How electricity works in DR Congo.
DR Congo electricity 2026: SNEL dollar tariffs, ARE regulation, the 2014 electricity law, licensing thresholds, very low access, hydro dominance and mini-grids.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Congolese franc (CDF) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
DR Congo energy at a glance.
Key figures for households in DR Congo. Each one links to its source on the full overview below.
Electricity price.
0.039 USD per kWh for households, including taxes. Figures for In force since 2009; confirmed June 2024.
Renewable share.
95% of electricity from renewable sources. Figures for 2025.
Selling back to the grid.
Can homes export electricity? No. Details are in the export section below.
Four things to check in DR Congo.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for DR Congo below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications DR Congo requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in DR Congo.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in DR Congo, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in DR Congo, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in DR Congo.
The energy market in DR Congo, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 1 October 2026.
On this page22 sections
The Democratic Republic of the Congo has one of the largest hydropower resources in the world and one of the lowest rates of electricity access. Grid supply is dominated by the Société Nationale d’Électricité (SNEL SA), a state-owned, vertically integrated company that generates, transmits, distributes and sells most of the country’s electricity. Law No. 14/011 of 17 June 2014 ended SNEL’s legal monopoly and created a sector regulator, the Autorité de Régulation du secteur de l’Électricité (ARE), and a rural electrification agency, ANSER. Policy belongs to the Ministry of Hydraulic Resources and Electricity (MRHE), and the 26 provinces have their own powers to grant some titles.
SNEL runs three separate interconnected grids – West (Kinshasa and Kongo Central), South (the Katanga mining provinces) and East (the Kivus) – plus isolated systems. Large mines on the high-voltage network take most of its output. In 2025 SNEL sold 8.8 TWh, of which only 1.65 TWh went to low-voltage customers. A national electricity access rate of 21.5% is used in the government’s National Energy Compact. In the 2023–24 Demographic and Health Survey, 22% of households had electricity: 55% in towns but only 3% in rural areas.
SNEL’s tariffs are set in US dollars and paid in Congolese francs. They are low – SNEL’s residential band averages USD 0.039/kWh – and well below cost. Private mini-grid operators in the east charge much more, for example USD 0.25/kWh in Goma. There is no net-metering or export scheme for households. Reforms under the 2025 National Energy Compact include revising the electricity law, a new tariff methodology and grid code, a national dispatch centre and a second public electricity company.
Energy snapshot.
Headline figures for electricity in DR Congo. Each shows its data year and links to its source.
- Population114,000,000 peopleSource 24October 2025
- HouseholdsNot identified from a reliable public source.
- Average household size5.3 people/householdSource 232023–24
- Electricity use per householdNot identified from a reliable public source.
- Household price (CDF)0.039 USD/kWhSource 4In force since 2009; confirmed June 2024
- Household price (EUR)0.034 EUR/kWhSource 262026
- Renewable electricity share95%Source 22025
- Solar capacity0.03 GWSource 222024
- Wind capacity0 GWSource 222024
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Partially liberalised
- Homes can export to the grid
- No
- Home equipment in grid services
- No
- Regulator
- Autorité de Régulation du secteur de l’Électricité (ARE), with tariffs approved by joint order of the economy and electricity ministers
- System operator
- SNEL SA, which runs the transmission grids and dispatch; a national dispatch centre is due by the end of 2027
- Distribution networks
- SNEL distributes in most connected towns; private concession holders and mini-grid operators (such as Virunga Energies, ENK and Nuru in North Kivu) run separate local networks.
- Currency
- Congolese franc (CDF)
- Voltage and frequency
- 220 V single-phase / 380 V three-phase (SNEL low-voltage supply up to 59 kW)
Electricity prices in DR Congo.
- Household price (CDF)
- 0.039 USD/kWh (In force since 2009; confirmed June 2024)Source 4SNEL residential band 1 (“Résidentiel 1”) average reference price. SNEL tariffs are set in US dollars and paid in Congolese francs at the Banque Centrale du Congo rate. Social customers using up to 100 kWh a month pay a flat USD 2.65; Résidentiel 2 averages USD 0.087/kWh. Taxes on household bills were not confirmed from an official source.
- Household price (EUR)
- 0.034 EUR/kWh (2026)Source 26Converted from USD 0.039/kWh at the ECB reference rate on 30 September 2026 of USD 1.1355 per euro: 0.039 ÷ 1.1355 = 0.034.
- Typical annual electricity bill
- Not identified from a reliable public source.
Under Article 25 of the 2014 electricity law, an operator proposes its tariffs to ARE, which gives an opinion within 15 days and sends them to the ministers for the economy and for electricity. The ministers set them by joint order (arrêté interministériel), and ARE publishes them. Article 27 requires every sale to be billed on actual consumption from calibrated meters and bans flat-rate (forfait) billing. SNEL still uses flat rates for its social category and estimates bills when meters cannot be read or are missing.
The 2022 tariff order
Joint Order No. 038/CAB/MIN/ECONAT/NKK/2022 and 060/CAB-MIN/RHE/OMM/22 of 5 November 2022, which ARE republished in August 2026, sets SNEL’s average reference tariffs by tariff zone (West, South, East and four isolated hydro centres) and by voltage. The average low-voltage final tariff is USD 0.1691/kWh in the West zone, USD 0.1790 in the South and USD 0.1950 in the East. It lists the existing domestic rates (social USD 0.0265, R1 USD 0.039, R2 USD 0.087/kWh) and sets four six-monthly increases. In the West zone, R1 would rise to USD 0.044 and R2 to USD 0.0981. The order allows SNEL a 28.57% margin and indexes tariffs to US consumer prices. It does not cover solar, thermal or other non-hydro sources, which are left for later proposals.
In practice, SNEL said in June 2024 that its dollar tariffs remained unchanged from the March 2009 schedule, and its website still shows that schedule. A December 2025 government proposal described SNEL’s average price as USD 0.17/kWh on paper but about USD 0.09/kWh in practice. Under the National Energy Compact, SNEL is to recover 100% of its operating costs by 2029 through gradual tariff increases. In September 2026 ARE validated a cost-of-service study and a new tariff methodology with the African Development Bank.
Off the SNEL grid, prices are much higher. The compact reports mini-grid tariffs of USD 0.25 to 0.70/kWh. ARE adopted a 3% levy in 2023 to fund regulation. SNEL said it would apply only to high-voltage mining customers, not households.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | SNEL low-voltage domestic tariffs have three categories: social (up to 100 kWh a month, flat USD 2.65), Résidentiel 1 (101–500 kWh a month, average USD 0.039/kWh) and Résidentiel 2 (above 500 kWh, average USD 0.087/kWh). Prices are set in US dollars and paid in Congolese francs at the central bank rate. |
| Prepayment | Limited | SNEL is rolling out prepaid meters in Kinshasa and provincial towns. Private mini-grid operators such as Virunga Energies supply customers through prepaid meters. |
| Time-of-use | No | There is no household time-of-use tariff. High- and medium-voltage customers pay two-part tariffs, with a capacity charge (USD/kW) and an energy charge (USD/kWh). |
| Dynamic | No | No tariff linked to wholesale prices is offered. |
| Other | Limited | Mini-grid operators charge tariffs approved by the authorities, generally USD 0.25–0.70/kWh. Virunga Energies charges households and small businesses USD 0.25/kWh including tax. |
Household prices compared with neighbouring countries (EUR per kWh).
- Rwanda€0.261
- Uganda€0.209
- South Africa€0.185
- Zimbabwe€0.075
- Zambia€0.036
- DR Congo€0.034
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- Not identified from a reliable public source.
- Average daily use per household
- Not identified from a reliable public source.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- Not identified from a reliable public source.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- 2 % of homes (2023–24)Source 23Share of households mainly using an electric cooker. Only 3% of households use clean fuels and technologies for cooking. Wood (60%) and charcoal (33%) dominate.
Most grid electricity goes to mines and industry. In 2025 SNEL sold 5,478 GWh to high-voltage customers, 1,243 GWh at medium voltage and 1,654 GWh at low voltage, which includes households and small businesses. Low-voltage sales have fallen each year since 2022 (1,848 GWh). Total SNEL sales fell from 10.4 TWh in 2023 to 8.8 TWh in 2025.
Few households use mains electricity. In the 2023–24 Demographic and Health Survey, 22% of households had electricity, but only 14% used it as their main source of lighting. Battery torches (43%), rechargeable lamps (21%) and solar lanterns (12%) are more common. One in five households (20%) owns a solar panel, and the share is similar in towns and the countryside. Ownership of appliances is low: 24% of households own a television and 9% a refrigerator.
Supply on the SNEL grid is rationed. Kinshasa receives 550–630 MW from Inga, Zongo and Sanga, and SNEL’s Kinshasa distribution director has said demand is up to three times higher. In 2025, 467 SNEL medium/low-voltage substations were under scheduled load shedding.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- Not identified from a reliable public source.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- Not identified from a reliable public source.
- Apartments and flats
- Not identified from a reliable public source.
- Urban population
- 48.8 % of population (October 2025)Source 24The National Energy Compact puts the urban share at about 46%.
In the 2023–24 survey, 64% of households lived in homes with earth or sand floors, and 22% had cement floors. In urban areas 54% of homes had cement floors and 13% had tiles. Over a quarter of households (26%) have only one room for sleeping.
Property and occupancy affect grid connection. To connect, SNEL asks for the title deed, a cadastral plan, a building permit and an approved wiring diagram. Tenants must provide a lease and a power of attorney from the owner. The consumer must take out a new subscription when moving into new premises, and any change of owner or use requires the subscription to be amended.
How the grid works in DR Congo.
- TransmissionSNEL SA – transmission, SNEL SA – dispatch
- DistributionSNEL distributes in most connected towns; private concession holders and mini-grid operators (such as Virunga Energies, ENK and Nuru in North Kivu) run separate local networks.
- MeteringSNEL SA
- Supply2 or more retail suppliers
Almost all grid electricity comes from hydropower. SNEL had 2,630 MW installed in 2025 (2,586 MW hydro), but only 1,929 MW was available. The two Inga stations on the Congo River (Inga I 351 MW and Inga II 1,424 MW) are the backbone. They supply Kinshasa and, through a long high-voltage direct-current line, the copper and cobalt mines of Lualaba and Haut-Katanga. In 2025 SNEL produced 12,712 GWh and imported 2,754 GWh, mainly for the southern mining grid. The Busanga independent hydro plant supplied a further 1,476 GWh.
Commercially, SNEL buys from independent producers, sells to eligible customers under bilateral contracts and supplies everyone else at regulated tariffs. Mines either buy from SNEL, import power or generate their own. The IFRI study estimates mining self-generation at about 363 MW. The country belongs to three regional power pools: the Southern African Power Pool (via Zambia), the Central African Power Pool and the Eastern Africa Power Pool (via Rwanda and Burundi).
Losses are very high. The compact reports technical and commercial losses of 46% in 2022, of which 35% was in distribution, and bill collection of 61%. The government aims to cut losses to 15% by 2030.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry of Hydraulic Resources and Electricity (MRHE) | Sets sector policy and planning. It grants concessions and licences that are not within provincial powers, and co-signs tariff orders with the Ministry of the National Economy. |
| Regulator | Autorité de Régulation du secteur de l’Électricité (ARE) | Public body created by Decree 16/013 of 21 April 2016 and operational since 2020. It assesses tariff proposals, reviews applications for titles, issues certificates of conformity before plants and networks are commissioned, keeps a list of applicable technical standards, admits eligible customers and settles disputes before they go to court. |
| TSO | SNEL SA – transmission | Operates three interconnected high-voltage grids (West, South and East), DC converter stations and cross-border links with the Republic of the Congo, Rwanda, Burundi, Zambia and Zimbabwe. Under the compact, SNEL is to formally take on the role of transmission and system operator. |
| System operator | SNEL SA – dispatch | Balances generation and demand on each grid, including scheduled load shedding. A national dispatch centre with associated technical requirements is a compact priority action due by 31 December 2027. |
| DSO | SNEL SA – distribution | Distributes at 30, 20, 6.6 and 0.4 kV in Kinshasa and at 15, 11, 6.6 and 0.4 kV in the provinces. It also runs isolated hydro and thermal systems such as Kisangani, Kalemie, Kamina and Gbadolite. |
| DSO | Private concessionaires and mini-grid operators | Companies such as Virunga Energies, Électricité du Nord-Kivu (ENK), Nuru and SOCODEE in North Kivu, and EDC in Tshikapa, generate and distribute power on their own networks under provincial or national titles. |
| Supplier | SNEL SA – commercial | Signs subscription agreements, reads meters, bills and collects payments through its customer service centres (Centres des Ventes et Services) and payment points. |
| Metering | SNEL SA | Owns and reads meters. Staff read post-paid meters every month. Where they cannot get access, the bill is estimated from the average of the last six bills. |
Compared with the UK system.
| UK concept | DR Congo equivalent | How it works |
|---|---|---|
| DNO | SNEL distribution (or a local concessionaire) | There are no regional network companies separate from supply. SNEL owns and operates the distribution network and sells the electricity. In parts of North Kivu and in some isolated towns, a private concession holder or mini-grid operator does both instead. |
| National Grid/NESO | SNEL transmission and dispatch | SNEL runs three separate high-voltage grids (West, South and East), which are not yet joined into one national system, and balances each one itself. No independent system operator exists. A national dispatch centre and a second public company for new transmission corridors are planned for 2027. |
| MPAN | Numéro du Point Alimenté (PA) | SNEL gives each subscription a supply point number (PA), which appears on the bill and is used for meter reading, billing, complaints and payments. It is SNEL’s internal account reference, not a national standardised code, and it is tied to the subscription contract rather than being a permanent property identifier. |
| MPRN | None | There is no piped natural gas network for homes. Households cook mainly with wood and charcoal, and some urban households use bottled LPG. |
| Meter operator | SNEL (or the mini-grid operator) | The network operator supplies, installs and reads the meter. No competitive metering market exists. Tampering with meter seals is a criminal offence under the 2014 law. |
| Supplier | SNEL or the local concessionaire | Households cannot choose their supplier. Only “eligible customers” admitted by ARE, mostly large mines, can buy from a producer of their choice. Elsewhere the distribution concession holder supplies everyone in its area. |
| Smart-meter infrastructure | Prepaid and communicating meters (SNEL) | No national smart-meter programme, data hub or switching platform exists. SNEL is replacing estimated billing with prepaid meters and planned to buy more than 300,000 communicating meters in 2025–26. |
How a supply point is identified.
PA 0123456789 (fictional – for illustration only; the real format is not published)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Numéro du Point Alimenté (PA) |
| Who issues it? | SNEL SA, when a subscription agreement is signed after connection |
| Format | Account reference allocated by SNEL to each supply point. SNEL does not publish its structure. |
| Length | Not published by SNEL |
| Stays with the property when you switch supplier? | No |
| Where to find it | On the SNEL subscription agreement and on every monthly bill, labelled “Numéro PA”. |
| Electronic access | SNEL has an online customer area, and its 2025 plan included a “Snel & moi” customer app. Bills are paid at official SNEL payment points. There is no national data platform. |
| Third-party access | No regulated third-party data access exists. Consumption data stays with SNEL. |
| Who keeps the register | SNEL’s own commercial database. Private concessionaires keep their own customer records. |
| Register scope | Per DSO |
A household becomes a SNEL customer by signing a subscription agreement (police d’abonnement) at its nearest customer service centre (Centre des Ventes et Services, CVS). The household must show an identity document and proof of its right to occupy the premises. After connection, SNEL issues the agreement in the customer’s name and allocates a supply point number, the numéro du Point Alimenté (PA). SNEL describes it as the customer’s unique reference for all dealings with the company. Meter readings, bills, complaints and payments are all recorded against it.
The PA is tied to the agreement rather than to the building. SNEL requires the subscription to be amended for any change at the supply point: moving in or out, a change of owner, the purchase or sale of the plot, or a change of use. The ARE consumer charter also obliges a new occupant to declare themselves and take out a new subscription before using power. Electricity is not traded between suppliers, so there is no national register or switching process. Each operator keeps its own customer database.
Connection and metering
A low-voltage connection application can be made online or at the CVS. It needs an identity card, the title deed, a cadastral plan, the planning authority’s connection notice, a building permit and an approved single-line wiring diagram showing the installed power and meter. Tenants also need the lease and a power of attorney from the owner. Connecting illegally carries a fine equal to 12 months’ consumption, and any significant change to the installation needs SNEL’s prior consent. Post-paid customers are billed monthly. Customers without a meter are billed on installed power estimated from their appliances, and bills must be paid within five days at an official SNEL payment point.
Fictional example
A fictional bill might show “Numéro PA: 0123456789”, the tariff category “BT ordinaire – Résidentiel 1”, opening and closing meter readings, and the amount in Congolese francs converted from the US dollar tariff. SNEL does not publish the PA format, so this example is illustrative only.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | No |
| Net metering | No |
| Net billing | No |
| How exported electricity is paid | None for households. No feed-in, net-metering or export tariff has been identified, and the 2022 tariff order expressly leaves solar tariffs for later proposals. |
| Can a household sell surplus solar power to SNEL? | No mechanism exists. Neither the 2014 law nor the 2022 SNEL tariff order provides for net metering or a household export tariff. |
| Who can sell electricity to the grid? | Independent producers of 1,000 kW and above need a licence and sell to distributors through the transmission networks. Production on public land, transmission and distribution need a concession. |
| Is a certificate needed before commissioning? | Yes for production, transmission and distribution infrastructure: Article 29 of the 2014 law requires a certificate of conformity from ARE before it is commissioned. |
Connecting a home system.
- Systems up to 50 kW on private land, with no lines crossing a public road, fall under the “freedom” regime and need no title. They must still comply with Congolese standards and safety rules.
- A self-generator of 51–99 kW files a written declaration with the local electricity administration. The installation must meet ARE standards and be certified by an independent expert.
- A self-generator of 100–999.99 kW needs an authorisation from the province or decentralised local authority.
- Any change to an installation connected to SNEL needs SNEL’s prior consent. No procedure for injecting household power into the SNEL grid has been published.
Household solar in the DRC is almost entirely off-grid or behind the meter. One in five households owns a solar panel, often a small solar home system, which is about as common as a mains connection. Grid-connected homes that install solar can only use the power themselves. They cannot export or receive credit for surplus power.
The legal regimes in the 2014 law set out what self-generators need to do, but they concern building and operating a plant, not selling to the grid. Reforms planned under the compact – a revised electricity law, a grid code with third-party access rules (validated by ARE in September 2026) and a mini-grid framework – may create connection rules for distributed generation. No household export scheme had been announced by October 2026.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity (self-generation, up to 50 kW) | Free (“liberté”) – no title, if the plant is entirely on private land and its lines do not cross a public road or come within 10 m of a public line | None (must meet national standards) | The law does not apply at all to plants of 50 kW or less for non-commercial use (Article 2). |
| Generate electricity (self-generation, 51–99 kW) | Written declaration (Article 76) | Local administration in charge of electricity | Must follow ARE standards and be certified by an independent expert. |
| Generate electricity (self-generation, 100–999.99 kW) | Authorisation (Article 74) | Province or decentralised territorial entity | Building self-generation or private lines without authorisation carries fines of CDF 1–50 million. |
| Generate electricity for sale (independent producer) | Licence at 1,000 kW and above off public land; concession for any production on public land | Application through ARE; decision by central government or, for provincial needs, the province | Concessions and licences are awarded by tender. Licences for independent production can last up to 30 years. |
| Store electricity | No storage-specific regime identified | Not defined | Batteries are treated as part of a generating or self-generating installation. No separate licence category exists in the 2014 law. |
| Export electricity to the grid (household) | Not available – no export scheme | SNEL / ARE | No net-metering or feed-in arrangement has been identified. |
| Sell / supply electricity to customers | Licence for commercialisation (Article 66); distribution itself requires a concession | ARE review; central government, or the province for supply within one province | Licences for sale run for 10 years and are renewable. A distribution concession holder must supply every non-eligible customer in its area. |
| Transmission and distribution networks | Concession (Article 46) | Ministry, or the provincial government for a network within one province | The concession contract includes a specification drawn up by ARE and may grant exclusivity over non-eligible customers. |
| Import / export electricity | Licence | Central government | Exports are subject to conditions set by decree. |
| Trade / buy as an eligible customer | Admission to eligible-customer status | ARE (favourable opinion) | ARE’s published list is made up mainly of mining companies in Lualaba and Haut-Katanga. |
| Aggregation, VPP, balancing and grid services | No regime defined | Not applicable | No balancing market or aggregator role exists. SNEL handles balancing internally. |
| Remote control of distributed assets | No specific rules identified | Not applicable | The grid code validated in September 2026 had not been published in full by October 2026. |
Law No. 14/011 of 17 June 2014, amended by Law No. 18/031 of 13 December 2018, sets five legal regimes: concession, licence, authorisation, declaration and freedom. Which one applies depends on the activity, the capacity and whether the plant is on public land. Applicants must be companies or individuals under Congolese law with a known address in the DRC, registered in the trade register, and able to show technical and financial capacity. Titles are published in the Official Journal.
Power is shared between levels of government. Central government grants concessions and licences for national networks and cross-border trade. The provinces grant authorisations, and licences and concessions for production, supply and networks serving one province. Operators say that provinces interpret the law differently. Under the compact, the law is to be revised by 31 December 2026 to introduce an incentive-based concession award procedure, a single title for isolated grids and simpler licensing through a one-stop shop.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Eligible-customer bilateral supply | Restricted | — | No | ARE / SNEL (network access). Consumers admitted by ARE as eligible customers, mainly mines, can contract with producers or importers of their choice and use public networks under access contracts. Network operators must give reasons for refusing access, and refusals can be appealed. |
| Regional power pools (SAPP, CAPP, EAPP) | Restricted | — | No | SNEL / pool operators. SNEL imports and exports through cross-border links. Harmonised transmission pricing for the pools was a compact action due in 2025 and was reported as delayed. |
| Utility load management | No | — | No | SNEL. Shortages are managed by scheduled load shedding of medium/low-voltage substations. Customers are not paid to reduce demand. |
There is no flexibility, balancing or ancillary-services market in the DRC, and no role for aggregators or virtual power plants. SNEL balances each of its grids with its hydro fleet, imports and load shedding. The grid code validated by ARE and the African Development Bank in September 2026 sets technical rules for connection and third-party access. A national dispatch centre is planned by the end of 2027. Both are preconditions for any future market in system services.
Distributed storage is growing as backup, not as a market service. Mines are adding solar and batteries at their own sites, and mini-grid operators use batteries to keep supply going. None of these assets is paid for grid services.
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | No national smart-meter programme; SNEL is rolling out prepaid meters and planned to buy more than 300,000 communicating meters in 2025–26 |
| Reading interval | Monthly manual reading for post-paid meters; no interval data |
| Meter owner | SNEL (or the mini-grid operator) |
| Billing | Monthly reading; estimated from the last six bills if the meter cannot be read; installed-power estimate where there is no meter |
| Prepayment | SNEL prepaid meters in Kinshasa and provincial towns; prepaid meters standard on private mini-grids |
| Communicating meters | More than 300,000 planned for 2025–26 (SNEL) |
| Legal basis | The 2014 law requires billing on actual consumption from calibrated meters and prohibits flat-rate billing |
Metering is a basic problem as well as a modernisation issue. Many SNEL customers are not metered or are billed on estimates. SNEL’s post-paid process relies on monthly readings by staff. When they cannot reach the meter, consumption is estimated from the average of the last six bills, and unmetered customers are billed on their estimated installed power. The National Energy Compact links prepaid metering and digitalisation, under the “SNEL & Moi” model, to cutting technical and commercial losses, and plans to extend it to all SNEL networks.
SNEL’s 2025 plan included buying more than 300,000 communicating meters, a “Snel-box” system to modernise low-voltage networks and analyse consumption, and the “Snel & moi” customer app. Prepaid meters have caused complaints. In September 2026, customers in Kinshasa’s Nsele commune said their credit ran out unusually quickly. No national meter data hub or common technical specification has been published.
Renewable electricity.
Electricity generation mix (2023).
- Hydro: 99.7%
- Solar: 0.2%
- Bioenergy: 0.1%
- Fossil fuels: 0.1%
- Renewable electricity share
- 95% (2025)Source 2Share of renewable energy in national generation as reported by the government in its Mission 300 Compact Progress Report. SNEL’s own 2025 production was 99.9% hydro (12,696.76 of 12,712.35 GWh), and IRENA puts renewables at almost 100% of national generation in 2023.
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- 5 MW (2024)Source 22IRENA net solar capacity change in 2024. Excludes the 233 MWp Kamoa-Kakula plant commissioned in 2026.
- Hydro
- 3.247 GW (2024)Source 22National total including non-SNEL plants. SNEL’s own hydro fleet was 2,586 MW in 2025.
- Solar PV
- 0.03 GW (2024)Source 22
- Bioenergy
- 0.003 GW (2024)Source 22
- Non-renewable (thermal)
- 0.421 GW (2024)Source 22Includes diesel and other thermal plants, much of it at mine sites. SNEL’s own thermal capacity was 43.88 MW in 2025.
Targets.
- Keep renewables at 95% of generation while total generation grows, from 15,261 GWh to 65,000 GWh by 2030 (National Energy Compact).
- Raise installed capacity from 3,067 MW to 13,576 MW by 2030.
- Award concessions for 4,000 MWp of private-sector solar projects through competitive tenders.
- Raise electricity access from 21.5% to at least 62% by 2030, reaching 60 million more people.
- Adopt quality standards for solar systems (IEC TS 62257-9-8) by 2026.
Hydropower supplies almost all of the DRC’s grid electricity. The country’s hydropower potential is estimated at about 100 GW, of which only around 3% is used. Grand Inga, Ruzizi 3 and new transmission corridors (Inga–Kolwezi and Inga–Bunia) are the central long-term projects.
Solar is growing mainly off-grid and at mines. Mini-grid operators such as Nuru run solar metro-grids. Nuru raised more than USD 40 million in 2023 for 13.7 MWp of projects in Goma, Kindu and Bunia. About 17 off-grid solar companies sell solar home systems. In August 2026 the 233 MWp Kamoa-Kakula solar-plus-battery plant near Kolwezi began supplying 30 MW of round-the-clock power to the mine.
Policy support for distributed renewables is still being developed. The compact commits to review customs and tax exemptions for distributed renewables, adopt solar quality standards and expand the Mwinda results-based financing fund for private mini-grids. Most of the related reform actions were reported as delayed in January 2026.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
Storage in the DRC is installed mainly at mines and mini-grids, not on the SNEL network. The Kamoa-Kakula facility shows that solar plus batteries can provide firm power to large industrial users. Mini-grid developers use batteries to supply power around the clock in towns without SNEL supply. No storage licensing category, grid-scale procurement or storage tariff exists in the regulatory framework.
Storage projects.
- Kamoa Copper solar/BESS baseload facility (CrossBoundary Energy): 233 MWp of solar PV and a 123 MVA / 526 MWh battery near Kolwezi, supplying 30 MW of baseload power to Kamoa Copper. The PPA was signed in April 2025 and commercial operation began on 12 August 2026.
- Nuru solar hybrid metro-grids: Solar hybrid metro-grids of 13.7 MWp in total in Goma, Kindu and Bunia, financed by a Series B equity round of more than USD 40 million in July 2023.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| SNEL SA (Société Nationale d’Électricité) | Owns and operates more than 90% of installed capacity (National Energy Compact) | No | No | No | No |
| Virunga Energies | About 30,700 households and 1,600 businesses in North Kivu (IFRI, 2025) | Yes | No | No | No |
Households cannot choose their supplier. In most towns with power, SNEL is the only option. In parts of eastern DRC, private operators hold local rights and generate, distribute and sell power themselves. They include Virunga Energies (hydro plants of about 29 MW in North Kivu), Électricité du Nord-Kivu (ENK) in Beni and Butembo, Nuru (solar metro-grids in Goma, Kindu and Bunia), SOCODEE in Goma, EDC in Tshikapa and Equatorial Power on Idjwi island. About 50 private electricity operators are registered with ARE.
Outside grid areas, solar home systems sold by off-grid solar companies are the main source of electricity. Several of these companies are members of the industry association ACERD.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Ministry of Hydraulic Resources and Electricity (MRHE) | Government | Electricity policy, planning, concessions and co-signing of tariffs | Leads the National Energy Compact and the revision of the electricity law. |
| Autorité de Régulation du secteur de l’Électricité (ARE) | Regulator | Sector regulator | Reviews tariffs and applications for titles, issues certificates of conformity, keeps the list of applicable standards and handles complaints. |
| ANSER – Agence Nationale de l’Électrification et des Services Énergétiques en milieux rural et périurbain | Government | Rural and peri-urban electrification agency | Plans and co-finances rural and peri-urban electrification, including private mini-grid and off-grid projects. |
| SNEL SA | Transmission | State-owned utility: generation, transmission, distribution and supply | Operates the national grids and supplies most connected customers. |
| ACERD – Congolese Association for Renewable and Decentralised Energy | Renewable Energy | Industry association for off-grid solar and mini-grid companies | Speaks for the decentralised energy sector to government and has partnered with the Africa Minigrid Developers Association on mini-grid policy. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Applicable standards list | ARE-TECH-DOC-01-01 (list of technical and environmental standards, 9 August 2023) | ARE | Reference list for designing, building, operating and certifying generation, transmission and distribution installations. It covers 294 electrotechnical standards and a rural electrification section. |
| Small renewable and hybrid systems | IEC (CEI) 62257 series | IEC, listed by ARE | Recommendations for small renewable energy and hybrid systems for rural electrification, including PV generators and selection of individual PV systems. The compact plans to adopt IEC TS 62257-9-8 quality standards for solar systems by 2026. |
| Certificate of conformity | Law No. 14/011, Article 29 | ARE | Production, transmission and distribution infrastructure needs an ARE certificate of conformity before it is commissioned. Approved independent experts carry out technical inspections. |
| Grid code | Grid code (validated September 2026) | ARE (with the African Development Bank, AESTAP-RDC project) | Technical and safety rules for connection and third-party access to networks. The full text had not been published as of October 2026. |
| Low-voltage supply | 220 V single-phase / 380 V three-phase, up to 59 kW | Joint tariff order of 5 November 2022 | Medium voltage is 6.6–30 kV; high-voltage customers take 1 MW or more at above 30 kV. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Small solar system (up to 50 kW) on private land | No | National | Falls under the freedom regime if no public road is crossed. It must comply with national standards and safety rules. |
| Self-generation 51–99 kW | Yes | Local | Written declaration to the local electricity administration, with certification by an independent expert. |
| Self-generation 100–999.99 kW | Yes | Regional | Authorisation from the province or decentralised territorial entity. |
| Building permit and land title (for a new SNEL connection) | Yes | Local | SNEL asks for the title deed, cadastral plan, planning authority’s connection notice and building permit with a low-voltage connection application. |
| Network operator consent | Limited | National | SNEL’s prior agreement is required for any significant addition or change to an installation connected to its network. |
For most households, the main formalities concern connection to SNEL rather than solar equipment. A rooftop or ground-mounted system of up to 50 kW on the owner’s land needs no electricity title. Larger self-generation follows the declaration and authorisation thresholds in the 2014 law. Land access is often contested: the compact notes frequent disputes over land for solar projects and calls for clear national and provincial rules.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Mwinda Fund (results-based financing for private mini-grids and off-grid solar) | Active | Results-based grant | Results-based financing for private distributed renewable energy operators. The National Energy Compact commits to expand it, with strict monitoring and compliance, alongside a revolving credit line. | — |
| Customs and tax exemptions for distributed renewables | Active | Customs and tax relief | Exemptions exist for distributed renewable energy equipment. The compact commits to evaluate and streamline how they are applied and renewed so that off-grid solutions become more affordable. A revision of the tax code is a priority action due by 2028. | — |
Data and connectivity.
- Fixed broadband
- Not identified from a reliable public source.
- 4G coverage
- 57 % of population (2025)Source 25Share of the population with access to 4G mobile internet.
- 5G coverage
- 1 % of population (2025)Source 25Internet Society reports less than 1%; the value shown is an upper bound.
Mobile networks are the main digital infrastructure. There were 64.7 million cellular connections in late 2025, and 79.6% of them were 3G, 4G or 5G. Large parts of the country lack 4G coverage, which limits remote monitoring of meters and distributed assets outside the main towns.
Grid conditions.
- National peak demand
- Not identified from a reliable public source.
- Annual electricity demand
- 16.7 TWh (2025)Source 7Energy received by SNEL’s transmission system (16,692.85 GWh): SNEL production, the Busanga independent producer and imports. Excludes mining self-generation, mini-grids and off-grid supply, and does not include demand left unmet by load shedding.
- Generation capacity
- 3.701 GW (2024)Source 22National installed capacity (IRENA). SNEL’s own installed capacity was 2,629.82 MW in 2025, of which 1,928.72 MW was available.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
The DRC’s grid problem is shortage, not surplus. SNEL’s available capacity was only 73% of installed capacity in 2025. Low water on the Lufira cut output at Mwadingusha and Koni, and imports rose to 2,754 GWh to supply the southern mining grid. SNEL reported more interruptions per 100 km of network in 2025 than in 2024. The three grids are not fully joined, so surplus in one region cannot always reach another.
Expansion depends on large projects. These include Grand Inga, the Inga–Kolwezi and Inga–Bunia corridors linking the southern and eastern African power pools, the rehabilitation of existing plants, and the second public operator planned to manage new transmission corridors.
Grid and capacity maps.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Cost-of-service study, tariff methodology and grid code validated | Current | September 2026 | ARE and the African Development Bank completed the AESTAP-RDC regulatory tools on 25 September 2026. They are a cost-of-service study, a tariff-setting methodology and a grid code with rules for third-party network access. |
| Revision of the 2014 electricity law | Upcoming | Due by 31 December 2026 | Compact priority action, reported on track in early 2026. It introduces an incentive-based concession award procedure and private investment rules for renewable mini-grids, with a simpler single title for isolated grids. |
| One-stop shop and simplified licensing | Upcoming | Due by 31 December 2026 | A one-stop shop for permits for major private projects, simplified licensing and standard agreements with multi-year tariffs. |
| SNEL restructuring and cost-reflective tariffs | Upcoming | Restructuring plan due by 31 December 2026; full operating-cost recovery targeted by 2029 | Council of Ministers adoption of SNEL’s new organisation and debt restructuring plan, an audited performance contract and gradual tariff increases. The government proposed ending below-cost pricing in December 2025. |
| National dispatch centre and second public electricity company | Upcoming | By 31 December 2027 | A national dispatch centre with technical requirements, and a second public operator, possibly with private participation, to manage new transmission corridors. |
| Delayed planning reforms | Upcoming | Originally due by 31 December 2025 | The power system master plan, the national electrification strategy, a transmission pricing methodology for the regional pools and ministerial decrees for distributed renewables and clean cooking were all reported as delayed in January 2026. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Low | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | — | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | High | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Low | Although 20% of households own a solar panel (EDS-RDC 2023–24), these are mostly small off-grid systems. There is no grid-connected residential solar framework or export scheme, and national solar capacity was about 30 MW in 2024 (IRENA). |
| Distributed energy market | Medium | Mini-grids and solar home systems are the main route to new access. About 50 private operators are registered with ARE, private mini-grids in the east serve tens of thousands of customers, and solar home system ownership matches grid access. |
| Grid flexibility market | Low | No balancing, ancillary-services or demand-response market exists. SNEL manages shortages through load shedding, and there is no aggregator role. |
| Energy storage adoption | Low | No grid-scale storage on the SNEL network and no storage framework. Batteries are used at mines (526 MWh at Kamoa-Kakula from 2026) and on mini-grids. |
| Renewable growth environment | Medium | Generation is already about 95–100% renewable (hydro), but capacity grew slowly before 2024. Large solar-plus-storage projects for mines started in 2026, and the compact targets 13.6 GW of capacity by 2030. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 31 sources
- Compact énergétique de la République Démocratique du Congo (Mission 300 National Energy Compact). Government of the DRC / World Bank, 2025. accessed 1 October 2026.
- Mission 300 Compact Progress Report – Democratic Republic of Congo (Q1 2026). Government of the DRC (CDMU) / World Bank, 2026. accessed 1 October 2026.
- Arrêté interministériel fixant les tarifs producteurs, d’accès aux réseaux et de vente aux consommateurs finals par la SNEL SA (No. 038/CAB/MIN/ECONAT/NKK/2022 and 060/CAB-MIN/RHE/OMM/22 of 5 November 2022). ARE, 2022. accessed 1 October 2026.
- Énergie : les tarifs de l’énergie électrique demeurent inchangés en devise. Agence Congolaise de Presse, 2024. accessed 1 October 2026.
- DRC to end below-cost utility pricing under new water and power reforms. Bankable, 2025. accessed 1 October 2026.
- La taxe de 3% sur les consommateurs d’énergie non encore d’application en RDC. Agence Congolaise de Presse, 2024. accessed 1 October 2026.
- Indicateurs de performance au 31 décembre 2025. SNEL SA, 2026. accessed 1 October 2026.
- L’Abonnement. SNEL SA, 2026. accessed 1 October 2026.
- La Facturation. SNEL SA, 2026. accessed 1 October 2026.
- La Relève. SNEL SA, 2026. accessed 1 October 2026.
- Le Raccordement. SNEL SA, 2026. accessed 1 October 2026.
- Le transport d’électricité. SNEL SA, 2026. accessed 1 October 2026.
- La Distribution d’Électricité. SNEL SA, 2026. accessed 1 October 2026.
- Loi n° 14/011 du 17 juin 2014 relative au secteur de l’électricité. Leganet.cd, 2014. accessed 1 October 2026.
- Statut de client éligible. ARE, 2024. accessed 1 October 2026.
- Normes applicables dans les domaines technique et environnemental en RDC (ARE-TECH-DOC-01-01). ARE, 2023. accessed 1 October 2026.
- Droits et obligations du consommateur. ARE. accessed 1 October 2026.
- Modernisation du secteur de l’électricité en RDC : l’ARE et la BAD dotent le pays d’outils de régulation de dernière génération. ARE, 2026. accessed 1 October 2026.
- Société nationale d’électricité : l’année 2025 placée sous les signes de matérialisation de redevabilité. Agence Congolaise de Presse, 2025. accessed 1 October 2026.
- Électricité : Kinshasa est alimentée par une quotité imposée entre 550 et 630 mégawatts. Agence Congolaise de Presse, 2025. accessed 1 October 2026.
- Les abonnés de la SNEL dénoncent la surconsommation des compteurs à prépaiement. Radio Okapi (via AllAfrica), 2026. accessed 1 October 2026.
- Energy Profile: Democratic Republic of the Congo. IRENA, 2025. accessed 1 October 2026.
- Enquête Démographique et de Santé en RDC 2023–2024 : Rapport final (EDS-RDC III). Institut National de la Statistique / The DHS Program, 2025. accessed 1 October 2026.
- Digital 2026: The Democratic Republic of the Congo. DataReportal, 2026. accessed 1 October 2026.
- Internet Society Pulse – Democratic Republic of the Congo country report. Internet Society, 2025. accessed 1 October 2026.
- Euro foreign exchange reference rates – US dollar (USD). European Central Bank, 2026. accessed 1 October 2026.
- Virunga Energies – households and SMEs. Virunga Energies, 2026. accessed 1 October 2026.
- Le secteur électrique en République démocratique du Congo. Ifri (Institut français des relations internationales), 2025. accessed 1 October 2026.
- CrossBoundary Energy launches Africa’s first solar-BESS baseload facility for Kamoa Copper. SolarQuarter, 2026. accessed 1 October 2026.
- Nuru closes over $40 million of equity funding to drive metrogrid scaling in the DRC. Global Energy Alliance for People and Planet, 2023. accessed 1 October 2026.
- Empowering energy access: ACERD and AMDA partner for mini-grid solutions in DRC. SolarQuarter, 2024. accessed 1 October 2026.
Questions about energy in DR Congo.
SNEL sets its tariffs in US dollars and bills in Congolese francs. Its published residential band 1 averages USD 0.039/kWh (about EUR 0.034), social customers using up to 100 kWh a month pay a flat USD 2.65, and the higher residential band averages USD 0.087/kWh. Private mini-grids charge much more, for example USD 0.25/kWh in Goma.
The state-owned SNEL SA supplies most connected customers and runs the transmission grids. In parts of eastern DRC, private operators such as Virunga Energies, ENK and Nuru supply their own local networks. Households cannot choose their supplier. Only “eligible customers” approved by ARE, mostly large mines, can buy from other producers.
The National Energy Compact uses a national access rate of 21.5%. The 2023–24 Demographic and Health Survey found that 22% of households had electricity: 55% in urban areas and 3% in rural areas. The government aims to reach 62% by 2030.
No. There is no net-metering, feed-in or export scheme for households. Solar systems of up to 50 kW on private land can be installed without an electricity title, but the power can only be used on site.
SNEL gives each subscription a “numéro du Point Alimenté” (PA), which appears on the bill and is used for reading, billing and payments. Unlike an MPAN, it is SNEL’s internal account reference and not a national standard identifier. It is linked to the subscription, which must be changed when the occupant or owner changes.
Not for systems of up to 50 kW on private land that do not cross a public road. From 51 to 99 kW you must file a declaration with the local electricity administration, and from 100 kW to just under 1 MW you need a provincial authorisation. Producing 1 MW or more for sale requires a licence.
The Autorité de Régulation du secteur de l’Électricité (ARE), created under the 2014 electricity law. Tariffs are formally set by joint order of the ministers for the economy and for electricity on the basis of ARE’s opinion.