How electricity works in Lesotho.
Lesotho electricity 2026: LEC prepaid STS supply, LEWA regulation, ’Muela hydro, Ramarothole solar, imports from Eskom and EDM, licensing and access targets.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Lesotho loti (plural maloti) (LSL) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Lesotho energy at a glance.
Key figures for households in Lesotho. Each one links to its source on the full overview below.
Selling back to the grid.
Can homes export electricity? No. Details are in the export section below.
Four things to check in Lesotho.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Lesotho below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Lesotho requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Lesotho.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Lesotho, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Lesotho, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Lesotho.
The energy market in Lesotho, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 10 October 2026.
On this page22 sections
Lesotho has a small, state-owned power sector built around one utility and one large hydro station. The Lesotho Electricity Company (LEC), wholly owned by the Government of Lesotho, holds a composite licence to transmit, distribute and supply electricity and is the only retail supplier in the country. It buys power from the 72 MW ’Muela hydropower station run by the Lesotho Highlands Development Authority (LHDA), from Eskom in South Africa and from Electricidade de Moçambique (EDM).
The sector is regulated by the Lesotho Electricity and Water Authority (LEWA), established under the Lesotho Electricity Authority Act 2002, which licenses generation, transmission, distribution, supply, import and export, and approves LEC’s tariffs. Lesotho is a member of the Southern African Power Pool through LEC.
Access to electricity is still limited: the World Bank estimates 60.6% of the population had access in 2024 (85.2% in towns, 41.4% in rural areas). The government’s stated aim is universal access by 2030, pursued through grid extension, mini-grids and solar home systems. New local generation is arriving mainly as solar: a 30 MW plant at Ha Ramarothole in Mafeteng was handed over in 2023, and work on a 50 MW second phase with an 8 MW battery began in July 2026.
Energy snapshot.
Headline figures for electricity in Lesotho. Each shows its data year and links to its source.
- Population2,363,325 peopleSource 12025
- HouseholdsNot identified from a reliable public source.
- Average household sizeNot identified from a reliable public source.
- Electricity use per householdNot identified from a reliable public source.
- Household price (LSL)Not identified from a reliable public source.
- Household price (EUR)Not identified from a reliable public source.
- Renewable electricity shareNot identified from a reliable public source.
- Solar capacity0.03 GWSource 302023
- Wind capacity0 GWSource 142026
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Single buyer
- Homes can export to the grid
- No
- Home equipment in grid services
- No
- Regulator
- Lesotho Electricity and Water Authority (LEWA)
- System operator
- Lesotho Electricity Company (LEC)
- Distribution networks
- LEC is the single national distributor and supplier under a composite licence
- Currency
- Lesotho loti (plural maloti) (LSL)
- Voltage and frequency
- 220 V single-phase / 380 V three-phase supply points
Electricity prices in Lesotho.
- Household price (LSL)
- Not identified from a reliable public source.
- Household price (EUR)
- Not identified from a reliable public source.
- Typical annual electricity bill
- Not identified from a reliable public source.
How prices are set
LEC files tariff applications with LEWA under the Tariff Filing and Review Procedure (2012), and LEWA decides them using its published tariff-setting methodology, public consultation guidelines and, since 2016, a pass-through mechanism for costs outside LEC’s control such as bulk power purchases. LEWA’s most recent determination is a multi-year tariff decision covering 2023/24 to 2025/26.
Past decisions show the pattern. For 2022/23 LEC asked for 12.32%; LEWA allowed 7.85% on energy and maximum-demand charges for all customer categories from 1 December 2022, approving revenue of M1.28 billion against M1.478 billion requested, after a 10% rise in 2021/22. Connection, wiring-test, survey and similar fees were left unchanged.
Reform under way
In August 2026 LEWA held a two-day stakeholder workshop in Maseru, supported by the African Development Bank, on a cost-of-service study and proposed changes to the electricity tariff structure. LEWA framed the exercise as balancing LEC’s financial sustainability with affordability, linked to the Mission 300 access programme.
Prices are uniform nationally. LEWA has reported rising meter tampering, which it links to the perceived cost of electricity, and treats bypassing meters as a criminal offence.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Prepayment | Yes | The standard arrangement for households. New domestic connections are registered for prepayment, and customers buy 20-digit STS tokens through LEC sales agents, banks (FNB, Standard Lesotho Bank, Nedbank, Post Bank), M-Pesa, EcoCash and third-party vendor networks. |
| Regulated | Yes | All tariffs – energy charges, maximum-demand charges and connection-related fees – are approved by LEWA on LEC’s application. The current schedule covers the 2024/25 and 2025/26 financial years under a multi-year tariff determination for 2023/24–2025/26. |
| Other | Limited | Large industrial and commercial customers are credit-metered with programmable meters and pay maximum-demand charges in addition to energy charges. |
| Fixed | No | There is one supplier and prices are set by the regulator; competitive fixed-price contracts do not exist. |
| Dynamic | No | No wholesale-indexed retail tariffs exist. |
Household prices compared with neighbouring countries (EUR per kWh).
- South Africa€0.185
- Eswatini€0.154
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- Not identified from a reliable public source.
- Average daily use per household
- Not identified from a reliable public source.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- Not identified from a reliable public source.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- Not identified from a reliable public source.
Electricity use is shaped above all by limited access. In 2024 the World Bank put access at 60.6% of the population – 85.2% in urban areas but only 41.4% in rural areas, where many villages are in mountainous terrain far from the grid. A LEWA article in 2025 cited about 47% of households having access and noted that the government had missed its target of 75% household electrification by 2022.
New connections are being added in small batches. LEC reports electrifying more than 740 households at Mokema in 2025 in a fully government-funded scheme costing over M22 million, and lists dozens of further village projects funded by the government and LHDA. Under Mission 300 and the World Bank-backed ASCENT programme the government plans to reach about 14,000 households with an M800 million budget over four years.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- Not identified from a reliable public source.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- Not identified from a reliable public source.
- Apartments and flats
- Not identified from a reliable public source.
- Urban population
- 44.7 % of population (2025)Source 1
Lesotho’s settlement pattern matters for electricity: the lowlands in the west hold the main towns, including Maseru, while highland villages are scattered and expensive to reach by line. Two highland districts, Qacha’s Nek and Mokhotlong, are still not connected to the national grid; Qacha’s Nek has been supplied directly from Eskom since 1996 and Mokhotlong from the Letšeng mine network since 2003.
Detailed housing and tenure statistics from the 2026 census were not yet published at the time of writing.
How the grid works in Lesotho.
- TransmissionLesotho Electricity Company (LEC), LEC
- DistributionLEC is the single national distributor and supplier under a composite licence
- MeteringLEC
- Supply1 or more retail suppliers
Physical flow
Power enters the grid from the ’Muela hydropower station (three 24 MW units, in service since January 1999), which uses water passing from Katse Dam through the Lesotho Highlands Water Project transfer tunnel on its way to South Africa; from the 30 MW Ramarothole solar plant in Mafeteng; from a few small hydro stations such as Semonkong and Mantšonyane; and from imports from Eskom and EDM. LEC carries it over 132 kV, 88 kV, 66 kV and 33 kV lines to 45 substations and on to 11 kV and low-voltage networks.
Before ’Muela was built, Lesotho depended entirely on South Africa for electricity. In 2023 the then Minister of Energy said the country had only 72 MW of its own capacity and needed some 200 MW more; the current Minister of Energy has since said Lesotho produces about half the electricity it consumes.
Commercial flow
There is no wholesale market. LEC acts as single buyer: LHDA’s generation licence obliges it to sell ’Muela’s output to LEC, solar generators sell to LEC, and the rest is imported under bilateral arrangements with Eskom and EDM. LHDA publishes summaries of electricity it bills to LEC and to Eskom alongside its water royalty statements.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry of Energy (Department of Energy) | Sets energy policy and runs rural electrification through its Rural Electrification Unit; owns the Ramarothole solar programme through the Lesotho Electricity Generation Company. |
| Regulator | Lesotho Electricity and Water Authority (LEWA) | Licenses generation, transmission, distribution, supply, import and export; approves LEC tariffs and charges; issues the Grid Code, Grid Connection Code and Distribution Grid Code and quality-of-service standards; handles escalated complaints. |
| TSO | Lesotho Electricity Company (LEC) | Runs the 132 kV, 88 kV, 66 kV and 33 kV transmission network and 45 substations; reports transmission availability above 99%. |
| System operator | LEC | Balances the system as the single buyer, combining ’Muela hydro, local solar and small hydro with imports from Eskom and EDM. |
| DSO | LEC Transmission & Distribution | Steps power down to 11 kV and to 220 V/380 V customer supply points; surveys, quotes for and builds new connections; reports about 95% availability on the distribution network. |
| Supplier | LEC | Sole retail supplier, selling prepaid electricity to households and credit-metered supply to large customers at LEWA-approved tariffs. |
| Metering | LEC | Owns and installs meters and runs the prepayment vending system, with a master station at head office and vending access points. |
| Exchange | Southern African Power Pool (SAPP) | Regional power pool; LEC is listed as Lesotho’s member utility. |
Compared with the UK system.
| UK concept | Lesotho equivalent | How it works |
|---|---|---|
| DNO | LEC (single national network) | There are no regional network companies. LEC owns and runs the whole distribution network and is also the retailer, so the network operator and the supplier are the same company. Its composite licence gives it exclusivity within 3.5 km of its existing distribution system. |
| National Grid/NESO | LEC transmission | LEC also owns the transmission network and dispatches supply. Unlike NESO, it is the buyer of all bulk power: the ’Muela station’s licence requires its output to be sold to LEC, and LEC contracts imports from Eskom and EDM. |
| MPAN | Prepaid meter number | There is no national supply-point number independent of the meter. A home is identified by the number of its STS prepaid meter, which is used to buy every token. |
| MPRN | No equivalent | Lesotho has no piped gas network for homes and no gas supply-point register. |
| Meter operator | LEC | LEC supplies, installs and tests meters itself; customers can ask LEC to test a meter they believe is inaccurate. |
| Supplier | LEC (single supplier) | Households cannot switch supplier; LEWA approves one national set of tariffs. |
| Smart-meter infrastructure | Offline STS prepaid meters | There is no DCC-style communications network. Household meters are stand-alone keypad meters; only large credit-metered customers have programmable meters, read with hand-held units while remote reading is developed. |
How a supply point is identified.
04123456789 (fictional)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Prepaid meter number (Meter No.) |
| Who issues it? | LEC (each STS prepayment meter has its own number; LEC registers the customer against it when the connection is commissioned) |
| Format | Numeric meter number printed on the meter, quoted when buying electricity; each purchase returns a 20-digit STS token keyed into the meter |
| Length | Not published |
| Stays with the property when you switch supplier? | Yes |
| Where to find it | On the front of the prepaid meter and on token receipts from vendors, banks and mobile-money purchases. |
| Electronic access | Tokens can be bought by meter number through M-Pesa, EcoCash, bank channels and vendor networks. Meters are not connected to LEC, so units cannot be loaded remotely and there is no online consumption data for households. |
| Third-party access | Anyone who knows the meter number can buy units for it. There is no regulated regime for third parties to access consumption data. |
| Who keeps the register | LEC’s customer and prepayment vending system (master station at head office) |
| Register scope | National |
How a home is identified
For almost every household the practical identifier of a supply point is the number of its STS prepayment meter. LEC uses Cashpower, Ecolec, Conlog and Plessey meters, all built to the Standard Transfer Specification so that tokens from any vending point work in any meter. The customer quotes the meter number at a vendor, bank or mobile-money menu and receives a 20-digit token to type into the meter’s keypad; the display then shows remaining credit and the rate of consumption. Supply disconnects automatically when credit runs out and reconnects when a token is loaded.
How a connection is created
A new domestic connection goes through six steps: a registered electrician tests the wiring and completes LEC Forms A and B; the customer applies for a survey (M100) with the wiring certificate and ID; LEC issues a quotation valid for 60 days; the customer pays for the service connection (M500, or 60% if the quotation exceeds M2,000) and LEC connects within about six weeks; LEC commissions the installation within seven working days; and the customer is registered for prepayment within 24 hours. LEWA’s quality-of-service rules require a quotation within ten working days where infrastructure already exists, and supply within one month on an existing network, two months for a low-voltage extension and four months for a medium-voltage extension.
Moving home
The meter belongs to the installation. LEWA explains that a customer who relocates asks LEC to settle the account and disconnect the old site, and applies for a new connection at the new address; credit cannot be transferred between addresses, so remaining units should be used before moving.
Who keeps the register
There is no independent data hub. LEC holds the customer, meter and vending records for the whole national grid, and LEWA monitors LEC through monthly reports and the Urban (2006) and Rural (2008) Electricity Quality of Service and Supply Standards.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | No |
| Net metering | No |
| Net billing | No |
| How exported electricity is paid | No household export scheme identified: neither LEWA nor LEC publishes net-metering rules, feed-in tariffs or an export application process. |
| Is there net metering in Lesotho? | No published net-metering or net-billing scheme was identified on LEWA’s or LEC’s websites, and a search of LEWA’s site for “net metering” returned nothing. |
| Which technical codes apply to generators? | LEWA publishes a Lesotho Grid Code, a Lesotho Grid Connection Code and a Lesotho Distribution Grid Code setting planning, operation and connection standards. |
| Does a household need a licence to generate? | Generally no: LEWA’s licence rules allow exemption for generation not exceeding 2 MW and for electricity generated and used on the same site. |
Connecting a home system.
- Self-generation for use on the same premises falls within LEWA’s licence exemptions; check with LEWA if the system exceeds 2 MW or supplies anyone else.
- Any connection to LEC’s network must follow the Lesotho Grid Connection Code and Distribution Grid Code, so contact LEC before connecting a grid-tied system.
- Larger generators selling to LEC need a LEWA generation licence and an agreement with LEC as single buyer.
Rooftop solar in Lesotho is used mainly to cut purchases from the grid or as back-up. LEWA promotes urban renewable energy, including rooftop PV and solar water heaters (it estimates a 50-litre solar geyser costs about M10,000), but notes that funding and suitable technology remain barriers. No framework for crediting household exports had been published as of October 2026, and the regulator mentions standardised agreements for renewable projects only in general terms.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity (own use / small scale) | May be exempted from licensing where generation does not exceed 2 MW, or where electricity is generated and used on the same premises; exemptions can carry conditions | LEWA | Licence Application Rules (LEA (Application for Licences) Rules 2012). |
| Generate electricity for sale | Generation licence | LEWA | LHDA holds a generation licence for ’Muela, whose output must be sold to LEC; LEGCO’s 30 MW Ramarothole plant holds a 30-year generation licence; NEO 1’s 20 MW plant has a conditional licence. |
| Store electricity | No separate storage licence category or threshold identified; storage at generating plants is part of the generation project | LEWA | The 8 MW battery at Ramarothole Phase II is part of the government solar project. |
| Export surplus to the grid | No household export framework identified | LEWA; LEC | Grid connection must comply with the Grid Connection Code. |
| Transmit, distribute and supply | Licence required; LEC holds a composite transmission, distribution and supply licence with exclusivity within 3.5 km of its existing network | LEWA | Distribution not exceeding 50 kW for domestic consumption may be exempted. |
| Sell / supply electricity to others | Supply licence, unless exempt (e.g. supplying a single consumer on the same premises as the generating station) | LEWA | |
| Mini-grids | Licence or exemption; LEWA has granted provisional licence exemptions for the Motete and Linakeng mini-grids, and the Department of Energy holds an exemption for electricity access pilot projects | LEWA | Mini-grids are one of the three delivery routes under Mission 300/ASCENT. |
| Import or export electricity across borders | Licence required | LEWA | LEC imports from Eskom and EDM. |
| Wholesale trading | No domestic wholesale market or trading licence exists | LEWA | LEC participates in SAPP as Lesotho’s member utility. |
| Balancing and grid services | No ancillary-services market or framework identified | LEWA; LEC | |
| Aggregation / virtual power plants | Not recognised; no licence category or market access | LEWA | |
| Remote control of customer assets | No specific rules identified; household meters are offline | LEC | |
| Electrical installation work | Wiring must be tested by an electrician who completes LEC Forms A and B before a connection; LEC registers contractors (including a Category D class for electricians under 35) | LEC; Department of Energy | No national solar-installer accreditation scheme identified. |
Under the Lesotho Electricity Authority Act 2002 and LEWA’s 2012 licence application rules, generation, transmission, distribution, supply, import and export require a licence. The exemption list is broad for small actors: generation up to 2 MW, distribution up to 50 kW for domestic use, on-site supply, supply to a single consumer on the same premises, and anyone else LEWA chooses to exempt, with conditions where appropriate.
In practice there are few licensees: LEC’s composite licence, LHDA’s generation licence for ’Muela, and licences for the new solar plants at Ha Ramarothole. LEWA notes that the proposed 60 MW Hirundo wind farm had not yet applied for a licence by January 2026.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| SAPP regional markets | No | — | No | Southern African Power Pool. Only member utilities such as LEC take part; distributed assets have no access. |
| Ancillary services / demand response | No | — | No | LEC. No ancillary-services or demand-response programme for distributed assets identified. |
Distributed assets cannot earn money from flexibility in Lesotho. There is no aggregator role, no balancing or capacity market and no household export scheme; balancing is LEC’s job, using ’Muela hydro and imports. The first grid battery – 8 MW at Ramarothole Phase II – is a state project intended to shift solar output into the evening.
Flexibility and aggregation platforms.
| Platform or aggregator | What it does |
|---|---|
| Southern African Power Pool | Regional pool in which LEC is Lesotho’s member. |
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | No smart-meter roll-out identified; households use offline STS prepaid meters |
| Reading interval | Not applicable (household meters are not remotely read) |
| Household metering | STS prepayment keypad meters (Cashpower, Ecolec, Conlog, Plessey) |
| Token format | 20 digits |
| Meter owner | LEC |
| Large customers | Credit meters (Enermax, Enermax Plus, Elster) with load profiling; read by hand-held units |
| Remote reading | Under development for large-customer online billing |
LEC’s prepayment system consists of the meters, a master station at head office and vending points. Because the household meters are stand-alone, LEC receives no interval data from homes. Large industrial and commercial customers have programmable credit meters that record load profiles and quality of supply; LEC downloads these with hand-held units and is developing remote reading to support online billing. LEWA notes tampering methods including bypassing, magnets and electronic interference.
Renewable electricity.
- Renewable electricity share
- Not identified from a reliable public source.
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- Not identified from a reliable public source.
- Hydro (’Muela)
- 0.072 GW (2026)Source 28Three 24 MW Francis turbines, delivering power since January 1999. Small LEC/government hydro stations (e.g. Semonkong, 220 kW) are excluded.
- Solar PV
- 0.03 GW (2023)Source 30Ramarothole Phase I. The 20 MW NEO 1 plant held a conditional licence; status unconfirmed.
- Wind
- 0 GW (2026)Source 14
Targets.
- Universal electricity access by 2030 (Mission 300 / ASCENT).
- 1,000 MW of clean energy generation by 2030, as reported by LEWA (an earlier target of 200 MW of renewable capacity by 2024).
- Ramarothole solar expanded from 30 MW to 80 MW with an 8 MW battery (Phase II launched July 2026).
A reliable annual generation mix was not identified from an official or statistical source, so no shares are shown. Domestic generation is hydro and solar: ’Muela (72 MW) runs on water transferred from Katse Dam for South Africa, Ramarothole Phase I (30 MW) has operated since 2023, and small hydro stations serve remote towns. The energy minister’s statement that Lesotho produces about 50% of its consumption implies roughly half of supply is imported, largely from South Africa’s coal-heavy system.
The pipeline is large relative to the system. Ramarothole Phase II adds 50 MW of solar and an 8 MW battery; the 60 MW Hirundo wind project in Mohale’s Hoek is expected to produce about 140 GWh a year, which LEWA says would be about 15% of the country’s needs; and LHDA plans a conventional hydropower scheme at Oxbow after deferring the Kobong pumped-storage option.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
Storage is at an early stage and is led by state projects rather than households. No storage-specific regulation, licence threshold or connection rule was identified.
Storage projects.
- Ramarothole Phase II battery (8 MW): Battery energy storage system included in the 50 MW Phase II solar expansion in Mafeteng, to store daytime solar output for use at night.
- Kobong pumped storage (deferred): LHWP Phase II originally envisaged pumped storage using Katse as the lower reservoir; LHDA deferred it for economic reasons in favour of conventional hydro.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Lesotho Electricity Company (LEC) | Sole national supplier | No | Unknown | No | No |
There is no retail competition. LEC, wholly owned by the government and established in its current form under the LEC (Pty) Ltd Establishing and Vesting Act 2006 (its predecessor dates from 1969), supplies every grid customer at LEWA-approved tariffs.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Government of Lesotho – Ministry of Energy | Government | Energy policy and rural electrification | Runs electrification programmes and the Ramarothole solar projects. |
| Lesotho Electricity and Water Authority (LEWA) | Regulator | Electricity and urban water regulator | Licensing, tariffs, grid codes and quality-of-service standards. |
| Lesotho Electricity Company (LEC) | Transmission | Transmission, distribution and supply | Connects every customer and owns all meters. |
| Lesotho Highlands Development Authority (LHDA) | Renewable Energy | Owner of ’Muela hydropower station | Largest domestic generator; developing further hydropower. |
| Southern African Power Pool (SAPP) | Market | Regional power pool | Regional trading framework in which LEC is a member. |
| LEWA complaints | Consumer | Escalation of unresolved complaints | Customers can escalate faults unattended for over two weeks to LEWA. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Grid connection | Lesotho Grid Connection Code | LEWA | Connection requirements for users of the grid. |
| Grid operation | Lesotho Grid Code; Lesotho Distribution Grid Code | LEWA | Planning, operation and connection standards for transmission and distribution. |
| Quality of supply and service | Urban (2006) and Rural (2008) Electricity Quality of Service and Supply Standards; LEWA (Electricity Supply) Regulations 2019 | LEWA | Voltage, frequency, harmonics and flicker limits; time frames for quotations, supply, faults and complaints. |
| Connection charges | Electricity Connection Charges Guidelines 2012 | LEWA | Methodology for connection charges and technical arrangements. |
| Metering | Standard Transfer Specification (STS) prepayment | LEC | All prepayment meters use STS for interoperability. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Wiring test certificate | Yes | National | Required before any new LEC connection (LEC Forms A and B). |
| LEWA licence or exemption | Limited | National | Generation up to 2 MW and on-site use may be exempt; selling to others needs a licence. |
| LEC connection approval | Unknown | National | No published procedure for grid-tied household generators was identified; the Grid Connection Code applies to grid users. |
| Building or planning permission | Unknown | Local | No specific planning rule for rooftop PV identified. |
For a household, the documented permission steps relate to obtaining supply (wiring test, survey, quotation, connection). Rules specific to small grid-connected generators have not been published by LEC or LEWA.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Mission 300 / ASCENT electrification | Active | Connection programme | Government programme to electrify about 14,000 households with an M800 million budget over four years through grid extension, mini-grids and solar home systems. | — |
| Government-funded village electrification schemes | Active | Connection subsidy | LEC delivers village connection projects funded by the government and LHDA, e.g. 740+ households at Mokema (over M22 million). | — |
Data and connectivity.
- Fixed broadband
- 0.38 fixed subscriptions per 100 people (2024)Source 1
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
Fixed broadband is rare (0.38 subscriptions per 100 people in 2024), while the World Bank records 70.3 mobile subscriptions per 100 people and 51.8% of people using the internet. Mobile money is already a main channel for buying electricity: LEC lists M-Pesa (1.3 million subscribers) and EcoCash among its vending routes.
Grid conditions.
- National peak demand
- Not identified from a reliable public source.
- Annual electricity demand
- Not identified from a reliable public source.
- Generation capacity
- Not identified from a reliable public source.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
The main constraint is supply: domestic generation covers about half of consumption, so Lesotho depends on imports from South Africa and Mozambique, and load shedding caused by supply-demand imbalance has been named a sector challenge in official statements. Network reach is the second constraint, with two highland districts still outside the national grid and many rural villages awaiting extensions.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Ramarothole Phase II solar and battery | Current | Construction launched 10 July 2026 | 50 MW of solar PV and an 8 MW battery, bringing the Mafeteng site to 80 MW. |
| Cost-of-service study and tariff-structure reform | Upcoming | 2026–27 (consultation held August 2026) | LEWA, with African Development Bank support, consulted on a cost-of-service study and proposed changes to the electricity tariff structure. |
| New multi-year tariff period | Upcoming | After 2025/26 | The current multi-year determination covers 2023/24–2025/26; a new determination is needed for later years. |
| Hirundo wind farm | Upcoming | Not yet licensed | Proposed 60 MW wind farm in Mohale’s Hoek connecting at Litšoeneng 132 kV substation. |
| Universal access by 2030 | Upcoming | 2030 | Mission 300 / ASCENT grid extension, mini-grids and solar home systems. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | — | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | — | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | — | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Low | No household export scheme or published rooftop installation data; LEWA cites funding and technology barriers. |
| Distributed energy market | Low | Distributed generation is limited to mini-grids under licence exemptions and solar home systems in electrification programmes. |
| Grid flexibility market | Low | No wholesale, balancing or ancillary-services market for third parties; aggregation is not recognised. |
| Energy storage adoption | Low | No grid storage in operation; one 8 MW battery under construction from July 2026. |
| Renewable growth environment | Medium | 30 MW of solar added in 2023 and 50 MW under construction, against about 102 MW of main domestic plant; 60 MW wind proposed. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 36 sources
- World Development Indicators – Lesotho (population, urban share, electricity access, clean cooking, broadband, mobile, internet). World Bank, 2024–2025. accessed 10 October 2026.
- Lesotho Population and Housing Census 2026. Bureau of Statistics Lesotho, 2026. accessed 10 October 2026.
- Monetary Policy. Central Bank of Lesotho. accessed 10 October 2026.
- Lesotho Electricity and Water Authority. LEWA. accessed 10 October 2026.
- Approved Electricity Tariffs & Charges. LEWA, 2025. accessed 10 October 2026.
- LEC Tariff Determinations. LEWA. accessed 10 October 2026.
- Guidelines & Principles. LEWA. accessed 10 October 2026.
- Codes. LEWA. accessed 10 October 2026.
- Quality of Service and Supply Standards. LEWA. accessed 10 October 2026.
- Licence Exemption. LEWA. accessed 10 October 2026.
- Licensees. LEWA. accessed 10 October 2026.
- Application Procedures. LEWA. accessed 10 October 2026.
- LEWA’s insight into frequently asked questions in the sectors it regulates. LEWA, 2026. accessed 10 October 2026.
- Lesotho actively explores and develops wind energy as part of its renewable energy mix. LEWA, 2026. accessed 10 October 2026.
- Unlocking the power of sustainable energy: a path to environmental and economic prosperity. LEWA, 2025. accessed 10 October 2026.
- Renewable Energy Integration in Urban Areas. LEWA, 2025. accessed 10 October 2026.
- Lesotho advances the conversation on electricity tariff reform. LEWA, 2026. accessed 10 October 2026.
- Adverse consequences associated with electricity and water meter tampering. LEWA, 2026. accessed 10 October 2026.
- The importance of reporting electricity, urban water and sewerage service faults. LEWA, 2026. accessed 10 October 2026.
- History. Lesotho Electricity Company. accessed 10 October 2026.
- Transmission Distribution. Lesotho Electricity Company. accessed 10 October 2026.
- Generation. Lesotho Electricity Company. accessed 10 October 2026.
- Metering Services. Lesotho Electricity Company. accessed 10 October 2026.
- New Connection. Lesotho Electricity Company. accessed 10 October 2026.
- LEC Vendors. Lesotho Electricity Company. accessed 10 October 2026.
- 740+ Mokema households electrified as Lesotho pushes for universal power access by 2030. Lesotho Electricity Company, 2025. accessed 10 October 2026.
- Current Projects. Lesotho Electricity Company. accessed 10 October 2026.
- LHWP Phase I. Lesotho Highlands Development Authority. accessed 10 October 2026.
- LHWP Phase II. Lesotho Highlands Development Authority. accessed 10 October 2026.
- Ramarothole solar power generation to benefit Basotho – PM. Government of Lesotho, 2023. accessed 10 October 2026.
- Sod turning of the Ramarothole Phase II solar generation project launch. Government of Lesotho, 2026. accessed 10 October 2026.
- In one bold initiative, Lesotho government is pursuing two goals: electrifying Basotho households in 2030 and generating employment for youth. Government of Lesotho. accessed 10 October 2026.
- Semonkong gets power boost as Lesotho government launched a hydro-power station. Government of Lesotho. accessed 10 October 2026.
- LEC increases tariffs. Government of Lesotho, 2022. accessed 10 October 2026.
- Load shedding a challenge for RERA chairperson. Government of Lesotho, 2023. accessed 10 October 2026.
- About SAPP – members. Southern African Power Pool. accessed 10 October 2026.
Questions about energy in Lesotho.
Tariffs are set by LEWA for LEC, the only supplier. The current schedule covers 2024/25 and 2025/26; this profile could not verify the per-kWh domestic rate from an accessible source. The last published increase found was 7.85% from 1 December 2022.
No net-metering or feed-in scheme for households has been published by LEWA or LEC. Small systems are used for self-consumption; larger generators sell to LEC under a LEWA generation licence.
The closest equivalent is the number of your STS prepaid meter, shown on the meter and on token receipts. It is used to buy 20-digit tokens. It stays with the installation, and credit cannot be transferred when you move.
No. The Lesotho Electricity Company is the sole supplier under a composite licence from LEWA.
From the 72 MW ’Muela hydropower station, the 30 MW Ramarothole solar plant and small hydro stations, plus imports from Eskom in South Africa and EDM in Mozambique. The government says the country produces about half of what it consumes.
LEWA’s rules allow exemption for generation not exceeding 2 MW and for electricity generated and used on the same premises. Selling electricity to others requires a licence.
Have your wiring tested by an electrician, apply to LEC for a survey (M100) with your ID, accept the quotation within 60 days, pay for the connection (M500 or 60% if the quote exceeds M2,000), and LEC commissions and registers your prepaid meter.