trinidad and Tobago: Not yet available.Olmack is not offered in Trinidad and Tobago yet. The market information on this page is provided for reference. Information last checked 10 October 2026.
Energy-market overview

How electricity works in Trinidad and Tobago.

Trinidad and Tobago electricity 2026: T&TEC single buyer, RIC-capped tariffs near TT$0.42/kWh, 99% gas-fired power, 92 MW Brechin Castle solar, no net metering.

This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Trinidad and Tobago dollar (TTD) where they relate to prices.

Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.

At a glance

Trinidad and Tobago energy at a glance.

Key figures for households in Trinidad and Tobago. Each one links to its source on the full overview below.

  • Electricity price.

    0.42 TTD per kWh for households, including taxes. Figures for 2023–2024 maximum tariffs.

  • Household use.

    7,524 kWh a year for a typical household. Figures for 2023.

  • Renewable share.

    0.1% of electricity from renewable sources. Figures for 2024.

  • Selling back to the grid.

    Can homes export electricity? No. Details are in the export section below.

Before you start

Four things to check in Trinidad and Tobago.

Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.

  1. Check the local rules.

    Read the connection, export and permission rules for Trinidad and Tobago below, and ask your local grid operator if anything is unclear.

  2. Choose a qualified installer.

    Look for an installer listed on an official register, with the certifications Trinidad and Tobago requires for the work.

  3. Look at current schemes.

    Check which support schemes are open now. Closed or scheduled schemes are labelled as such.

  4. Talk to your energy supplier.

    Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.

Local detail

Schemes, rules and certifications in Trinidad and Tobago.

The full detail sits in the sections below. Each item shows its status and links to the official source.

  • Support schemes.

    Grants, tax relief and export payments in Trinidad and Tobago, each labelled Active, Scheduled or Closed.

  • Connection and export.

    How equipment is connected to the grid in Trinidad and Tobago, and the steps to export electricity.

  • Standards and certifications.

    The technical standards and installer certifications that apply to energy equipment in Trinidad and Tobago.

Full overview

The energy market in Trinidad and Tobago, in detail.

Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.

Profile last updated 10 October 2026.

On this page22 sections

Trinidad and Tobago is a natural-gas producer, and almost all of its electricity is generated from domestic gas. Ember data put 2024 generation at 9.55 TWh, of which gas produced 99.5%, oil 0.4% and solar 0.1%. Electricity is supplied through a single-buyer model: the state-owned Trinidad and Tobago Electricity Commission (T&TEC) buys power from independent power producers, buys all the fuel they burn, dispatches every generator, owns and runs the whole transmission and distribution network across both islands, and bills every customer. T&TEC also owns the Cove power station in Tobago.

The Regulated Industries Commission (RIC) sets the maximum rates T&TEC may charge in five-year price reviews. Its Final Determination for 2023–2027 raised domestic tariffs for the first time since 2009, moved households from two-monthly to monthly billing and introduced four consumption tiers. Even after that increase, a household using the average 627 kWh a month pays about TT$0.42 per kWh including VAT, roughly €0.06, which is among the lowest residential prices in the Caribbean.

Renewable generation is at an early stage. The 92.2 MW Brechin Castle solar plant in Couva, developed with Lightsource bp, Shell and bp, began delivering power in July 2025. There is still no legal framework for households or independent renewable producers to sell electricity to the grid: the Ministry of Energy and Energy Industries states that the T&TEC Act and the RIC Act make no provision for renewable generation by independent producers, and the Government says it is finalising a Renewable Energy Policy.

Energy snapshot.

Headline figures for electricity in Trinidad and Tobago. Each shows its data year and links to its source.

  • Population1,367,764 peopleSource 212025
  • Households401,382 householdsSource 202011
  • Average household size3.31 people/householdSource 202011
  • Electricity use per household7,524 kWh/yrSource 12023
  • Household price (TTD)0.42 TTD/kWhSource 12023–2024 maximum tariffs
  • Household price (EUR)0.056 EUR/kWhSource 262023–2024 maximum tariffs
  • Renewable electricity share0.1%Source 272024
  • Solar capacity0.097 GWSource 302025
  • Wind capacity0 GWSource 312025
  • Energy storage capacityNot identified from a reliable public source.
  • Smart-meter shareNot identified from a reliable public source.
Market structure
Single buyer
Homes can export to the grid
No
Home equipment in grid services
No
Regulator
Regulated Industries Commission (RIC)
System operator
Trinidad and Tobago Electricity Commission (T&TEC), which dispatches all generating plant
Distribution networks
One national transmission and distribution network on both islands owned and run by T&TEC, managed through five distribution areas (Northern, Southern, Eastern, Central and Tobago)
Currency
Trinidad and Tobago dollar (TTD)
Voltage and frequency
60 Hz; domestic supply single-phase 2- or 3-wire at 115 or 230 V (three-phase at T&TEC’s discretion)

Electricity prices in Trinidad and Tobago.

Household price (TTD)
0.42 TTD/kWh (2023–2024 maximum tariffs)Source 1Derived for a 627 kWh month: the RIC gives a bill of TT$234.30 before VAT (customer charge TT$7.50 + 200 kWh at 0.28 + 427 kWh at 0.40), plus VAT at 12.5% as shown in the RIC’s sample residential bill = TT$263.59, i.e. TT$0.420/kWh. RIC tariffs may be adjusted annually to 2027; no later adjustment notice was found on the RIC website.
Household price (EUR)
0.056 EUR/kWh (2023–2024 maximum tariffs)Source 26Converted from TT$0.420/kWh at TT$7.563 per euro: the ECB reference rate of USD 1.1206 per euro on 9 October 2026 × the World Bank 2025 official rate of TT$6.7488 per US dollar (PA.NUS.FCRF).
Typical annual electricity bill
3,163 TTD/yr (2023–2024 maximum tariffs)Source 1Derived: TT$263.59 a month (627 kWh, incl. 12.5% VAT) × 12.

Household price trend (TTD per kWh).Source 5

0.3550.3870.422009-092023
Trinidad and Tobago household electricity price, TTD per kWh
2009-090.355 TTD/kWh
20230.42 TTD/kWh

Household electricity prices are set by regulation, not by a market. The RIC fixes the maximum revenue T&TEC may recover over a five-year control period and the tariff structure for each customer class. The second price review (PRE2) covers 2023–2027 and was the first tariff change since 1 September 2009. The RIC can carry out annual tariff adjustments during the period, and T&TEC must publish any new tariffs in a daily newspaper at least 21 days before they apply.

What changed in 2023

Under the 2009 rates households were billed every two months in three tiers (TT$0.26, 0.32 and 0.37/kWh) with a TT$6 two-monthly customer charge. The Final Determination switched to monthly billing, added a fourth tier and raised every tier. The RIC estimated that a household using 200 kWh a month would pay TT$63.50 before VAT (15% more), and one using the average 627 kWh would pay TT$234.30 (18% more). Bills at very high consumption rose most: up to 64% for 3,500 kWh a month.

Generation costs and subsidy

Fuel and generation costs are largely passed through. T&TEC buys all of the natural gas used by the independent power producers, and the RIC allowed 95% of projected fuel costs and 98% of capacity payments into rates for 2023–2027. Allowed fuel costs rise from TT$1.75 billion in 2023 to TT$2.26 billion in 2027. The Government’s 2026 budget described electricity as subsidised and introduced the commercial and industrial surcharge to reduce that burden, while stating that rates will remain well below those of trading partners.

VAT

RIC tariffs are quoted without VAT. The RIC’s sample residential bill applies VAT at 12.5% to the full bill, and the same rate is used for the prices on this page.

Price history

The chart compares the same 627 kWh-a-month household under both tariffs, including 12.5% VAT. The 2009 figure is derived from the rates still listed on T&TEC’s tariffs page (two-monthly bands of 1–400 kWh at TT$0.26, 401–1,000 kWh at TT$0.32 and over 1,000 kWh at TT$0.37, plus TT$6 per two months): 1,254 kWh costs TT$395.98 before VAT, about TT$0.355/kWh with VAT. The 2023 figure uses the RIC’s new tariffs as above.

Tariff types.

Tariff types.
TariffAvailableDetail
RegulatedYesResidential Rate A, 2023–2024 maximum tariffs approved by the RIC and billed monthly: TT$0.28/kWh for 1–200 kWh, 0.40 for 201–700 kWh, 0.54 for 701–1,400 kWh and 0.68 above 1,400 kWh, plus a customer charge of TT$7.50 a month. Prices exclude VAT. Rate A applies to supplies for one family in one residence from one meter.
Time-of-useNoNo time-of-use tariff exists. The RIC required T&TEC to study the feasibility of time-of-use rates and report within 24 months of the November 2023 Final Determination, noting that the existing AMI cannot support them.
DynamicNoThere is no wholesale market or retail competition, so no dynamic or spot-indexed tariff exists.
PrepaymentNoNo prepayment tariff appears among the RIC-approved rates. Residential customers pay a refundable service deposit and are billed in arrears.
OtherLimitedCommercial (B1, B2), industrial (C, D1–D5, E) and street-lighting classes have separate RIC tariffs. From 1 January 2026 the Government added an electricity surcharge of TT$0.05/kWh for commercial and industrial customers; residential customers, schools, hospitals and street lighting are exempt.

Household prices compared with neighbouring countries (EUR per kWh).

Household prices including taxes, converted to euros as stated on each country page.

Household electricity use.

Electricity use per household
7,524 kWh/yr (2023)Source 1Derived: the RIC’s average residential consumption of 627 kWh a month × 12. RIC forecasts for 2023 (3,257 GWh across 464,148 residential customers) imply about 7,017 kWh per account.
Average daily use per household
20.6 kWh/day (2023)Source 1Derived: 627 kWh a month × 12 ÷ 365.
Typical household peak demand
Not identified from a reliable public source.
Electricity use per person
6,334 kWh/person/yr (2024)Source 29All sectors (Ember via Our World in Data, 6,333.8 kWh). Industry, including petrochemical and steel plants, uses more electricity than households.
Heat pumps
Not identified from a reliable public source.
Air conditioning
Not identified from a reliable public source.
Electric vehicles
Not identified from a reliable public source.
Electric cooking
Not identified from a reliable public source.

Average household use is high for the region: the RIC’s reference customer uses 627 kWh a month, about 20 kWh a day. Cheap tariffs, a hot climate and widespread use of electrical appliances all contribute. Residential customers are forecast to use about 3,257 GWh in 2023, compared with about 4,164 GWh for industrial customers, which include world-scale petrochemical plants at Point Lisas.

Total demand is growing slowly. T&TEC’s forecast in the price review projected residential consumption rising from 3,257 GWh in 2023 to 3,458 GWh in 2027, and system peak demand from 1,371 MW in 2022 to 1,581 MW in 2027.

Electric vehicles

From 1 January 2022 the Government removed motor vehicle tax and VAT on imported battery electric vehicles. The 2026 budget proposed 10% duty and 12.5% VAT on electric vehicles with a CIF value above TT$400,000, keeping relief for cheaper models. Households can charge at home on the normal residential tariff; the RIC has considered, but not yet introduced, a separate EV charging rate.

Housing and households.

Dwellings
398,571 dwelling units (2011)Source 202011 Population and Housing Census Community Register total (366,009 buildings).
Owner-occupied
Not identified from a reliable public source.
Private rented
Not identified from a reliable public source.
Social or public housing
Not identified from a reliable public source.
Houses
Not identified from a reliable public source.
Apartments and flats
Not identified from a reliable public source.
Urban population
54 % of population (2025)Source 23World Bank (UN World Urbanization Prospects).

The 2011 census, the most recent with published results found, counted 401,382 households in 398,571 dwelling units, with an average of about 3.3 people per household. The next census was scheduled for 2022, but no results were found on the Central Statistical Office website.

Opening a T&TEC account requires proof of ownership (a deed or certificate of title), or, for tenants, a letter from the owner authorising the account. Most domestic supplies are single-phase, so rooftop systems and home chargers are normally connected on a single-phase service.

How the grid works in Trinidad and Tobago.

  1. TransmissionTrinidad and Tobago Electricity Commission (T&TEC)
  2. DistributionOne national transmission and distribution network on both islands owned and run by T&TEC, managed through five distribution areas (Northern, Southern, Eastern, Central and Tobago)
  3. MeteringT&TEC Metering Department
  4. Supply1 or more retail suppliers

Trinidad and Tobago runs as a single buyer. Four companies generate electricity: T&TEC, which owns the Cove power station in Tobago (maximum capacity 64 MW), and three independent power producers in Trinidad. These are the Power Generation Company of Trinidad and Tobago (PowerGen), with stations at Point Lisas and Penal; ContourGlobal Trinity Power, at Couva; and Trinidad Generation Unlimited (TGU), whose 720 MW combined-cycle plant at La Brea is not regulated by the RIC. T&TEC buys their output under long-term power purchase agreements, and the projected contracted capacity for 2023–2027 is 1,754 MW.

T&TEC buys all the natural gas burned by the generators and decides in real time which machines run. Because T&TEC pays for available capacity under take-or-pay contracts, this capacity has often been more than peak demand plus reserve. The RIC allows only 98% of capacity payments into tariffs.

From the power stations, electricity flows over T&TEC’s transmission network, including 220 kV lines introduced with the La Brea plant and 132 kV upgrades into Port of Spain, then through T&TEC’s distribution network to customers. Total system losses averaged 8.52% between 2016 and 2020, above the RIC’s 6.75% target.

The commercial flow is equally simple. Customers pay T&TEC under RIC tariffs; T&TEC pays the generators capacity and energy charges and pays for the fuel. Since July 2025 it has also bought solar power from the Brechin Castle plant, under costs the RIC has included in allowed conversion costs from 2025.

Who does what.

Who does what.
RoleOrganisationWhat it does
MinistryMinistry of Public Utilities (MPU)Line ministry for T&TEC and the RIC. The Minister grants generation and standby-generator licences, on the advice of the RIC or T&TEC. Its Government Electrical Inspectorate Division inspects and certifies installations before connection.
MinistryMinistry of Energy and Energy Industries (MEEI)Leads energy policy, including the Renewable Energy Policy being finalised, the Brechin Castle solar project and the wind resource assessment programme.
RegulatorRegulated Industries Commission (RIC)Sets maximum tariffs for T&TEC in five-year price reviews, sets quality-of-service standards for T&TEC and for three of the generating companies, and handles customer complaints.
TSOTrinidad and Tobago Electricity Commission (T&TEC)State-owned utility that owns the transmission network (66, 132 and 220 kV), plans and controls the system, and dispatches every generating station in real time.
DSOT&TEC distribution areasT&TEC is also the only distribution company, running five distribution areas (Northern, Southern, Eastern, Central and Tobago) over a network of about 24,900 km.
SupplierT&TECThe single buyer and only retailer. It buys power from the generators, buys their fuel, and bills all residential, commercial and industrial customers.
MeteringT&TEC Metering DepartmentOwns, installs, reads and tests all customer meters. T&TEC charges for a customer-requested meter test only if the meter is found accurate.

Compared with the UK system.

Compared with the UK system.
UK conceptTrinidad and Tobago equivalentHow it works
DNOT&TEC (five distribution areas)There is one distribution company for the whole country. T&TEC owns and runs every low- and medium-voltage line on both islands, so there is no regional choice of network operator.
National Grid/NESOT&TEC System ControlT&TEC also owns the transmission network and dispatches every power station, telling each generator how much to produce and which machines to keep on standby. There is no separate system operator or balancing market.
MPANT&TEC customer (account) number and meter numberThere is no national supply-point register or standard supply-point code. A connection is identified within T&TEC’s billing system by the customer’s account number and the serial number of the meter installed at the premises.
MPRNNo equivalent for electricityNatural gas is used mainly by industry and power stations; there is no piped-gas supply-point number for homes comparable to the MPRN.
Meter operatorT&TECT&TEC owns, installs, reads and tests meters. Customers cannot appoint their own meter operator.
SupplierT&TEC (sole retailer)There is no supplier choice. Every household is a T&TEC customer on the RIC-approved Residential Rate A.
Smart-meter infrastructureT&TEC Advanced Metering Infrastructure (AMI)T&TEC installed an AMI system in 2007–2009 for remote reading and outage detection. The RIC says most of these meters are near the end of their life, and about half of all meters are to be replaced during 2023–2027. There is no DCC-style national data service.

How a supply point is identified.

How a supply point is identified.
QuestionAnswer
What is it called?T&TEC customer account number (with meter number)
Who issues it?Trinidad and Tobago Electricity Commission (T&TEC)
FormatUtility-assigned account reference held in T&TEC’s billing system; the structure is not published. T&TEC’s online payment form accepts an account number of up to 19 characters. Transactions also quote the meter serial number.
LengthNot published
Stays with the property when you switch supplier?No
Where to find itOn the T&TEC bill, which also shows the meter number, meter readings and whether the reading was actual or estimated; the meter number is printed on the meter itself.
Electronic accessCustomers can check balances and pay through T&TEC’s online portal, quick-pay service and e-billing. No public interface for consumption data or downloads of interval data was found.
Third-party accessNo regulated third-party data access exists. Tenants and new occupiers deal with T&TEC directly when opening or transferring an account.
Who keeps the registerT&TEC customer and billing system
Register scopeNational

Trinidad and Tobago has no standardised supply-point code like an MPAN or an EAN. With only one utility, one network and no retail competition, there is no need for a switching register. T&TEC identifies each connection by the customer account in its billing system and by the meter installed at the premises.

How an account is opened, moved or closed

Accounts belong to customers rather than to properties. To open a residential account the customer shows proof of ownership (or, for a tenant, a letter from the owner), identification, a refundable service deposit per meter (TT$95 for a residential account) and an Inspection Certificate of Approval from the Government Electrical Inspectorate Division. When transferring an account to a new occupier, T&TEC asks for the meter number and a meter reading as close as possible to the transfer date. A fresh inspection certificate is needed if the property is new or has been without supply for more than three months. A departing customer must close the account in writing, quoting the customer number, meter number and a final reading. Otherwise they remain liable for charges run up by the next occupant.

Meter reading and billing

T&TEC’s customer pages say domestic meters are read every other billing period, with estimated bills in between, based on average consumption over the previous four bills. AMI meters can be read remotely and on demand. Customers can submit their own reading within five working days of the scheduled read date. The RIC’s 2023 determination moved all customer classes to monthly billing.

Who keeps the register

The only record of supply points is T&TEC’s customer and billing system, which covers both islands. The RIC monitors T&TEC’s service against its Quality of Service Standards but does not hold a separate register.

Sending electricity to the grid.

Sending electricity to the grid.
QuestionAnswer
Can homes export electricity?No
Net meteringNo
Net billingNo
How exported electricity is paidNone. There is no feed-in tariff, net-metering or net-billing scheme for customer-owned generation.
Can a household sell solar power to the grid?Not under current law. The Ministry of Energy and Energy Industries states that the T&TEC Act and the RIC Act make no provision for renewable generation by independent producers, and both Acts are under review.
Is a feed-in tariff planned?A UNEP-supported framework for feed-in tariff policy and legislation was prepared for the Ministry. In 2023 the RIC said a feed-in tariff policy allowing customers up to a set size to sell renewable energy was expected; the 2026 budget says a Renewable Energy Policy is being finalised. No scheme was in force at October 2026.
Can I install solar for my own use?Yes. Systems for self-consumption can be installed, but they need a GEID inspection and certificate before use. Standby or private generators also need a licence from the Minister of Public Utilities, granted on T&TEC’s recommendation.
Which technical rules apply?The national electrical wiring code was revised with a Part III covering renewable energy systems, prepared by a committee including TTBS, T&TEC, the RIC and the Inspectorate. Grid-tie inverter demonstration projects were installed at T&TEC’s Mount Hope headquarters and UTT’s O’Meara campus.

Connecting a home system.

  1. Renewable systems must be inspected by the Government Electrical Inspectorate Division (GEID) and receive an Inspection Certificate of Approval before they are used, as for any special equipment.
  2. Any wiring work must be carried out or supervised by a GEID-licensed wireman, who applies jointly with the owner for the inspection.
  3. No T&TEC procedure for exporting power to the grid or being paid for it has been published.

Trinidad and Tobago is one of the few Caribbean countries without a rooftop solar export scheme. Cheap gas-fired electricity has made such a scheme less of a priority, and the legal framework of the T&TEC Act (1945) and the RIC Act was written for a single utility buying from licensed thermal producers.

Stakeholders asked for households to be allowed to generate and connect renewable energy during consultation on the 2023–2027 price review. The RIC replied that this needs government policy, legislation and incentives, which are outside a price review. It pointed to its 2019 staff paper on renewable energy deployment in the electricity sector.

Until a framework exists, solar in homes and businesses is used only on site behind the meter, with or without batteries, and must still pass GEID inspection.

Licensing and approvals.

Requirements depend on the activity. The table sets out what each activity needs and who grants it.

Licensing and approvals.
ActivityLicence or registrationAuthorityNotes
Generate electricity for the gridLicence granted by the Minister responsible for public utilities, on the RIC’s advice; the Minister may exempt an entity under section 38 of the RIC ActMinister of Public Utilities / RICPowerGen, ContourGlobal Trinity Power and T&TEC are regulated generators; TGU is not listed in the RIC Act’s First Schedule and is unregulated.
Standby or private generator (incl. on-site generation)Licence required for all standby/private generators; fee TT$12 per kW, which may be waivedMinister of Public Utilities, on T&TEC’s recommendationT&TEC says it is unlawful to operate a generator without a valid licence. A GEID inspection certificate is also needed.
Renewable generation by independent producersNo licensing route; the T&TEC Act and RIC Act make no provision for itMinistry of Energy and Energy Industries (policy)Brechin Castle was developed as a government-backed project selling to T&TEC; a general framework is pending.
Store electricity (batteries)No specific storage licence; behind-the-meter systems need GEID inspectionGovernment Electrical Inspectorate DivisionNo grid-scale storage regime has been published.
Export / sell surplus to the gridNot permitted; no net-metering or feed-in framework—Pending the Renewable Energy Policy and amendments to the T&TEC and RIC Acts.
Transmission, distribution and retail supplyStatutory function of T&TEC under the T&TEC Act (Chap. 54:70)T&TEC / RICT&TEC is the sole transmission, distribution and retail utility.
Aggregation, VPP, balancing and grid servicesNo framework; no market exists—All balancing is done by T&TEC dispatching contracted thermal plant.
Wholesale tradingNo wholesale market; bilateral PPAs with T&TEC only—Generation costs are passed through under RIC rules.
Electrical installation workWireman’s licence, valid for two yearsGovernment Electrical Inspectorate Division (MPU)The licensed wireman applies jointly with the owner for preliminary and final inspections.
Remote control of customer assetsNo framework—No utility demand-response or direct load-control programme was found.

Licensing is concentrated on large thermal generators and on electrical safety. Generation licences are granted by the Minister, with the RIC advising, and the RIC Act lets the Minister exempt an entity, as happened with TGU. The RIC has asked for TGU to be brought under its oversight.

For households and small businesses the practical requirements are electrical safety ones: a licensed wireman, GEID inspection and a certificate before connection or before using equipment such as standby generators or renewable energy systems. The GEID publishes specific inspection requirements for renewable energy generation systems. In Tobago, inspectors of the Tobago House of Assembly follow the Chief Electrical Inspector’s guidelines.

Flexibility and grid services.

Aggregation of home equipment: No

Flexibility and grid services.
Market or serviceAccess for home equipmentMinimum sizeVia an aggregatorDetail
Balancing and reservesNo—NoT&TEC. T&TEC keeps spinning reserve by dispatching contracted thermal units; there is no market for third-party reserves or frequency response.
Demand response / time-of-useDeveloping—NoT&TEC / RIC. The RIC required T&TEC to study time-of-use tariffs and noted that new metering would be needed. AMI meters are mentioned as a way to enable demand-response programmes, but none has started.

There is no flexibility, capacity or ancillary-services market, and distributed assets cannot take part in system operation. Dispatch is centralised in T&TEC, which also buys all fuel.

The building blocks are being discussed rather than built: a time-of-use feasibility study, replacement of ageing AMI meters with equipment that could support price signals, and a future renewable energy framework.

Smart meters.

Smart meters.
FactValue
Smart-meter rolloutFirst AMI installed 2007–2009, now ageing; about half of meters due for replacement in 2023–2027
Reading intervalNot published
Owner / operatorT&TEC
First AMI deployment2007–2009
Replacement planAbout 50% of all meters during PRE2 (2023–2027); the RIC allowed 50% of the replacement capital cost from 2024
Time-of-use capabilityThe RIC states the existing AMI cannot support time-of-use rates
PenetrationNot published

T&TEC introduced an Advanced Metering Infrastructure system in 2007–2009 so that meters could be read remotely, without entering customers’ premises, and so that defective meters and outages could be detected early. The RIC notes that some features, such as full integration with an Outage Management System, were never completed. This delayed automatic payments to customers for breaches of the guaranteed standard on restoring supply.

In the 2023–2027 price review the RIC found that most AMI meters were nearing the end of their useful life and that their accuracy was declining. It allowed T&TEC to replace about half of all meters during the period. No public figure for the share of customers on AMI meters, or on the communications technology used, was found.

Renewable electricity.

Electricity generation mix (2024).

  • Natural gas: 99.5%
  • Oil: 0.4%
  • Solar: 0.1%
Source 27
Renewable electricity share
0.1% (2024)Source 27Ember data via Our World in Data: solar 0.10% of 9.55 TWh; gas 99.48%, oil 0.42%. Trinidad and Tobago does not import electricity, so the generation and consumption shares are the same. The 2024 figure predates the 92.2 MW Brechin Castle solar plant, which began delivering power in July 2025.
Home solar
Not identified from a reliable public source.
Solar added each year
0.092 GW (2025)Source 30Derived: IRENA capacity 96.6 MW (2025) minus 4.6 MW (2024), mainly the Brechin Castle plant.
Solar PV
0.097 GW (2025)Source 30
Wind
0 GW (2025)Source 31

Targets.

  • Reduce emissions from power generation, transport and industry by 15% by 2030 against business-as-usual (Nationally Determined Contribution).
  • Finalise a national Renewable Energy Policy (in preparation, 2026 budget).
  • Bankable onshore and offshore wind resource data by 2026; 2.75 GW onshore and 32 GW offshore wind potential identified.
  • Long-term aim of 25 GW of offshore wind and 1.5 million tonnes of green hydrogen by 2044 (2026 budget).

Until 2025 renewable electricity was negligible, at about 0.1% of generation in 2024 from small solar systems, including a solar park at Piarco International Airport. The 92.2 MW Brechin Castle plant in Couva changed this. It is a joint project of the Government, Lightsource bp, Shell Trinidad and Tobago and bp Alternative Energy Trinidad and Tobago, which began delivering power in July 2025. The Ministry expected it to supply the equivalent of 31,500 homes and avoid about 123,000 tonnes of CO₂ a year. IRENA data show national solar capacity rising from 4.6 MW in 2024 to 96.6 MW in 2025.

Wind is the next resource being studied. National Energy runs an onshore Wind Resource Assessment Programme, expanded in July 2025 with masts at Los Iros/Santa Flora and Toco/Manzanilla. The Ministry has also called for proposals for an offshore assessment, backed by an EU-funded National Wind Energy Action Plan.

Because gas is produced domestically and is cheap for power generation, the main case made for renewables is saving gas for export and petrochemicals and cutting emissions, not cutting household bills.

Energy storage.

Home batteries
Not identified from a reliable public source.
Grid-scale storage
Not identified from a reliable public source.

No grid-scale storage operates or has been announced in official sources reviewed, and no rules cover connecting batteries to the grid. Home batteries can be installed behind the meter as part of a self-consumption or backup system, subject to GEID inspection. Many households and businesses rely on standby generators for backup, and these need a licence.

Electricity suppliers.

Electricity suppliers.
SupplierMarket shareRenewable tariffTime of useDynamicExport tariff
Trinidad and Tobago Electricity Commission (T&TEC)100% (sole retailer)NoNoNoNo

T&TEC is the only electricity supplier. It served over 450,000 customers in 2014 and, by the RIC’s 2023 forecast, about 464,000 residential, 57,000 commercial and 4,000 industrial customers. Its customer services include 14 service centres, payment through banks and agents, online quick pay, e-billing and the Utilities Assistance Programme for eligible low-income households.

Key organisations.

Key organisations.
OrganisationCategoryWhat it doesWhy it matters
Ministry of Energy and Energy IndustriesGovernmentEnergy policy, renewable energy and wind programmesLeads the Renewable Energy Policy, the Brechin Castle project and the feed-in tariff framework.
Ministry of Public UtilitiesGovernmentLine ministry for T&TEC and the RIC; generation and generator licensingGrants licences and runs the Government Electrical Inspectorate Division.
Government Electrical Inspectorate Division (GEID)GovernmentInspects installations, enforces the wiring code, licenses wiremenIts Inspection Certificate of Approval is needed before connection and before using renewable energy systems.
Regulated Industries Commission (RIC)RegulatorEconomic regulator for electricity and waterSets T&TEC’s maximum tariffs and quality-of-service standards.
Trinidad and Tobago Electricity Commission (T&TEC)TransmissionSingle buyer, transmission, distribution, dispatch and retailRuns the whole grid and is every customer’s supplier.
National Energy Corporation of Trinidad and TobagoRenewable EnergyExecuting agency for the Wind Resource Assessment ProgrammeLeads wind measurement for future utility-scale wind projects.

Technical standards.

Technical standards.
AreaStandardIssued byNotes
Wiring and installationsTrinidad and Tobago Electrical Wiring Code (incl. Part III for renewable energy)Trinidad and Tobago Bureau of Standards (TTBS) / Electrical Wiring Code CommitteePart III covers renewable energy systems and their integration with the grid; enforced by the GEID.
Service connection“Wiring for Light and Power”, 8th edition (2005)T&TECT&TEC’s requirements and standards for connecting to the supply.
Supply qualityElectricity Supply Rules under the Electricity (Inspection) Act, Chap. 54:72Government of Trinidad and TobagoPermits voltage variation of 6% above or below declared voltage.
InspectionRenewable Energy Generation Systems Inspection RequirementsGovernment Electrical Inspectorate Division (MPU)Inspection requirements for PV and other renewable systems.
Solar water heatingTTS 106:2012 Solar water heater systems – design and installationTTBSPerformance, safety and installation requirements for solar water heaters.
Service qualityRIC Quality of Service Standards (electricity transmission and distribution; generating entities, 2021)RICGuaranteed and overall standards for T&TEC; performance reporting for regulated generators.

Permissions.

Permissions.
PermissionRequiredLevelDetail
Electrical inspection certificateYesNationalGEID Inspection Certificate of Approval required before first connection, after rewiring or supply changes, and before using standby generators or renewable energy systems.
Licensed wiremanYesNationalWiring work must be done or supervised by a GEID-licensed wireman.
Generator licenceYesNationalStandby and private generators need a licence from the Minister of Public Utilities on T&TEC’s recommendation (TT$12/kW fee, may be waived).
Utility approval to exportNoNationalNot available: no export or net-metering framework exists.

Permissions for small systems are about safety. The GEID inspection regime applies to every new or altered installation and to special equipment, and T&TEC will not connect or reconnect a supply without the certificate. Planning requirements for rooftop solar were not identified from official sources.

Support schemes, taxes and incentives.

Support schemes, taxes and incentives.
SchemeStatusTypeDetailPeriod
VAT zero-rating of solar PV panels, solar water heaters and wind turbinesActiveVAT reliefIntroduced by the Finance Act No. 13 of 2010 from 1 January 2011 and listed as a renewable energy incentive by the Ministry of Energy and Energy Industries. Check the current position with the Board of Inland Revenue.From January 2011
Solar water heater tax creditActiveTax credit25% of the cost of household solar water heating equipment up to TT$10,000 (maximum credit TT$2,500), as listed by the Ministry of Energy and Energy Industries.From January 2011
Wear-and-tear allowance on renewable equipmentActiveCapital allowanceAllowance of 150% of expenditure on wind turbines, solar PV systems and solar water heaters (business taxpayers), as listed by the Ministry.From January 2011
Utilities Assistance ProgrammeActiveBill assistanceWater and electricity bill relief for eligible households; the 2026 budget reported TT$7.2 million reaching more than 12,000 families, and TT$1.8 million for tanks and solar panels for rural households.—

Data and connectivity.

Fixed broadband
27 fixed subscriptions per 100 people (2024)Source 25World Bank / ITU. 82.2% of people used the internet in 2024 (IT.NET.USER.ZS).
4G coverage
Not identified from a reliable public source.
5G coverage
Not identified from a reliable public source.

Internet use is widespread: 82% of people used the internet in 2024, and the 2026 budget announced a TT$200 million fibre-to-the-home expansion by the state telecoms company TSTT. The communications technology of T&TEC’s AMI meters is not published, and there is no national smart-home or demand-response data standard.

Grid conditions.

National peak demand
1.356 GW (2021)Source 1T&TEC maximum demand (Table 6.1). T&TEC forecast 1,544 MW for 2026.
Annual electricity demand
9.55 TWh (2024)Source 28Total generation (Ember via Our World in Data); no imports or exports.
Generation capacity
1.754 GW (2023–2027)Source 1Projected contracted capacity at the IPPs’ power stations; excludes T&TEC’s 64 MW Cove plant and the Brechin Castle solar plant.
Interconnection
Not identified from a reliable public source.
Curtailment
Not identified from a reliable public source.

The system has a large thermal capacity margin: contracted capacity of about 1.75 GW against a 2021 peak of 1.36 GW. This reflects the take-or-pay contracts the RIC has discussed in its price reviews. Total system losses averaged 8.52% between 2016 and 2020.

Reliability is regulated through RIC Quality of Service Standards. In 2023–2027 T&TEC faces incentives and penalties linked to interruptions per feeder and to reducing losses by 0.15 percentage points a year.

Regulatory changes.

Regulatory changes.
ChangeStatusDateDetail
Electricity surcharge on commercial and industrial customersCurrent1 January 2026TT$0.05/kWh bill-level surcharge on commercial and industrial customers to reduce the electricity subsidy; residential customers, schools, hospitals and street lighting are exempt. Estimated to raise TT$269 million.
Brechin Castle 92.2 MW solar plantCurrentJuly 2025First utility-scale solar plant, delivering power to T&TEC since July 2025.
Renewable Energy Policy and amendments to the T&TEC and RIC ActsUpcomingNot yet announcedThe Government says it is finalising a Renewable Energy Policy; a feed-in tariff framework has been prepared, but laws allowing independent renewable producers and customer export are not yet in force.
AMI meter replacementUpcoming2024–2027About half of all meters are to be replaced during the 2023–2027 control period, as the 2007–2009 AMI meters reach end of life.
Time-of-use tariff studyUpcomingReport due within 24 months of the November 2023 Final DeterminationT&TEC must report to the RIC on the feasibility of time-of-use rates; no outcome had been published by October 2026.
National Budget 2027Upcoming12 October 2026To be presented to Parliament by the Minister of Finance; may contain new energy or electricity fiscal measures.
Next T&TEC price reviewUpcomingFor the period after 2027The current RIC control period (PRE2) covers 2023–2027; annual tariff adjustments may be made until then.

Market indicators.

Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.

Market indicators.
IndicatorLevelBasis
Electricity costLowLow below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros).
Household electricity useHighLow below 2,500 kWh a year, high at 5,000 kWh or more (average use per household).
Renewable shareLowLow below 30%, high at 60% or more (renewable share of electricity).
Smart-meter adoption—Low below 30%, high at 80% or more (share of meters that are smart).
Home solar adoptionLowNo net-metering or export scheme; no official residential solar figure; total solar was 4.6 MW before Brechin Castle (IRENA 2024).
Distributed energy marketLowLaws make no provision for independent renewable generation; distributed generation is limited to behind-the-meter systems and licensed standby generators.
Grid flexibility marketLowNo wholesale, balancing or ancillary-services market; T&TEC dispatches all plant; no time-of-use tariffs.
Energy storage adoptionLowNo grid-scale storage identified and no storage framework.
Renewable growth environmentMediumSolar capacity rose from 4.6 MW (2024) to 96.6 MW (2025) with Brechin Castle, from a base of 0.1% of generation; wind assessments and a Renewable Energy Policy are in progress.

Sources.

Public sources used for this profile, with the date each was accessed.

Show all 31 sources
  1. Final Determination for the Electricity Transmission and Distribution Sector of Trinidad and Tobago 2023–2028 (Price Review 2023–2027). Regulated Industries Commission, 2023. accessed 10 October 2026.
  2. New Maximum Electricity Rates – RIC’s Final Determination on T&TEC’s Price Review 2023–2027 (brochure). Regulated Industries Commission, 2023. accessed 10 October 2026.
  3. RIC New Maximum Tariffs 2023–2024 – press advertisement. Regulated Industries Commission, 2023. accessed 10 October 2026.
  4. Quality of Service Standards Scheme for Electricity Generating Entities – Annual Performance Report Oct 2021–Dec 2022. Regulated Industries Commission, 2024. accessed 10 October 2026.
  5. Tariffs – Summary of Electricity Rates. Trinidad and Tobago Electricity Commission. accessed 10 October 2026.
  6. T&TEC’s Structure and Functions. Trinidad and Tobago Electricity Commission. accessed 10 October 2026.
  7. Account Transactions – Opening, Closing and Transferring an Account. Trinidad and Tobago Electricity Commission. accessed 10 October 2026.
  8. Reading Your Meter. Trinidad and Tobago Electricity Commission. accessed 10 October 2026.
  9. Billing Enquiries – Frequently Asked Questions. Trinidad and Tobago Electricity Commission. accessed 10 October 2026.
  10. Standby Generator Licences. Trinidad and Tobago Electricity Commission. accessed 10 October 2026.
  11. Quality of Supply. Trinidad and Tobago Electricity Commission. accessed 10 October 2026.
  12. Renewable Energy Electricity Generation in Trinidad and Tobago. Ministry of Energy and Energy Industries. accessed 10 October 2026.
  13. Renewable Energy Technical Standards. Ministry of Energy and Energy Industries. accessed 10 October 2026.
  14. Renewable Energy and Energy Efficiency Fiscal Incentives. Ministry of Energy and Energy Industries. accessed 10 October 2026.
  15. Ministerial Delegation Visits Trinidad and Tobago’s First Utility Scale Solar Plant. Ministry of Energy and Energy Industries, 2025. accessed 10 October 2026.
  16. Wind Energy Identified as a Key Resource for Utility-Scale Renewable Energy Power Generation. Ministry of Energy and Energy Industries, 2025. accessed 10 October 2026.
  17. Government Electrical Inspectorate Services Division. Ministry of Public Utilities. accessed 10 October 2026.
  18. Budget Statement 2026 – T&T First: Building Economic Fairness through Accountable Fiscal Policies. Ministry of Finance, 2025. accessed 10 October 2026.
  19. Media Release: National Budget Statement 2027. Ministry of Finance, 2026. accessed 10 October 2026.
  20. 2011 Population and Housing Census Community Register. Central Statistical Office, 2011. accessed 10 October 2026.
  21. Population, total – Trinidad and Tobago (SP.POP.TOTL). World Bank, 2025. accessed 10 October 2026.
  22. Official exchange rate, LCU per US$ – Trinidad and Tobago (PA.NUS.FCRF). World Bank, 2025. accessed 10 October 2026.
  23. Urban population (% of total) – Trinidad and Tobago (SP.URB.TOTL.IN.ZS). World Bank, 2025. accessed 10 October 2026.
  24. Individuals using the Internet – Trinidad and Tobago (IT.NET.USER.ZS). World Bank / ITU, 2024. accessed 10 October 2026.
  25. Fixed broadband subscriptions per 100 people – Trinidad and Tobago (IT.NET.BBND.P2). World Bank / ITU, 2024. accessed 10 October 2026.
  26. Euro foreign exchange reference rates (9 October 2026). European Central Bank, 2026. accessed 10 October 2026.
  27. Share of electricity production by source – Trinidad and Tobago (Ember). Our World in Data / Ember, 2024. accessed 10 October 2026.
  28. Electricity generation – Trinidad and Tobago (Ember). Our World in Data / Ember, 2024. accessed 10 October 2026.
  29. Per capita electricity consumption – Trinidad and Tobago (Ember). Our World in Data / Ember, 2024. accessed 10 October 2026.
  30. Installed solar PV capacity – Trinidad and Tobago (IRENA). Our World in Data / IRENA, 2025. accessed 10 October 2026.
  31. Cumulative installed wind capacity – Trinidad and Tobago (IRENA). Our World in Data / IRENA, 2025. accessed 10 October 2026.

Questions about energy in Trinidad and Tobago.

Talk to us about Olmack in Trinidad and Tobago.Tell us about your home, housing portfolio or school estate in Trinidad and Tobago. We'll explain what is possible there now.