How electricity works in Angola.
Angola electricity market 2026: state-owned PRODEL, RNT and ENDE, RNT as single buyer, IRSEA-regulated tariffs, hydro-led generation and 55% access.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Angolan kwanza (AOA) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Angola energy at a glance.
Key figures for households in Angola. Each one links to its source on the full overview below.
Electricity price.
14.16 AOA per kWh for households, including taxes. Figures for 2026.
Renewable share.
73.7% of electricity from renewable sources. Figures for 2024.
Selling back to the grid.
Can homes export electricity? No. Details are in the export section below.
Four things to check in Angola.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Angola below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Angola requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Angola.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Angola, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Angola, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Angola.
The energy market in Angola, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 10 October 2026.
On this page22 sections
Angola’s public electricity system is run by three state-owned companies created by Presidential Decree 305/14 of 20 November 2014: PRODEL-EP generates electricity, RNT-EP owns and operates the transmission network and acts as system operator, and ENDE-EP distributes and sells electricity to end customers. ENDE was formed by merging the former Luanda distributor EDEL with the distribution business of the former national utility ENE. Policy is set by the Ministry of Energy and Water (MINEA) and tariffs and service quality are regulated by IRSEA, the Instituto Regulador dos Serviços de Electricidade e de Água.
Generation is dominated by hydropower. According to Ember data, hydro supplied about 71% of the 15.6 TWh generated in 2024, with oil and gas making up most of the rest and solar just under 3%. The World Bank describes RNT as the designated system operator and single buyer of the power system, purchasing from PRODEL and a handful of independent producers.
Access to electricity remains limited and highly uneven. The World Bank estimates that 55.5% of the population had access in 2024 — 78% in urban areas but only 1.3% in rural areas — and the 2023 Demographic and Health Survey found 53.9% of households with electricity. Household tariffs are set nationally by IRSEA and were left unchanged in the August 2026 partial tariff update, which applied to medium- and high-voltage customers only.
Energy snapshot.
Headline figures for electricity in Angola. Each shows its data year and links to its source.
- Population38,778,554 peopleSource 162026 (estimate)
- Households8,430,000 householdsSource 32026 (derived)
- Average household size4.6 people/householdSource 32023
- Electricity use per householdNot identified from a reliable public source.
- Household price (AOA)14.2 AOA/kWhSource 42026
- Household price (EUR)0.014 EUR/kWhSource 92026
- Renewable electricity share73.7%Source 102024
- Solar capacity0.385 GWSource 132025
- Wind capacityNot identified from a reliable public source.
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Single buyer
- Homes can export to the grid
- No
- Home equipment in grid services
- No
- Regulator
- IRSEA (Instituto Regulador dos Serviços de Electricidade e de Água)
- System operator
- RNT-EP — national transmission company, system operator and single buyer
- Distribution networks
- One state-owned national distributor and retailer, ENDE-EP, serves almost all grid customers
- Currency
- Angolan kwanza (AOA)
- Voltage and frequency
- 220/380 V nominal low-voltage supply (IRSEA); frequency not verified from an official source
Electricity prices in Angola.
- Household price (AOA)
- 14.2 AOA/kWh (2026)Source 4Energy charge for the single-phase domestic (Doméstico Monofásico) low-voltage category in IRSEA’s 2026 tariff table, plus a fixed term of 117.00 × contracted power in kVA. The tariffs were approved by Despacho 3133/25; IRSEA’s August 2026 update left household categories unchanged. Excludes the fixed term; VAT treatment not verified.
- Household price (EUR)
- 0.014 EUR/kWh (2026)Source 9Converted from AOA 14.16/kWh at the Banco Nacional de Angola EUR reference rate (selling) of 1,048.8286 AOA per euro on 9 October 2026. Energy charge only, excluding the fixed kVA term.
- Typical annual electricity bill
- Not identified from a reliable public source.
Electricity tariffs in Angola are set nationally by IRSEA and are the same throughout the country. Each low-voltage bill has two parts: a fixed term proportional to the contracted power in kVA and an energy charge per kWh. In IRSEA’s 2026 table a single-phase household pays 117.00 Kz per kVA of contracted power plus 14.16 Kz/kWh — about €0.0135/kWh for the energy charge at the Banco Nacional de Angola reference rate in October 2026.
Tariff categories
Low-voltage customers (below 1 kV) fall into seven categories: Social I (3.20 Kz/kWh) and Social II (8.33 Kz/kWh) with no fixed term; public lighting (58.50 × kVA + 9.17 Kz/kWh); single-phase domestic (117.00 × kVA + 14.16 Kz/kWh); three-phase domestic and commerce and services (130.00 × kVA + 19.16 Kz/kWh); and low-voltage industry (130.00 × kVA + 16.67 Kz/kWh). Medium-voltage (1–35 kV) and high-voltage (35–60 kV) customers pay a charge on their maximum 15-minute demand in kW plus an energy price between 10.23 and 15.00 Kz/kWh.
Tariff cycle and subsidies
Tariffs for the 2025–2028 tariff cycle were approved by Despacho 3133/25 of 12 May 2025, alongside Despacho 3134/25 setting the annual revenue requirement of the public electricity companies. On 17 August 2026 IRSEA approved a partial update (Despachos 7535/2026 and 7536/2026) that raised prices only for medium- and high-voltage customers and created a new Large Customers category for contracted power of 2,000 kVA or more; social, single-phase and three-phase domestic tariffs were unchanged.
Tariffs have long been below cost. The World Bank noted in 2021 that the average tariff of 12.09 Kz/kWh (May 2019) compared with a cost of service of about 23.4 Kz/kWh including fuel, that tariffs had been frozen from 2006 to 2016, and that the government’s 2018 price subsidy to ENDE amounted to 55% of the utility’s total revenue.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | National low-voltage tariffs set by IRSEA. Domestic single-phase customers pay 117.00 × contracted power (kVA) plus 14.16 Kz/kWh; domestic three-phase customers pay 130.00 × contracted power plus 19.16 Kz/kWh (2026 table). |
| Other | Yes | Social domestic tariffs with no fixed term: Doméstico Social I at 3.20 Kz/kWh and Doméstico Social II at 8.33 Kz/kWh. Eligibility conditions and consumption limits were not published on the pages consulted. |
| Prepayment | Yes | Low-voltage customers can be supplied on prepayment, governed by Presidential Decree 42/21 (Regulamento da Modalidade de Pré-Pagamento de Energia Eléctrica em BT). IRSEA tells consumers they may pay under prepayment or postpaid arrangements. |
| Time-of-use | No | No time-of-day tariff for households appears in IRSEA’s tariff table. Medium- and high-voltage customers pay a demand charge on their maximum 15-minute demand plus an energy charge. |
Household prices compared with neighbouring countries (EUR per kWh).
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- Not identified from a reliable public source.
- Average daily use per household
- Not identified from a reliable public source.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 353.5 kWh/person/yr (2024)Source 2Electric power consumption per capita, all sectors (World Bank). Ember’s per-capita electricity demand for 2024 is 411.5 kWh.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- 2.6 % of homes (2023)Source 3Households cooking with electricity, Angola Demographic and Health Survey 2023 (1.4% in 2015–16).
Electricity use per person is low: the World Bank puts consumption at about 353 kWh per person in 2024, across all sectors. The main constraint is access rather than demand — only 53.9% of households had electricity in the 2023 Demographic and Health Survey, up from 41.6% in 2015–16, and rural access is close to zero.
Household electricity is used mainly for lighting, appliances and cooling. Only 2.6% of households cooked with electricity in 2023. IRSEA’s consumer guidance attributes seasonal increases in bills to air-conditioning use, shorter daylight hours and more time spent at home in the rainy season.
Demand grew quickly after the end of the civil war: the World Bank reports that electricity consumption rose by 15.5% a year between 2008 and 2014.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- Not identified from a reliable public source.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- Not identified from a reliable public source.
- Apartments and flats
- Not identified from a reliable public source.
- Urban population
- 65.7 % of population (2024)Source 17Share of the population in urban areas, 2024 census (RGPH 2024). The World Bank’s 2025 estimate is 71.46%.
The 2024 General Population and Housing Census (RGPH 2024) counted about 36.6 million people, 65.7% of them in urban areas and 24% in Luanda province. The World Bank’s 2021 appraisal noted that nearly 60% of ENDE’s 1.5 million customers were in Luanda province.
Average household size was 4.6 people in the 2023 Demographic and Health Survey. The census dashboard reports dwelling types (including cubatas and barracas), lighting sources and cooking fuels as percentages, but the underlying tables were not available in a readable form, so dwelling counts, tenure and dwelling-type shares are left blank.
How the grid works in Angola.
- TransmissionRede Nacional de Transporte de Electricidade (RNT-EP)
- DistributionOne state-owned national distributor and retailer, ENDE-EP, serves almost all grid customers
- MeteringENDE-EP
- Supply1 or more retail suppliers
Physical flow
Ember data show 15.59 TWh generated in 2024: 70.6% hydro, 17.3% oil, 9.0% gas, 2.8% solar and 0.3% bioenergy. Most hydro output comes from public plants operated by PRODEL. The World Bank reported total installed capacity above 5,100 MW in 2020 and described four historically isolated systems — northern, central, southern and eastern — of which the northern and central systems were joined by the 400 kV Laúca–Huambo line.
Power is transmitted by RNT and delivered by ENDE at medium voltage (30, 20, 15 or 3 kV) and low voltage (220/380 V), with high-voltage supply at 60 kV, according to IRSEA’s quality-of-product standards. The World Bank reported transmission and distribution losses of 11.26% of output in 2024, while ENDE’s total system losses, including commercial losses, stood at 39% in its project baseline.
Commercial flow
RNT buys electricity from PRODEL and from a small number of independent producers — the World Bank listed four operating in 2020, including the 100 MW Biocom biomass plant — and sells it to ENDE and to large customers. IRSEA’s tariff table includes zero-fixed-charge categories for commercialisers (comercializadores) at medium and high voltage. There is no wholesale market or retail competition.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry of Energy and Water (MINEA) | Sets energy and water policy and is a party, for the State, to concession contracts such as the 2026 Angola–DRC interconnector agreements. |
| Regulator | IRSEA (Instituto Regulador dos Serviços de Electricidade e de Água) | Regulates electricity and water services: approves tariffs and the public companies’ annual revenue requirement, sets service-quality standards (SAIFI, SAIDI and other indicators) and handles consumer complaints. |
| TSO | Rede Nacional de Transporte de Electricidade (RNT-EP) | Owns and operates the transmission network, coordinates real-time system operation and, according to the World Bank, is the single buyer of the power system. Takes part in the Southern African Power Pool (SAPP). |
| DSO | Empresa Nacional de Distribuição de Electricidade (ENDE-EP) | National distribution and retail company formed from EDEL and the distribution business of ENE. Reported 1.5 million customers in the World Bank’s 2021 appraisal. |
| Supplier | ENDE-EP | Sells electricity to households and businesses at IRSEA’s national tariffs, on postpaid or prepaid arrangements. |
| Metering | ENDE-EP | Installs and reads customer meters, including prepaid meters under Presidential Decree 42/21. |
Compared with the UK system.
| UK concept | Angola equivalent | How it works |
|---|---|---|
| DNO | ENDE-EP | There are no regional network companies: ENDE, a single national state company, owns and operates distribution networks across the provinces and connects new customers. IRSEA lists no private distribution concessionaires. |
| National Grid/NESO | RNT-EP | RNT combines the roles of transmission owner, system operator and single buyer. Angola historically had separate northern, central, southern and eastern systems; the 400 kV Laúca–Huambo line joined the northern and central systems. |
| MPAN | ENDE customer contract and meter number | A connection is identified by the supply contract ENDE opens and the meter it installs. No public specification of a standardised national supply-point number was identified. |
| MPRN | No equivalent identified | No piped gas distribution to households or gas supply-point register was identified. |
| Meter operator | ENDE-EP | The distributor supplies, installs and reads meters; there is no separate metering market. |
| Supplier | ENDE-EP | There is no retail competition. Customers buy from ENDE at national tariffs approved by IRSEA. |
| Smart-meter infrastructure | Prepaid meters; small smart-meter pilot | ENDE uses prepaid meters for part of its customer base. A World Bank-financed project targets 15,000 smart meters for revenue protection by September 2026; none had been reported installed by December 2024. There is no national smart-meter data hub. |
How a supply point is identified.
| Question | Answer |
|---|---|
| What is it called? | ENDE customer contract and meter number |
| Who issues it? | ENDE-EP, when the supply contract is signed and the meter installed |
| Format | Not published. Neither IRSEA nor the accessible ENDE pages document the structure of customer, contract or meter numbers. |
| Length | Not verified |
| Stays with the property when you switch supplier? | Not identified from a reliable public source. |
| Where to find it | On the meter and on ENDE bills for postpaid customers; prepaid customers use the meter number when buying credit. |
| Electronic access | Not verified — ENDE’s website returned server errors when consulted. |
| Third-party access | No framework for third-party access to metering or customer data was identified. |
| Who keeps the register | ENDE’s commercial and metering records |
| Register scope | National |
In Angola a household connection is administered by ENDE, the national distribution company, under the Commercial Relations Regulation (Presidential Decree 2/11) and the Network Access and Interconnection Regulation (Presidential Decree 19/11). The customer signs a supply contract specifying a tariff category — social, single-phase domestic or three-phase domestic — and, for non-social categories, a contracted power in kVA that sets the fixed part of the bill.
Each supply is then identified by its ENDE contract and meter. Postpaid customers are billed from meter readings; IRSEA states that where no actual reading is available ENDE uses consumption estimation models. Prepaid customers buy credit in advance under the rules of Presidential Decree 42/21.
Because ENDE is in practice the only distributor and retailer, its customer database functions as the national register of supply points. IRSEA requires suppliers to give advance notice of changes to contract conditions and to respond to complaints within 15 working days. No public specification of the format or length of ENDE’s account or meter numbers was identified, so no example is shown here.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Unknown |
| Net metering | No |
| Net billing | No |
| How exported electricity is paid | Not identified. IRSEA’s tariff table contains no export, net-metering or feed-in tariff for small producers. |
| Can households sell solar power to the grid? | No household export, net-metering or feed-in arrangement appears in IRSEA’s published tariffs, consumer information or electricity sector pages. |
| Can private companies sell power to the grid? | Yes, as independent producers selling to the single buyer under the Independent Electricity Production Regulation (Presidential Decree 43/21); the text could not be read for this profile, so thresholds are not stated. |
Connecting a home system.
- No published procedure for connecting and exporting from a household solar system was identified; contact ENDE and IRSEA.
Accessible official sources describe no scheme allowing households to export surplus solar electricity to ENDE’s network or to be credited for it. Rooftop solar in homes is therefore used behind the meter or as back-up. With household energy charges of 14.16 Kz/kWh or less, the grid price is low compared with the cost of self-generation.
Larger generators connect as independent producers selling to RNT under Presidential Decree 43/21. Anyone planning a grid-tied system should confirm current requirements with ENDE and IRSEA, particularly in light of the 2025 amendment to the General Electricity Law (Law 6/25).
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity for sale to the grid (independent producer) | Authorised under the Independent Electricity Production Regulation; thresholds and exemptions not verified | MINEA; IRSEA | Presidential Decree 43/21. Sales are to RNT as single buyer. |
| Generate for own use (rooftop solar) | No published threshold or exemption identified | MINEA; IRSEA; ENDE (if grid-connected) | Confirm requirements with the regulator. |
| Export / sell surplus to the grid | No household export regime identified | IRSEA; ENDE | No net-metering or feed-in tariff in the published tariff table. |
| Transmit electricity and operate the system | Carried out by RNT-EP | Government of Angola; IRSEA | Private interconnector concessions are possible: the Angola–DRC interconnectors were awarded to a private promoter on a BOOT basis in 2026. |
| Distribute and supply electricity | Carried out by ENDE-EP; private concessions provided for but none listed by IRSEA | Government of Angola; IRSEA | Regulated by Presidential Decree 76/21 on production, transport, distribution and commercialisation. |
| Wholesale trading / commercialisation | Commercialiser tariff categories exist at medium and high voltage | IRSEA | Licensing conditions for commercialisers were not verified. |
| Store electricity | No specific storage licensing regime identified | — | Not addressed in the sources consulted. |
| Aggregate, balancing, grid services, VPP, remote control of assets | No regime identified | — | There is no organised wholesale or flexibility market in which these activities exist. |
The legal framework is the General Electricity Law (Law 14-A/96), amended by Law 27/15 and most recently by Law 6/25 of 23 July 2025, with implementing regulations on production, transport, distribution and commercialisation (Presidential Decree 76/21), independent production (Presidential Decree 43/21), tariffs (Presidential Decree 4/11), commercial relations (Presidential Decree 2/11), network access and interconnections (Presidential Decree 19/11) and service quality (Presidential Decree 310/10).
These texts are published by IRSEA as scanned documents that could not be read for this profile, so licence thresholds and exemptions for small generators are not stated here. In practice the sector is run by the three state companies, with a small number of independent producers and, since 2026, a private BOOT concession for interconnectors with the DRC.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Energy, balancing and ancillary services | No | — | No | RNT-EP. RNT balances the system as operator and single buyer. No market for distributed resources, demand response or aggregation was identified. |
| Southern African Power Pool (SAPP) | No | — | No | SAPP. RNT takes part in SAPP; regional trading is between utilities, not distributed assets. |
Angola has no domestic wholesale or flexibility market open to distributed resources. The only demand-related price signal is the charge on maximum 15-minute demand paid by medium- and high-voltage customers. Regionally, RNT participates in the Southern African Power Pool, and the World Bank noted an ambition to sell up to 800 MW of firm energy into the SAPP market.
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | No national smart-meter programme; prepaid meters for part of ENDE’s customers and a 15,000-meter revenue-protection pilot |
| Reading interval | Not published |
| Meter supply | ENDE-EP |
| Prepayment rules | Presidential Decree 42/21 (low voltage) |
| Prepaid share | Under 30% of customers (World Bank, 2021) |
| Smart-meter target (World Bank project) | 15,000 by September 2026; 0 reported by December 2024 |
| Smart-meter share | Not published |
ENDE operates both postpaid meters, read for periodic bills, and prepaid meters under Presidential Decree 42/21. When the World Bank appraised its Electricity Sector Improvement and Access Project in 2021, fewer than 30% of ENDE’s 1.5 million customers had prepaid meters, and collection was below 75%.
That project includes installing 15,000 smart meters under a revenue-protection programme and reducing total system losses from 39% to 29% by September 2026. The December 2024 progress report showed no smart meters installed and losses still at the 39% baseline.
Renewable electricity.
Electricity generation mix (2024).
- Hydro: 70.6%
- Oil: 17.3%
- Gas: 9%
- Solar: 2.8%
- Bioenergy: 0.3%
- Renewable electricity share
- 73.7% (2024)Source 10Share of generation: hydro 70.56%, solar 2.82%, bioenergy 0.32% (Ember data via Our World in Data). The World Bank reports hydro at 73.06% of production in 2024. Angola is not a significant net importer.
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- 22.6 MW (2025)Source 13Derived: 0.38454542 GW (2025) minus 0.3619054 GW (2024).
- Total installed (all sources)
- 5.1 GW (2020)Source 14World Bank: installed capacity “above 5100 MW”.
- Solar PV
- 0.385 GW (2025)Source 13
- Biomass (Biocom)
- 100 MW (2020)Source 14Independent producer listed by the World Bank.
Targets.
- Angola Energia 2025: 60% national electricity access by 2025 (as cited by the World Bank in 2021). The World Bank’s estimate for 2024 was 55.5%.
- No current, officially published renewable electricity target for after 2025 could be verified from accessible government sources.
Hydropower is Angola’s main source of electricity, supplying 70.6% of generation in 2024 according to Ember (73.1% according to the World Bank). The rest comes mainly from oil-fired (17.3%) and gas-fired (9.0%) plants; in 2020 the World Bank put the capacity mix at 67% hydro, 27% gas and 7% diesel.
Utility-scale solar arrived quickly: IRENA statistics show solar capacity rising from about 1.4 MW in 2021 to 285 MW in 2022 and 385 MW in 2025. Solar provided 2.8% of generation in 2024. Bioenergy comes mainly from the 100 MW Biocom sugar-cane plant, one of four independent producers the World Bank identified in 2020.
Ember records no wind generation. The World Bank’s 2021 appraisal noted plans to reduce hydro’s share of capacity below 60% by 2030 and cut diesel to 3%.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
No official statistics on battery storage were identified, and the accessible regulatory texts contain no specific licensing or market rules for storage.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Empresa Nacional de Distribuição de Electricidade (ENDE-EP) | Sole supplier on the public grid (1.5 million customers, 2021) | No | No | No | No |
ENDE is the only retail electricity supplier for households on Angola’s public grid. It sells to domestic, commercial and industrial customers under IRSEA’s national tariff table; large medium- and high-voltage customers are billed with a demand charge. IRSEA lists no private distribution concessionaires.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| IRSEA (Instituto Regulador dos Serviços de Electricidade e de Água) | Regulator | Electricity and water regulator | Approves tariffs and revenue requirements, sets service-quality standards and handles consumer complaints. |
| Ministry of Energy and Water (MINEA) | Government | Energy and water ministry | Sets sector policy and signs concession contracts on behalf of the State. |
| Rede Nacional de Transporte de Electricidade (RNT-EP) | Transmission | Transmission company, system operator and single buyer | Operates the high-voltage network and the power system and buys electricity from producers. |
| Empresa Nacional de Distribuição de Electricidade (ENDE-EP) | Distribution | National distributor and retailer | Connects, meters and bills electricity customers. |
| Empresa Pública de Produção de Electricidade (PRODEL-EP) | Renewable Energy | State generation company | Operates the public power plants. |
| Instituto Nacional de Estatística (INE) | Government | National statistics office | Publishes population estimates and the 2024 census results. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Service and supply quality | Regulamento da Qualidade de Serviço (Presidential Decree 310/10) | IRSEA | Sets continuity indicators (SAIFI, SAIDI, SARI and others), voltage quality at nominal levels (220/380 V low voltage) and commercial-quality standards such as connection times. |
| Grid connection | Regulamento do Acesso às Redes e às Interligações (Presidential Decree 19/11) | Government of Angola; IRSEA | Network access and interconnection rules. No published technical code for small inverter-connected generators was identified. |
| Installer accreditation | No national scheme identified | — | No certification scheme for solar installers was verified. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| ENDE supply contract and connection | Yes | National | Contract with ENDE specifying tariff category and contracted power, under the Commercial Relations Regulation. |
| Regulator or ministry approval for grid-connected generation | Limited | National | Required for independent producers under Presidential Decree 43/21; rules for small household systems could not be verified. |
| Planning permission | Unknown | Local | No national rule on planning consent for rooftop solar was identified. |
For a household the administrative relationship is with ENDE, which connects, meters and bills the supply. Requirements for connecting private generation to ENDE’s network were not identified in accessible official sources; independent producers selling to the grid fall under Presidential Decree 43/21.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Social domestic electricity tariffs | Active | Social tariff | Doméstico Social I (3.20 Kz/kWh) and Social II (8.33 Kz/kWh) with no fixed charge, against 14.16 Kz/kWh plus a kVA charge on the standard single-phase domestic tariff. | — |
Data and connectivity.
- Fixed broadband
- 40.7 % of population using the internet (2024)Source 1Share of individuals using the internet (ITU via World Bank), not fixed-broadband coverage.
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
About 41% of the population used the internet in 2024, according to World Bank data. No information was identified on the communication technology used by ENDE’s prepaid or smart meters.
Grid conditions.
- National peak demand
- Not identified from a reliable public source.
- Annual electricity demand
- Not identified from a reliable public source.
- Generation capacity
- 5.1 GW (2020)Source 14World Bank: “above 5100 MW”; no more recent official total was identified.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
Angola’s transmission grid grew from separate regional systems. The World Bank described northern, southern, central and eastern grids operating in isolation, with the northern and central systems connected by the 400 kV Laúca–Huambo line and a 400 kV Huambo–Lubango line planned to join the south.
Losses are high: the World Bank reported transmission and distribution losses of 11.26% of output in 2024, while ENDE’s total system losses (technical, commercial and collection) were 39% at its project baseline. RNT monitors supply quality using SAIDI, SAIFI and SARI indicators.
On 30 September 2026 RNT signed contracts with the private promoter Somagec Energy Holding for two interconnectors with the Democratic Republic of the Congo on a build-own-operate-transfer basis: a northern link (400 kV Soyo–Matadi–Inga and 60 kV Cabinda–Moanda) that will connect the Cabinda exclave to the national system through the DRC, and an eastern link (400 kV Capanda–Xá-Muteba–Luau–Kolwezi).
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Partial tariff update for 2025–2028 cycle | Current | Approved 17 August 2026 | Despachos 7535/2026 and 7536/2026 raise medium- and high-voltage tariffs and create a Large Customers category (≥2,000 kVA); social and domestic tariffs unchanged. |
| Amendment to the General Electricity Law | Current | Law 6/25 of 23 July 2025 | Amends Law 14-A/96. The text is published as a scanned document; its detailed provisions could not be verified for this profile. |
| Angola–DRC regional interconnectors | Upcoming | Contracts signed 30 September 2026 | Private BOOT concession for northern (Soyo–Matadi–Inga 400 kV; Cabinda–Moanda 60 kV) and eastern (Capanda–Xá-Muteba–Luau–Kolwezi 400 kV) interconnectors, approved by Presidential Decrees 115/26 and 141/26. |
| Electricity Sector Improvement and Access Project | Current | Approved February 2021; closing target September 2026 | US$250 million World Bank project for 196,500 household connections, 15,000 smart meters and a cut in total losses from 39% to 29%. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Low | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | — | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | High | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Low | No official residential solar statistics and no household export or net-metering scheme identified; household grid energy charges are 14.16 Kz/kWh or less. |
| Distributed energy market | Low | No published framework for small distributed generation on ENDE’s network; independent production regulated only for grid sales to the single buyer. |
| Grid flexibility market | Low | Single-buyer structure with no wholesale or flexibility market; RNT is the sole system operator. |
| Energy storage adoption | Low | No official statistics or regulatory framework for battery storage identified. |
| Renewable growth environment | Medium | Solar capacity rose from about 1.4 MW in 2021 to 385 MW in 2025 (IRENA), but solar was still 2.8% of generation in 2024 and the renewable share is dominated by existing hydro. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 19 sources
- World Development Indicators: population, urban population, access to electricity, internet users — Angola. World Bank, 2025. accessed 10 October 2026.
- World Development Indicators: hydro share, renewable output, electric power consumption per capita, T&D losses — Angola. World Bank, 2024. accessed 10 October 2026.
- Angola DHS/MIS surveys: households with electricity, cooking with electricity, mean household size. The DHS Program (ICF), 2023. accessed 10 October 2026.
- Tarifas de electricidade 2026 (homepage tariff table). IRSEA, 2026. accessed 10 October 2026.
- Electricidade — sector structure, tariffs and quality of service. IRSEA. accessed 10 October 2026.
- Legislação. IRSEA. accessed 10 October 2026.
- Consumidores. IRSEA. accessed 10 October 2026.
- IRSEA aprova ajuste parcial das tarifas de electricidade. IRSEA, 2026. accessed 10 October 2026.
- Taxa de referência EUR (venda), 9 October 2026. Banco Nacional de Angola, 2026. accessed 10 October 2026.
- Share of electricity production by source — Angola (Ember data). Our World in Data / Ember, 2024. accessed 10 October 2026.
- Electricity generation — Angola (Ember data). Our World in Data / Ember, 2024. accessed 10 October 2026.
- Per capita electricity demand — Angola (Ember data). Our World in Data / Ember, 2024. accessed 10 October 2026.
- Installed solar PV capacity — Angola (IRENA data). Our World in Data / IRENA, 2025. accessed 10 October 2026.
- Project Appraisal Document — Angola Electricity Sector Improvement and Access Project (P166805). World Bank, 2021. accessed 10 October 2026.
- Implementation Status and Results Report #8 — Angola Electricity Sector Improvement and Access Project (P166805). World Bank, 2025. accessed 10 October 2026.
- Estimativa da População (2026). Instituto Nacional de Estatística (INE), 2026. accessed 10 October 2026.
- Recenseamento Geral da População e Habitação 2024 — resultados. Instituto Nacional de Estatística (INE), 2024. accessed 10 October 2026.
- RNT-EP rubrica contratos para conector Angola–RDC. RNT-EP, 2026. accessed 10 October 2026.
- Estatísticas de exploração. RNT-EP. accessed 10 October 2026.
Questions about energy in Angola.
Under IRSEA’s 2026 tariffs a single-phase household pays 14.16 kwanzas per kWh plus 117.00 Kz per kVA of contracted power — about €0.0135/kWh for the energy charge. Social tariffs are 3.20 and 8.33 Kz/kWh with no fixed charge.
The state company ENDE-EP distributes and sells electricity to almost all grid customers. PRODEL-EP generates power and RNT-EP runs the transmission grid and buys power as single buyer.
Mostly hydropower: about 71% of the 15.6 TWh generated in 2024, with oil (17%), gas (9%) and solar (3%) supplying the rest, according to Ember data.
The World Bank estimates 55.5% of the population had access in 2024 — 78% in urban areas and 1.3% in rural areas. The 2023 Demographic and Health Survey found 53.9% of households with electricity.
There is no published standardised supply-point number. A connection is identified by its ENDE contract and meter, with the tariff category and contracted power in kVA recorded on the contract.
No household net-metering or feed-in scheme was identified; IRSEA’s tariffs contain no export price. Independent producers can sell to RNT under Presidential Decree 43/21.
In August 2026 IRSEA approved a partial update raising medium- and high-voltage tariffs, but left social, single-phase and three-phase domestic tariffs unchanged.