Countries

Energy in Eswatini, explained.

How electricity works in Eswatini: prices, the grid and local rules. Olmack status: Not yet available. Information last checked 1 October 2026.

Olmack in Eswatini: Not yet available.Olmack is not offered in Eswatini yet. The market information on this page is provided for reference. Information last checked 1 October 2026.
Energy-market overview

How electricity works in Eswatini.

Eswatini electricity 2026: EEC prepaid STS tariff, ESERA regulation, new embedded-generation feed-in credits, import dependence, licensing, standards and solar IPPs.

This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Eswatini lilangeni (plural emalangeni) (SZL) where they relate to prices.

Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.

At a glance

Eswatini energy at a glance.

Key figures for households in Eswatini. Each one links to its source on the full overview below.

  • Electricity price.

    2.862 SZL per kWh for households, including taxes. Figures for From 1 April 2026.

  • Household use.

    1,617 kWh a year for a typical household. Figures for 2024/25.

  • Renewable share.

    35.8% of electricity from renewable sources. Figures for 2024.

  • Selling back to the grid.

    Can homes export electricity? Yes. Details are in the export section below.

Before you start

Four things to check in Eswatini.

Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.

  1. Check the local rules.

    Read the connection, export and permission rules for Eswatini below, and ask your local grid operator if anything is unclear.

  2. Choose a qualified installer.

    Look for an installer listed on an official register, with the certifications Eswatini requires for the work.

  3. Look at current schemes.

    Check which support schemes are open now. Closed or scheduled schemes are labelled as such.

  4. Talk to your energy supplier.

    Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.

Local detail

Schemes, rules and certifications in Eswatini.

The full detail sits in the sections below. Each item shows its status and links to the official source.

  • Support schemes.

    Grants, tax relief and export payments in Eswatini, each labelled Active, Scheduled or Closed.

  • Connection and export.

    How equipment is connected to the grid in Eswatini, and the steps to export electricity.

  • Standards and certifications.

    The technical standards and installer certifications that apply to energy equipment in Eswatini.

Full overview

The energy market in Eswatini, in detail.

Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.

Profile last updated 1 October 2026.

On this page22 sections

Eswatini has a small, vertically integrated power sector. The state-owned Eswatini Electricity Company (EEC) generates, imports, transmits, distributes and sells electricity to almost every grid customer in the country – 298,918 customers in the 2024/25 financial year. The Eswatini Energy Regulatory Authority (ESERA), created by the Energy Regulatory Act 2007, licenses every activity in the electricity supply industry and approves EEC’s tariffs. Policy sits with the Ministry of Natural Resources and Energy.

Most electricity is imported. EEC’s own hydro stations and a 10 MW solar plant, plus sugar-mill biomass cogeneration, cover roughly a third of supply; the rest comes mainly from Eskom/NTCSA in South Africa, with smaller volumes from Electricidade de Moçambique and the Southern African Power Pool. That is why the generation that does happen inside the country is almost entirely renewable (about 97% in 2024, by Ember’s figures) while the electricity people actually use is not.

Households pay a single regulated energy charge with no fixed fee, almost always through prepaid STS meters. From 1 April 2026 the domestic rate rose 15.09% to E2.8624/kWh after a government subsidy trimmed ESERA’s approved increase. On 1 August 2026 EEC started crediting approved rooftop solar systems for surplus electricity under a net-billing feed-in tariff of 51.23 c/kWh, and on 2 September 2026 ESERA opened an online application portal for embedded generation up to 2 MW.

Energy snapshot.

Headline figures for electricity in Eswatini. Each shows its data year and links to its source.

  • Population1,256,174 peopleSource 352025
  • HouseholdsNot identified from a reliable public source.
  • Average household sizeNot identified from a reliable public source.
  • Electricity use per household1,617 kWh/yrSource 162024/25
  • Household price (SZL)2.862 SZL/kWhSource 1From 1 April 2026
  • Household price (EUR)0.154 EUR/kWhSource 34From 1 April 2026
  • Renewable electricity share35.8%Source 332024
  • Solar capacity0.03 GWSource 332024
  • Wind capacity0 GWSource 332024
  • Energy storage capacityNot identified from a reliable public source.
  • Smart-meter shareNot identified from a reliable public source.
Market structure
Vertically integrated
Homes can export to the grid
Yes
Home equipment in grid services
No
Regulator
Eswatini Energy Regulatory Authority (ESERA)
System operator
Eswatini Electricity Company (EEC)
Distribution networks
EEC distributes nationally; two small licensees (RES Corp and UFPC) serve their own estates
Currency
Eswatini lilangeni (plural emalangeni) (SZL)
Voltage and frequency
230 V single-phase / 400 V three-phase, 50 Hz

Electricity prices in Eswatini.

Household price (SZL)
2.862 SZL/kWh (From 1 April 2026)Source 1EEC S1 Domestic energy charge, 2026/27. There is no monthly fixed charge on S1. Includes the 2.5% Rural Electrification Access Fund levy; VAT is applied only to non-domestic customers.
Household price (EUR)
0.154 EUR/kWh (From 1 April 2026)Source 34Converted from E2.8624/kWh using the ECB reference rate of 1 EUR = 18.6123 ZAR on 30 September 2026; the lilangeni is pegged at par to the South African rand within the Common Monetary Area (2.8624 ÷ 18.6123 = 0.1538).
Typical annual electricity bill
4,628 SZL/yr (2026/27 tariff)Source 1Derived: average domestic use of 1,617 kWh a year (2024/25) × the 2026/27 S1 rate of E2.8624/kWh. S1 has no fixed charge and households pay no VAT, so the energy charge is the whole bill.

Household price trend (SZL per kWh).Source 2

2.3272.5952.8622024/252025/262026/27
Eswatini household electricity price, SZL per kWh
2024/252.3266 SZL/kWh
2025/262.4871 SZL/kWh
2026/272.8624 SZL/kWh

How prices are set

ESERA sets EEC’s allowed revenue under its 2011 Tariff Methodology and holds public hearings in all four regions before each decision. Import costs from Eskom/NTCSA, EDM and Ubombo Sugar are treated as pass-through costs. For 2026/27 EEC asked for a 20.67% average rise because renegotiated power purchase agreements raised import costs (NTCSA prices rose 8.4% from September 2025, and the contracted capacity went from 160 MW to 190 MW) and because of an E262.8 million under-recovery from 2024/25.

ESERA approved a 13.61% average increase, with 17.23% for domestic customers, 6% for lifeline customers and 4.86% on fixed and access charges. The government then put up E200 million to cushion customers, which brought the average increase down to 11.74% and the domestic increase to 15.09%. The domestic rate moved from E2.4871/kWh in 2025/26 to E2.8624/kWh.

Taxes, levies and subsidies

Every tariff includes a 2.5% levy on the energy charge that funds the Rural Electrification Access Fund. VAT at the standard 15% applies only to non-domestic customers. ESERA notes that all domestic tariffs are cross-subsidised by business customers, and its cost-of-supply work is aimed at narrowing that subsidy over time; the lifeline tariff is meant to target support more precisely.

Trends

Domestic prices rose from E2.3266/kWh in 2024/25 to E2.8624/kWh in 2026/27 – about 23% in two years – driven mainly by the cost of imported power. EEC reported a net loss of E80.4 million in 2024/25 and says tariff awards have repeatedly fallen short of import cost increases. Prices are uniform across the country.

Tariff types.

Tariff types.
TariffAvailableDetail
PrepaymentYesStandard for households. Units are bought in advance by meter number at EEC offices, retailers, mobile money, SMS (8888) or the *8888# self-service code, and loaded on the meter as a 20-digit token.
RegulatedYesS1 Domestic: a single energy charge of E2.8624/kWh from 1 April 2026, with no facility (fixed) charge. S2 General Purpose: E208.16 a month plus E3.3920/kWh.
OtherLimitedS10 Lifeline: a stepped social tariff for low-income households – E1.5685/kWh for the first 75 kWh a month, E2.8624 for 76–100 kWh and E6.2973 above 100 kWh (2026/27). Customers apply after three months on supply, with a form stamped by a royal kraal (umphakatsi) or Tinkhundla centre.
Time-of-useLimitedOnly for large commercial, industrial and small irrigation customers (T1–T4), with peak/standard/off-peak energy rates that differ between low- and high-demand seasons plus demand and access charges. Not offered to households.
FixedNoPrices are set annually by ESERA for every customer; there is no competing supplier offering fixed-price contracts.
DynamicNoNo wholesale-indexed retail tariffs exist.

Household prices compared with neighbouring countries (EUR per kWh).

Household prices including taxes, converted to euros as stated on each country page.

Household electricity use.

Electricity use per household
1,617 kWh/yr (2024/25)Source 16Derived: EEC domestic sales of 448,366,016 kWh in 2024/25 divided by 277,312 domestic customers. This is use per domestic account (including lifeline customers), not per household nationally.
Average daily use per household
4.4 kWh/day (2024/25)Source 16Derived: 1,617 kWh a year per domestic account ÷ 365.
Typical household peak demand
Not identified from a reliable public source.
Electricity use per person
1,330 kWh/person/yr (2024)Source 33All-sector electricity demand per person (1.33 MWh).
Heat pumps
Not identified from a reliable public source.
Air conditioning
Not identified from a reliable public source.
Electric vehicles
Not identified from a reliable public source.
Electric cooking
Not identified from a reliable public source.

Household use is modest. EEC’s domestic customers bought 448 GWh in 2024/25 – about 38% of the 1,181 GWh EEC sold – and domestic sales grew by less than 0.3% even though the number of domestic customers rose 5%. Most new connections are rural homes added through electrification schemes, which use little electricity, so average consumption per account is drifting down.

The national system peaks in the evening (244.6 MW at 19:00 in March 2025) and in the southern-hemisphere summer and autumn rather than winter: in 2024/25 demand was lowest in August and highest in March. EEC notes that the rapid drop in rooftop solar output at sunset adds to the evening ramp.

Access has expanded quickly. EEC reports that 92.84% of emaSwati had access to electricity in 2024/25, and the World Bank estimates 89.3% of the population in 2024 (92.1% urban, 88.3% rural). The World Bank–financed ASCENT programme aims to reach universal access by 2030.

Housing and households.

Dwellings
Not identified from a reliable public source.
Owner-occupied
Not identified from a reliable public source.
Private rented
Not identified from a reliable public source.
Social or public housing
Not identified from a reliable public source.
Houses
Not identified from a reliable public source.
Apartments and flats
Not identified from a reliable public source.
Urban population
26.7 % of population (2025)Source 36

Eswatini is predominantly rural: about three-quarters of people live outside towns, many on Swazi Nation Land in homesteads of several buildings rather than in a single house. The main urban areas are Mbabane, Manzini and the Matsapha industrial corridor between them.

This shapes how electricity is administered. A new connection needs proof of identity and of the right to occupy the land – an ownership form, a lease, or the landlord’s identity document – and the meter account is tied to that installation. Large estates such as the sugar companies run their own townships and private distribution networks.

How the grid works in Eswatini.

  1. TransmissionEswatini Electricity Company (EEC), EEC National Control Centre
  2. DistributionEEC distributes nationally; two small licensees (RES Corp and UFPC) serve their own estates
  3. MeteringEEC, Embedded Generation Application Platform
  4. Supply1 or more retail suppliers

Physical flow

Power enters the grid from EEC’s four hydro stations (Maguga 20 MW, Ezulwini 20 MW, Edwaleni 15 MW, Maguduza 5.6 MW), the 10 MW Lavumisa solar plant, sugar-mill cogeneration at Ubombo Sugar and the Royal Eswatini Sugar Corporation, and imports. The 400 kV line from Camden in South Africa through Edwaleni II to Maputo is the backbone for imports; 132 kV and 66 kV lines carry power to 11 kV distribution substations.

In 2024/25 EEC’s own stations produced 281 GWh, Ubombo Sugar supplied 65.9 GWh and EEC imported between 979 GWh and 1,084 GWh (its annual report gives both figures), against 1,364 GWh sent out. EEC says it generates at least 30% of its needs and imports about 70%, with Eskom/NTCSA the largest supplier.

Commercial flow

There is no wholesale market inside Eswatini. EEC buys under long-term bilateral agreements – a power supply agreement with NTCSA/Eskom whose 25-year term ended in August 2025 and was renegotiated, a contract with EDM, and a purchase agreement with Ubombo Sugar – and tops up on SAPP markets when prices and volumes allow. New local generation is procured by ESERA through competitive tenders, after which the winning IPP is licensed and signs a power purchase agreement with EEC.

Private generators may now use EEC’s network to supply their own sites elsewhere under the 2022 Wheeling Framework; ESERA approved the wheeling and grid-impact assessment charges with effect from 1 July 2026.

Who does what.

Who does what.
RoleOrganisationWhat it does
MinistryMinistry of Natural Resources and EnergySets energy policy, including the Independent Power Producer Policy and the Energy Master Plan 2034, and can exempt off-grid and mini-grid schemes from licensing.
RegulatorEswatini Energy Regulatory Authority (ESERA)Licenses generation, transmission, system operation, distribution, supply, import and export; approves tariffs and charges; issues the Grid Code and embedded-generation, storage and wheeling rules; runs competitive procurement of IPPs; accredits solar installers.
TSOEswatini Electricity Company (EEC)The only licensed transmission company. Operates 400 kV, 132 kV and 66 kV lines and about 58 substations, including the 400 kV Camden–Edwaleni II–Maputo interconnection.
System operatorEEC National Control CentreBalances the national system in real time using EEC hydro, imports under bilateral contracts and short-term purchases on the Southern African Power Pool markets.
DSOEEC DistributionDesigns, quotes for and builds connections and runs the low- and medium-voltage network across the country; approves and connects embedded generators.
DSORES Corp and UFPC (private distribution licensees)Two small licensees distribute to their own estates and townships: 2,695 and 637 customers respectively in 2024/25.
SupplierEECThe single retail supplier for the national grid, selling prepaid and credit-metered electricity at ESERA-approved tariffs.
MeteringEECOwns and installs all customer meters (including bi-directional meters for embedded generators) and runs the prepaid vending system.
Data hub / registryEmbedded Generation Application PlatformOnline register launched in September 2026 for embedded-generation applications up to 2 MW, supply licensing and installer registration, shared by ESERA and EEC.
ExchangeSouthern African Power Pool (SAPP)Regional power pool in which EEC trades as a national utility; EEC bought 49.41 GWh on SAPP markets in 2024/25.

Compared with the UK system.

Compared with the UK system.
UK conceptEswatini equivalentHow it works
DNOEEC Distribution (plus two estate licensees)There are no regional network companies. EEC owns and runs the distribution network nationwide and is also the retailer, so the “network operator” and “supplier” are the same organisation. RES Corp and UFPC hold distribution licences only for their own estates.
National Grid/NESOEEC Transmission and National Control CentreEEC is the sole transmission licensee and integrated system operator. Unlike NESO it also owns most local generation and buys almost all imports, so planning, dispatch and procurement sit in one company.
MPANPrepaid meter number (11 digits)A domestic supply point is identified by the number of its STS prepaid meter, used to buy every token. There is no separate national supply-point number independent of the meter; replacing the meter means a new number that EEC must activate.
MPRNNo equivalentThere is no piped gas network for homes and so no gas supply-point register; household gas is LPG in cylinders, regulated by ESERA as a petroleum product.
Meter operatorEECEEC owns every meter and installs it through its own staff or contractors. Embedded-generation meters also remain EEC property and are paid for by the customer through the connection charge.
SupplierEEC (single supplier)Households cannot switch supplier. ESERA approves one set of national tariffs; the only alternative is self-generation.
Smart-meter infrastructurePrepaid STS meters; smart conversion plannedThere is no DCC-style data network. Households use offline keypad meters with a customer interface unit. EEC’s 2026 smart-meter specification calls for split prepaid/postpaid meters using G3-PLC power-line communication and DLMS/COSEM, with remote disconnection and load limiting.

How a supply point is identified.

04000012345 (fictional)

Fictional example in the real format.

How a supply point is identified.
QuestionAnswer
What is it called?Prepaid meter number (Meter No.)
Who issues it?EEC (each STS meter carries a unique number; EEC activates it against the customer’s account in its vending system)
FormatNumeric meter number printed on the meter/customer interface unit and the meter card, entered when buying units; tokens returned are 20 digits
Length11 digits
Stays with the property when you switch supplier?Yes
Where to find itOn the customer interface unit (CIU) and the meter card left at the property, and on every prepaid receipt or token SMS. Credit-metered customers also have an EEC account number on their bill.
Electronic accessTokens can be bought and re-sent by meter number through *8888# self-service, SMS to 8888 with a voucher PIN, mobile money and authorised vendors. Remote loading of units is not yet possible; EEC says it is working on automated meters.
Third-party accessAnyone who knows the meter number can buy units for it through vendors. There is no regulated consumption-data access regime for third parties such as installers.
Who keeps the registerEEC’s customer and prepaid vending system (upgraded in 2024/25); embedded generators are additionally recorded on the ESERA/EEC embedded-generation platform
Register scopeNational

How a home is identified

For almost every household the practical identifier of a supply point is the number of its prepaid meter. EEC’s own example on its vending page is an 11-digit number of the form 01000000032. Customers type it into an SMS with a voucher PIN, quote it at a vendor, or enter it in the *8888# menu, and receive a 20-digit token to key into the customer interface unit – the in-home keypad of a split meter whose measuring part sits outside.

The number belongs to the meter, not to the person. When a meter is replaced after a fault the customer receives a new number, which must be activated by EEC staff before any units can be bought; units bought for a wrong number can only be moved by a technician visit, currently charged at E285. Units left on a removed meter are refunded through a free-issue form.

Moving home

The meter and its card stay with the property. EEC asks customers who move out to complete a disconnection form, settle any debt and leave the prepaid card in the house so the next occupant can apply for reconnection. A new occupant applies with an identity document, proof of the right to occupy (ownership form or lease) and the previous tenant’s details; any old post-paid debt linked to the account must be cleared before units can be bought.

Who keeps the register

There is no independent national data hub. EEC holds the customer, meter and vending records for the whole national grid, and ESERA monitors EEC against the SZNS 026 quality-of-service standard, which covers prepayment metering and reconnections. In 2024/25 EEC also had to carry out the STS token-identifier (TID) rollover across its prepaid meter fleet – the industry-wide change that keeps keypad meters accepting tokens.

Solar and other embedded generators get a second record: since September 2026 every system, including zero-export systems, is registered on the online Embedded Generation Application Platform, and approved exporters have their meter replaced with an EEC-owned bi-directional meter.

Sending electricity to the grid.

Sending electricity to the grid.
QuestionAnswer
Can homes export electricity?Yes
Net meteringNo
Net billingYes
How exported electricity is paidNet billing: exports are credited at an ESERA-approved feed-in tariff (51.23 c/kWh flat for residential and small commercial customers, excl. VAT, 1 Aug 2026–31 Mar 2027) against the customer’s energy purchases; no cash payments
How big can a household system be?Under ESERA’s Embedded Generation Bylaws the generation capacity may not exceed the main circuit-breaker rating or 80% of the supplying LV transformer’s kVA rating, and inverter nameplate power is limited to 100% of the customer’s installed capacity. Export capacity follows SZNS NRS 097; on a shared LV feeder that is 25% of the customer’s capacity (for example 3.5 kVA on a 60 A single-phase supply) and above 4.6 kVA of export the supply must be three-phase.
Is there a national cap?The aggregate embedded-generation capacity is set by the system operator and approved by ESERA. A 2024 developer guide reported a cap of 37 MW (about 15% of maximum demand); about 24 MW had been registered by mid-2026. Connections in an area are first come, first served.
What happens to surplus credits?Netting applies only to the energy part of the bill, monthly. Excess credit carries forward but cannot be paid out in cash and is forfeited at the end of the financial year (31 March), or if the system is sold, the property changes hands or the agreement ends. Nothing is paid for deemed generation during outages.
Do zero-export and battery systems need approval?Yes. Every system electrically connected to the EEC network must be registered and approved, including zero-export and battery back-up systems. Only fully off-grid systems, solar water heaters, UPS units and stand-alone generators are exempt.
What if a system is not registered?EEC can disconnect it under section 52(1) of the Electricity Act 2007, and ESERA has approved a non-compliance penalty of E15,489.09 for unregistered, modified or unauthorised systems, including unauthorised exports.
Can a battery charge from the grid?Yes, but the AC charging current is limited to 25% of the customer’s installed capacity unless ESERA approves another criterion.
Are time-of-use export rates available?Yes, for customers on TOU tariffs: from 31.49 c/kWh (low-season off-peak) to 166.02 c/kWh (high-season peak), excluding VAT.

Connecting a home system.

  1. Check EEC and ESERA requirements and appoint an ESERA-accredited solar installer.
  2. Apply on the online Embedded Generation Application Platform (www.eg.energy.org.sz), uploading proof of ownership, system specifications and inverter compliance certificates.
  3. EEC assesses compliance, metering, safety and network capacity and responds within 45 working days; systems above 350 kVA need a grid impact study at the customer’s cost.
  4. If accepted, EEC issues a Conditional Approval to Install – nothing may be installed or connected before this.
  5. Install as approved, notify EEC before testing, commission the system and upload the test records and certificates.
  6. Pay the connection charge (E10,326.06 incl. VAT for systems of 1–350 kVA) and sign the connection and supply agreements.
  7. EEC inspects, fits a bi-directional meter and issues final approval to generate; export credits start from then.

Export is new in Eswatini. Until mid-2026 EEC required all grid-tied systems to be registered but did not allow them to feed power back, advising customers to size for self-consumption. ESERA developed the Small-Scale Embedded Generation Framework in 2021, published Embedded Generation Bylaws in 2024 and approved EEC’s feed-in tariffs, connection charges and penalty in October 2025, with national roll-out from 1 August 2026.

The feed-in tariff is calculated by the avoided-cost method at 50% of EEC’s avoided bulk supply cost, a deliberately conservative level chosen to limit revenue loss for EEC. At 51.23 c/kWh the flat export rate is about 18% of the E2.8624/kWh domestic retail price, so the value of rooftop solar for households lies mainly in self-consumption; the credit arrangements are valid until 31 March 2027, when the rates are due to be reviewed.

Embedded generators may not supply electricity to third parties on other premises; selling power to others needs a supply licence or the separate wheeling route.

Licensing and approvals.

Requirements depend on the activity. The table sets out what each activity needs and who grants it.

Licensing and approvals.
ActivityLicence or registrationAuthorityNotes
Generate electricity (rooftop / own use)No licence below 100 kW installed capacity; 100 kW or more requires an exemption from ESERA (application fee E10,000). EEC connection approval is always required.ESERA (exemption); EEC (connection)Embedded Generation Bylaws 2024 and ESERA FAQ. All grid-connected systems must be registered regardless of size.
Generate electricity for sale (IPP)Generation licence (up to 40 years), issued only after the project wins an ESERA competitive tender; then a PPA with EECESERAESERA decides licence applications within 120 days of advertisement. Unlicensed generation for supply is an offence (fine of not less than E50,000 and/or up to 24 months).
Store electricity (behind the meter)Below 100 kW: register with ESERA. 100 kW or more for own use: exemption. Any size used commercially: generation and supply licences.ESERAEnergy Storage Systems Guidelines 2024 – storage is not a separately licensable activity, so it is attached to other licences.
Store electricity (grid-scale)Transmission-connected storage for arbitrage needs a supply licence; for ancillary services it sits under EEC’s transmission licence or an IPP generation licence. Distribution-connected IPP storage needs a generation licence.ESERAApplications need an environmental and social management plan, a fire safety management plan and a siting plan.
Export surplus to the gridNo licence for embedded generators; requires EEC final approval, a bi-directional meter and connection and supply agreementsEEC under ESERA rulesCompensation is by net-billing credit only.
Sell / supply electricity to othersSupply licence (up to 25 years); exempt if selling under 1 GWh a year on terms no less favourable than the licensee’s tariffsESERAEmbedded generators may not supply third parties on other premises.
Distribute electricityDistribution licence (up to 25 years)ESERAHeld by EEC, RES Corp and UFPC.
Transmission and system operationTransmission and system-operator licences (up to 30 years)ESERAEEC is the only transmission licensee.
Import or export electricity across bordersImport or export licenceESERAEEC imports from South Africa and Mozambique and trades on SAPP.
Mini-grids and off-grid supplyOff-grid/mini-grid supply licence unless exempted by the Minister; micro-grids with storage up to 100 kW register with ESERA; mini-grids with 100–500 kW storage need generation, distribution and supply licences or a combined licenceESERA; Minister of Natural Resources and Energy (exemptions)Mini-grid and Micro-grid Guidelines; Africa Minigrids Program Eswatini.
Wheel power to own or contracted load elsewhereGenerator must be licensed or exempt and contract use of EEC’s network under the Wheeling Framework (2022), paying approved wheeling and grid-impact charges (from 1 July 2026)ESERA; EEC
Wholesale tradingNo domestic wholesale market or trading licence exists; EEC trades on SAPP. ESERA’s storage guidelines anticipate trading with a non-exclusive central buyer under the IPP Policy once market rules allow.ESERAEEC lists market rules among its strategic initiatives.
Balancing and grid servicesNo ancillary-services framework yet; the system operator is to develop standard ancillary-service contracts for ESERA approvalESERA; EEC as system operatorFrequency, voltage, black-start and congestion services are defined in the storage guidelines.
Aggregation / virtual power plantsNot recognised; no licence category or market access for aggregatorsESERA
Remote control of customer assetsNo specific licence. EEC may disconnect embedded generators that breach the Grid Code; demand-side control of household devices is not offered.EEC under ESERA rulesEEC’s planned smart meters include remote disconnection and load limiting.
Install solar PV systemsESERA installer accreditation: Level 2 (PV mounter, mechanical mounting only) or Level 3 (PV installer – design, install, commission and sign off single-phase systems); EEC applications require an accredited installerESERAAccreditation programme launched in 2025 with the Directorate of Industrial and Vocational Training (DIVT); the public register lists certificate holders.

The Electricity Act 2007 requires a licence from ESERA for generation, transmission, integrated system operation, distribution, supply, off-grid and mini-grid supply, and cross-border import or export. Three exemptions matter in practice: generation for own use approved by ESERA, selling less than 1 GWh a year on terms at least as good as the licensee’s, and mini-grids exempted by the Minister.

ESERA has turned those principles into thresholds through bylaws and guidelines. Household and most commercial rooftop systems fall below the 100 kW line and need only EEC’s connection approval; larger own-use plants apply for an exemption. Storage follows the same 100 kW threshold and is never licensed on its own – it rides on registration, exemption, or a generation, supply or transmission licence depending on what it is used for. New grid-scale capacity is only licensed after a competitive procurement run by ESERA’s Capacity Procurement Unit.

Flexibility and grid services.

Aggregation of home equipment: No

Flexibility and grid services.
Market or serviceAccess for home equipmentMinimum sizeVia an aggregatorDetail
SAPP day-ahead and intra-day marketsNo—NoSouthern African Power Pool. Only national utilities and licensed traders take part; EEC buys there to cut import costs (49.41 GWh in 2024/25, saving about E28.65 million).
Ancillary services (frequency, voltage, black start)Developing—NoEEC (system operator). There is no ancillary-services framework. ESERA’s 2024 storage guidelines value such services against SAPP alternatives and ask the system operator to draft standard contracts; ESERA will decide whether to offer them to storage owners.
Wheeling to own or contracted loadRestricted—NoEEC. Approved generators can transport power over EEC’s network under the Wheeling Framework, with charges in force from 1 July 2026. It is a bilateral supply route, not a flexibility market.
Demand response / time-of-useRestricted—NoEEC. Peak-shifting relies on seasonal time-of-use tariffs for large customers and EEC’s demand-side management campaigns. There is no paid demand-response programme for households.

Distributed assets in Eswatini cannot yet earn money from flexibility. Households and businesses can lower their bills with solar and storage, and since August 2026 receive net-billing credits for exports, but there is no aggregator role, no capacity or balancing market, and no virtual-power-plant scheme.

The building blocks are being put in place. The 2024 storage guidelines define arbitrage and ancillary services and anticipate a non-exclusive central buyer under the IPP Policy; EEC lists market rules and the optimisation of energy trading among its strategic initiatives; and the smart meters EEC plans to buy support time-of-use billing and remote load limiting. Until rules are written, system balancing remains EEC’s job, using its hydro stations, contracted imports and the SAPP markets.

Flexibility and aggregation platforms.

Flexibility and aggregation platforms.
Platform or aggregatorWhat it does
Southern African Power PoolRegional market used by EEC for short-term purchases.
Embedded Generation Application PlatformRegistration and approval platform for distributed generators up to 2 MW; not a trading platform.

Smart meters.

Smart meters.
FactValue
Smart-meter rolloutPrepaid STS keypad meters are the household norm; smart metering is at pilot stage, with a 2026 plan to convert about 300,000 customers
Reading intervalNot published (smart-meter specification requires an 8-channel load profile)
Household meteringSplit prepaid STS meters with in-home customer interface unit (since 2008)
Token format20 digits, bought by 11-digit meter number
Meter ownerEEC
Planned smart-meter standardsSTS, DLMS/COSEM, IEC 62055-31, NRS 049, IDIS, G3-PLC
Embedded-generation metersBi-directional, two-way communicating, time-of-use capable; paid by customer
Remote reading for net billingMonthly reading required, physically or remotely; estimates not allowed

Prepayment began in the Manzini region in 2008 and was extended to Hhohho, Lubombo and Shiselweni to reduce billing errors and losses. Today households buy units in advance and key tokens into a customer interface unit. These meters are not connected to EEC, so there is no interval data for households and units cannot be loaded remotely.

EEC ran a smart-metering pilot in 2024/25. In 2026 it invited meter makers to partner in a local smart-meter factory, explaining that it intends to convert its current 300,000 customers from conventional to smart meters over the next few years and must fit a smart meter at each of at least 30,000 new connections due by 2030. The specification is a split power-line-carrier meter that can run in prepaid or post-paid time-of-use mode, with remote disconnection, load limiting and four-quadrant measurement. No roll-out date or penetration target has been published.

Renewable electricity.

Electricity generation mix (2024).

  • Hydro: 57.4%
  • Bioenergy: 34.4%
  • Solar: 4.9%
  • Coal: 3.3%
Source 33
Renewable electricity share
35.8% (2024)Source 33Derived: domestic renewable generation (96.7% of 0.61 TWh, about 0.59 TWh) as a share of total demand (1.65 TWh), from Ember. Used instead of the generation share because net imports of 1.04 TWh, mostly from South Africa's coal-heavy system, supplied about two-thirds of demand. Renewable content of the imports is not included.
Home solar
Not identified from a reliable public source.
Solar added each year
Not identified from a reliable public source.
Bioenergy (sugar-mill cogeneration)
0.11 GW (2024)Source 33
Hydro
0.06 GW (2024)Source 33EEC’s stations total 60.6 MW (Maguga 20, Ezulwini 20, Edwaleni 15, Maguduza 5.6).
Solar PV
0.03 GW (2024)Source 33
Wind
0 GW (2024)Source 33

Targets.

  • Increase the share of renewables in the electricity mix by 50% by 2030 compared with 2010 (NDC).
  • Universal electricity access by 2030 (ASCENT programme).
  • Energy Master Plan 2034: reduce import dependence and expand local generation.
  • 75 MW of solar PV procured from IPPs through ESERA’s programme, with the first plants due in 2027.

Domestic generation is overwhelmingly renewable because the country’s own plants are hydro and sugar-industry biomass. Ubombo Sugar and the Royal Eswatini Sugar Corporation burn bagasse in cogeneration plants rated at 41.5 MW and 65.5 MW, mainly for their own mills, with Ubombo selling surplus to EEC. Hydro output depends on rainfall: drought made 2024/25 EEC’s second-worst generation year in five, with output down 11.9% to 281 GWh.

Solar is small but the pipeline is substantial relative to a 245 MW peak. EEC’s 10 MW Lavumisa tracking plant (13.75 MWp) produced 22.4 GWh in 2024/25. ESERA’s 75 MW solar IPP programme comprises Tsamela 20 MW (construction from early 2026, operation expected mid-2027 under a 25-year PPA), Nsoko 10 MW (site launched August 2026), and three 15 MW projects at Ndzevane, Bhalekane and Ngwenya. Ubombo Sugar signed a 40 MW biomass cogeneration PPA in December 2025 for operation from June 2028, and the 13.5 MW Lower Maguduza run-of-river hydro IPP is due in early 2027. Geothermal sites have been identified but need exploration funding.

Energy storage.

Home batteries
Not identified from a reliable public source.
Grid-scale storage
Not identified from a reliable public source.

Storage in Eswatini is at the earliest stage. ESERA issued Energy Storage Systems Guidelines in July 2024 that fit storage into existing licence categories, set the 100 kW registration/exemption line for behind-the-meter batteries and describe how arbitrage and ancillary services would be valued. EEC has now commissioned a feasibility study for grid batteries under the World Bank–financed ASCENT project.

For households, batteries are mainly used for back-up during outages and to shift solar output into the evening. They must be registered with EEC like any other embedded generation, and grid charging is capped at 25% of the customer’s installed capacity.

Storage projects.

  • Sigcineni solar-battery mini-grid (EEC): Pilot off-grid system of about 35 kW of solar PV with 200 kWh of battery storage supplying 22 households.
  • EEC BESS feasibility study: Consultancy tender issued in August 2026 (ref. SZ-ECC-561947-CS-CQS) to assess battery storage on the EEC grid, including solar-plus-storage hybrids, siting and ownership models.

Electricity suppliers.

Electricity suppliers.
SupplierMarket shareRenewable tariffTime of useDynamicExport tariff
Eswatini Electricity Company (EEC)Sole national supplier; 298,918 customers (2024/25)NoLimitedNoYes

There is no retail competition. EEC supplies every customer on the national grid at ESERA-approved tariffs. RES Corp and UFPC hold distribution licences and supply small numbers of customers on their own estates; ESERA monitors all three against the same quality-of-service standard.

Key organisations.

Key organisations.
OrganisationCategoryWhat it doesWhy it matters
Ministry of Natural Resources and EnergyGovernmentEnergy policy and planningOwns the IPP Policy and Energy Master Plan 2034 and oversees EEC as shareholder.
Eswatini Energy Regulatory Authority (ESERA)RegulatorElectricity and petroleum regulatorIssues licences, tariffs, the Grid Code, embedded-generation and storage rules, and runs IPP procurement.
Eswatini Electricity Company (EEC)TransmissionUtility: generation, transmission, distribution, supplyApproves and connects every embedded generator and owns all meters.
ESERA Accredited Solar Installers registerSolarPublic list of accredited PV mounters and installersEEC applications require an accredited installer.
Embedded Generation Application PlatformDistributionOnline application and registration systemMandatory route for registering and approving grid-connected solar and other embedded generation.
Southern African Power Pool (SAPP)MarketRegional power pool and marketSource of short-term imports for EEC.
Africa Minigrids Program – EswatiniRenewable EnergyMini-grid development programmeSupports mini-grid delivery models and capacity building for unelectrified communities.
ESERA consumer complaintsConsumerComplaints and dispute handlingRoute for customers whose complaints to EEC are not resolved.

Technical standards.

Technical standards.
AreaStandardIssued byNotes
Grid connection of embedded generationSZNS NRS 097-2-1:2017 and NRS 097-2-3:2014Eswatini Standards Authority (adopted from South African NRS)Utility-interface requirements and simplified connection criteria for LV generators, including export limits on shared feeders.
Inverters / anti-islandingNRS 097-2-1 third-party test certificateEEC requirementInverters without independent certification are prohibited in new and existing installations; reverse-feed blocking does not remove the requirement.
Grid CodeEswatini Grid CodeESERAApplies to all licensees and embedded generators.
WiringSZNS SANS 10142-1 (wiring of premises, LV installations)Eswatini Standards AuthorityGenerators must be permanently wired.
MeteringSZNS SANS 474 / NRS 057; STS (IEC 62055) for prepaymentEswatini Standards Authority; EECEG meters must be bi-directional, two-way communicating and TOU-capable.
Quality of supply and serviceSZNS 028 (quality of supply), SZNS 026 (quality of service)Eswatini Standards Authority; enforced by ESERAEmbedded generators must keep supply quality within SZNS 028 limits.
Installer accreditationEswatini Solar PV Installer Accreditation Programme (Level 2 / Level 3)ESERA with DIVTLevel 3 installers may design, commission and sign off single-phase systems.
Fire and siting (storage)Energy Storage Systems Guidelines 2024ESERALicensed storage needs fire safety, environmental and social management, and siting plans.

Permissions.

Permissions.
PermissionRequiredLevelDetail
EEC conditional and final approvalYesNationalRequired for every grid-connected system, including zero-export and battery back-up; nothing may be installed before conditional approval.
ESERA licence or exemptionLimitedNationalNot needed below 100 kW; own-use plants of 100 kW or more apply for an exemption; selling power to others needs licences.
Grid impact studyLimitedNationalMandatory above 350 kVA (customer pays); may be required for smaller systems exceeding NRS 097-2-3 limits.
Connection and supply agreements, bi-directional meterYesNationalNeeded before any export; the connection charge covers metering and inspection.
Accredited installer sign-offYesNationalApplications must be supported by an ESERA-accredited installer.
Building or planning permissionUnknownLocalNo specific planning rule for rooftop PV was identified; owners should check with the local authority where building regulations apply.

Permission for small systems is handled almost entirely by EEC under ESERA’s rules, now through one online platform. The decisive steps are EEC’s conditional approval before installation and final approval after inspection; ESERA becomes directly involved only at 100 kW and above, or where power is sold or wheeled.

Support schemes, taxes and incentives.

Support schemes, taxes and incentives.
SchemeStatusTypeDetailPeriod
Embedded generation feed-in tariff (net billing)ActiveNet billing export creditSurplus exports are credited at 51.23 c/kWh (flat, excl. VAT) or seasonal TOU rates of 31.49–166.02 c/kWh against energy purchases. Credits are not paid in cash and lapse at the end of the financial year.1 Aug 2026 – 31 Mar 2027
Lifeline tariff (S10)ActiveSocial tariffDiscounted first 75 kWh a month (E1.5685/kWh in 2026/27) for qualifying low-income households, with higher rates above 100 kWh.—
Government tariff cushion 2026/27ActiveTariff subsidyE200 million of government funding (E100 million allocated for 2026) reduced the 2026/27 average increase from 13.61% to 11.74% and the domestic increase from 17.23% to 15.09%.Apr 2026 – Mar 2027
Rural Electrification Access FundActiveConnection subsidyFunded by a 2.5% levy on all energy charges; supports group schemes and rural connections (156 group schemes completed in 2024/25).—

Data and connectivity.

Fixed broadband
2.5 fixed subscriptions per 100 people (2024)Source 39
4G coverage
Not identified from a reliable public source.
5G coverage
Not identified from a reliable public source.

Fixed broadband is scarce (about 2.5 subscriptions per 100 people in 2024), but mobile use is high: the World Bank records 139.8 mobile subscriptions per 100 people and 63.4% of people using the internet in 2024. Mobile money and USSD (*8888#) are already the main channels for buying prepaid electricity.

For metering, EEC has chosen power-line communication (G3-PLC) with DLMS/COSEM data models in its smart-meter specification rather than relying on cellular links for every meter. Embedded-generation meters must support two-way communication so they can be read remotely for monthly net billing.

Grid conditions.

National peak demand
0.245 GW (2024/25)Source 16System maximum demand of 244.60 MW in March 2025 at 19:00; the previous year’s peak was 252.52 MW.
Annual electricity demand
1.364 TWh (2024/25)Source 16Units sent out by EEC. Ember estimates 2024 national demand at 1.65 TWh.
Generation capacity
0.203 GW (2023/24)Source 28Biomass 106.5 MW, hydro 63.4 MW, solar 30.9 MW and coal 2.2 MW, including industrial cogeneration and embedded solar; EEC’s own fleet is about 70 MW.
Interconnection
Not identified from a reliable public source.
Curtailment
Not identified from a reliable public source.

The grid’s main constraint is supply, not wires: local plants cover about a third of demand and imports depend on contracts with NTCSA/Eskom and EDM. Total system losses were 13.54% in 2024/25, with distribution losses of 3.15% and commercial (theft) losses of 0.43%; copper theft is a persistent problem.

Network reinforcement is under way: a 52 km 132 kV Edwaleni–Stonehenge line, an 83 km 132 kV Nhlangano–Lavumisa line under the World Bank NRAP project, and a planned north-eastern 132 kV reinforcement funded through ASCENT. Locally, embedded-generation export is capped by feeder and transformer limits, and by an aggregate national cap set by the system operator.

Regulatory changes.

Regulatory changes.
ChangeStatusDateDetail
Feed-in credits for embedded generatorsCurrent1 August 2026National roll-out of ESERA-approved net-billing feed-in tariffs, connection charges and a non-compliance penalty, valid to 31 March 2027.
Online embedded generation portalCurrent2 September 2026All applications for systems up to 2 MW, supply licensing and installer registration moved to www.eg.energy.org.sz.
Wheeling chargesCurrent1 July 2026ESERA-approved charges for using EEC transmission and distribution networks, plus grid impact assessment charges.
2026/27 tariff increaseCurrent1 April 2026Average +11.74% after government support; domestic +15.09%, lifeline +6%.
Feed-in tariff reviewUpcomingFrom 1 April 2027The current export rates expire on 31 March 2027 and must be re-approved.
New multi-year tariff methodology and cost-of-supply frameworkUpcoming2026–27 (consultation)ESERA consulted in 2026 on a revised Multi-Year Price Determination methodology and a cost-of-supply framework intended to make tariffs more cost-reflective and reduce cross-subsidies.
Appliance and equipment standards regulationsUpcoming2026 (draft)Draft regulations for enforcing electrical and electronic equipment and appliance standards were issued for consultation.
Smart-meter conversionUpcomingNext few years (no date set)EEC plans to replace conventional meters for about 300,000 customers and sought a local manufacturing partner in 2026.
New local generationUpcoming2027–2028Lower Maguduza hydro (13.5 MW, early 2027), Tsamela solar (20 MW, mid-2027) and other 75 MW programme plants, and Ubombo Sugar biomass (40 MW, June 2028).

Market indicators.

Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.

Market indicators.
IndicatorLevelBasis
Electricity costMediumLow below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros).
Household electricity useLowLow below 2,500 kWh a year, high at 5,000 kWh or more (average use per household).
Renewable shareMediumLow below 30%, high at 60% or more (renewable share of electricity).
Smart-meter adoption—Low below 30%, high at 80% or more (share of meters that are smart).
Home solar adoptionLowAbout 24 MW of embedded generation of all sizes registered by mid-2026, against 277,312 domestic customers; export credits only began in August 2026.
Distributed energy marketMediumRegistered embedded generation equals roughly 10% of peak demand, and industrial biomass cogeneration (about 107 MW) is a large share of local capacity, but a national cap limits further connections.
Grid flexibility marketLowNo wholesale, balancing or ancillary-services market for third parties; aggregation is not recognised.
Energy storage adoptionLowNo grid-scale storage in operation; only a 200 kWh pilot mini-grid battery and an August 2026 feasibility tender.
Renewable growth environmentMediumAbout 129 MW of new solar, biomass and hydro IPP capacity under procurement or construction for 2027–2028, against a 245 MW peak; solar was about 0.03 GW in 2024.

Sources.

Public sources used for this profile, with the date each was accessed.

Show all 40 sources
  1. 2026/2027 Residential/Domestic Tariffs. Eswatini Electricity Company, 2026. accessed 1 October 2026.
  2. General Notices (tariff schedules 2024/25 and 2025/26; EG feed-in tariffs). Eswatini Electricity Company, 2024–2026. accessed 1 October 2026.
  3. ESERA Decision on EEC’s Tariff Adjustment Application for FY2026/2027 (Tariff Order 2026). Eswatini Energy Regulatory Authority, 2026. accessed 1 October 2026.
  4. E200m electricity cushion minimal relief. Eswatini Observer, 2026. accessed 1 October 2026.
  5. Schedule for Approved Feed-in Tariffs and Associated Costs for EG 2026/27. Eswatini Electricity Company, 2026. accessed 1 October 2026.
  6. ESERA Decision on Feed-in Tariff and Associated Charges for Embedded Generators. Eswatini Energy Regulatory Authority, 2025. accessed 1 October 2026.
  7. Embedded Generation (EG) Bylaws, 2024 (public review draft). Eswatini Energy Regulatory Authority, 2024. accessed 1 October 2026.
  8. Eswatini Energy Storage Systems Regulatory Guidelines, 2024. Eswatini Energy Regulatory Authority, 2024. accessed 1 October 2026.
  9. Press Statement – Decision on the EEC Wheeling Charges and Grid Impact Assessment Charges. Eswatini Energy Regulatory Authority, 2026. accessed 1 October 2026.
  10. Public Notices (consultations on MYPD methodology, cost of supply, appliance standards). Eswatini Energy Regulatory Authority, 2026. accessed 1 October 2026.
  11. Types of Licences. Eswatini Energy Regulatory Authority. accessed 1 October 2026.
  12. Frequently Asked Questions – Electricity. Eswatini Energy Regulatory Authority. accessed 1 October 2026.
  13. Electricity Sector. Eswatini Energy Regulatory Authority. accessed 1 October 2026.
  14. Annual Electricity Compliance Report 2024/25. Eswatini Energy Regulatory Authority, 2025. accessed 1 October 2026.
  15. Accredited Solar Installers. Eswatini Energy Regulatory Authority. accessed 1 October 2026.
  16. Integrated Annual Report 2025. Eswatini Electricity Company, 2025. accessed 1 October 2026.
  17. How It Works: From Application to Feeding Back. Eswatini Electricity Company, 2026. accessed 1 October 2026.
  18. Solar Embedded Generator Registration Updates. Eswatini Electricity Company, 2026. accessed 1 October 2026.
  19. Prepaid Electricity. Eswatini Electricity Company. accessed 1 October 2026.
  20. Prepaid Electricity Vouchers. Eswatini Electricity Company. accessed 1 October 2026.
  21. Customer FAQs. Eswatini Electricity Company. accessed 1 October 2026.
  22. Generation of Electricity. Eswatini Electricity Company. accessed 1 October 2026.
  23. Transmission of Electricity. Eswatini Electricity Company. accessed 1 October 2026.
  24. Key Electricity Sector Legislation. Eswatini Electricity Company. accessed 1 October 2026.
  25. RFP 02 of 2026/2027 – Smart Meter Local Manufacturing Technical and Financial Partner Procurement. Eswatini Electricity Company, 2026. accessed 1 October 2026.
  26. Sell your solar power to EEC. Eswatini Observer, 2026. accessed 1 October 2026.
  27. Eswatini, Namibia open rooftop solar application portals. pv magazine, 2026. accessed 1 October 2026.
  28. Eswatini: Solar PV-Embedded Generation Market – Developer Guide. GET.invest, 2024. accessed 1 October 2026.
  29. Eswatini launches 20MW Tsamela solar PV plant, first project under 75MW ESERA solar programme. SolarQuarter, 2025. accessed 1 October 2026.
  30. Eswatini strengthens energy security with 40 MW biomass power PPA between Ubombo Sugar Limited and EEC. SolarQuarter, 2026. accessed 1 October 2026.
  31. Consultancy services for the feasibility study of a battery energy storage system (BESS) in Eswatini. AllBusiness.Africa (tender listing), 2026. accessed 1 October 2026.
  32. 3 ways to power Eswatini’s path to energy security and sustainability. UNDP Climate Promise, 2024. accessed 1 October 2026.
  33. Yearly electricity data – Eswatini. Ember, 2024. accessed 1 October 2026.
  34. Euro foreign exchange reference rates – South African rand. European Central Bank, 2026. accessed 1 October 2026.
  35. Population, total – Eswatini (SP.POP.TOTL). World Bank, 2025. accessed 1 October 2026.
  36. Urban population (% of total) – Eswatini (SP.URB.TOTL.IN.ZS). World Bank, 2025. accessed 1 October 2026.
  37. Access to electricity (% of population) – Eswatini (EG.ELC.ACCS.ZS). World Bank, 2024. accessed 1 October 2026.
  38. Access to clean fuels and technologies for cooking – Eswatini (EG.CFT.ACCS.ZS). World Bank, 2023. accessed 1 October 2026.
  39. Fixed broadband subscriptions (per 100 people) – Eswatini (IT.NET.BBND.P2). World Bank, 2024. accessed 1 October 2026.
  40. Eswatini Government and UNFPA launch results of the 2017 Population and Housing Census. UNFPA Eswatini, 2020. accessed 1 October 2026.

Questions about energy in Eswatini.

Talk to us about Olmack in Eswatini.Tell us about your home, housing portfolio or school estate in Eswatini. We'll explain what is possible there now.