How electricity works in Senegal.
Senegal electricity market 2026: CRSE tariffs, Senelec, Woyofal prepaid meters, autoproduction and surplus sales, licensing, renewables, storage and reforms.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in West African CFA franc (XOF) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Senegal energy at a glance.
Key figures for households in Senegal. Each one links to its source on the full overview below.
Electricity price.
84.05 XOF per kWh for households, including taxes. Figures for 2026.
Household use.
1,140 kWh a year for a typical household. Figures for H1 2024 (annualised).
Renewable share.
14.7% of electricity from renewable sources. Figures for 2023.
Selling back to the grid.
Can homes export electricity? Limited. Details are in the export section below.
Four things to check in Senegal.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Senegal below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Senegal requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Senegal.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Senegal, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Senegal, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Senegal.
The energy market in Senegal, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 1 October 2026.
On this page22 sections
Senegal’s electricity sector is built around Senelec, the state-owned national utility, which produces, transmits, distributes and sells electricity across most of the country and buys the output of independent power producers. Four rural electrification concessions are run by private concession holders (COMASEL, SCL Energie Solutions and Energie Rurale Africaine) under the oversight of the rural electrification agency ASER. The Commission de Régulation du Secteur de l’Énergie (CRSE) regulates tariffs, issues opinions on licences and monitors service quality.
Household prices are set by tariff grids approved by the CRSE. From 1 January 2026 the first consumption band for small domestic customers was cut by 10%, from 91.17 to 82.00 FCFA per kWh, for both postpaid and Woyofal prepaid customers; higher bands were left unchanged. A 2.5% municipal tax is added, and VAT applies only to the third band.
Generation is still dominated by oil- and gas-fired plants, with solar and wind supplying about 14% of electricity in 2023 and hydro power imported from shared river-basin schemes. The 2021 Electricity Code opened the sector to licensed producers, storage operators and self-producers, and in 2026 the government was negotiating separate transmission and distribution concession contracts with Senelec as part of its restructuring.
Energy snapshot.
Headline figures for electricity in Senegal. Each shows its data year and links to its source.
- Population18,126,390 peopleSource 72023
- Households2,059,855 householdsSource 82023
- Average household size8.6 people/householdSource 82023
- Electricity use per household1,140 kWh/yrSource 2H1 2024 (annualised)
- Household price (XOF)84.1 XOF/kWhSource 12026
- Household price (EUR)0.128 EUR/kWhSource 112026
- Renewable electricity share14.7%Source 102023
- Solar capacity0.273 GWSource 102024
- Wind capacity0.159 GWSource 102024
- Energy storage capacity0.02 GWhSource 32025
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Single buyer
- Homes can export to the grid
- Limited
- Home equipment in grid services
- No
- Regulator
- Commission de Régulation du Secteur de l’Énergie (CRSE)
- System operator
- Senelec (national transmission network and dispatch)
- Distribution networks
- Senelec nationally, plus private rural electrification concession holders (COMASEL, SCL Energie Solutions, ERA) in four rural concessions
- Currency
- West African CFA franc (XOF)
- Voltage and frequency
- 230 V / 50 Hz
Electricity prices in Senegal.
- Household price (XOF)
- 84.1 XOF/kWh (2026)Source 1Derived: CRSE first-band price for small domestic customers (DPP, 0–150 kWh) of 82.00 FCFA/kWh from 1 January 2026, plus the 2.5% municipal tax (TCO) that the CRSE billing inquiry lists among deductions from each purchase. The first and second bands are VAT-exempt. The 82.00 FCFA price already includes the 0.7 FCFA/kWh rural electrification levy.
- Household price (EUR)
- 0.128 EUR/kWh (2026)Source 11Converted from 84.05 FCFA/kWh at the fixed parity of 655.957 FCFA per euro (unchanged on 1 October 2026). First band including the 2.5% municipal tax.
- Typical annual electricity bill
- Not identified from a reliable public source.
Household price trend (XOF per kWh).Source 12
| 2023 | 91.17 XOF/kWh |
|---|---|
| 2024 | 91.17 XOF/kWh |
| 2025 | 91.17 XOF/kWh |
| 2026 | 82 XOF/kWh |
Retail electricity prices in Senegal are regulated. The CRSE approves Senelec’s tariff grid, and the state compensates Senelec for the gap between its regulated maximum allowed revenue and what it collects at those tariffs. In 2025 the CRSE assessed Senelec’s maximum allowed revenue at 923.7 billion FCFA for sales of 5,867.53 GWh, against tariff revenues of about 763.4 billion FCFA; the state committed 181.5 billion FCFA in compensation during the year.
Rising block tariff
Households pay by consumption band. Small domestic customers (DPP) pay a social first-band price for up to 150 kWh, then higher rates. The CRSE’s billing inquiry describes the first band as 150 kWh over a 60-day billing period for postpaid bills and over 30 days for Woyofal prepaid purchases. In the first half of 2024, 68% of prepaid customers and 31% of postpaid customers fell within the social band.
2026 reduction
Following a government announcement in October 2025, the CRSE’s grid dated 26 December 2025 cut the first-band price for small domestic and small professional customers by 10% from 1 January 2026 (DPP from 91.17 to 82.00 FCFA/kWh; small professional to 147.43 FCFA/kWh). Around 2.6 million customers were covered, and the regulator estimated the revenue reduction for Senelec at 18.3 billion FCFA.
Taxes and levies
A rural electrification levy of 0.7 FCFA/kWh is built into the domestic and professional prices. A 2.5% municipal tax (TCO) is added to bills, VAT is charged only on the third band, and Woyofal customers have a monthly fixed charge deducted from their first purchase of the month. Stamp duty applies to prepaid purchases above 100,000 FCFA.
Prices are the same across Senelec’s territory, and the CRSE harmonises the tariffs of rural concession holders with Senelec’s so that rural households pay the same first-band price.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | Small domestic (DPP) postpaid from 1 January 2026: 82.00 FCFA/kWh for 0–150 kWh, 136.49 FCFA/kWh for 151–250 kWh and 159.36 FCFA/kWh above 250 kWh. Medium-power domestic (DMP): 111.23 / 143.54 / 158.46 FCFA/kWh for 0–50, 51–300 and over 300 kWh. |
| Prepayment | Yes | Woyofal prepaid customers pay the same first two band prices (82.00 and 136.49 FCFA/kWh for DPP); any third-band consumption is charged at the second-band price. Bands are assessed on purchases made since the start of each month. |
| Time-of-use | Limited | Only high-power domestic customers (DGP) have peak and off-peak prices: 118.37 FCFA/kWh off-peak and 170.53 FCFA/kWh at peak (19:00–23:00), plus a monthly fixed charge of 956.13 FCFA per kW subscribed. |
| Other | Yes | In the rural concessions, CRSE-approved harmonised tariffs apply: 82.00 FCFA/kWh for domestic users on the grid, with a monthly meter charge (redevance) of 429 FCFA and minimum monthly recharges. |
Household prices compared with neighbouring countries (EUR per kWh).
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- 1,140 kWh/yr (H1 2024 (annualised))Source 2Derived: Senelec’s low-voltage domestic customers (1,979,388 postpaid and prepaid contracts) consumed 1,128,592 MWh in the first half of 2024, about 570 kWh per contract, doubled to an annual figure. This is per domestic contract, not per household; several households may share one meter.
- Average daily use per household
- 3.1 kWh/day (H1 2024 (annualised))Source 2Derived from the annualised 1,140 kWh per low-voltage domestic contract.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 325 kWh/person/yr (2023)Source 10Derived: total generation of 5,888 GWh in 2023 (IRENA) divided by the 2023 census population of 18,126,390. All sectors.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- 0.3 % of homes (2023)Source 9Share of households using electricity as the main cooking energy. Gas (45.2%), firewood (38.4%) and charcoal (14.3%) dominate.
Electricity is mainly used for lighting, fans, refrigeration, televisions and phone charging. According to the 2023 census, 74.4% of households used electricity as their main source of lighting (94.1% in towns, 40.5% in rural areas), and 8.5% relied on solar lighting, up from 2.2% in 2013. Electric cooking is almost absent (0.3% of households).
Senelec’s consumption data show modest average use. In the first half of 2024, 1.43 million domestic Woyofal prepaid contracts consumed 705,680 MWh and 550,834 domestic postpaid contracts consumed 422,912 MWh. Demand is strongly seasonal: Senelec’s director general said demand rose from about 700 MW in January 2023 to 1,050 MW in October 2023, driven by heat.
No reliable national figures were identified for air-conditioner ownership, electric vehicles or heat pumps.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- 72.5% (2023)Source 9Share of ordinary households: owners 67.4% plus co-owners 5.1%.
- Private rented
- 23.3% (2023)Source 9Tenants 20.2% plus co-tenants 3.1% of ordinary households (rented status; landlord type not split).
- Social or public housing
- Not identified from a reliable public source.
- Houses
- 84.7% (2023)Source 9Single-storey houses (maison basse) 62.8% plus multi-storey houses 21.9% of ordinary households. Traditional huts (cases) account for a further 11.8%.
- Apartments and flats
- 1.4% (2023)Source 9Households living in apartment buildings.
- Urban population
- Not identified from a reliable public source.
Senegal’s 2023 census counted 2,059,855 households with an average of 8.6 people in ordinary households, among the largest household sizes in the world: 7.4 in towns and 10.7 in the countryside. Large extended-family compounds are common, which affects metering because several households may sit behind one Senelec connection.
Most households live in single-storey houses (62.8%) or multi-storey houses (21.9%); only 1.4% live in apartment buildings, and traditional huts house 27.8% of rural households. Owner occupation is high nationally (67.4% owners, 5.1% co-owners), but Dakar is different: 47.2% of households there are tenants and a further 6.4% co-tenants. 63.2% of ordinary households are urban.
Senelec requires a legal occupancy document (lease, land title or occupancy authorisation) to open a new contract, which can be an obstacle for tenants and informal settlements.
How the grid works in Senegal.
- TransmissionSenelec
- DistributionSenelec nationally, plus private rural electrification concession holders (COMASEL, SCL Energie Solutions, ERA) in four rural concessions
- MeteringSenelec / concession holders
- Supply2 or more retail suppliers
Senegal’s installed capacity reached 1,928 MW in 2025, according to the CRSE. Independent power producers (15 of them, under power purchase agreements with Senelec) account for 878 MW (46%), Senelec’s own plants for 474.9 MW (25%), rented capacity — including a Karpowership floating power plant whose contract is ending — for 360 MW (19%), and regional hydro imports for 135 MW (7%). The 366 MW Cap des Biches combined-cycle plant was synchronised to the grid in April 2025, and a 220 MW gas plant at Gandon near Saint-Louis close to the Grand Tortue Ahmeyim gas field has been licensed.
Hydro power comes from dams on the Senegal and Gambia rivers built and run by the river-basin organisations OMVS and OMVG, whose shared transmission lines connect Senegal with neighbouring member states. The OMVG’s 1,677 km, 225 kV ring links Senegal with Guinea, The Gambia and Guinea-Bissau and is connected to the West African Power Pool.
Commercial flow
Senelec acts as the single buyer: it purchases the output of IPPs and imports, adds its own generation, and sells to customers at CRSE-approved tariffs. Rural concession holders buy bulk power from Senelec at a regulated tariff (119.86 FCFA/kWh in 2026). The 1999 concession and licence contract between the state and Senelec expired on 31 March 2024 and was extended twice by one year while new contracts reflecting the 2021 reform — third-party access to networks and Senelec’s restructuring — were negotiated.
Service quality
The CRSE reported energy not supplied of 11.28 GWh in 2025 (0.19% of sales), and in the Dakar region an average of 7.13 interruptions per customer and 28 minutes average waiting time per outage, all within the standards set for 2023–2027. Supply problems still occur: in June 2026 heat and plant outages caused load shedding.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministère de l’Énergie, du Pétrole et des Mines (MEPM) | Sets energy policy, grants licences and concessions on the CRSE’s advice, and negotiates Senelec’s new concession contracts. |
| Regulator | Commission de Régulation du Secteur de l’Énergie (CRSE) | Independent administrative authority created by Law 2021-32. Approves tariff grids, sets Senelec’s maximum allowed revenue, gives binding opinions on licences, processes self-production declarations and monitors quality-of-service standards. |
| TSO | Senelec | Owns and operates the national high-voltage network and its interconnections, and dispatches generation. Separate transmission and distribution concession contracts were being finalised in 2026. |
| DSO | Senelec | Distributes and sells electricity to about 2.5 million low-voltage customers (June 2024) through regional delegations and local agencies. |
| DSO | COMASEL SA | Rural electrification concession holder for Dagana-Podor-Saint-Louis and Louga-Linguère-Kébémer (Compagnie Marocco-Sénégalaise d’électricité). |
| DSO | SCL Energie Solutions | Rural electrification concession holder for Mbour (STEG International, Cogelec and Les Câbleries du Sénégal). |
| DSO | Energie Rurale Africaine (ERA) | Rural electrification concession holder for Kaffrine-Tambacounda-Kédougou. |
| Metering | Senelec / concession holders | Each distributor owns, installs and reads its own meters. There is no independent meter operator role. |
Compared with the UK system.
| UK concept | Senegal equivalent | How it works |
|---|---|---|
| DNO | Senelec (and rural concession holders) | Senelec owns the distribution network, connects customers, installs meters, bills and collects payment across most of the country. In four rural concessions, private concession holders supervised by ASER do the same at harmonised tariffs. Network and retail are not separated. |
| National Grid/NESO | Senelec | Senelec combines transmission ownership, system operation and dispatch. Under the 2021 Electricity Code transmission becomes a separate concession; a concession contract was negotiated with Senelec in 2026. |
| MPAN | Woyofal meter number / Senelec contract number | There is no national supply-point number. Prepaid homes are identified by the 11-digit number of their STS Woyofal meter, used to buy credit; postpaid homes by the contract number on their bill. Both live in Senelec’s own customer system. |
| MPRN | No equivalent | Households cook mainly with bottled LPG; there is no piped household gas network and therefore no gas supply-point number. |
| Meter operator | Senelec | Senelec buys, installs, tests and replaces meters; customers cannot appoint an independent meter operator. |
| Supplier | Senelec or the local rural concession holder (no choice) | Households cannot switch supplier. The Electricity Code provides for eligible customers to buy from other licensed sellers, but the threshold had not been set in a decree identified as in force. |
| Smart-meter infrastructure | STS prepaid vending system and Senelec remote reading | Instead of a national data network, Senelec runs its Woyofal prepaid vending platform and a remote-reading system for about 8,000 large (high-power) customers; communicating household meters were piloted from 2020. |
How a supply point is identified.
54123456780 (fictional Woyofal meter number)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Woyofal prepaid meter number (STS) / Senelec contract number (Numéro de compteur Woyofal) |
| Who issues it? | The meter number is allocated by the meter manufacturer under the STS standard and registered by Senelec when it installs the meter; contract numbers are issued by Senelec when a customer subscribes |
| Format | Woyofal meters follow the Standard Transfer Specification (IEC 62055-41), whose meter number is a manufacturer code, a serial number and a check digit. Woyofal meter numbers quoted in the CRSE’s 2025 inquiry are 11 digits. Postpaid contract numbers quoted in the same report are 10 digits; older postpaid meters have shorter serial numbers. |
| Length | 11 digits (Woyofal meter number); 10 digits (postpaid contract number) |
| Stays with the property when you switch supplier? | Not identified from a reliable public source. |
| Where to find it | Printed on the meter and its keypad unit and on every Woyofal purchase receipt; postpaid customers find the contract number on their bimonthly bill. |
| Electronic access | Credit is bought online through payment partners and mobile money (the CRSE inquiry records purchases via Wave and Orange Money among others) using the meter number; each purchase returns a 20-digit token to type into the meter. |
| Third-party access | Anyone who knows the meter number can buy credit for it. There is no regulated scheme giving third parties access to consumption data. |
| Who keeps the register | Senelec’s customer information system (the Nouveau Système d’Information Clients) and prepaid vending system; rural concession holders keep their own records. |
| Register scope | Per DSO |
Senegal has no national, utility-independent supply-point identifier like an MPAN. A household connection is identified in practice by Senelec’s customer contract and, for the majority of homes now on prepaid meters, by the number of the Woyofal meter itself.
How the Woyofal meter number works
Woyofal is Senelec’s prepaid system. Its meters use the Standard Transfer Specification, the open international standard under which a vending system generates an encrypted 20-digit token valid only for one meter. The meter number is the key: it identifies the meter and its tariff category (for example DPP for small domestic) in Senelec’s vending system, which then works out how many kWh to credit after deducting taxes, any outstanding debts and, at the first purchase of the month, the fixed charge. A fictional example is 54123456780.
At 30 June 2024, 1,830,957 of Senelec’s 2,509,451 low-voltage contracts were prepaid. The meters come mainly from Hexing (about 73%), Clou (14%) and Powercom (11%), and all were less than ten years old. From 15 October 2024 customers received three 20-digit codes with their next purchase so that meters could be updated when the original version of the STS security standard reached end of life.
Postpaid contracts
Postpaid customers have a contract number and are billed on meter readings taken every two months. The CRSE found that 91% of postpaid meters were more than ten years old, and most were electromechanical single-phase meters installed over 20 years ago.
Does it stay with the property?
Senelec treats the contract as personal: a customer who moves must terminate the subscription, and on termination can choose to leave the meter in place. The meter number therefore normally stays with the premises while the contract changes, but a replacement meter receives a new number.
Getting a new connection
For a new Woyofal connection, the applicant goes to the local Senelec agency with a legal occupancy document (lease, land title or occupancy authorisation) and, for new or renovated buildings, a certificate of conformity of the internal wiring issued by COSSUEL, the Senegalese committee for electricity users’ safety, which inspects installations on Senelec’s behalf for a fee. Senelec then collects connection and subscription fees and installs the meter.
Who keeps the register
There is no central registry. Senelec holds its customer and meter database, and each rural concession holder keeps its own. Because there is no supplier switching, there is no national register for moving customers between suppliers.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Limited |
| Net metering | No |
| Net billing | Limited |
| How exported electricity is paid | Sale of surplus to the concession holder under a purchase contract, at a tariff set by the CRSE; capped at 10% of the self-producer’s annual consumption |
| What law applies? | Decree 2023-286 of 7 February 2023 on self-production of electricity, made under the 2021 Electricity Code. It repealed the 2011 decree on purchase of renewable surplus. |
| Do I need a licence? | Systems below the thresholds (solar PV and solar thermal 1 MW, wind, hydro and thermal 500 kW, biomass 2 MW) only need a declaration; above them a self-production licence is required. A licence to sell surplus is mandatory whenever surplus is to be sold, regardless of size. |
| Is there a size limit? | Yes. A domestic system selling surplus may not exceed 120% of the household’s peak demand (110% of installed equipment for professional and industrial users), and subscribed connection power may not exceed this limit. |
| How much surplus can be sold? | No more than 10% of the self-producer’s annual consumption. The surplus purchase price is set by the CRSE; a current household rate was not confirmed from a published source. |
| Can export be curtailed? | Yes. If the network cannot absorb the power safely, the concession holder may disconnect the generator or ask it to reduce injection, informing the self-producer without delay. |
Connecting a home system.
- Before commissioning, file a self-production declaration (systems up to 1 MW for solar PV) by post with the Minister of Energy and the CRSE, with a wiring diagram, equipment specifications and a consumption profile.
- The CRSE checks the file is complete within 5 days and examines it within 30 days, then issues a receipt (récépissé).
- To sell surplus, obtain a licence for the sale of surplus (required whatever the system size) and sign a surplus purchase contract with the concession holder on the CRSE-approved model.
- The concession holder sets the grid access point and installs a separate meter for the surplus, read monthly. Connection costs are paid by the self-producer.
Senegal does not have net metering. Instead, Decree 2023-286 lets self-producers sell surplus electricity to the network concession holder (Senelec or a rural concessionaire) under a purchase contract, at a price set by the CRSE, with renewable surplus bought in priority when the network can take it. The sale is tightly limited: no more than 10% of the self-producer’s annual consumption, and the system may not exceed 120% of a household’s peak demand.
Self-production is regulated in two tiers. Small systems — up to 1 MW for solar PV — need a prior declaration to the ministry and the CRSE; the CRSE delivers a receipt after a 30-day examination. Larger systems need a self-production licence after a 15-day public consultation. Separately, anyone selling surplus needs a licence for the sale of surplus. Model specifications for these licences were approved by ministerial order on 5 February 2025.
In practice the framework is used mainly by businesses. In 2025 the CRSE processed 22 declarations and issued 16 receipts (14 of them to the telecoms operator Sonatel), and gave favourable opinions on self-production licences for solar plants of 3 to 15 MWp for agribusiness, the water utility SEN’EAU, a steel company and a chemicals producer. No household surplus-sale contracts were reported.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity for the grid | Production licence, normally awarded by competitive tender; direct negotiation possible by exception after a binding CRSE opinion | Minister of Energy on CRSE opinion (Electricity Code, Law 2021-31) | IPPs sign power purchase agreements with Senelec. Recent licences include the 220 MW Ndar Energies gas plant and the 60 MWp NEA Kolda solar plant. |
| Generate for own use (self-production) | Declaration up to 1 MW (solar PV), 500 kW (wind, hydro, thermal) or 2 MW (biomass); self-production licence above those thresholds | Minister of Energy and CRSE (Decree 2023-286; CRSE regulation RA-01-2023) | Declaration does not exempt the owner from planning, safety and environmental authorisations. |
| Export / sell surplus to the grid | Licence for the sale of surplus, required at any size, plus a purchase contract with the concession holder | Minister of Energy / CRSE; contract with Senelec or rural concession holder | Capped at 10% of annual consumption; system capped at 120% of peak demand for households. |
| Store electricity | Storage licence for grid storage; CRSE has issued a model licence specification | Minister of Energy on CRSE opinion | NEA Kolda received production and storage licences in December 2025 (20 MW / 72 MWh). A CRSE regulation on remuneration of storage was in draft in 2025. |
| Transmit electricity | Transmission concession (exclusive public service) | State (concession contract), CRSE opinion | Model contract approved August 2025; Senelec’s concession contract was under CRSE review in September 2026. |
| Distribute and supply electricity to households | Distribution concession; rural electrification under ASER-awarded concessions | State / CRSE (tariffs); ASER for rural concessions | Households have no supplier choice. Model distribution contract approved August 2025. |
| Sell electricity to third parties (eligible customers) | Sale licence; buyers must be eligible customers above a power threshold to be set by decree | Minister of Energy on CRSE opinion | Provided for by the 2021 Electricity Code; no decree setting the eligibility threshold was identified as in force. |
| Import and export electricity | Import and export licences | Minister of Energy on CRSE opinion | The CRSE gave an opinion on Senelec’s application for import and export licences in September 2026. |
| Electrical installation work and wiring | Compliance with standard NS 01-001 and a COSSUEL conformity certificate before connection of new buildings | ASN (standard) / COSSUEL (inspection) | No national licence or accreditation scheme specific to solar installers was identified. |
| Aggregation, VPP, balancing and grid services, remote control of assets | No framework identified | — | There is no route for aggregators or small distributed assets to provide balancing or ancillary services. |
The 2021 Electricity Code (Law 2021-31) restructured licensing around separate titles for production, self-production, storage, transmission, distribution, sale, import and export. Licences are granted by the Minister of Energy after a binding opinion from the CRSE, and models of the specifications attached to production, self-production or surplus-sale, and storage licences were approved in February 2025.
For households and small businesses the relevant rules are those on self-production: a declaration for systems under the thresholds, and a separate licence if surplus is to be sold. The CRSE has also been policing unauthorised self-production, sending reminders and investigating operators found running plants without a title.
The Code foresees eligible customers buying directly from licensed sellers over the networks, and Senelec being split into separate activities. In 2026 the CRSE gave opinions on Senelec’s applications for production, storage, sale, import and export licences and for transmission and distribution concessions, and on the negotiated concession contracts.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Frequency regulation (bilateral with Senelec) | Restricted | — | No | Senelec. The Walo Storage plant (16 MWp solar with a 10 MW / 20 MWh battery) provides frequency regulation under a long-term contract with Senelec. There is no open market for these services. |
| Wholesale / energy | No | — | No | Senelec (single buyer). Generators sell to Senelec under power purchase agreements; there is no spot or day-ahead market. |
Senegal has no flexibility or demand-response market. Senelec dispatches the system centrally and procures services from individual plants by contract. The first battery dedicated to frequency regulation, Walo Storage at Bokhol, began commercial operation in July 2025.
Draft CRSE regulations on network access tariffs for transmission and distribution and on the remuneration of storage were being prepared in 2025, which would be needed before third parties could use the networks or be paid for storage services.
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | Prepaid STS meters (Woyofal) for 57% of low-voltage customers; remote reading for about 8,000 large customers; communicating household meters piloted from 2020 |
| Reading interval | Not published |
| Prepaid share of LV customers (June 2024) | 57% |
| Prepaid meter suppliers | Hexing, Clou, Powercom (STS) |
| Token | 20 digits per purchase |
| Postpaid meters over 10 years old | 91% |
| Remote-read customers | About 8,000 (mostly high-power) |
| Postpaid billing period | 60 days |
Smart metering in Senegal is led by Senelec rather than by a national programme with data rules. The main change of the past decade has been the shift to Woyofal prepaid meters: by mid-2024, 1.83 million low-voltage contracts were prepaid, all with meters less than ten years old. Some models are designated as communicating (“COMM”) variants, but no published figure shows how many are read remotely.
Senelec launched a pilot of communicating meters on Gorée island in August 2020, promising remote reading, remote top-up and reconnection and alerts by SMS, with plans for 50,000 meters in Dakar. No later official rollout figure was identified. About 8,000 customers — almost all high-power customers — are remote-read monthly.
Metering accuracy has been contentious. After complaints that followed the January 2023 tariff increase, the CRSE’s inquiry found tariffs were correctly applied but that around 15% of billing complaints were linked to undetected meter faults, and recommended checking meters in service for more than 15 years and revising the meter-testing procedure.
Renewable electricity.
Electricity generation mix (2023).
- Fossil (oil and gas): 85.3%
- Solar: 7.2%
- Wind: 6.5%
- Bioenergy: 1%
- Renewable electricity share
- 14.7% (2023)Source 10Derived from IRENA: 867 GWh renewable out of 5,888 GWh generated (solar 423 GWh, wind 382 GWh, bioenergy 62 GWh). Hydro power imported from the OMVS and OMVG river-basin schemes is not counted as domestic generation.
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- 42 MW (2024)Source 10
- Solar
- 0.273 GW (2024)Source 10
- Wind
- 0.159 GW (2024)Source 10
- Bioenergy
- 0.049 GW (2024)Source 10
- Fossil fuels
- 1.42 GW (2024)Source 10
- Regional hydro imports
- 0.135 GW (2025)Source 3Senegal’s share of OMVS/OMVG hydro capacity counted by the CRSE in national capacity.
Targets.
- Universal electricity access by 2029, from 84% in 2024 (National Energy Compact presented at the Mission 300 summit, January 2025).
- 40% renewable share in the electricity mix by 2030.
- Senelec tender (March 2026) for 500 MW of solar PV at Linguère (200 MW) and Kolda (300 MW) with 100 MW / 400 MWh of battery storage.
Senegal’s domestic renewable generation is mainly solar and wind. IRENA records 5,888 GWh of generation in 2023, of which 423 GWh solar, 382 GWh wind and 62 GWh bioenergy, a renewable share of about 15%. Most solar and wind output comes from utility-scale plants under power purchase agreements with Senelec. Hydro is imported from dams shared through OMVS and OMVG and is not counted as domestic generation.
Capacity growth in 2024 was dominated by gas: IRENA records 329 MW of new fossil capacity against 42 MW of solar. Renewable capacity reached 481 MW in 2024.
The state aims to raise the renewable share to 40% and is tendering large solar-plus-storage capacity. Off-grid solar remains important in rural areas, where 20.3% of households used solar lighting in 2023.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- 20 MWh (2025)Source 3Walo Storage only (10 MW / 20 MWh) in operation; NEA Kolda (72 MWh) licensed in December 2025.
Grid storage in Senegal is at an early stage but now has a legal basis: the 2021 Electricity Code created a storage licence, the CRSE published a model specification for it, and a regulation on how storage is paid was being drafted. The first battery, Walo Storage, provides frequency regulation for Senelec, and new solar procurements now include storage.
Household batteries are used mainly with off-grid or backup solar systems. There are no specific rules or incentives for home storage and no official installed figure.
Storage projects.
- Walo Storage, Bokhol: 16 MWp solar with a 10 MW / 20 MWh battery for frequency regulation; commercial operation July 2025, inaugurated January 2026.
- NEA Kolda solar and storage: 60 MWp solar with 20 MW / 72 MWh battery; production and storage licences granted by orders of 9 December 2025.
- Senelec 500 MW solar-plus-storage tender: Linguère and Kolda sites with 100 MW / 400 MWh of storage; bids were due 22 April 2026.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Senelec | About 2.5 million low-voltage contracts (June 2024) | No | Limited | No | Limited |
| COMASEL SA | Rural concessions Dagana-Podor-Saint-Louis and Louga-Linguère-Kébémer | No | No | No | Unknown |
Households do not choose their electricity supplier. Senelec supplies most of the country, and rural concession holders — COMASEL, SCL Energie Solutions (Mbour) and Energie Rurale Africaine (Kaffrine-Tambacounda-Kédougou) — supply their concession areas at CRSE-harmonised tariffs, with the state compensating them for the difference from their cost-reflective reference tariffs. Rural concessionaires served 99,686 customers in 2025.
Senelec’s restructuring under the Electricity Code is moving towards separate transmission and distribution concessions and separate licences for production, storage, sale, import and export, with a share of generation capacity reserved for a Senelec production subsidiary by ministerial order.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Ministère de l’Énergie, du Pétrole et des Mines | Government | Energy policy and licensing authority | Grants licences, receives self-production declarations and negotiates Senelec’s concessions. |
| Commission de Régulation du Secteur de l’Énergie (CRSE) | Regulator | Electricity and gas regulator | Publishes tariff grids, decisions, licence opinions and annual reports. |
| Senelec | Transmission | National utility: transmission, distribution, supply and generation | Operates the grid, connects and meters customers and buys IPP output. |
| Agence Sénégalaise d’Électrification Rurale (ASER) | Distribution | Rural electrification agency | Awards and supervises rural electrification concessions. |
| Agence Nationale pour les Énergies Renouvelables (ANER) | Renewable Energy | Renewable energy promotion agency | Promotes renewable energy deployment and programmes. |
| Agence pour l’Économie et la Maîtrise de l’Énergie (AEME) | Government | Energy efficiency agency | Leads energy efficiency policy and programmes. |
| Organisation pour la Mise en Valeur du fleuve Sénégal (OMVS) | Transmission | River-basin organisation operating shared hydro and transmission | Source of shared hydro power imported into Senegal. |
| West African Power Pool (WAPP) | Transmission | Regional power pool | Framework for cross-border interconnection and trade in ECOWAS. |
| Agence Sénégalaise de Normalisation (ASN) | Consumer | National standards body | Publishes the mandatory low-voltage installation standard NS 01-001. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Low-voltage installations | NS 01-001 (2009) Règles des installations électriques à basse tension | Agence Sénégalaise de Normalisation | Mandatory for installations up to 1,000 V AC and 1,500 V DC, including homes and commercial buildings. |
| Grid connection | Code de réseau (grid code), approved by order 006531/MPE of 27 April 2022 | Ministry of Energy / CRSE | Self-producers that inject surplus must meet its technical requirements and a connection contract with the network operator. |
| Self-production and surplus sale | Decree 2023-286 and CRSE regulation RA-01-2023 | Government / CRSE | Declaration thresholds, surplus caps, metering and curtailment rules. |
| Prepaid metering | Standard Transfer Specification (IEC 62055-41) | IEC / STS Association | Used by all Woyofal prepaid meters. |
| Installation conformity | COSSUEL certificate of conformity | COSSUEL | Required by Senelec for new and renovated buildings before a new connection. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Self-production declaration | Yes | National | Required before commissioning any self-production system below the licence thresholds, including household solar (up to 1 MW). |
| Licence for sale of surplus | Limited | National | Only if surplus is to be sold to the grid; required at any size. |
| Network operator connection approval | Limited | National | For injection: a connection contract and surplus meter from Senelec or the rural concession holder, with connection costs paid by the self-producer. |
| Wiring conformity certificate | Yes | National | COSSUEL certificate needed for new or renovated buildings before Senelec connects them. |
| Planning or building permit | Unknown | Local | The CRSE’s declaration procedure states that it does not exempt the owner from planning and environmental authorisations; no rooftop-solar-specific rule was identified. |
The legal steps for a household solar system depend on whether it will sell electricity. A system used only behind the meter needs a self-production declaration to the ministry and the CRSE, which issues a receipt; selling surplus additionally requires a licence and a purchase contract with the network operator. In practice the declaration route has so far been used mostly by businesses.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Social first-band tariff | Active | Social tariff | Small domestic customers pay 82.00 FCFA/kWh for the first 150 kWh (reduced by 10% from 1 January 2026); the first two bands are VAT-exempt. | From 1 January 2026 |
| Rural tariff harmonisation | Active | Tariff compensation | Customers of rural concession holders pay the same first-band price as Senelec customers, with the state compensating the concessionaires for the difference. | — |
| Tax exemptions on renewable energy equipment | Active | Tax relief | A VAT exemption for renewable energy equipment was introduced in 2020 (IRENA), and the National Energy Compact commits to tax exemptions on renewable equipment. The current scope and conditions were not confirmed from a primary source. | — |
Data and connectivity.
- Fixed broadband
- Not identified from a reliable public source.
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
Prepaid electricity in Senegal depends heavily on mobile money: the CRSE’s inquiry found that most Woyofal purchases in its sample were made through Wave and Orange Money, with smaller shares through other operators. The three mobile networks are Orange (Sonatel), Yas and Expresso; the telecoms regulator ARTP measured their 2G, 3G and 4G coverage and quality in a national campaign from November 2024 to March 2025.
Reliable national coverage percentages for 4G and 5G were not confirmed from an official source.
Grid conditions.
- National peak demand
- 1.05 GW (Oct 2023)Source 21Demand of 1,050 MW in October 2023 stated by Senelec’s director general, against about 700 MW in January 2023. No official annual peak series was identified.
- Annual electricity demand
- 5.87 TWh (2025)Source 3Senelec electricity sales of 5,867.53 GWh, excluding exports.
- Generation capacity
- 1.928 GW (2025)Source 3Includes IPPs, Senelec plants, rented capacity and 135 MW of regional hydro imports.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
Senegal’s grid is linked to its neighbours through the OMVS network on the Senegal river and the OMVG 225 kV ring (1,677 km, 800 MW transfer capacity) with Guinea, The Gambia and Guinea-Bissau, which has a dispatch centre at Tambacounda and is interconnected with the West African Power Pool.
Supply adequacy has improved with new gas-fired capacity, but outages and maintenance at large units can still cause shortages: in June 2026 Senelec cited a planned outage at Bel Air, unexpected failures and heat-driven demand for load shedding, and IRENA counted 312 load-shedding events in 2024.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| 10% cut in the first-band domestic tariff | Current | 1 January 2026 | DPP first band reduced from 91.17 to 82.00 FCFA/kWh for postpaid and Woyofal customers; other bands unchanged. |
| Self-production decree in force | Current | 7 February 2023 | Decree 2023-286 replaced the 2011 renewable surplus decree, introducing declarations, surplus-sale licences and a 10% surplus cap. |
| Senelec transmission and distribution concessions | Upcoming | CRSE opinion 3 September 2026; signature pending | The CRSE reviewed concession contracts negotiated between the ministry and Senelec and asked for the asset inventories to be completed before signature. |
| Network access and storage remuneration rules | Upcoming | 2026 (drafts) | CRSE draft regulations on transmission and distribution access tariffs (TARTE, TARDE) and on the remuneration of storage. |
| 500 MW solar-plus-storage procurement | Upcoming | Bids due April 2026; 24-month build | Senelec EPC-plus-finance tender for 500 MW PV and 100 MW / 400 MWh of batteries at Linguère and Kolda. |
| Universal access target | Upcoming | 2029 | National Energy Compact target of 100% electricity access, from 84% in 2024. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Low | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | Low | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | Low | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Low | No household surplus-sale contracts reported; self-production declarations in 2025 numbered 22, mostly from businesses. Solar lighting used by 8.5% of households (2023 census), mainly off-grid. |
| Distributed energy market | Low | Distributed generation is mainly commercial and industrial self-production (licences for 3–15 MWp plants in 2025); surplus sales are capped at 10% of consumption. |
| Grid flexibility market | Low | No flexibility, demand-response or aggregation market; Senelec is the single buyer and procures frequency regulation bilaterally. |
| Energy storage adoption | Low | One grid battery in operation (20 MWh, 2025), one licensed (72 MWh) and a 400 MWh tender launched in March 2026. |
| Renewable growth environment | Medium | Solar and wind supplied 13.7% of generation in 2023 (IRENA) and a 500 MW solar tender was launched in 2026, but 2024 capacity additions were dominated by gas (+329 MW fossil vs +42 MW solar). |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 26 sources
- Grilles tarifaires Senelec et CER applicables à compter du 1er janvier 2026. Commission de Régulation du Secteur de l’Énergie, 2025. accessed 1 October 2026.
- Enquête sur les systèmes de comptage et de facturation de l’énergie électrique par Senelec — rapport d’analyse. Commission de Régulation du Secteur de l’Énergie, 2025. accessed 1 October 2026.
- Rapport annuel 2025. Commission de Régulation du Secteur de l’Énergie, 2026. accessed 1 October 2026.
- Avis n°46/2026 portant sur les projets de contrats de concession de transport et de distribution d’énergie électrique. Commission de Régulation du Secteur de l’Énergie, 2026. accessed 1 October 2026.
- Décret n°2023-286 relatif à l’activité d’autoproduction d’énergie électrique. République du Sénégal (via CRSE), 2023. accessed 1 October 2026.
- Règlement d’application RA-01-2023 relatif à la déclaration d’autoproduction. Commission de Régulation du Secteur de l’Énergie, 2023. accessed 1 October 2026.
- Les principaux résultats du 5e Recensement Général de la Population et de l’Habitat du Sénégal. Agence Nationale de la Statistique et de la Démographie, 2024. accessed 1 October 2026.
- Rapport définitif — Caractéristiques des ménages (RGPH-5, 2023). Agence Nationale de la Statistique et de la Démographie (via vie-publique.sn), 2023. accessed 1 October 2026.
- Rapport définitif — Habitat et conditions de vie des ménages (RGPH-5, 2023). Agence Nationale de la Statistique et de la Démographie (via vie-publique.sn), 2023. accessed 1 October 2026.
- Energy Profile: Senegal. IRENA, 2025. accessed 1 October 2026.
- Fixed parity: 1 euro = 655.957 FCFA. Banque Centrale des États de l’Afrique de l’Ouest. accessed 1 October 2026.
- Sénégal: Baisse de 10 % des tarifs de l’électricité — plus de 2,6 millions de clients concernés (régulateur). AllAfrica (APS), 2025. accessed 1 October 2026.
- Woyofal — compteur prépayé SENELEC (FAQ). Senelec. accessed 1 October 2026.
- Senelec annonce un changement important concernant les compteurs Woyofal. Senego, 2024. accessed 1 October 2026.
- Digitalisation de l’électricité : la Senelec lance son nouveau compteur intelligent. Seneweb, 2020. accessed 1 October 2026.
- Cossuel : le maillon qui transforme l’accès à l’électricité au Sénégal en parcours du combattant. Dakaractu, 2026. accessed 1 October 2026.
- NS 01-001 Règles des installations électriques à basse tension. Agence Sénégalaise de Normalisation, 2009. accessed 1 October 2026.
- Africa REN commissions 16 MWp solar-plus-storage power plant in Senegal. SolarQuarter, 2026. accessed 1 October 2026.
- Senegal launches 500 MW solar tender with battery storage. SolarQuarter, 2026. accessed 1 October 2026.
- Compact énergétique du Sénégal au Sommet des Chefs d’État africains sur l’énergie « Mission 300 ». Vie Publique Sénégal, 2025. accessed 1 October 2026.
- Hausse des factures de l’électricité (Senelec director general on 2023 demand). Seneweb, 2023. accessed 1 October 2026.
- Heat wave and plant failures put Senegal’s electricity supply under strain. Ecofin Agency, 2026. accessed 1 October 2026.
- Nationalisation de West African Energy. AllAfrica, 2026. accessed 1 October 2026.
- The new Electricity Code (Senegal). Mondaq / Alexander & Partner, 2022. accessed 1 October 2026.
- Guinea’s electricity surge powering local small businesses and communities (OMVG interconnection). World Bank, 2025. accessed 1 October 2026.
- Couverture et QoS voix, données et SMS 2G/3G/4G au Sénégal : les résultats de la campagne ARTP. OSIRIS, 2025. accessed 1 October 2026.
Questions about energy in Senegal.
From 1 January 2026 small domestic customers pay 82.00 FCFA/kWh for the first 150 kWh, 136.49 FCFA/kWh for 151–250 kWh and 159.36 FCFA/kWh above that (postpaid). A 2.5% municipal tax is added, so the first band costs about 84 FCFA/kWh (around €0.13). VAT applies only to the third band.
Woyofal is Senelec’s prepaid electricity system. Customers buy credit at Senelec agencies, approved shops or through mobile money, receive a 20-digit code and enter it on their STS meter. By mid-2024, 57% of Senelec’s low-voltage customers used it.
Only in a limited way. Under Decree 2023-286 you can sell surplus to Senelec or your rural concession holder at a price set by the CRSE, but you need a licence for the sale of surplus, a purchase contract and a separate meter, and you may sell no more than 10% of your annual consumption. There is no net metering.
Yes. Any self-production system below 1 MW (solar PV) must be declared to the Ministry of Energy and the CRSE before it is commissioned; the CRSE issues a receipt. Larger systems need a self-production licence, and selling surplus needs a separate licence.
There is none. Prepaid homes are identified by their 11-digit Woyofal meter number, printed on the meter and receipts; postpaid homes by the contract number on their Senelec bill. Senelec keeps these in its own customer system.
No. Senelec supplies most of the country and rural concession holders supply their areas at the same regulated tariffs. The 2021 Electricity Code provides for large eligible customers to choose, but the threshold has not been set.
The Commission de Régulation du Secteur de l’Énergie (CRSE) approves tariffs, sets Senelec’s allowed revenue and gives binding opinions on licences. The Ministry of Energy, Petroleum and Mines sets policy and grants licences.