How electricity works in Cuba.
Cuba electricity 2026: Unión Eléctrica monopoly, 18-band residential tariff, 90 CUP/kWh for renewable exports, solar park build-out, customs and tax incentives.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Cuban peso (CUP) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Cuba energy at a glance.
Key figures for households in Cuba. Each one links to its source on the full overview below.
Electricity price.
0.33 CUP per kWh for households, including taxes. Figures for 2026.
Renewable share.
10% of electricity from renewable sources. Figures for 2025.
Selling back to the grid.
Can homes export electricity? Yes. Details are in the export section below.
Four things to check in Cuba.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Cuba below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Cuba requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Cuba.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Cuba, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Cuba, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Cuba.
The energy market in Cuba, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 10 October 2026.
On this page22 sections
Cuba’s electricity sector is run by a single state organisation, the Unión Eléctrica (UNE), which is responsible for generation, transmission, distribution and sale of electricity across the island. It works through 16 provincial electricity companies (Empresas Eléctricas), seven thermal power stations and a group of national service companies. Energy policy sits with the Ministry of Energy and Mines (MINEM), and electricity prices are set by the Council of Ministers and the Ministry of Finance and Prices.
The system depends heavily on oil. According to IRENA, Cuba generated 15,496 GWh in 2023, 95% of it from fossil fuels, and generation had fallen from about 21 TWh in 2018. Ageing thermal units and fuel shortages have caused long daily outages: on 21 September 2026 UNE forecast a peak deficit of 1,975 MW against expected demand of 3,150 MW, and the national grid collapsed completely on 11 September 2025.
Solar power has expanded quickly. UNE reports that 52 photovoltaic parks with more than 1,000 MW were installed and that installed solar capacity exceeds 1,300 MW, raising the renewable share of generation from 3.6% to 10% in 2025. Since May 2026 UNE pays 90 Cuban pesos (CUP) per kWh for renewable electricity delivered to the grid by households and businesses, and imports of solar systems and lithium-ion batteries are exempt from customs duty until the end of 2027.
Energy snapshot.
Headline figures for electricity in Cuba. Each shows its data year and links to its source.
- Population10,937,203 peopleSource 12025
- HouseholdsNot identified from a reliable public source.
- Average household sizeNot identified from a reliable public source.
- Electricity use per householdNot identified from a reliable public source.
- Household price (CUP)0.33 CUP/kWhSource 62026
- Household price (EUR)0 EUR/kWhSource 72026
- Renewable electricity share10%Source 152025
- Solar capacity1.3 GWSource 152026
- Wind capacityNot identified from a reliable public source.
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Vertically integrated
- Homes can export to the grid
- Yes
- Home equipment in grid services
- No
- Regulator
- No independent regulator — Ministry of Energy and Mines (MINEM) for policy; Council of Ministers and Ministry of Finance and Prices for tariffs
- System operator
- Unión Eléctrica (UNE) — state-owned, vertically integrated operator of the national electricity system (SEN)
- Distribution networks
- 16 provincial electricity companies (Empresas Eléctricas) belonging to UNE, one per province plus Isla de la Juventud
- Currency
- Cuban peso (CUP)
- Voltage and frequency
- 115 V single-phase and 115/230 V three-wire / 60 Hz
Electricity prices in Cuba.
- Household price (CUP)
- 0.33 CUP/kWh (2026)Source 6Rate for the first consumption band (0–100 kWh) of the residential tariff set by Council of Ministers Agreement 9810/2024, in force since 1 March 2024. The tariff has 18 bands rising to 7.00 CUP/kWh at 451–500 kWh, 11.50 CUP/kWh at 501–600 kWh and 25.00 CUP/kWh above 5,000 kWh, so the average price depends strongly on consumption. No separate taxes are shown in the tariff.
- Household price (EUR)
- 0 EUR/kWh (2026)Source 7Derived: 0.33 CUP/kWh divided by 781.38 CUP per euro, the Banco Central de Cuba “Segment III” rate shown on its exchange-rate page when accessed on 10 October 2026 (the page did not display an effective date). Cuba operates several official exchange-rate segments, so the euro equivalent varies greatly with the rate chosen; treat it as indicative only.
- Typical annual electricity bill
- Not identified from a reliable public source.
Residential electricity prices are set nationally by the Council of Ministers and are the same in every province. The current tariff was adopted on 24 January 2024 as Agreement 9810/2024 and came into force on 1 March 2024, replacing the residential tariff of Agreement 8957 of November 2020. It has 18 bands: the lowest, up to 100 kWh a month, costs 0.33 CUP/kWh, and the rate rises steeply with consumption to 25.00 CUP/kWh above 5,000 kWh a month. The structure is designed to keep basic use cheap and to discourage high consumption.
Currency
Prices are in Cuban pesos. The Banco Central de Cuba publishes several official exchange-rate segments, and in October 2026 its Segment III rate was 781.38 CUP per euro. Converted at that rate, the first-band price is a tiny fraction of a euro cent, but the result depends heavily on which rate is used.
Business tariffs and peak pricing
Under Decree 110/2024, UNE charges new high-consuming enterprises (those using an average of 30 MWh or more a month) for peak-hour electricity at the real cost of diesel generation, valued at the official exchange rate. The decree defines the daytime peak as 11:00–13:00 and the evening peak as 17:00–21:00.
What the tariff does not show
Because supply is frequently interrupted by generation shortfalls, the price per kWh is only part of the cost to households. Many use backup equipment, but no official data on spending on alternatives were identified.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | Residential tariff in 18 consumption bands per month (Agreement 9810/2024, from 1 March 2024): 0–100 kWh 0.33; 101–150 kWh 1.07; 151–200 kWh 1.43; 201–250 kWh 2.46; 251–300 kWh 3.00; 301–350 kWh 4.00; 351–400 kWh 5.00; 401–450 kWh 6.00; 451–500 kWh 7.00; 501–600 kWh 11.50; 601–700 kWh 11.81; 701–1,000 kWh 12.31; 1,001–1,800 kWh 13.50; 1,801–2,600 kWh 14.75; 2,601–3,400 kWh 16.13; 3,401–4,200 kWh 17.44; 4,201–5,000 kWh 18.75; over 5,000 kWh 25.00 CUP/kWh. |
| Time-of-use | No | Households have no time-of-use tariff. Decree 110/2024 instead requires UNE to charge new high-consuming enterprises for peak-hour electricity at the real cost of diesel generation, converted at the official exchange rate. |
| Other | Yes | Separate tariffs apply to state and non-state businesses; these were not reviewed for this profile. Enterprises in the Mariel Special Development Zone are exempt from the diesel-cost peak tariff and pay UNE’s tariffs for the zone. |
Household prices compared with neighbouring countries (EUR per kWh).
- Jamaica€0.304
- Bahamas€0.277
- United States€0.161
- Mexico€0.077
- Cuba€0
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- Not identified from a reliable public source.
- Average daily use per household
- Not identified from a reliable public source.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- Not identified from a reliable public source.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- Not identified from a reliable public source.
According to the World Bank, 100% of Cubans had access to electricity in 2024. Generation has nonetheless fallen sharply: IRENA records about 21 TWh in 2018 and 15.5 TWh in 2023, reflecting a lack of fuel and generating capacity rather than lower demand.
Demand regularly exceeds what the system can supply. On 21 September 2026 UNE expected peak demand of 3,150 MW against 1,215 MW of available capacity, and in a September 2026 article it described typical deficits of 1,800–1,900 MW at the evening peak, with outages exceeding 20 hours a day at the worst points.
Detailed residential statistics (appliance ownership, average use) are published by the national statistics office ONEI, but its website could not be reached for this profile.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- Not identified from a reliable public source.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- Not identified from a reliable public source.
- Apartments and flats
- Not identified from a reliable public source.
- Urban population
- 77.2 % of population (2025)Source 2World Bank estimate.
More than three-quarters of the population lives in urban areas, according to the World Bank. Tenure and dwelling-type figures come from ONEI’s census, which could not be accessed, so they are left blank.
To open a residential electricity supply, applicants must prove legal possession of the dwelling with a property title, usufruct certificate, habitability certificate from the housing authority, construction licence, exchange resolution, a contract with the owning entity, or an authorisation from a competent body such as a municipal government or cooperative.
How the grid works in Cuba.
- TransmissionUnión Eléctrica (UNE), Unión Eléctrica (UNE)
- Distribution16 provincial electricity companies (Empresas Eléctricas) belonging to UNE, one per province plus Isla de la Juventud
- MeteringProvincial Empresas Eléctricas
- Supply1 or more retail suppliers
Physical flow
Cuba’s grid is an isolated island system with no international interconnections. Nominal voltages are 220 kV and 110 kV for transmission, 33 kV and 66 kV for sub-transmission, and a range of distribution voltages down to 115 V single-phase and 115/230 V three-wire supply for homes, all at 60 Hz. UNE lists seven thermal power stations (including Antonio Guiteras, Lidio Ramón Pérez, Máximo Gómez, Carlos Manuel de Céspedes, Antonio Maceo, Ernesto Guevara and 10 de Octubre), alongside distributed diesel and fuel-oil generating sets and a growing fleet of solar parks.
IRENA puts total installed capacity at 6.7 GW in 2024, but much of it is unavailable. In September 2026 UNE reported that 10 of 16 thermal units were out of service through breakdowns or maintenance, 106 distributed-generation plants were idle for lack of fuel, and 80% of generating units had exceeded their design life.
Commercial flow
There is no electricity market. UNE generates most electricity itself and is legally obliged to buy all renewable electricity delivered by independent producers that meet its technical standards (Decree-Law 345, Article 15). It then sells to all customers at tariffs fixed by the state. Sugar mills that cogenerate from bagasse and households and businesses with solar panels are paid regulated prices for what they deliver.
Reliability
Shortfalls are managed through scheduled load-shedding by circuit. On 11 September 2025 the entire system went down to 0 MW; UNE restored about 1,000 MW within 24 hours by bringing back regional subsystems and reconnecting them. In 2026 UNE also reported more than 460 criminal investigations into theft and vandalism of grid equipment, especially transformer oil.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministerio de Energía y Minas (MINEM) | Sets energy policy, issues the regulations under Decree-Law 345 on renewables and energy efficiency, and oversees UNE and the national energy-efficiency office ONURE. |
| Regulator | Council of Ministers / Ministerio de Finanzas y Precios | There is no independent energy regulator. The Council of Ministers sets residential tariffs; the Ministry of Finance and Prices sets the prices UNE pays independent renewable producers and grants tax and customs exemptions. |
| System operator | Unión Eléctrica (UNE) | State organisation responsible for generating, transmitting, distributing and selling electricity. Dispatches the national electricity system (SEN) and publishes daily system notes on availability, demand and expected shortfalls. |
| TSO | Unión Eléctrica (UNE) | Owns and operates the 220 kV and 110 kV transmission network and 33 kV and 66 kV sub-transmission. |
| DSO | 16 Empresas Eléctricas provinciales | One distribution and retail company per province (Pinar del Río, Artemisa, La Habana, Mayabeque, Matanzas, Villa Clara, Cienfuegos, Sancti Spíritus, Ciego de Ávila, Camagüey, Las Tunas, Holguín, Granma, Santiago de Cuba, Guantánamo) and Isla de la Juventud. Their commercial offices take applications, sign contracts and handle meters. |
| Supplier | Unión Eléctrica, through the provincial companies | Sole supplier of electricity at state-set tariffs. |
| Metering | Provincial Empresas Eléctricas | Install, read and replace meters (metros contadores). Meters may be changed at the customer’s request or on an inspector’s order when defective, inadequate or damaged. |
Compared with the UK system.
| UK concept | Cuba equivalent | How it works |
|---|---|---|
| DNO | Empresa Eléctrica provincial | Each province has one distribution company, all part of UNE. They own the low- and medium-voltage networks, connect customers through local commercial offices and enforce the technical rules for internal installations. |
| National Grid/NESO | Unión Eléctrica (SEN) | UNE runs the transmission network and dispatches every power station on the island. There is no separation between system operator, network owner and generator. When the grid fails, UNE restores it in islands — on 11 September 2025 several provinces ran as separate subsystems until they could be reconnected. |
| MPAN | Residential service contract (no published code) | A supply point is administered as a service contract between the provincial company and a named holder for a specific address, recorded on internal forms such as the H-65 connection/disconnection order with the holder’s identity-card number. No public, standardised supply-point identifier was identified. |
| MPRN | No equivalent identified | No national gas supply-point register was identified in the sources consulted. |
| Meter operator | Empresa Eléctrica provincial | The utility installs the meter; under the 1975 service regulations only its workers may handle, repair or change it, and the customer must protect it. There is no competitive metering market. |
| Supplier | Unión Eléctrica | No retail choice. All households buy from UNE’s provincial company at the national residential tariff. Reselling or passing electricity to another person is prohibited by Law 1287 of 1975. |
| Smart-meter infrastructure | None identified | Residential consumption is measured by meters the utility installs and reads; the 1975 regulations provide for monthly or four-monthly readings. No smart-meter programme or data hub was identified. |
How a supply point is identified.
| Question | Answer |
|---|---|
| What is it called? | Contrato de servicio eléctrico residencial (residential service contract) |
| Who issues it? | The provincial Empresa Eléctrica, at its commercial office, when a residential service is contracted |
| Format | Not published. Contracts and changes are recorded on the utility’s internal H-65 “orden de conexión y desconexión” form, which records the holder’s identity-card (carné de identidad) number; no public customer or supply-point code format was identified. |
| Length | Not published |
| Stays with the property when you switch supplier? | Not identified from a reliable public source. |
| Where to find it | On the electricity bill or payment record issued by the provincial company; the exact identifiers printed were not verified. |
| Electronic access | No online customer portal with consumption data was identified on UNE’s website. |
| Third-party access | No framework for third-party access to metering or customer data was identified. |
| Who keeps the register | Commercial records of each provincial Empresa Eléctrica, within Unión Eléctrica |
| Register scope | Per DSO |
In Cuba a household connection is administered as a service contract between the occupant and the provincial electricity company for a specific address. The applicant goes to the company’s commercial office with an identity card and gives the full address (street, number, cross streets, flat or, in rural areas, road, kilometre or farm name), a telephone number, the number of household members, and a list of the lights and appliances to be connected with their power and voltage. They must also prove legal possession of the dwelling — for example with a property title, usufruct certificate or habitability certificate — and, when moving, bring the final account from their previous address.
The company accepts the application only when all the information is complete and the installation meets technical standards. Under the 1975 service regulations a residential contract is indefinite until the holder ends it, the customer must allow utility staff access for readings and inspections, and the internal wiring beyond the meter is the customer’s responsibility.
The supply belongs to a named holder at an address. A change of holder (cambio de nombre) requires the last paid bill and one of the documents used for a new contract; any arrears must be cleared first. Staff record the change on the H-65 form with the new holder’s identity-card number. When a meter is replaced, the first bill afterwards is based on average consumption.
UNE does not publish a standard supply-point code, so no fictional example is given here. Because each provincial company is the only distributor and supplier in its area, its commercial records serve as the register of supply points.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Yes |
| Net metering | Unknown |
| Net billing | Yes |
| How exported electricity is paid | Regulated purchase price of 90.00 CUP/kWh for renewable electricity delivered to the national grid at any hour, for residential (CFR) and non-residential (C1F) producers (Resolution 114/2026, extended to all renewable sources by Resolution 179/2026). Income from these sales is exempt from the services tax. |
| Can households sell solar power to the grid? | Yes. Decree-Law 345 requires MINEM to promote self-generation, including in the residential sector, and UNE must buy all renewable electricity from independent producers that meets technical standards. |
| Is there a size limit for home systems? | No maximum power limit applies to residential photovoltaic systems under MINEM Resolution 123/2019. |
| How much is paid? | 90.00 CUP/kWh at any hour since May 2026, up from 6.00 CUP/kWh for residential producers under Resolution 238/2023. |
| Who installs the export meter? | UNE installs the measuring equipment for energy delivered to the grid and certifies the readings; reading arrangements are set in the purchase contract. |
| Is authorisation needed to connect a generator? | Yes. The 1975 electricity service regulations prohibit connecting any other generating source to the utility’s lines without written authorisation, and UNE must certify the interconnection point. |
Connecting a home system.
- Install a renewable system (for households normally rooftop solar); equipment can be imported free of customs duty under Resolution 180/2026.
- Apply to the provincial Empresa Eléctrica. UNE indicates the delivery point for interconnection and the producer builds or adapts it.
- UNE supervises and certifies that the delivery point meets Cuban technical standards and, at the producer’s request, connects the installation to the grid.
- UNE installs the meter that records energy delivered to the grid and agrees reading arrangements in the purchase contract.
- Energy delivered is paid at the regulated price (90 CUP/kWh since May 2026).
The legal basis is Decree-Law 345 “On the development of renewable sources and the efficient use of energy”, signed on 23 March 2017 and published in the Official Gazette on 28 November 2019. It requires MINEM to promote generation by consumers, including households, for their own supply and sale of surplus, and obliges UNE to buy all renewable electricity from independent producers that meets technical standards, with the purchase price based on the fossil-fuel generation cost avoided.
MINEM Resolution 123/2019 sets the practical rules: UNE installs the meter for energy delivered to the grid, the producer is responsible for building the delivery point, UNE tells the producer where it must be and certifies it before connecting, and no maximum power limit applies to residential photovoltaic systems.
Purchase price
Prices are set by the Ministry of Finance and Prices. Resolution 238/2023 paid residential producers 6.00 CUP/kWh, non-residential solar and biogas producers 3.00 CUP/kWh, and sugar-mill cogenerators 4.00–12.00 CUP/kWh depending on the time of day. Resolution 114/2026 of 6 May 2026 raised the price for residential and non-residential renewable producers to 90.00 CUP/kWh at any hour and exempted the income from the services tax; Resolution 179/2026 of 5 August 2026 extended it to electricity from any renewable source.
The sources consulted refer to energy “delivered” to the grid; whether households are paid for gross exports or for net exports after their own consumption was not stated.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate for own use (households) | Permitted and promoted under Decree-Law 345; no maximum power for residential PV (MINEM Resolution 123/2019) | MINEM; provincial Empresa Eléctrica for connection | Connecting a generator to the grid needs the utility’s written authorisation and certification of the delivery point. |
| Export / sell surplus to the grid | Purchase contract with UNE; UNE meter on the delivery point; regulated price of 90 CUP/kWh | UNE; Ministry of Finance and Prices (price) | UNE must buy all renewable energy that meets technical standards. |
| Independent renewable generation by businesses | Investment process with an energy licence (licencia energética) and ONURE conditions; sale to UNE at the regulated price | MINEM / ONURE; UNE | Tax relief requires an ONURE energy assessment (Dictamen Energético) confirming the system meets technical requirements. |
| Generate for the public system (thermal and utility solar) | Carried out by UNE | State | Utility-scale solar parks are built under state programmes. |
| Transmission, distribution and supply | Reserved to UNE and its provincial companies | State | No retail competition. |
| Sell or pass electricity to third parties | Prohibited for consumers (Law 1287 of 1975, Article 13) | UNE | Electricity must be used only at the contracted premises; sale to the grid is the only permitted route. |
| Store electricity | No specific licensing regime identified | — | Lithium-ion and other accumulators are on the customs-exemption list of Resolution 180/2026. |
| Aggregate, trade, wholesale, balancing, grid services, VPP, remote control of assets | No regime identified | — | There is no electricity market. |
Cuba has no electricity licensing regime in the European sense: generation, transmission, distribution and supply are carried out by the state through UNE. The basic service law is Law 1287 of 2 January 1975 with its service regulations, which set technical standards, contracting rules and prohibitions such as reselling electricity and connecting other generators without authorisation.
Renewable generation by consumers is governed by Decree-Law 345 and MINEM Resolution 123/2019. Decree 110/2024 adds obligations for high-consuming organisations (30 MWh or more a month, or 50,000 litres of fuel): they must certify an ISO 50001 energy-management system, and new high-consuming investments must cover 50% of their daytime-peak consumption with renewables, or contract capacity in UNE’s solar parks where roof space is insufficient.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Energy, balancing and ancillary services | No | — | No | Unión Eléctrica. UNE balances the system centrally through its own plants and scheduled load-shedding. No market for distributed resources, demand response or aggregation was identified. |
Demand is managed administratively. Decree 110/2024 requires organisations to follow monthly electricity plans including a peak-hour consumption plan, defines daytime (11:00–13:00) and evening (17:00–21:00) peaks, and allows UNE to cut supply for up to 72 hours as a penalty for breaches.
Payment for renewable exports is a flat price at any hour, so there is no price signal for when households export or store energy.
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | No smart-meter programme identified |
| Reading interval | Monthly or four-monthly readings (1975 regulations) |
| Meter installer | Provincial Empresa Eléctrica |
| Meter change | On customer request or inspector’s order (H-65 form) |
| Billing after meter change | First bill based on average consumption |
| Export metering | Installed by UNE (Resolution 123/2019) |
| Smart-meter share | Not published |
Residential consumption is measured by meters installed by the provincial companies. The 1975 service regulations provide for monthly or four-monthly readings and require private customers to pay within ten working days of notification; reconnection after non-payment requires settling the debt.
No information on smart or remotely read meters was found on UNE’s website.
Renewable electricity.
Electricity generation mix (2023).
- Fossil fuels: 95.3%
- Bioenergy: 2.3%
- Solar: 1.2%
- Hydro: 0.7%
- Wind: 0.4%
- Renewable electricity share
- 10% (2025)Source 15UNE states that the renewable share of electricity generation rose from 3.6% to 10% in 2025. IRENA records 727 GWh of renewable generation out of 15,496 GWh in 2023 (4.7%). Cuba has no electricity imports.
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- 12 MW (2024)Source 5IRENA net addition for 2024. UNE reports a much larger build-out of solar parks in 2025–26.
- Total installed (all sources)
- 6.7 GW (2024)Source 5Renewables about 12% of capacity; much thermal capacity is unavailable.
- Solar PV
- 1,300 MW (2026)Source 15UNE: “more than 1,300 MW” installed.
- Solar parks installed in the recent programme
- 52 parks (2026)Source 15Contributing more than 1,000 MW.
- Solar added in 2024
- 12 MW (2024)Source 5
Targets.
- At least 24% of electricity generation from renewable sources by 2030 (Decree-Law 345, preamble).
- New high-consuming investments to cover 50% of daytime-peak consumption with renewables (Decree 110/2024).
Historically Cuba’s renewable electricity came mainly from sugar-cane bagasse burned in sugar mills. IRENA records 364 GWh of bioenergy, 190 GWh of solar, 113 GWh of hydro and 60 GWh of wind in 2023 — 4.7% of generation.
Solar has since grown rapidly. UNE reports 52 new photovoltaic parks with more than 1,000 MW, total solar capacity above 1,300 MW, and a renewable share that rose from 3.6% to 10% of generation in 2025; during the day the parks can provide more than half of the country’s electricity. Typical parks are 21.8 MW: Las Tunas province has eight parks totalling 64 MW, and Granma’s Las Tapias park (21.8 MW) is the province’s fourth. On 20 September 2026 the solar parks produced 3,141 MWh with a maximum output of 490 MW.
Wind is small. A 33 MW wind farm, Herradura 1 (22 turbines), is being developed in Las Tunas with Chinese technical assistance.
Decree-Law 345 sets the priorities for renewable development: bioelectric plants in the sugar industry, wind farms, hydropower, photovoltaic panels and solar water heaters, and energy from agricultural, industrial and urban waste.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
Decree-Law 345 lists the use of energy-storage technologies among the requirements for maximising renewables in the national system, but no national storage figures were found. Lithium-ion batteries and other accumulators are exempt from customs duty when imported by individuals or organisations under Resolution 180/2026, valid until 31 December 2027.
Storage projects.
- Punta Brava solar park (Amancio, Las Tunas): 5 MW solar park with energy storage capability, a Chinese donation; storage capacity not published.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Unión Eléctrica (UNE) | Sole supplier through 16 provincial Empresas Eléctricas | No | No | No | Yes |
UNE is the only electricity supplier. Households buy at the national residential tariff from their provincial company, and those with renewable systems can sell electricity delivered to the grid at 90 CUP/kWh.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Ministerio de Energía y Minas (MINEM) | Government | Ministry responsible for energy | Sets energy policy and the regulations for renewable development under Decree-Law 345. |
| Ministerio de Finanzas y Precios | Regulator | Sets prices and tax incentives | Sets the price paid for renewable electricity and the customs and tax exemptions for renewable equipment. |
| Unión Eléctrica (UNE) | Transmission | Vertically integrated state utility | Generates, transmits, distributes and sells electricity; publishes daily system status notes. |
| Empresas Eléctricas provinciales | Distribution | 16 provincial distribution and retail companies | Handle new connections, contracts, meters and grid connection of self-generators. |
| Oficina Nacional para el Control del Uso Racional de la Energía (ONURE) | Government | National energy-efficiency office attached to MINEM | Certifies appliance efficiency, issues energy licences and the Dictamen Energético required for tax relief on renewable systems. |
| Gaceta Oficial de la República de Cuba | Government | Official journal | Publishes tariffs, purchase prices and renewable-energy regulations. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Electricity service and supply voltages | Law 1287 (1975) and the Electricity Service Regulations | Council of Ministers / Ministry of the Electricity Industry | 60 Hz; 115 V and 115/230 V residential supply; internal installations must follow the Electrical Safety Code; generator interconnection needs written authorisation. |
| Renewable generation and grid delivery | Decree-Law 345 (2017); MINEM Resolution 123/2019 | Council of State; MINEM | UNE must buy compliant renewable energy, installs export meters and certifies delivery points; no power limit for residential PV. |
| Energy management | NC ISO 50001 | Oficina Nacional de Normalización | Mandatory certification for high-consuming organisations (Decree 110/2024). |
| Appliance and equipment efficiency | Energy Efficiency Label; ONURE certification | ONURE | Equipment for final energy use and renewable equipment sold in Cuba must carry the Energy Efficiency Label (Decree 110/2024). |
| Grid connection (inverter / anti-islanding technical rules) | Not identified | — | Resolution 123/2019 refers to “Cuban technical standards” for the delivery point, but the specific standards were not found. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Residential service contract | Yes | National | Applied for at the provincial company’s commercial office with identity card, address details, load list and proof of legal possession of the dwelling. |
| Utility approval to connect a generator | Yes | National | Written authorisation needed to connect any generator; UNE indicates and certifies the delivery point and installs the export meter. |
| ONURE Dictamen Energético | Limited | National | Needed to claim the income-tax exemptions or allowances of Resolution 180/2026. |
| Energy licence for investment projects | Limited | National | Required for organisations’ new investments, remodelling and expansions (Decree 110/2024). |
| Planning permission for rooftop solar | Unknown | Local | No specific rule identified. |
For a household, the key relationship is with the provincial Empresa Eléctrica, which connects the supply, authorises any generator connection, certifies the export point and installs the meter. Tax relief requires an energy assessment from ONURE.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Purchase price for renewable electricity | Active | Export payment | 90.00 CUP/kWh for renewable electricity delivered to the grid at any hour by residential and non-residential producers, with the income exempt from the services tax (Resolutions 114/2026 and 179/2026). | May 2026 – |
| Customs duty exemption for solar systems and renewable equipment | Active | Customs exemption | Individuals and organisations pay no customs duty on PV systems and key parts (including modules, inverters and lithium-ion batteries), solar water heaters, solar pumps, small wind turbines, biodigesters and renewable-powered EV chargers. For individuals these goods do not count towards non-commercial import limits if declared separately (Resolution 180/2026). | Aug 2026 – 31 Dec 2027 |
| Income-tax exemption for self-generation | Active | Tax exemption | Individuals and organisations carrying out economic activities that install renewables for own use or export are exempt from profit or personal income tax up to the value of the investment during its payback period, for up to eight years, subject to an ONURE Dictamen Energético (Resolution 180/2026). | — |
| Tax allowance for social renewable investments | Active | Tax allowance | The full cost of renewable systems donated to public service centres, multi-family buildings, homes of electricity-dependent people, street lighting or water supply can be deducted from tax due (Resolution 180/2026). | — |
| Sales-tax exemption on renewable equipment | Active | Tax exemption | Wholesale and retail sales of renewable technologies are exempt from sales tax for one year, and such equipment must be sold at non-revenue prices with a margin of no more than 25% on costs (Resolution 180/2026). | Aug 2026 – Aug 2027 |
| Earlier purchase prices and exemptions (Resolutions 238/2023, 169/2025, 41/2026) | Closed | Export payment / customs exemption | Residential purchase price of 6.00 CUP/kWh and earlier customs exemptions, superseded in 2026. | — |
Data and connectivity.
- Fixed broadband
- 70.5 % of population using the internet (2024)Source 4Share of individuals using the internet (ITU via World Bank), not fixed-broadband coverage.
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
About 70% of the population used the internet in 2024, according to the World Bank. No information was identified on communication technologies for electricity metering.
Grid conditions.
- National peak demand
- 3.15 GW (2026)Source 14Maximum demand forecast by UNE for 21 September 2026, against 1,215 MW of available peak capacity; not an annual peak.
- Annual electricity demand
- 15.5 TWh (2023)Source 5Total generation (15,496 GWh); Cuba has no imports, so supply equals generation. Unserved demand is not included.
- Generation capacity
- 6.7 GW (2024)Source 5Installed capacity; available capacity is far lower because of breakdowns, maintenance and fuel shortages.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
The system’s main constraint is a lack of available generation rather than network capacity. On a typical day in May 2026, UNE said, about 1,100 MW could not be generated for lack of fuel, and it reported four months without fuel deliveries from December 2025. In March 2026 there were three nationwide outages.
Solar output now covers much of daytime demand, but the evening peak, when solar is unavailable, is when the deficit is greatest — typically 1,800–1,900 MW according to UNE.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| 90 CUP/kWh purchase price extended to all renewable sources | Current | 7 August 2026 | Resolution 179/2026 amends Resolution 114/2026 so the 90 CUP/kWh price applies to electricity from any renewable source. |
| Consolidated renewable tax and customs incentives | Current | 7 August 2026 | Resolution 180/2026 replaces Resolution 41/2026 with customs, income-tax and sales-tax exemptions for renewable equipment and self-generation. |
| New purchase price for renewable exports | Current | 21 May 2026 | Resolution 114/2026 raises the price for residential and non-residential producers to 90 CUP/kWh at any hour, up from 6 and 3 CUP/kWh. |
| Decree 110/2024 on energy use and renewables | Current | 26 November 2024 | Rules for high-consuming organisations, including a 50% renewable requirement at the daytime peak for new investments and diesel-cost peak pricing. |
| Residential tariff revision | Current | 1 March 2024 | 18-band residential tariff from 0.33 to 25.00 CUP/kWh. |
| Sales-tax exemption on renewable equipment ends | Upcoming | August 2027 | The one-year sales-tax exemption in Resolution 180/2026 expires. |
| Customs exemption lists expire | Upcoming | 31 December 2027 | The annexed lists of exempt goods in Resolution 180/2026 run until this date. |
| 24% renewable generation target | Upcoming | 2030 | Target set in Decree-Law 345. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Low | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | — | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | Low | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Low | Residential export is permitted with no size limit and paid 90 CUP/kWh since 2026, but no figures on residential installations are published and fuel-driven outages dominate household energy use. |
| Distributed energy market | Medium | UNE reports more than 1,000 MW of distributed (mainly fossil-fuelled) generation recovered by late 2025; Las Tunas alone reports 4,141 PV modules in homes, institutions and isolated dwellings. |
| Grid flexibility market | Low | Vertically integrated state utility with no electricity or flexibility market. |
| Energy storage adoption | Low | No national storage figures; only a 5 MW solar park with storage capability identified. Batteries are customs-exempt until 2027. |
| Renewable growth environment | High | UNE: 52 solar parks with more than 1,000 MW installed and renewable share up from 3.6% to 10% of generation in 2025. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 28 sources
- Population, total — Cuba. World Bank, 2025. accessed 10 October 2026.
- Urban population (% of total) — Cuba. World Bank, 2025. accessed 10 October 2026.
- Access to electricity (% of population) — Cuba. World Bank, 2024. accessed 10 October 2026.
- Individuals using the Internet (% of population) — Cuba. World Bank, 2024. accessed 10 October 2026.
- Energy Profile: Cuba. IRENA, 2025. accessed 10 October 2026.
- Gaceta Oficial No. 10 Extraordinaria 2024 — Acuerdo 9810/2024 (tarifa eléctrica sector residencial). Gaceta Oficial de la República de Cuba, 2024. accessed 10 October 2026.
- Tasas de cambio. Banco Central de Cuba, 2026. accessed 10 October 2026.
- Misión y visión. Unión Eléctrica. accessed 10 October 2026.
- Contacto — empresas eléctricas, empresas nacionales y centrales termoeléctricas. Unión Eléctrica. accessed 10 October 2026.
- Solicitud de servicio. Unión Eléctrica. accessed 10 October 2026.
- Cambio de metro contador de energía eléctrica. Unión Eléctrica. accessed 10 October 2026.
- Cambios de nombre. Unión Eléctrica. accessed 10 October 2026.
- Marco regulatorio. Unión Eléctrica. accessed 10 October 2026.
- Nota informativa (21 September 2026). Unión Eléctrica, 2026. accessed 10 October 2026.
- El impacto del bloqueo energético en la generación de electricidad en Cuba. Unión Eléctrica, 2026. accessed 10 October 2026.
- Resolución 114/2026: nueva tarifa para venta de energía renovable al SEN. Unión Eléctrica, 2026. accessed 10 October 2026.
- Las Tunas no se queda atrás: transición energética. Unión Eléctrica, 2026. accessed 10 October 2026.
- Granma solar: avances constructivos del parque solar Las Tapias. Unión Eléctrica, 2025. accessed 10 October 2026.
- Actualización restablecimiento del SEN. Unión Eléctrica, 2025. accessed 10 October 2026.
- Delitos contra el Sistema Electroenergético Nacional en Cuba: una amenaza a la soberanía energética. Unión Eléctrica, 2026. accessed 10 October 2026.
- Ley 1287 de 2 de enero de 1975 del Servicio Eléctrico y Reglamento. Unión Eléctrica, 1975. accessed 10 October 2026.
- Gaceta Oficial No. 95 Ordinaria 2019 — Decreto-Ley 345; MINEM Resoluciones 123 y 124; BCC Instrucción 6/2019. Gaceta Oficial de la República de Cuba, 2019. accessed 10 October 2026.
- Gaceta Oficial No. 71 Extraordinaria 2023 — Resolución 238/2023 (MFP). Gaceta Oficial de la República de Cuba, 2023. accessed 10 October 2026.
- Resolución 114 de 2026 de Ministerio de Finanzas y Precios. Gaceta Oficial de la República de Cuba, 2026. accessed 10 October 2026.
- Gaceta Oficial No. 66 Ordinaria 2026 — Resoluciones 179/2026 y 180/2026 (MFP). Gaceta Oficial de la República de Cuba, 2026. accessed 10 October 2026.
- Resolución 169 de 2025 de Ministerio de Finanzas y Precios. Gaceta Oficial de la República de Cuba, 2025. accessed 10 October 2026.
- Resolución 41 de 2026 de Ministerio de Finanzas y Precios. Gaceta Oficial de la República de Cuba, 2026. accessed 10 October 2026.
- Gaceta Oficial No. 115 Ordinaria 2024 — Decreto 110/2024 (control y uso eficiente de los portadores energéticos y las fuentes renovables). Gaceta Oficial de la República de Cuba, 2024. accessed 10 October 2026.
Questions about energy in Cuba.
The residential tariff in force since 1 March 2024 has 18 monthly bands, from 0.33 CUP/kWh for the first 100 kWh to 7.00 CUP/kWh at 451–500 kWh and 25.00 CUP/kWh above 5,000 kWh. Prices are set nationally by the Council of Ministers.
The state-owned Unión Eléctrica (UNE) generates, transmits, distributes and sells all public-grid electricity through 16 provincial electricity companies. There is no retail choice.
Yes. UNE must buy renewable electricity from independent producers, including households, that meets technical standards. Since May 2026 the price is 90 CUP/kWh at any hour, and residential PV systems have no maximum power limit.
There is no published standard supply-point code. A household supply is a service contract between a named holder and the provincial Empresa Eléctrica for a specific address, recorded on the utility’s internal forms.
IRENA recorded 4.7% renewable generation in 2023, mostly from bagasse. UNE says the share rose from 3.6% to 10% in 2025 as more than 1,000 MW of new solar parks came online. The legal target is at least 24% by 2030.
Available generation regularly falls short of demand because of ageing thermal plants, breakdowns and fuel shortages. In September 2026 UNE forecast deficits of nearly 2,000 MW at peak.
No customs duty applies to PV systems, their key parts and lithium-ion batteries imported by individuals or organisations under Resolution 180/2026, with the exemption lists valid until 31 December 2027.