Energy in Japan, explained.

How electricity works in Japan: prices, the grid and local rules. Olmack status: Not yet available. Information last checked 1 October 2026.

Olmack in Japan: Not yet available.Olmack is not offered in Japan yet. The market information on this page is provided for reference. Information last checked 1 October 2026.
Energy-market overview

How electricity works in Japan.

Japan electricity market 2026: household prices, ten regional grid companies, the 22-digit supply point number, smart meters, FIT export rules and licensing.

This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Japanese yen (JPY) where they relate to prices.

Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.

At a glance

Japan energy at a glance.

Key figures for households in Japan. Each one links to its source on the full overview below.

  • Electricity price.

    30.17 JPY per kWh for households, including taxes. Figures for Jun–Oct 2026.

  • Household use.

    3,917 kWh a year for a typical household. Figures for FY2023.

  • Renewable share.

    23.6% of electricity from renewable sources. Figures for 2025.

  • Selling back to the grid.

    Can homes export electricity? Yes. Details are in the export section below.

Before you start

Four things to check in Japan.

Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.

  1. Check the local rules.

    Read the connection, export and permission rules for Japan below, and ask your local grid operator if anything is unclear.

  2. Choose a qualified installer.

    Look for an installer listed on an official register, with the certifications Japan requires for the work.

  3. Look at current schemes.

    Check which support schemes are open now. Closed or scheduled schemes are labelled as such.

  4. Talk to your energy supplier.

    Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.

Local detail

Schemes, rules and certifications in Japan.

The full detail sits in the sections below. Each item shows its status and links to the official source.

  • Support schemes.

    Grants, tax relief and export payments in Japan, each labelled Active, Scheduled or Closed.

  • Connection and export.

    How equipment is connected to the grid in Japan, and the steps to export electricity.

  • Standards and certifications.

    The technical standards and installer certifications that apply to energy equipment in Japan.

Full overview

The energy market in Japan, in detail.

Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.

Profile last updated 1 October 2026.

On this page22 sections

Japan’s electricity system is organised around ten regional areas rather than one national grid. In each area a general transmission and distribution company (一般送配電事業者) owns the wires, balances its area and owns and reads every meter. Except in Okinawa, these network companies have been legally separate from the generation and retail arms of the former regional utilities since April 2020. Policy and licensing sit with the Ministry of Economy, Trade and Industry (METI) and its Agency for Natural Resources and Energy. Market monitoring is done by the Electricity and Gas Market Surveillance Commission (EGC). Cross-regional planning, the capacity and balancing markets and the retail switching system are run by the Organization for Cross-regional Coordination of Transmission Operators (OCCTO).

Households have been free to choose their retailer since April 2016, and 823 retail electricity businesses were registered on 30 September 2026. New entrants held 25.6% of household (lighting) contracts in June 2026. However, the former regional utilities still serve about three-quarters of homes, and 47% of household contracts were still on the regulated tariffs those utilities must continue to offer. A typical regulated bill in the Kansai area works out at about 30 yen/kWh including taxes before the temporary government subsidy. The east (50 Hz) and west (60 Hz) halves of the country are linked only through frequency-converter stations with 2.1 GW of capacity. Japan has no international interconnectors.

Fossil fuels still dominate. In FY2024 renewables supplied 23.1% of generation and nuclear 9.4%, according to the government’s energy balance, and Ember estimates a 23.6% renewable share for calendar year 2025, with solar at about 10%. Japan has more than 90 GW of solar, much of it on rooftops, and over 1.1 million grid-connected home battery systems have been shipped. Key changes for 2025–2027 include the roll-out of next-generation smart meters, the opening of all balancing-market products to aggregated low-voltage resources such as home batteries from FY2026, a front-loaded feed-in tariff for new rooftop solar, and the end of FIT/FIP support for new ground-mounted solar from FY2027.

Energy snapshot.

Headline figures for electricity in Japan. Each shows its data year and links to its source.

  • Population122,838,000 peopleSource 11 Apr 2026
  • Households57,125,000 householdsSource 21 Oct 2025
  • Average household size2.15 people/householdSource 22025
  • Electricity use per household3,917 kWh/yrSource 5FY2023
  • Household price (JPY)30.2 JPY/kWhSource 9Jun–Oct 2026
  • Household price (EUR)0.169 EUR/kWhSource 9Jun–Oct 2026
  • Renewable electricity share23.6%Source 432025
  • Solar capacity92.2 GWSource 432025
  • Wind capacity6.24 GWSource 432025
  • Energy storage capacity0.64 GWSource 32end Dec 2025
  • Smart-meter shareNot identified from a reliable public source.
Market structure
Partially liberalised
Homes can export to the grid
Yes
Home equipment in grid services
Developing
Regulator
METI (Agency for Natural Resources and Energy), with the Electricity and Gas Market Surveillance Commission (EGC) monitoring markets and tariffs
System operator
Ten area network companies balance their own areas; OCCTO coordinates between areas and runs the capacity and balancing markets
Distribution networks
Ten general transmission and distribution companies, one per area (Hokkaido, Tohoku, Tokyo, Chubu, Hokuriku, Kansai, Chugoku, Shikoku, Kyushu, Okinawa), each owning both the transmission and distribution networks and all meters in its area
Currency
Japanese yen (JPY)
Voltage and frequency
100 V / 200 V single-phase; 50 Hz in eastern Japan and 60 Hz in western Japan

Electricity prices in Japan.

Household price (JPY)
30.2 JPY/kWh (Jun–Oct 2026)Source 9Derived from Kansai Electric Power’s published model bill for its regulated residential tariff (従量電灯A): 7,843 yen for 260 kWh a month, including the bank-transfer discount, fuel-cost adjustment, renewable surcharge and consumption tax, before the temporary government subsidy. With the 3.5 yen/kWh subsidy, the October 2026 bill is 6,933 yen (26.67 yen/kWh). Kansai is one of the cheaper areas. The EGC’s June 2026 data give an average household (lighting) revenue of 28.58 yen/kWh nationally (446.6 billion yen ÷ 15.63 TWh; tax treatment not stated).
Household price (EUR)
0.169 EUR/kWh (Jun–Oct 2026)Source 9Converted from 30.17 JPY/kWh at the ECB reference rate of 178.27 JPY per EUR on 30 September 2026.
Typical annual electricity bill
158,628 JPY/yr (2025)Source 4Derived: the Family Income and Expenditure Survey reports average spending on electricity of 13,219 yen a month for households of two or more people in 2025 (up 10.1% in nominal terms), multiplied by 12. Single-person households are not included.

Household price trend (JPY per kWh).Source 9

26.628.38530.17Oct 2021Oct 2022Oct 2023Oct 2024Oct 2025Oct 2026
Japan household electricity price, JPY per kWh
Oct 202126.6 JPY/kWh
Oct 202228.83 JPY/kWh
Oct 202327.14 JPY/kWh
Oct 202429.48 JPY/kWh
Oct 202529.97 JPY/kWh
Oct 202630.17 JPY/kWh

A Japanese household bill has a basic charge, set either by contracted amperage (commonly 30–60 A) or as a minimum charge depending on the area, plus a three-step per-kWh energy charge, the fuel-cost adjustment (燃料費調整) and the renewable energy surcharge (再エネ賦課金). Consumption tax at 10% is included in published prices. The renewable surcharge funds the FIT/FIP schemes and is set nationally each year. METI set it at 4.18 yen/kWh for meter readings from May 2026 to April 2027, which costs 1,672 yen a month for a 400 kWh household.

Network charges (託送料金) are paid by the retailer to the area network company and are built into the energy price, not shown separately. Since FY2023 they have been set under a five-year revenue-cap regime approved by METI after review by the EGC. Retailers must balance supply and demand for every 30-minute period and pay imbalance charges if they miss. Wholesale prices on JEPX therefore feed through to market tariffs quickly, especially for new entrants with little generation of their own.

Regional differences and trend

Prices differ by area because each former utility has its own generation mix and network costs. Areas with operating nuclear plants, such as Kansai and Kyushu, are generally cheaper than Hokkaido or Tokyo. Kansai’s model regulated bill for 260 kWh, before subsidies, rose from 6,916 yen in October 2021 to 7,497 yen in October 2022, when the fuel-cost adjustment first hit its legal cap. It then eased to 7,056 yen in October 2023 thanks to a low renewable surcharge, and climbed to 7,664 yen (October 2024), 7,791 yen (October 2025) and 7,843 yen (October 2026). In 2026 the regulated fuel-cost adjustment was again held at its ceiling, because the average fuel price (53,500 yen/kl) exceeded the 40,700 yen/kl upper limit. Market tariffs have no such cap.

Government bill subsidies

The government has repeatedly paid temporary per-kWh discounts, applied automatically by retailers. For July, August and September 2026 usage the discount was 3.5, 4.5 and 3.5 yen/kWh on low-voltage supply, and 1.8, 2.3 and 1.8 yen/kWh on high-voltage supply. METI authorised the former utilities to apply it to their regulated tariffs on 12 June 2026. No extension beyond September 2026 usage had been announced when this was checked.

Tariff types.

Tariff types.
TariffAvailableDetail
RegulatedYesThe former regional utilities must still offer METI-approved regulated tariffs (特定小売供給約款), such as 従量電灯A/B. They have a basic or minimum charge, a three-step energy charge and a fuel-cost adjustment with an upper limit. In June 2026, 39.4 million household (lighting) contracts, 47% of all household contracts, were on regulated tariffs.
VariableYesMost market (free) tariffs follow the same structure as the regulated ones, but the fuel-cost adjustment has no cap and follows imported oil, LNG and coal prices with a lag of three to five months. Some new entrants instead add a market-price adjustment.
Time-of-useYesFormer utilities and new entrants offer time-of-use plans, often for all-electric homes with heat-pump water heaters (Eco Cute), EVs or batteries. Examples include Kansai Electric’s はぴeタイムR, Chubu Electric Power Miraiz’s スマートライフプラン and daytime-weighted 昼とくプラン, and Tokyo Gas’s 時間帯別プラン.
DynamicLimitedSome retailers offer plans indexed to the JEPX spot market, priced in 30-minute periods using smart-meter data. One example is Looop’s スマートタイムONE. They expose households to wholesale price swings and make up a minority of contracts.
OtherYesRenewable-backed tariffs that use non-fossil certificates (for example Tokyo Gas’s さすてな電気) are widely available.

Household prices compared with neighbouring countries (EUR per kWh).

Household prices including taxes, converted to euros as stated on each country page.

Household electricity use.

Electricity use per household
3,917 kWh/yr (FY2023)Source 5Derived: the Ministry of the Environment’s household CO2 survey reports electricity use of 14.1 GJ per household per year (converted at 1 kWh = 3.6 MJ, as the survey states). It was 15.6 GJ in FY2017 and 14.2 GJ in FY2022.
Average daily use per household
10.7 kWh/day (FY2023)Source 5Derived: 3,917 kWh a year divided by 365.
Typical household peak demand
Not identified from a reliable public source.
Electricity use per person
8,370 kWh/person/yr (2025)Source 43Total electricity demand across all sectors per person (Ember: 8.37 MWh, more than double the world average).
Heat pumps
16.8 % of households (FY2023)Source 5Households using an electric heat-pump water heater (Eco Cute and similar): 28.3% of detached houses and 3.4% of apartments, up from 13.4% in FY2017. Air-to-air heat pumps (air conditioners) are counted separately below.
Air conditioning
92.2 % of homes (end Mar 2026)Source 6Ownership of room air conditioners among households of two or more people, with 284.5 units per 100 households. Most are reversible heat pumps used for heating as well as cooling.
Electric vehicles
54,390 new battery-electric cars sold (FY2025)Source 72.2% of 2,471,215 registered passenger cars sold between April 2025 and March 2026, plus 40,355 plug-in hybrids (1.6%). Kei (mini) cars, which include some popular EVs, are not counted. No official count of the EV fleet was found.
Electric cooking
Not identified from a reliable public source.

Household electricity use is falling slowly. Ministry of the Environment survey data show it fell from 15.6 GJ per household in FY2017 to 14.1 GJ (about 3,900 kWh) in FY2023, as appliances became more efficient and households smaller. OCCTO’s January 2026 forecast expects “household and other” low-voltage demand to fall from an estimated 293.4 TWh in FY2025 to 276.6 TWh in FY2035. National demand is still expected to rise, driven by semiconductor plants.

Electricity covers most cooling and a growing share of heating. Room air conditioners, which are reversible heat pumps, are in 92% of family homes. One household in six uses a heat-pump water heater, rising to nearly half of detached houses built since 2006. Gas, LPG and kerosene are still important for space heating in colder regions and for cooking. Plug-in vehicles are a small share of new car sales, so EV charging does not yet shape household load the way air conditioning does.

Housing and households.

Dwellings
65,047,000 dwellings (1 Oct 2023)Source 3Housing and Land Survey 2023, a record high. Of these, 9.00 million (13.8%) were vacant.
Owner-occupied
60.9% (2023)Source 3Share of occupied dwellings (33.876 million owner-occupied).
Private rented
28.2% (2023)Source 315.684 million privately rented homes. A further 2.3% are employer-provided (給与住宅).
Social or public housing
4.5% (2023)Source 3Derived: public (prefectural and municipal) rented housing, 3.2% (1.76 million), plus UR (Urban Renaissance Agency) and public-corporation housing, 1.3% (716,000).
Houses
52.7% (2023)Source 3Detached houses (29.319 million occupied dwellings). Row houses (長屋建) add 1.265 million.
Apartments and flats
44.9% (2023)Source 3Apartment buildings (24.968 million), a record share. In Tokyo it is 71.6%.
Urban population
92.3 % of population (2025)Source 8World Bank urban population estimate, based on the UN World Urbanization Prospects definition.

Three in five homes are owner-occupied, and more than half of occupied dwellings are detached houses. These are the main market for rooftop solar, home batteries and heat-pump water heaters, because the owner can decide alone and usually has a dedicated roof and meter. Apartments now make up 44.9% of the stock and over 70% in Tokyo. There, rooftop systems need the agreement of the condominium management association, and each flat has its own meter and supply point behind a shared building connection.

Japan also has a large and growing stock of vacant homes, 9.0 million or 13.8% of all dwellings, concentrated in rural areas and older apartment blocks. In rented homes the tenant normally holds the electricity contract and chooses the retailer, but adding generation or storage needs the landlord’s consent.

How the grid works in Japan.

  1. TransmissionOrganization for Cross-regional Coordination of Transmission Operators (OCCTO), General transmission and distribution companies (ten areas)
  2. DistributionTen general transmission and distribution companies, one per area (Hokkaido, Tohoku, Tokyo, Chubu, Hokuriku, Kansai, Chugoku, Shikoku, Kyushu, Okinawa), each owning both the transmission and distribution networks and all meters in its area
  3. MeteringArea network companies, OCCTO switching support system (スイッチング支援システム)
  4. Supply5 or more retail suppliers

Large thermal, nuclear and hydro plants feed 500 kV and 275 kV backbone networks in each area. The network company steps power down through 154 kV and 66 kV systems to 6.6 kV distribution lines, then to 100/200 V single-phase service for homes. The ten areas are linked in a chain from Hokkaido to Kyushu, while Okinawa is isolated. Because eastern Japan (Hokkaido, Tohoku, Tokyo) runs at 50 Hz and the rest at 60 Hz, east–west transfers pass through frequency converters with 2.1 GW of capacity. OCCTO’s May 2026 progress report expects this to reach 3.0 GW in December 2028. Hokkaido–Honshu DC capacity is due to rise from 0.9 GW to 1.2 GW by the end of FY2027, and the Tohoku–Tokyo link from 5.73 GW to 10.28 GW by November 2027.

Commercially, the household buys energy from its retailer. The retailer pays network charges to the area company under a consignment-supply (託送供給) contract, buys power from its own plants, bilateral contracts or JEPX, and must submit 30-minute plans that match supply and demand. Generators have also paid a generation-side network charge (発電側課金) since FY2024. When there is too much solar for the area to absorb or export, the network company orders output control on thermal plants first, then on renewables, under national priority-dispatch rules.

Who does what.

Who does what.
RoleOrganisationWhat it does
MinistryMinistry of Economy, Trade and Industry (METI) – Agency for Natural Resources and EnergySets energy policy, including the 7th Strategic Energy Plan. It registers retail businesses, receives notifications from generation and aggregation businesses, licenses the network companies, approves regulated tariffs, sets FIT/FIP prices and the renewable surcharge, and writes the grid-connection technical guideline. METI’s regional industrial-safety bureaus enforce electrical safety rules.
RegulatorElectricity and Gas Market Surveillance Commission (EGC)Commission within METI that monitors the wholesale and retail markets and reviews network charges and regulated tariffs. It publishes monthly retail statistics (sales, shares, contracts, switching by area) and advises the minister.
System operatorOrganization for Cross-regional Coordination of Transmission Operators (OCCTO)Membership body set up in 2015 under the Electricity Business Act. It forecasts demand, reviews supply plans and plans inter-regional lines. It can order cross-regional power transfers in emergencies, runs the capacity market, the long-term decarbonisation auction and the balancing market (需給調整市場), and operates the switching support system that retailers use to change supply points.
TSOGeneral transmission and distribution companies (ten areas)Hokkaido Electric Power Network, Tohoku Electric Power Network, TEPCO Power Grid, Chubu Electric Power Grid, Hokuriku Electric Power Transmission & Distribution, Kansai Transmission and Distribution, Chugoku Electric Power Network, Shikoku Electric Power Transmission & Distribution, Kyushu Electric Power Transmission and Distribution, and Okinawa Electric Power. Each owns the 500 kV down to 100/200 V network in its area, keeps its area in balance and dispatches balancing resources.
DSOThe same ten network companiesThere is no separate distribution tier. The area company connects every home, issues its supply point number, handles grid-connection applications for solar and batteries, and imposes output control (curtailment). Okinawa Electric Power is exempt from legal unbundling because its island grid is small and isolated, so it remains vertically integrated, with conduct rules in place instead.
MeteringArea network companiesMeters are a network monopoly. The area company owns, installs, reads and replaces all meters, including smart meters, and supplies 30-minute data to retailers. Customers cannot appoint an independent meter operator.
SupplierRegistered retail electricity businesses (小売電気事業者)823 registered at 30 September 2026. They include the ten former regional utilities (みなし小売電気事業者, some acting through retail subsidiaries such as TEPCO Energy Partner and Chubu Electric Power Miraiz), gas companies, oil companies, telecoms firms and specialist new entrants.
Data hub / registryOCCTO switching support system (スイッチング支援システム)A national system, available only to registered retailers and demand-response contractors. It lets them look up a supply point’s equipment details, retrieve 13 months of usage history and submit start, change and termination requests to the area network company by API or web screen.
ExchangeJapan Electric Power Exchange (JEPX)Runs the day-ahead (spot) market in 48 half-hour products, the intraday market and other markets. Spot prices form separate area prices when inter-regional links are congested.
Flexibility marketOCCTO balancing market and capacity marketsThe balancing market buys primary to tertiary reserves from qualified resources. From FY2026 aggregated low-voltage resources can bid into all products. The capacity market and the long-term decarbonisation auction pay for firm capacity, including batteries and pumped hydro.

Compared with the UK system.

Compared with the UK system.
UK conceptJapan equivalentHow it works
DNOGeneral transmission and distribution company (一般送配電事業者), e.g. TEPCO Power Grid or Kansai Transmission and DistributionThere are ten, one per area, and each combines the roles of a UK DNO, the transmission owner and the area system operator. Since April 2020 they have been separate subsidiaries of the former utilities, except in Okinawa. A household cannot choose its network company; it is fixed by location.
National Grid / NESOOCCTO plus the ten area network companiesNo single company operates the whole country. Each area company runs its own control centre and balances its area. OCCTO coordinates between areas, publishes national demand forecasts, plans inter-regional reinforcements (such as the east–west frequency converters) and runs the national capacity and balancing markets.
MPANSupply point specific number (供給地点特定番号)A 22-digit number assigned by the area network company to each place where electricity is used. Its first two digits identify the area and the third the voltage class. It stays with the property and is what retailers use to switch supply. See the supply-point section.
MPRNGas supply point specific number (ガスの供給地点特定番号)Since gas retail opened in April 2017, city-gas supply points also carry a supply point number, sometimes described as the meter number, issued by the local gas network operator. It is needed to switch gas retailer. Japan’s gas networks are local, not national, and many homes use LPG cylinders outside this system.
Meter operatorThe area network companyMetering is not competitive. The network company owns and maintains the meter, collects 30-minute readings over its own communications network (the “A route”) and passes them to the retailer. There is no equivalent of the UK’s choice of meter operator or meter asset provider.
SupplierRetail electricity business (小売電気事業者)Registered with METI and free to set prices, except for the regulated tariffs the former utilities must still offer. To switch, the customer contacts only the new retailer, which submits the change through OCCTO’s switching system. The switch takes effect on a meter-reading date, and the old contract ends automatically.
Smart-meter infrastructure (DCC / SMETS2)Each network company’s own meter network (A route) plus the in-home “B route”There is no national communications body like the DCC. Each network company runs its own head-end and radio mesh or mobile links. Customers can register a home energy management system (HEMS) to read the meter directly over the B route (920 MHz wireless, plus 2.4 GHz on next-generation meters). Consent-based access to smart-meter data for other companies goes through the certified Electricity Data Management Association.

How a supply point is identified.

0502012345678901234567 (fictional)

Fictional example in the real format.

How a supply point is identified.
QuestionAnswer
What is it called?Supply point specific number (供給地点特定番号)
Who issues it?The general transmission and distribution company for the area (for example Hokuriku Electric Power Transmission & Distribution in the Hokuriku area)
FormatDigits 1–2: the area’s own code (for example “05” for Hokuriku). Digit 3: voltage class (0 = low voltage, 1 = high or extra-high voltage). Digits 4–22: a number assigned in sequence by the network company, with no pattern by prefecture, municipality or retailer.
Length22 digits
Stays with the property when you switch supplier?Yes
Where to find itPrinted on the retailer’s bill or monthly usage notice (検針票 / 電気ご使用量のお知らせ) since January 2016, and shown in the retailer’s online account. If the customer cannot find it, the new retailer can look it up.
Electronic accessRetailers query a supply point’s details in OCCTO’s switching support system, searching by supply point number or meter number. From September 2025 the search was changed to handle the 10-digit numbers of next-generation smart meters, alongside the 7-digit numbers still used on current Kansai and Kyushu meters. Customers see their number and half-hourly usage in their retailer’s or network company’s web service. With a registered HEMS they can also read live data from the meter over the B route.
Third-party accessOnly registered retailers and demand-response contractors can use the switching system, and they need the customer’s application to switch or retrieve usage history. Since the 2022 amendment to the Electricity Business Act, other businesses can obtain an individual household’s smart-meter data only with that person’s consent, through the Electricity Data Management Association, which METI certified on 30 June 2022.
Who keeps the registerEach network company keeps the supply point and meter register for its area. OCCTO’s switching support system is a national gateway to those registers, not a single central database.
Register scopePer DSO

Every place where electricity is used, such as a detached house, a flat in an apartment block or a shop unit, has its own 22-digit supply point specific number. The number identifies the location, not the person or the contract. When someone moves in, changes retailer or changes tariff, the number stays the same. It changes only if the network company sets up a new supply point, for example when a building is demolished and rebuilt. Hokuriku Electric Power Transmission & Distribution explains that only the first three digits carry meaning: an area code, then a voltage digit. The rest is a running number. The number is not the same as the customer number, which belongs to the retailer, or the meter number, which belongs to the physical meter and changes when the meter is replaced.

How switching uses it

To switch, the customer gives the new retailer their name, current retailer, customer number, supply point number and preferred switch date. The new retailer sends a switching request through OCCTO’s switching support system. The area network company confirms the supply point and reassigns it to the new retailer’s consignment contract at the next meter reading, and the old contract ends without the customer contacting the old retailer. Switching is heavily used: the EGC counted 270,487 low-voltage switches in June 2026 alone, and 40.06 million cumulative switches since April 2016.

Generation and export points

A home with solar that exports surplus power also has a separate supply point for the reverse flow, recorded by the network company when the export connection is approved. The surplus purchase contract with the FIT buyer or retailer refers to that point. Smart meters measure import and export separately, so a net-metering arrangement is not needed.

Sending electricity to the grid.

Sending electricity to the grid.
QuestionAnswer
Can homes export electricity?Yes
Net meteringNo
Net billingYes
How exported electricity is paidFeed-in tariff for 10 years for new home systems (24 yen/kWh for years 1–4, then 8.3 yen/kWh for years 5–10 in FY2026), paid under the FIT purchase contract. After FIT ends (卒FIT), retailers buy surplus power at their own published rates.
Is there net metering?No. Imports and exports are metered separately. Exported surplus is paid at the FIT price or a retailer’s purchase price, while imported electricity is billed at the full retail tariff, including the renewable surcharge.
What does a new home solar system earn in FY2026?Under the “initial investment support scheme” introduced in October 2025, new residential systems under 10 kW receive 24 yen/kWh for the first four years and 8.3 yen/kWh for years 5–10. Rooftop systems of 10 kW or more receive 19 yen/kWh for five years, then 8.3 yen/kWh to year 20. These rates also apply to certifications in the second half of FY2025, and METI has set FY2027 rates on the same basis.
What sizes can connect at low voltage?Under METI’s grid-connection technical guideline (revised 1 December 2024), generation of under 50 kW per site can in principle connect to the low-voltage distribution network, and under 2,000 kW to high-voltage lines. Larger systems connect at extra-high voltage. Inverter-based systems that export must avoid causing voltage rise and must have anti-islanding protection.
Can export be curtailed?Yes. Output control now happens in all ten areas: Tokyo carried out its first renewable curtailment on 1 March 2026. In FY2024 the curtailment rate for variable renewables was highest in Kyushu, at 4.8%. Rules on which plants are curtailed first, and how compensation works, depend on size and connection date.
Is ground-mounted solar still supported?No new support from FY2027. METI’s March 2026 decision ends FIT/FIP certification for new ground-mounted commercial solar (10 kW and above) from FY2027, apart from FY2026 auction winners. Rooftop and residential systems remain eligible.

Connecting a home system.

  1. Choose an installer and system. Check roof ownership, landlord or condominium association consent, and any local building or landscape rules.
  2. The installer applies to the area network company for a low-voltage grid connection with reverse power flow. The network company checks the local transformer and voltage and confirms any conditions, such as output-control equipment or power-factor settings.
  3. If selling under FIT, apply for METI business-plan certification. Applications for solar under 50 kW are handled through the JPEA application agent centre (JP-AC), and certification is needed before the FIT purchase starts.
  4. Install the system using a qualified electrician (first- or second-class 電気工事士) and an inverter (power conditioner) that meets the grid guideline. JET-certified units simplify the network company’s technical review.
  5. The network company fits or reconfigures the smart meter to measure export, and the export connection is commissioned.
  6. Sign the surplus-power purchase contract (the FIT purchase contract, or a retailer’s purchase plan for systems outside FIT). Export is paid per kWh measured by the meter. Imports continue to be billed at the retail tariff.

Japan pays for exports rather than netting them. The FIT rate for new home systems is now front-loaded: 24 yen/kWh in the first four years, close to the retail price, then 8.3 yen/kWh, well below the roughly 30 yen/kWh that households pay for imported power. So from year five, using solar power at home is worth far more than exporting it, which is why many new systems are sold with a battery or a heat-pump water heater that runs in the daytime.

Many systems installed in the early years of the scheme have already passed their 10-year FIT term. Their owners need a post-FIT purchase contract with a retailer (for example Tokyo Gas offers a 卒FIT buyback service) to be paid for surplus power. Post-FIT rates are set by each retailer and are generally far below the retail price, so many owners add a battery instead.

Licensing and approvals.

Requirements depend on the activity. The table sets out what each activity needs and who grants it.

Licensing and approvals.
ActivityLicence or registrationAuthorityNotes
Generate electricityNotification as a generation business (発電事業) to METI when connected generation, including storage, is large enough to meet the statutory thresholds (aggregate output of more than 10 MW from units of at least 1 MW). Home and small commercial systems need no business licence or notification.METI (Agency for Natural Resources and Energy)The public list of notified generation businesses had 1,594 entries on 30 September 2026. Safety rules apply by size whatever the business status: under 10 kW is a general electrical facility; 10–50 kW is a small-scale business facility with a notification duty; 50 kW and above needs a chief electrical engineer and safety regulations.
Store electricityNo licence for home batteries. Large grid batteries are treated as generation equipment for business notification and supply-plan purposes once over the thresholds.METI; area network company for connection; local fire departmentFire Service Act rules apply by stored energy from 1 January 2024: up to 10 kWh is outside the rules, 10–20 kWh must meet the fire standards or a JIS standard, and above 20 kWh needs notification to the fire department.
Export surplus powerGrid connection agreement with the area network company. For FIT payments, METI business-plan certification (applications for under 50 kW via JP-AC) and a purchase contract with the buyer.Area network company; METISystems of 10–50 kW must meet a self-consumption (local use) requirement to obtain new FIT certification. Residential systems under 10 kW have no such requirement.
Sell / supply electricity to consumersRegistration as a retail electricity business under the Electricity Business Act, with duties on supply capacity, customer information and 30-minute balancing.METI, with EGC oversight823 registered retailers on 30 September 2026.
Aggregate distributed resources (VPP / DR)Notification as a specified wholesale supply business (特定卸供給事業) at least 30 days before starting, when aggregated resources supplied to retailers or network companies exceed the statutory size (1,000 kW). Cybersecurity measures to METI’s guideline are required.METIIn force since April 2022. The METI list showed 181 notified businesses on 30 September 2026. Smaller aggregators work through a notified business or a retailer.
Trade on the wholesale marketTrading membership of JEPX. There is no separate trading licence, but participants are normally retailers, generators or notified aggregators, because physical positions need a balancing group.JEPX; METI for the underlying business categoryThe EGC monitors JEPX trading for market abuse.
Balancing and grid servicesRegistration and pre-qualification of resources for the balancing market through OCCTO and a contract with the area network company. Low-voltage resources are aggregated using the list-pattern method.OCCTO; area network companiesFrom FY2026 low-voltage receiving-point resources can enter all products, and device-level metering using special metering devices is allowed for low-voltage resources. Device-level metering for high-voltage resources under 1,000 kW follows from FY2027.
Remote control of customer assetsNo separate licence. A party controlling home batteries or heat pumps for DR does so under its contract with the customer and, above the threshold, as a specified wholesale supply business.METIThe national home-battery subsidy requires owners to sign a DR contract with a battery aggregator or join a retailer’s DR menu until 31 March 2027.
Install and connect equipmentElectrical work on home installations must be done by a licensed electrician (first- or second-class 電気工事士) under the Electrician Act.METI; prefectural governments issue licencesApplies to residential solar under 10 kW and to battery wiring.
Operate transmission and distribution networksLicence as a general transmission and distribution business (one per area), with legal unbundling from generation and retail except in Okinawa.METISeparate categories exist for transmission businesses, specified T&D businesses (local private networks) and distribution businesses.

The Electricity Business Act defines business categories, not technology licences: retail (registration), generation (notification above thresholds), general transmission and distribution (licence), and since 2022 specified wholesale supply (aggregators, by notification) and distribution businesses. A household that installs solar and a battery and exports surplus power does not become a business in any of these categories. Its obligations come from the grid-connection agreement, the FIT certification if used, and the electrical safety rules for its size band.

Safety regulation is size-based and separate from market regulation. Solar under 10 kW is a “general electrical facility”: no filings are needed, but it must meet METI’s technical standards and be installed by a licensed electrician. Systems of 10–50 kW have been “small-scale business electrical facilities” since 20 March 2023. Their owners must notify basic information, carry out a pre-use self-check, report accidents and keep to the technical standards. At 50 kW and above, owners must file safety regulations and appoint a chief electrical engineer.

Flexibility and grid services.

Aggregation of home equipment: Yes

Flexibility and grid services.
Market or serviceAccess for home equipmentMinimum sizeVia an aggregatorDetail
Balancing market (需給調整市場): primary to tertiary reservesDevelopingPooled via list-pattern; resources of 1,000 kW and above bid individuallyYesOCCTO and the area network companies. Reserve products are procured by the network companies through OCCTO’s market system. From FY2026, aggregated low-voltage resources such as home batteries and heat-pump water heaters can bid into all products at the receiving point. Device-level metering using special metering devices allows a battery to be measured separately from the household load. It covers low-voltage resources only where next-generation smart meters are fitted.
Capacity market (main auction)Yes—YesOCCTO. An annual auction for capacity four years ahead, paid for by retailers. Demand response (as “variable power sources”) and storage can take part, and aggregators commonly bid demand-response capacity.
Long-term decarbonisation auctionRestricted—NoOCCTO. A 20-year fixed capacity payment for new low-carbon capacity. In the auction for the 2025 bidding year, contracts covered 0.82 GW of lithium-ion batteries and existing pumped hydro and 0.89 GW of other storage, new pumped hydro and long-duration storage, out of 4.26 GW of decarbonised capacity. Projects are utility-scale.
JEPX day-ahead and intradayRestricted—LimitedJEPX. Open to JEPX members. Households take part only through their retailer, for example through market-linked tariffs or retailer-run demand response that shifts load into cheap half-hours.
Retailer and network DR programmesYes—YesRetailers, aggregators and network companies. Retailers run “raise” and “lower” DR events for households, often rewarded with points. Network companies can also buy flexibility through aggregators to ease local constraints and curtailment.

Aggregation is a recognised legal activity in Japan, and small resources are steadily gaining market access. The key FY2026 change is that home-scale resources can be pooled into every balancing product. Device-level metering means a battery or heat pump can be settled on its own sub-meter rather than on the whole-house meter, but only where a next-generation smart meter is installed. Those meters are being rolled out from FY2025 on a schedule set by each network company.

Policy links subsidies to flexibility. The national home-battery subsidy requires the owner to sign a DR contract with an aggregator or retailer, so newly subsidised batteries enter the market with remote-control capability.

Flexibility and aggregation platforms.

Flexibility and aggregation platforms.
Platform or aggregatorWhat it does
OCCTO balancing and capacity market systemsRegistration, qualification and bidding for the balancing market and capacity auctions.
JEPXSpot and intraday trading in 30-minute products.
METI list of specified wholesale supply businessesPublic register of notified aggregators (181 entries on 30 September 2026).
Electricity Data Management AssociationCertified body through which non-electricity businesses can obtain smart-meter data with customer consent.

Smart meters.

Smart meters.
FactValue
Smart-meter rolloutFirst-generation roll-out to low-voltage customers essentially complete; next-generation meters being installed from FY2025
Reading interval30 minutes
Owner and operatorArea network company (no competitive metering)
Installed baseAbout 80 million smart meters and similar meters nationwide (network companies, June 2022)
Roll-out startFrom 2014 (for example Chubu: October 2014, about 9.8 million by March 2023)
Next generationFrom FY2025 for low voltage, high voltage from late FY2026; schedule differs by company
Meter numberUnified at 10 digits on next-generation meters; current Kansai and Kyushu meters use 7 digits
In-home interface“B route” to a HEMS over 920 MHz wireless; next-generation meters also support 2.4 GHz
Third-party dataWith consent, via the Electricity Data Management Association (certified 30 June 2022)

Japan’s smart meters were rolled out by each network company, not under a national programme with competitive suppliers. Each company owns its meters and its communications network (the “A route”, mainly radio mesh with some mobile links) and collects 30-minute readings for billing, settlement and switching. Customers can ask the network company to open the “B route”, which lets a HEMS read the meter directly every few seconds to minutes. This is how most home energy management and battery-control systems get live data.

Next-generation meters follow standard functions set by METI’s study group in May 2022. They support finer-grained data, remote functions and both 920 MHz and 2.4 GHz B-route radios. They also use a unified 10-digit meter number, and OCCTO changed its switching manual from September 2025 to handle it. The new meters are needed for device-level metering in the balancing market, so where they reach first will shape where home batteries can earn from reserves.

Renewable electricity.

Electricity generation mix (FY2024 (Apr 2024–Mar 2025)).

  • Gas (LNG): 32.2%
  • Coal: 28.1%
  • Oil and other: 7.2%
  • Solar: 9.9%
  • Nuclear: 9.4%
  • Hydro: 7.4%
  • Biomass: 4.2%
  • Wind: 1.2%
  • Geothermal: 0.4%
Source 22
Renewable electricity share
23.6% (2025)Source 43Ember estimate for calendar year 2025, as a share of 1,030 TWh total generation: solar 9.8%, hydro 7.2%, bioenergy 5.3%, wind 1.3%. The government’s official figure for FY2024 (April 2024–March 2025) is 23.1%, including hydro.
Home solar
Not identified from a reliable public source.
Solar added each year
2.61 GW (2025)Source 43Derived: Ember’s 92.21 GW at the end of 2025 minus 89.6 GW at the end of 2024.
Solar PV
92.2 GW (2025)Source 43
Wind
6.24 GW (2025)Source 43
Hydro
28.3 GW (2025)Source 43Ember series; excludes pumped storage generation capacity.
Bioenergy
6.06 GW (2025)Source 43
Nuclear
33.1 GW (2025)Source 43Installed fleet, including reactors not yet restarted.
Gas
82.4 GW (2025)Source 43
Coal
54.6 GW (2025)Source 43

Targets.

  • 7th Strategic Energy Plan (Cabinet decision, February 2025), FY2040 outlook: renewables about 40–50% of generation (solar 23–29%, wind 4–8%, hydro 8–10%, geothermal 1–2%, biomass 5–6%), nuclear about 20% and thermal about 30–40%, with total generation of 1.1–1.2 trillion kWh.
  • Greenhouse-gas reduction of 73% from FY2013 levels by FY2040, and net zero by 2050.
  • Tokyo Metropolitan Government: from April 2025, large housebuilders must fit solar panels on new buildings under 2,000 m² (applies to firms supplying 20,000 m² or more of floor space a year in Tokyo).

Japan’s renewable share has roughly doubled since 2013, mainly because of solar built under the FIT that started in July 2012. Government data show solar generation rising from 12.9 TWh in FY2013 to 98.1 TWh in FY2024, almost a tenth of output. Hydro is long established, and biomass has grown strongly. Wind has lagged: it supplied only 1.2% in FY2024, and large offshore projects are still at an early stage. Nuclear has partly recovered since 2015 as reactors restart, reaching 9.4% in FY2024.

Flat land is scarce and support for new ground-mounted solar ends in FY2027, so growth is moving to rooftops, building-integrated systems and self-consumption. The FY2026 tariffs are designed to speed up rooftop investment, and Tokyo’s new-build mandate does the same in the largest housing market. Integration is now the main constraint: curtailment has spread to every area, and the government is backing batteries, inter-regional links and demand shifting to absorb midday solar.

Energy storage.

Home batteries
1,136,132 systems (cumulative shipments) (end FY2025)Source 44Cumulative shipments of grid-connected stationary lithium-ion battery systems by the 14 companies in JEMA’s statistics, totalling 9.57 GWh. In FY2025, 154,000 systems (1.55 GWh) were shipped, averaging 10.06 kWh. These are mostly home systems, but small commercial units are included and installed totals are not published.
Grid-scale storage
0.64 GW (end Dec 2025)Source 32Grid-scale batteries already connected (high voltage and above), excluding pumped hydro.

Japan has one of the world’s largest home-battery markets. It grew after the 2011 earthquake for backup power and since then for self-consumption once FIT terms expire. Annual shipments of grid-connected stationary battery systems have held around 150,000–160,000 for three years, and the typical system size has risen to about 10 kWh. National DR-linked subsidies and local schemes such as Tokyo’s support purchases.

Grid-scale batteries are growing fast from a small base. Developers are attracted by the balancing market, the long-term decarbonisation auction, wholesale price spreads and local subsidies. The huge connection queue, nearly 200 GW of studies and applications, far exceeds what will be built, and METI is changing the rules to prioritise mature projects.

Storage projects.

  • Long-term decarbonisation auction (bidding year 2025): 20-year capacity contracts signed by August 2026 for 0.819 GW of lithium-ion batteries and existing pumped hydro, and 0.886 GW of other storage, new pumped hydro and long-duration storage.
  • Grid battery connection queue: About 30 GW of grid-scale battery projects had applied for connection contracts and about 172 GW were at the connection-study stage at the end of December 2025, against 0.64 GW connected. METI is reforming connection rules because of the size of the queue.

Electricity suppliers.

Electricity suppliers.
SupplierMarket shareRenewable tariffTime of useDynamicExport tariff
TEPCO Energy Partner—UnknownUnknownUnknownYes
Kansai Electric Power—UnknownYesNoYes
Chubu Electric Power Miraiz—UnknownYesNoYes
Tokyo Gas—YesYesNoYes
Looop—UnknownYesYesUnknown

The ten former regional utilities, now acting directly or through retail subsidiaries, still dominate household supply. In June 2026 new entrants held 25.6% of household lighting contracts and 29.5% of household lighting volume. Utilities operating outside their home area held only 0.4% of contracts. The share of new entrants varies widely by area. In June 2026, 71.3% of low-voltage lighting volume was sold on free tariffs, but in Hokkaido and Tohoku more than a third was still on regulated tariffs.

Company-level market shares are not published by the EGC. Tariff attributes marked Unknown were not checked on the supplier’s own pages.

Key organisations.

Key organisations.
OrganisationCategoryWhat it doesWhy it matters
Agency for Natural Resources and Energy (METI)GovernmentEnergy policy, licensing, FIT/FIP and grid-connection rulesPublishes the Strategic Energy Plan, FIT prices, the energy balance and the registers of retailers, generators and aggregators.
Electricity and Gas Market Surveillance Commission (EGC)RegulatorMarket monitoring and tariff reviewMonthly retail statistics by area, switching data and reviews of network charges.
OCCTOTransmissionCross-regional coordination and marketsDemand forecasts, inter-regional grid plans, capacity and balancing markets, switching system.
TEPCO Power Grid (largest of the ten area network companies)DistributionArea transmission and distribution, metering and connectionGrid-connection applications, output control notices, supply point numbers and smart-meter data are handled by the area company.
Japan Electric Power Exchange (JEPX)MarketWholesale power exchangeSpot and intraday prices by area.
Japan Photovoltaic Energy Association (JPEA)SolarSolar industry associationIndustry guidance and the JP-AC centre that handles FIT applications for systems under 50 kW.
Japan Electrical Manufacturers’ Association (JEMA)StorageManufacturers’ associationPublishes stationary battery and power-conditioner shipment statistics.
Sustainable open Innovation Initiative (SII)StorageSubsidy administratorRuns national subsidy programmes, including the DR-ready home battery scheme.
Japan Electrical Safety & Environment Technology Laboratories (JET)MeteringTesting and certificationVoluntary certification of grid-interconnection protection devices and power conditioners, accepted by network companies.
Electricity Data Management AssociationFlexibilityCertified smart-meter data intermediaryConsent-based access to household smart-meter data for non-electricity businesses.

Technical standards.

Technical standards.
AreaStandardIssued byNotes
Grid connectionGrid-interconnection technical requirements guideline for power quality (電力品質確保に係る系統連系技術要件ガイドライン), revised 1 December 2024METI (Agency for Natural Resources and Energy)Sets voltage-class limits (under 50 kW low voltage, under 2,000 kW high voltage), power factor, voltage-rise control, protection and anti-islanding requirements. Network companies’ detailed rules and the Japan Electric Association’s grid-interconnection code (JEAC 9701) build on it.
Inverters / anti-islandingJET grid-interconnection protection device certificationJETVoluntary third-party certification of power conditioners and protection functions for small distributed generation. Network companies accept the certificate in place of detailed technical documents.
Electrical safetyElectricity Business Act technical standards; size bands for solar (under 10 kW, 10–50 kW, 50 kW and above)METI industrial safetyUnder 10 kW: duty to meet technical standards, no filings. 10–50 kW: basic-information notification and pre-use self-check (since 20 March 2023). 50 kW and above: safety regulations and a chief electrical engineer.
Installer qualificationElectrician Act (電気工事士法)METI; licences issued by prefecturesWiring of home solar, batteries and other general electrical facilities must be done by a first- or second-class licensed electrician. There is no separate national solar-installer accreditation.
Fire safety of batteriesFire Service Act ministerial ordinance and municipal fire-prevention ordinances (kWh-based rules from 1 January 2024)Fire and Disaster Management Agency; municipalitiesUp to 10 kWh: outside the rules. Over 10 kWh to 20 kWh: fire standards or a JIS standard. Over 20 kWh: fire standards and notification to the fire department.
Smart-meter interfaceB-route (920 MHz wireless; 2.4 GHz on next-generation meters) to HEMSNetwork companies, following METI’s next-generation smart meter study groupUsed by home energy management systems and battery controllers to read live meter data.
Aggregator cybersecurityCybersecurity guideline for specified wholesale supply businesses; ERAB security guidelineMETIMust be met by notified aggregators that control customer resources.

Permissions.

Permissions.
PermissionRequiredLevelDetail
Grid connection approval (network company)YesRegionalApplication to the area network company for any system that will run in parallel with the grid. Export needs a reverse-flow connection, and the company may set conditions on voltage control or output-control equipment.
FIT business-plan certificationLimitedNationalOnly needed to receive the FIT price. Applications for solar under 50 kW are handled via JP-AC.
Building permission / planningLimitedLocalOrdinary rooftop panels on a house do not normally need building confirmation. Local landscape ordinances, historic districts and some municipal solar ordinances can impose design or notification rules, especially for ground-mounted systems.
Landlord or condominium association consentLimitedLocalNeeded for rented homes and for shared roofs or common areas of apartment buildings.
Electrical safety notificationLimitedNationalNot needed for solar under 10 kW. For 10–50 kW, a basic-information notification and pre-use self-check are needed. At 50 kW and above, safety regulations and a chief electrical engineer are required.
Fire department notification for batteriesLimitedLocalOnly for battery installations above 20 kWh; typical home batteries (about 10 kWh) are below this.
Tokyo new-build solar requirementLimitedRegionalSince April 2025, large housebuilders must meet solar installation targets across the new buildings under 2,000 m² they supply in Tokyo. The duty falls on the builder, not the individual buyer, and existing buildings are excluded.

For a typical home solar and battery system there is no national planning permit. The key gate is the area network company’s connection approval, followed by FIT certification if the owner wants the feed-in tariff. Electrical safety obligations depend on system size, and battery fire rules depend on stored energy. Local rules matter more for ground-mounted and larger systems, many of which now face municipal solar ordinances.

Support schemes, taxes and incentives.

Support schemes, taxes and incentives.
SchemeStatusTypeDetailPeriod
Feed-in tariff for residential solar (under 10 kW), initial investment support schemeActiveFeed-in tariff24 yen/kWh for years 1–4, then 8.3 yen/kWh for years 5–10, for surplus power. It applies to certifications from October 2025 and in FY2026, with FY2027 set on the same basis. The surplus is bought for 10 years under the FIT purchase contract.Oct 2025 – Mar 2028
FIT/FIP for rooftop commercial solar (10 kW and above)ActiveFeed-in tariff19 yen/kWh for years 1–5, then 8.3 yen/kWh to year 20. Rooftop projects are exempt from auctions. Ground-mounted solar is no longer supported for new certifications from FY2027.Oct 2025 – Mar 2028
DR-ready home battery subsidy (FY2025 supplementary budget)ClosedGrantUp to 3/10 of equipment and installation cost, capped at 600,000 yen per application, for home batteries whose owners sign a DR contract with an aggregator or retailer until 31 March 2027. Applications opened on 24 March 2026, with a scheduled end of 10 December 2026. Secondary reports say the budget of about 5.4 billion yen was used up and applications closed on 29 May 2026.Mar – May 2026
Tokyo Metropolitan Government residential solar subsidiesActiveGrantNew Tokyo Zero Emission homes: 120,000 yen/kW up to 360,000 yen (100,000 yen/kW above 3.6 kW). Existing homes: 150,000 yen/kW up to 450,000 yen (120,000 yen/kW above 3.75 kW). There are separate Tokyo schemes for batteries and panel recycling.—
Electricity and gas bill support (July–September 2026 usage)ClosedBill discountAutomatic discount of 3.5, 4.5 and 3.5 yen/kWh on low-voltage supply for July, August and September 2026 usage, applied by retailers. No later round had been announced at the time of checking.Jul – Sep 2026

Data and connectivity.

Fixed broadband
97.1 % of households (end FY2023)Source 52Fibre-optic (FTTH) household coverage. The estimation method was revised, so it is not comparable with earlier years.
4G coverage
Not identified from a reliable public source.
5G coverage
98.6 % of population (end FY2025 (31 Mar 2026))Source 51Range by prefecture 89.2%–99.9%. The target is 99% nationally and in every prefecture by the end of FY2030.

Smart meters do not rely on household broadband. Each network company runs its own A-route network, mostly radio mesh with mobile links in sparse areas, and household devices connect locally over the B route. Home batteries, heat-pump water heaters and EV chargers sold for DR are normally linked to the aggregator’s cloud over the home’s broadband and use the ECHONET Lite protocol commonly used in Japanese HEMS. Fibre and 5G coverage are near-universal, so connectivity is rarely a barrier to remote control of home assets.

Grid conditions.

National peak demand
158.8 GW (FY2025 summer)Source 33Sum of the ten areas’ summer peak demand at the sending end (158,815 MW actual), not a simultaneous national peak. Tokyo alone was 54.5 GW. OCCTO expects 164.6 GW by FY2035.
Annual electricity demand
843.4 TWh (FY2025 (estimated actual))Source 33Sending-end demand (843,389 GWh). Usage-end demand was 803.4 TWh, of which household and other low-voltage demand was 293.4 TWh.
Generation capacity
322.9 GW (2025)Source 43Derived: Ember’s clean capacity (165.89 GW) plus fossil capacity (157.02 GW).
Interconnection
2.1 GW (2026)Source 34East–west (50/60 Hz) frequency-converter capacity, the main internal bottleneck. It is due to rise to 3.0 GW in December 2028. Japan has no international interconnectors.
Curtailment
1.6 TWh (FY2024)Source 31Derived: the sum of area figures for curtailed variable renewables in METI’s March 2026 paper, about 16.0 億kWh. Kyushu had the highest rate (4.8%, 0.75 TWh). For FY2025 the network companies forecast a 6.1% rate in Kyushu.

Demand had been flat or falling for a decade, but OCCTO now expects it to grow slowly to FY2035 because of semiconductor plants, even as household demand falls. Peak demand comes in summer heatwaves, with a winter peak in the north. Supply has been tight at times, and the government has issued supply-shortage warnings in severe cold or heat.

Midday solar surpluses are now a nationwide issue. Kyushu has curtailed renewables regularly since 2018, and Tokyo, the last area without curtailment, carried out its first on 1 March 2026. The planned expansions of the Tohoku–Tokyo link, the east–west converters, the Hokkaido–Honshu link and later Chubu–Kansai and Chugoku–Kyushu are meant to share renewable output between areas. Batteries and demand shifting are the near-term tools.

Grid and capacity maps.

Regulatory changes.

Regulatory changes.
ChangeStatusDateDetail
Low-voltage resources in all balancing productsCurrentFY2026 (from April 2026)Aggregated low-voltage resources can bid into all balancing-market products, and device-level metering is allowed for low-voltage resources with next-generation smart meters.
Next-generation smart metersCurrentFrom FY2025Phased replacement of first-generation meters, with a unified 10-digit meter number and dual-band B-route. High-voltage next-generation meters start from the second half of FY2026.
Renewable surcharge 4.18 yen/kWhCurrentMay 2026 – April 2027 meter readingsSet by METI in March 2026. It costs 1,672 yen a month for a 400 kWh household.
Front-loaded FIT for rooftop solarCurrentOctober 2025 – FY2027Residential under 10 kW: 24 yen/kWh for four years, then 8.3 yen/kWh. Rooftop 10 kW and above: 19 yen/kWh for five years, then 8.3 yen/kWh.
End of FIT/FIP support for new ground-mounted solarUpcomingFY2027 (from April 2027)New ground-mounted commercial solar (10 kW and above) will no longer be certified, apart from FY2026 auction winners.
High-voltage device-level metering in the balancing marketUpcomingFY2027Extends device-level metering to high-voltage resources under 1,000 kW.
Inter-regional grid reinforcementsUpcomingNovember 2027 – March 2039Tohoku–Tokyo to 10.28 GW (November 2027); Hokkaido–Honshu to 1.2 GW (end of FY2027); east–west converters to 3.0 GW (December 2028); Chubu–Kansai to about 6 GW (June 2030); Chugoku–Kyushu reinforcement (March 2039).
7th Strategic Energy Plan FY2040 outlookUpcomingFY2040Renewables about 40–50%, nuclear about 20% and thermal about 30–40% of generation.

Market indicators.

Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.

Market indicators.
IndicatorLevelBasis
Electricity costMediumLow below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros).
Household electricity useMediumLow below 2,500 kWh a year, high at 5,000 kWh or more (average use per household).
Renewable shareLowLow below 30%, high at 60% or more (renewable share of electricity).
Smart-meter adoption—Low below 30%, high at 80% or more (share of meters that are smart).
Home solar adoptionHighNetwork companies reported 77.4 GW of solar connected at the end of March 2025, much of it small-scale. Detached houses are 52.7% of occupied dwellings, the FY2026 FIT for home systems is front-loaded at 24 yen/kWh, and Tokyo requires solar on new homes from large builders. No official count of residential systems was found.
Distributed energy marketHigh181 notified aggregators (September 2026), over 1.1 million grid-connected home battery systems shipped, heat-pump water heaters in 16.8% of homes, and consent-based smart-meter data access since 2022.
Grid flexibility marketMediumBalancing, capacity and long-term decarbonisation markets exist and accept aggregated resources, but low-voltage access to all balancing products only began in FY2026 and depends on next-generation meters.
Energy storage adoptionHighJEMA counts 1.14 million grid-connected stationary battery systems shipped (9.57 GWh) and 154,000 in FY2025. Grid-scale batteries were 0.64 GW connected at the end of 2025, with about 30 GW applying for connection.
Renewable growth environmentMediumRenewable share rose from 10.9% (FY2013) to 23.1% (FY2024), and solar additions slowed to about 2.6 GW in 2025. The FY2040 target is 40–50%.

Sources.

Public sources used for this profile, with the date each was accessed.

Show all 55 sources
  1. Population Estimates, monthly report (September 2026). Statistics Bureau of Japan, 2026. accessed 1 October 2026.
  2. 2025 Population Census: preliminary counts summary. Statistics Bureau of Japan, 2026. accessed 1 October 2026.
  3. 2023 Housing and Land Survey: basic tabulation summary. Statistics Bureau of Japan, 2024. accessed 1 October 2026.
  4. Family Income and Expenditure Survey: 2025 average results (households of two or more). Statistics Bureau of Japan, 2026. accessed 1 October 2026.
  5. Household CO2 Emissions Survey: year-on-year comparison of main items FY2017–FY2023. Ministry of the Environment, 2025. accessed 1 October 2026.
  6. Consumer Confidence Survey (July 2026): ownership of major durable goods. Cabinet Office, Economic and Social Research Institute, 2026. accessed 1 October 2026.
  7. Passenger car sales by fuel type and maker, April 2025–March 2026. Japan Automobile Dealers Association, 2026. accessed 1 October 2026.
  8. Urban population (% of total population) – Japan. World Bank, 2025. accessed 1 October 2026.
  9. Fuel-cost adjustment for October 2026 electricity bills (model bill for 従量電灯A). Kansai Electric Power, 2026. accessed 1 October 2026.
  10. Fuel-cost adjustment for October 2025 electricity bills. Kansai Electric Power, 2025. accessed 1 October 2026.
  11. Fuel-cost adjustment for October 2024 electricity bills. Kansai Electric Power, 2024. accessed 1 October 2026.
  12. Fuel-cost adjustment for October 2023 electricity bills. Kansai Electric Power, 2023. accessed 1 October 2026.
  13. Fuel-cost adjustment for October 2022 electricity bills. Kansai Electric Power, 2022. accessed 1 October 2026.
  14. Fuel-cost adjustment for October 2021 electricity bills. Kansai Electric Power, 2021. accessed 1 October 2026.
  15. Euro foreign exchange reference rates: Japanese yen. European Central Bank, 2026. accessed 1 October 2026.
  16. Status of electricity trading (June 2026). Electricity and Gas Market Surveillance Commission, 2026. accessed 1 October 2026.
  17. Full retail liberalisation of electricity and city gas (explainer, December 2016). Electricity and Gas Market Surveillance Commission, 2016. accessed 1 October 2026.
  18. Exception to legal unbundling for Okinawa Electric Power. Electricity and Gas Market Surveillance Commission, 2018. accessed 1 October 2026.
  19. FIT/FIP purchase prices from FY2026 and FY2026 surcharge. METI, 2026. accessed 1 October 2026.
  20. FIT/FIP purchase prices and periods (FY2026 onwards). Agency for Natural Resources and Energy, 2026. accessed 1 October 2026.
  21. Special approvals for electricity and gas bill discounts, July–September 2026 usage. METI, 2026. accessed 1 October 2026.
  22. Energy supply and demand results for FY2024 (final). Agency for Natural Resources and Energy, 2026. accessed 1 October 2026.
  23. The 7th Strategic Energy Plan (outline). Agency for Natural Resources and Energy, 2025. accessed 1 October 2026.
  24. List of registered retail electricity businesses (30 September 2026). Agency for Natural Resources and Energy, 2026. accessed 1 October 2026.
  25. List of notified generation businesses (30 September 2026). Agency for Natural Resources and Energy, 2026. accessed 1 October 2026.
  26. Notification duty for specified wholesale supply businesses. Agency for Natural Resources and Energy, 2026. accessed 1 October 2026.
  27. List of notified specified wholesale supply businesses (30 September 2026). Agency for Natural Resources and Energy, 2026. accessed 1 October 2026.
  28. Grid-interconnection technical requirements guideline for power quality (1 December 2024). Agency for Natural Resources and Energy, 2024. accessed 1 October 2026.
  29. Guide to installing solar power generation equipment (safety rules by size). METI, 2026. accessed 1 October 2026.
  30. Small-scale business electrical facilities (from 20 March 2023). METI Hokkaido Industrial Safety and Inspection Department, 2023. accessed 1 October 2026.
  31. Long-term outlook for renewable output control (16 March 2026). Agency for Natural Resources and Energy, 2026. accessed 1 October 2026.
  32. Measures for faster grid connection of grid-scale batteries and other plant (27 March 2026). Agency for Natural Resources and Energy, 2026. accessed 1 October 2026.
  33. National electricity demand forecast (January 2026). OCCTO, 2026. accessed 1 October 2026.
  34. Progress of cross-regional grid development plans (FY2025 Q4). OCCTO, 2026. accessed 1 October 2026.
  35. Device-level metering and low-voltage resources in the balancing market (from FY2026). OCCTO, 2025. accessed 1 October 2026.
  36. Issues in device-level metering in the balancing market (13 November 2025). OCCTO, 2025. accessed 1 October 2026.
  37. Long-term decarbonisation auction: capacity contract results (bidding year 2025). OCCTO, 2026. accessed 1 October 2026.
  38. Switching manual changes for next-generation smart meters (19 June 2025). OCCTO, 2025. accessed 1 October 2026.
  39. Switching support system: frequently asked questions. OCCTO, 2023. accessed 1 October 2026.
  40. What do the digits of the supply point specific number mean? (FAQ No. 464). Hokuriku Electric Power Transmission & Distribution, 2024. accessed 1 October 2026.
  41. Completion of smart meter installation (15 May 2023). Chubu Electric Power Grid, 2023. accessed 1 October 2026.
  42. Participation in the Electricity Data Management Association and its certification (30 June 2022). The ten general transmission and distribution companies (via Kyushu Electric Power), 2022. accessed 1 October 2026.
  43. Japan: electricity data and country profile (yearly data to 2025). Ember, 2026. accessed 1 October 2026.
  44. JEMA stationary storage system statistics: FY2025 shipments. Japan Electrical Manufacturers’ Association, 2026. accessed 1 October 2026.
  45. DR-ready home battery subsidy (FY2025 supplementary budget) flyer. Sustainable open Innovation Initiative, 2026. accessed 1 October 2026.
  46. Battery subsidies 2026 summary (DR subsidy budget reached 29 May 2026). Hojyokin Portal, 2026. accessed 1 October 2026.
  47. Solar panel installation requirement starts April 2025. Tokyo Metropolitan Government, 2025. accessed 1 October 2026.
  48. Tokyo subsidies for solar installation (solar portal). Tokyo Metropolitan Government Bureau of Environment, 2026. accessed 1 October 2026.
  49. Revision of fire-prevention ordinance for battery installations (kWh-based rules from January 2024). Oiso Town (Kanagawa), 2023. accessed 1 October 2026.
  50. Reference materials on storage and JET grid-interconnection certification (10 November 2023). Cabinet Office, Task Force on Renewable Energy Regulatory Reform, 2023. accessed 1 October 2026.
  51. Publication of 5G development status (as at the end of FY2025). Ministry of Internal Affairs and Communications, 2026. accessed 1 October 2026.
  52. White Paper on Information and Communications 2026: infrastructure status. Ministry of Internal Affairs and Communications, 2026. accessed 1 October 2026.
  53. Electricity tariff menu (household). Chubu Electric Power Miraiz, 2026. accessed 1 October 2026.
  54. Tokyo Gas electricity plans. Tokyo Gas, 2026. accessed 1 October 2026.
  55. Looop Denki tariff plans (Smart Time ONE). Looop, 2026. accessed 1 October 2026.

Questions about energy in Japan.

Talk to us about Olmack in Japan.Tell us about your home, housing portfolio or school estate in Japan. We'll explain what is possible there now.