Energy in Turks and Caicos Islands, explained.

How electricity works in Turks and Caicos Islands: prices, the grid and local rules. Olmack status: Not yet available. Information last checked 10 October 2026.

Olmack in Turks and Caicos Islands: Not yet available.Olmack is not offered in Turks and Caicos Islands yet. The market information on this page is provided for reference. Information last checked 10 October 2026.
Energy-market overview

How electricity works in Turks and Caicos Islands.

Turks and Caicos Islands electricity 2026: an oil-fired island grid, one integrated utility, Energy and Utilities Department oversight, licensed solar installers and early solar growth.

This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in United States dollar (USD) where they relate to prices.

Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.

At a glance

Turks and Caicos Islands energy at a glance.

Key figures for households in Turks and Caicos Islands. Each one links to its source on the full overview below.

  • Renewable share.

    3.7% of electricity from renewable sources. Figures for 2024.

  • Selling back to the grid.

    Can homes export electricity? Limited. Details are in the export section below.

Before you start

Four things to check in Turks and Caicos Islands.

Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.

  1. Check the local rules.

    Read the connection, export and permission rules for Turks and Caicos Islands below, and ask your local grid operator if anything is unclear.

  2. Choose a qualified installer.

    Look for an installer listed on an official register, with the certifications Turks and Caicos Islands requires for the work.

  3. Look at current schemes.

    Check which support schemes are open now. Closed or scheduled schemes are labelled as such.

  4. Talk to your energy supplier.

    Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.

Local detail

Schemes, rules and certifications in Turks and Caicos Islands.

The full detail sits in the sections below. Each item shows its status and links to the official source.

  • Support schemes.

    Grants, tax relief and export payments in Turks and Caicos Islands, each labelled Active, Scheduled or Closed.

  • Connection and export.

    How equipment is connected to the grid in Turks and Caicos Islands, and the steps to export electricity.

  • Standards and certifications.

    The technical standards and installer certifications that apply to energy equipment in Turks and Caicos Islands.

Full overview

The energy market in Turks and Caicos Islands, in detail.

Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.

Profile last updated 10 October 2026.

On this page21 sections

The Turks and Caicos Islands (TCI) is a British Overseas Territory of inhabited islands south-east of the Bahamas, with no electrical link to any other country. Each inhabited island group runs its own isolated system, and electricity is supplied by a single vertically integrated utility, known as FortisTCI. Fortis Inc., the Canadian group that owned it, reports that it disposed of its Turks and Caicos business in 2025; the utility remains the islands’ only public electricity supplier.

Oversight sits with the Energy and Utilities Department (EUD), a multi-sector regulator for electricity, fuel and water that works under the Electricity Ordinance, the Petroleum Ordinance and the Water and Sewerage Ordinance. The EUD licenses electricians and solar PV installers and runs government renewable projects, many funded by the European Union’s RESEMBID programme.

Generation is almost entirely from imported oil. Ember data show the system producing about 0.26 TWh from oil in 2024, with the first measurable solar output (about 0.01 TWh) recorded that year. Demand is concentrated on Providenciales, the tourism and residential centre, which accounted for 88% of the electricity supplied in 2022 according to the Statistics Authority.

Energy snapshot.

Headline figures for electricity in Turks and Caicos Islands. Each shows its data year and links to its source.

  • Population52,299 peopleSource 12025
  • HouseholdsNot identified from a reliable public source.
  • Average household sizeNot identified from a reliable public source.
  • Electricity use per householdNot identified from a reliable public source.
  • Household price (USD)Not identified from a reliable public source.
  • Household price (EUR)Not identified from a reliable public source.
  • Renewable electricity share3.7%Source 102024
  • Solar capacityNot identified from a reliable public source.
  • Wind capacityNot identified from a reliable public source.
  • Energy storage capacityNot identified from a reliable public source.
  • Smart-meter shareNot identified from a reliable public source.
Market structure
Vertically integrated
Homes can export to the grid
Limited
Home equipment in grid services
Unknown
Regulator
Energy and Utilities Department (EUD)
System operator
FortisTCI (vertically integrated utility)
Distribution networks
No separate DSOs: the integrated utility generates, distributes and supplies electricity on each island system.
Currency
United States dollar (USD)
Voltage and frequency
120/240 V / 60 Hz

Electricity prices in Turks and Caicos Islands.

Household price (USD)
Not identified from a reliable public source.
Household price (EUR)
Not identified from a reliable public source.
Typical annual electricity bill
Not identified from a reliable public source.

The Turks and Caicos Islands has no competitive retail market. Every home on the grid is a customer of the integrated utility, and the price it pays reflects the cost of running small, isolated oil-fired systems on several islands. There is no public, regulator-hosted tariff schedule on the EUD website, so this profile does not quote a price per kWh.

What drives the price

Ember data show oil providing almost all generation in every year from 2015 to 2024, so household prices move with the cost of imported diesel and fuel oil. The government’s Department of Trade, Industry and Fair Competition publishes regular fuel price reports for road and household fuels under the Consumer Protection Ordinance, but these do not cover electricity tariffs.

Island differences

Providenciales carries most of the load and the rest of the islands are much smaller systems. Statistics Authority data for 2022 show Grand Turk and Salt Cay together at 23,465 MWh, South Caicos at 5,017 MWh, North Caicos at 4,106 MWh and Middle Caicos at 585 MWh, against 243,244 MWh on Providenciales.

Tariff types.

Tariff types.
TariffAvailableDetail
RegulatedYesHouseholds buy from the single utility on its published residential tariff. Tariff levels are set under the Electricity Ordinance framework overseen by the EUD; the current rate schedule could not be verified from an accessible source.
VariableUnknownBecause almost all electricity is generated from imported oil, the cost of fuel is the main driver of the bill. Whether and how it is passed through as a separate per-kWh charge could not be confirmed from an official page on the access date.
Time-of-useUnknownNo household time-of-use tariff identified in official sources.

Household prices compared with neighbouring countries (EUR per kWh).

Household prices including taxes, converted to euros as stated on each country page.

Household electricity use.

Electricity use per household
Not identified from a reliable public source.
Average daily use per household
Not identified from a reliable public source.
Typical household peak demand
Not identified from a reliable public source.
Electricity use per person
6,029 kWh/person/yr (2022)Source 3All sectors. Derived: 276,417 MWh of electricity supplied in 2022 (Statistics Authority) divided by the World Bank 2022 population of 45,847. Tourism (hotels and visitor demand) inflates the per-resident figure.
Heat pumps
Not identified from a reliable public source.
Air conditioning
Not identified from a reliable public source.
Electric vehicles
Not identified from a reliable public source.
Electric cooking
Not identified from a reliable public source.

Electricity use has grown steadily. Total supply across the islands rose from 230,456 MWh in 2016 to 276,417 MWh in 2022, about 20% in six years, with a dip in 2020 when tourism stopped. Residential demand on Providenciales grew faster, from 62,310 MWh in 2016 to 88,491 MWh in 2022, an increase of around 42%.

Who uses the power

Adding the island tables published by the Statistics Authority, homes bought 102,717 MWh in 2022, about 37% of all electricity sold. On Providenciales, commercial customers (49,619 MWh), medium hotels and small manufacturers (46,762 MWh) and large hotels (39,597 MWh) together used more than households did, reflecting an economy built on tourism. The water company, which runs desalination plants, used 10,028 MWh on Providenciales alone.

Seasonal pattern

Monthly data show a clear summer cooling peak: supply in 2022 ranged from 18,694 MWh in February to 26,897 MWh in July, about 44% higher. June to August were the three highest months.

Housing and households.

Dwellings
Not identified from a reliable public source.
Owner-occupied
Not identified from a reliable public source.
Private rented
Not identified from a reliable public source.
Social or public housing
Not identified from a reliable public source.
Houses
Not identified from a reliable public source.
Apartments and flats
Not identified from a reliable public source.
Urban population
94.2 % of population (2024)Source 12World Bank (UN World Urbanization Prospects) estimate.

Most residents live on Providenciales, where residential demand is now the single largest customer class. The World Bank classifies about 94% of the population as urban. Census housing tables (2012) are published by the Statistics Authority only through a sign-in-protected file, so tenure and dwelling-type shares are not given here.

For rooftop solar, the practical points are that homes are typically detached, cooling dominates use, and installations must withstand hurricane conditions. The government’s own solar projects have paired panels with batteries specifically to keep facilities running during grid outages.

How the grid works in Turks and Caicos Islands.

  1. TransmissionFortisTCI
  2. DistributionNo separate DSOs: the integrated utility generates, distributes and supplies electricity on each island system.
  3. MeteringNot identified from a reliable public source.
  4. Supply1 or more retail suppliers

Electricity in the Turks and Caicos Islands is organised as a classic small-island monopoly. The utility owns the oil-fired power stations, runs the distribution networks on each island and bills customers directly. There is no wholesale market, no unbundling between generation and networks, and no retail choice.

Physical systems

The Statistics Authority reports electricity supplied separately for Providenciales, Grand Turk and Salt Cay, South Caicos, North Caicos and Middle Caicos. Providenciales took 88% of the 2022 total. Grand Turk, the seat of government, is a much smaller system (8.5%), and the remaining islands are a few thousand MWh each or less.

Regulation

The EUD describes itself as a multi-sector regulatory body overseeing energy, fuel and water utilities under the Electricity Ordinance, the Water and Sewerage Ordinance and the Petroleum Ordinance. Its stated mission is to support a regulatory framework for a transition to green energy, energy efficiency and reliable utility services. The ordinance text is published by the Attorney General’s Chambers.

Ownership change

Fortis Inc., the Canadian utility holding company, states in its 2026 quarterly results that it disposed of its businesses in Turks and Caicos and Belize in 2025, and its list of operating companies no longer includes a Turks and Caicos utility. The EUD continues to list the utility as Fortis TCI.

Who does what.

Who does what.
RoleOrganisationWhat it does
MinistryMinistry of Home Affairs, Transportation, Broadcasting, Energy and UtilitiesParent ministry of the Energy and Utilities Department and the implementing body for the EU-funded project “Transitioning Towards Green Energy in the Turks and Caicos Islands”.
RegulatorEnergy and Utilities Department (EUD)Multi-sector regulator for electricity, petroleum and water/sewerage under the respective ordinances. Licenses electricians and solar PV installers, keeps public registers of licensees, and delivers government renewable projects.
System operatorFortisTCIThe integrated utility that generates, distributes and supplies electricity on the islands’ separate grids. Fortis Inc. reports that it disposed of its Turks and Caicos business in 2025.
SupplierFortisTCIThe only public retail supplier; customers cannot choose another company.

Compared with the UK system.

Compared with the UK system.
UK conceptTurks and Caicos Islands equivalentHow it works
DNOThe integrated utility (FortisTCI)There is no separate distribution company. The same utility owns the generators and the wires on each island and connects every customer.
National Grid/NESONo national transmission systemEach island group is an isolated grid balanced by the utility’s own power station. There is no transmission operator, wholesale market or interconnector.
MPANUtility customer account / premises recordNo publicly documented national supply-point number exists. Premises are identified within the utility’s own customer system; no format has been published by the regulator.
MPRNNot applicableThere is no piped gas network; cooking and other fuel needs are met with bottled gas and petroleum products regulated under the Petroleum Ordinance.
Meter operatorThe utilityMeters are owned, installed and read by the utility itself; there is no separate meter-operator role.
SupplierThe utility (sole supplier)Supply is a monopoly. There is no switching and no competing retailer.
Smart-meter infrastructureUtility-run metering (no national DCC equivalent)Any advanced metering is a utility system, not a national data hub. No public information on rollout status was identified.

How a supply point is identified.

How a supply point is identified.
QuestionAnswer
What is it called?Utility customer account number
Who issues it?The integrated utility (FortisTCI)
FormatNot published. Supply points are identified by the utility’s internal account and meter records; no regulator-defined national identifier exists.
LengthNot published
Stays with the property when you switch supplier?Not identified from a reliable public source.
Where to find itOn the customer’s electricity bill and in the utility’s customer account services.
Electronic accessThrough the utility’s own customer channels; no public data hub or regulator portal.
Third-party accessNo published framework for third-party access to metering data was identified.
Who keeps the registerThe utility’s customer information system; no separate public or regulator-held register.
Register scopeUnknown

Unlike Great Britain, where every supply point has a nationally registered number managed under industry codes, the Turks and Caicos Islands has a single utility that both supplies and distributes electricity. A home is identified by its account and meter in the utility’s own systems, and because no other supplier can serve it there is no need for a national registration scheme to support switching.

No official source describing the format of the account or premises number, or whether it stays with the property when occupants change, could be retrieved. Anyone needing to identify a supply point, for example for a solar installation, works from the account details printed on the bill and deals with the utility directly.

Electrical work on the premises is subject to the Electricity Ordinance, and the EUD keeps public lists of licensed electricians (master, journeyman, wireman, electrical engineer and apprentice grades) and licensed solar PV installers.

Sending electricity to the grid.

Sending electricity to the grid.
QuestionAnswer
Can homes export electricity?Unknown
Net meteringUnknown
Net billingUnknown
How exported electricity is paidNot verified: any export arrangement is set by the utility under the Electricity Ordinance framework, and its current terms could not be retrieved from an official source.
Who licenses solar installers?The Energy and Utilities Department, which publishes a list of licensed solar PV installers (three companies listed on the access date).
Is there a published net-metering tariff?No current net-metering or feed-in rate could be verified from a government or regulator page on the access date.
Are batteries used with solar?Yes in government projects: the EU-funded health-clinic systems include batteries to keep power on during grid outages, and the EUD has tendered further rooftop solar systems with battery storage.

Connecting a home system.

  1. Engage an installer from the EUD’s list of licensed solar PV installers.
  2. Have electrical work carried out or certified by an electrician licensed by the EUD under the Electricity Ordinance.
  3. Apply to the utility to connect the system to its grid and agree the metering and any export arrangement.
  4. Obtain any planning or building approval required; EUD applications can be submitted through the EUD or the Department of Planning.

Grid-connected solar is new in the Turks and Caicos Islands: Ember records no solar generation until 2024. Installation work is regulated through the EUD’s licensing of electricians and solar PV installers, but the commercial terms for exporting to the grid sit with the utility and were not available from an official source on the access date.

Because there is a single utility on small isolated grids, the amount of variable generation it can accept on each island is a practical limit, and connection is a matter for the utility’s own interconnection process rather than a regulator-run scheme.

Licensing and approvals.

Requirements depend on the activity. The table sets out what each activity needs and who grants it.

Licensing and approvals.
ActivityLicence or registrationAuthorityNotes
Generate electricity for the public gridGoverned by the Electricity Ordinance; public supply is provided by the incumbent utility. Thresholds for independent generators are not published on the EUD website.Government of the Turks and Caicos Islands / EUDOrdinance text available from the Attorney General’s Chambers.
Self-generation (rooftop solar for own use)Installation must be carried out by licensed installers and electricians; no separate generation licence for households is described on the EUD website.EUDGrid connection is agreed with the utility.
Store electricity (behind-the-meter batteries)No specific storage licence identified; installation falls under electrical licensing.EUDGovernment clinic and school projects include batteries.
Export to the gridSubject to the utility’s approval and metering; terms not verified.Utility, under the Electricity Ordinance
Supply / sell electricity to othersPublic supply is a utility function under the Electricity Ordinance; no competitive supply licences are issued.Government / EUDNo retail competition.
Install electrical systemsElectrician licence required, renewed annually by paying the licence fee; grades include master electrician, journeyman, wireman, electrical engineer and apprentice.EUD67 approved licensed electricians listed as of 21 August 2026; some licences are restricted to one employer.
Install solar PV systems (as a business)Listed as a licensed solar PV installer with the EUD; electrical companies complete a checklist and assessment form for small-scale business applications.EUDThree installers listed on the access date.
Aggregate, trade, wholesale, balancing, grid services, VPP or remote control of assetsNo market exists for these activities, so no licence category applies.Not applicableAll balancing is done by the utility.

Licensing in the Turks and Caicos Islands is about who may do electrical work rather than who may trade electricity. The EUD licenses individual electricians under the Electricity Ordinance and maintains a register of licensed solar PV installers; businesses apply using its checklist and assessment forms.

Market activities familiar in Great Britain, such as supply licences, aggregation, wholesale trading or balancing services, have no counterpart, because the utility performs all of them within one business.

Flexibility and grid services.

Aggregation of home equipment: No

Flexibility and grid services.
Market or serviceAccess for home equipmentMinimum sizeVia an aggregatorDetail
Wholesale / balancing marketsNo—NoThere is no wholesale market or balancing mechanism; the utility dispatches its own generators on each island.

No flexibility or demand-response market for households has been identified. On isolated oil-fired grids, the main value of household batteries is resilience during outages and greater self-consumption of solar, which is how the government’s own clinic and school projects use them.

Smart meters.

Smart meters.
FactValue
Smart-meter rolloutNo public information on rollout status
Reading intervalNot published
Owner of metersThe utility
National data hubNone
PenetrationNot published

Metering is a utility function. No regulator or statistics-office publication on smart-meter coverage, reading intervals or customer data access was identified.

Renewable electricity.

Electricity generation mix (2024).

  • Oil: 96.3%
  • Solar: 3.7%
Source 10
Renewable electricity share
3.7% (2024)Source 10Derived from Ember data via Our World in Data: 0.01 TWh solar against 0.26 TWh oil-fired generation in 2024. Both inputs are rounded to 0.01 TWh, so the share is approximate (roughly 2–5%). Ember records no renewable generation for 2015–2023. There are no imports, so generation and consumption shares are the same.
Home solar
Not identified from a reliable public source.
Solar added each year
Not identified from a reliable public source.
Solar PV
Not identified from a reliable public source.
Wind
Not identified from a reliable public source.

Targets.

  • No quantified national renewable-electricity target was identified on official pages accessed. The EUD states it is establishing milestones for renewable energy, energy efficiency and emissions reduction, and has commissioned a strategic transition plan and an energy-efficiency market analysis under RESEMBID.

Ember data show oil as the only source of generation from 2015 to 2023 and a first measurable solar contribution of about 0.01 TWh in 2024, roughly 3.7% of the total. Because Ember rounds to 0.01 TWh, this share should be read as approximate.

Government projects

The EUD completed solar PV systems at five healthcare facilities in early 2025: Blue Hills Clinic (Providenciales), Bottle Creek Clinic (North Caicos), the Middle Caicos clinic, South Caicos Primary Health Clinic and the Wellness Centre on Grand Turk. They were funded by the EU’s Resilience, Sustainable Energy and Marine Biodiversity Programme (RESEMBID), implemented by Expertise France. The EUD has since issued requests for rooftop solar systems at three schools and a tender for a second phase of five rooftop systems with battery storage.

Land for green energy

In February 2025 the EUD sought a consultant for a Green Energy Task Force, intended to identify and reserve Crown land for renewable projects and set policies on how that land is allocated and leased.

Energy storage.

Home batteries
Not identified from a reliable public source.
Grid-scale storage
Not identified from a reliable public source.

Battery storage is appearing first in public buildings, where the aim is continuity of supply after storms or grid faults. No data on household or utility-scale storage were identified.

Storage projects.

Electricity suppliers.

Electricity suppliers.
SupplierMarket shareRenewable tariffTime of useDynamicExport tariff
FortisTCISole public supplierUnknownUnknownNoUnknown

There is one public electricity utility. The EUD lists it as Fortis TCI and links to its website; Fortis Inc. reports that it disposed of the business in 2025.

Key organisations.

Key organisations.
OrganisationCategoryWhat it doesWhy it matters
Energy and Utilities Department (EUD)RegulatorElectricity, fuel and water regulator; licensing of electricians and solar installersPublishes the licensing registers, forms and renewable project information.
Statistics AuthorityGovernmentOfficial statistics, including electricity supplied by island and sectorSource of population and electricity consumption data.
Attorney General’s ChambersGovernmentPublishes ordinances including the Electricity OrdinanceLegal basis for electricity regulation and licensing.
Caribbean Centre for Renewable Energy and Energy Efficiency (CCREEE)Renewable EnergyRegional renewable energy centre; EUD project partnerListed by the EUD as a partner for renewable energy capacity building.
RESEMBID (Expertise France / EU)Renewable EnergyEU programme funding resilience and sustainable energy in Caribbean overseas territoriesFunds the TCI green energy transition project and public-sector solar.

Technical standards.

Technical standards.
AreaStandardIssued byNotes
Electrical installationElectricity Ordinance and EUD electrician licensingGovernment of the Turks and Caicos Islands / EUDWork must be done by licensed electricians; the licensing grades are master, journeyman, wireman, electrical engineer and apprentice.
Installer accreditationEUD licensed solar PV installer listEUDPublic register of licensed solar installers.
Grid connectionUtility interconnection requirementsThe utilityNo regulator-published grid code or inverter standard was identified on official pages accessed.

Permissions.

Permissions.
PermissionRequiredLevelDetail
Licensed installer / electricianYesNationalElectrical and solar work by EUD-licensed electricians and installers.
Utility approval to connectYesNationalGrid-connected systems are connected by the single utility; terms not verified.
Planning / building approvalLimitedNationalThe EUD notes that applications may be submitted at its office or at the Department of Planning; specific planning rules for rooftop solar were not identified.

Permissions are handled at territory level, as there is no local government tier for electricity. The EUD oversees who may carry out the work, the utility controls connection to its grid, and the Department of Planning handles building matters.

Data and connectivity.

Fixed broadband
Not identified from a reliable public source.
4G coverage
Not identified from a reliable public source.
5G coverage
Not identified from a reliable public source.

No official data on broadband or mobile coverage were identified for this profile. Telecommunications are regulated by the Telecommunications Commission, which sits under the same ministry as the EUD.

Grid conditions.

National peak demand
Not identified from a reliable public source.
Annual electricity demand
0.276 TWh (2022)Source 3276,417 MWh of electricity supplied across all islands (Statistics Authority). Ember reports about 0.27 TWh of generation in 2024.
Generation capacity
Not identified from a reliable public source.
Interconnection
0 GWSource 10No interconnection with other countries; each island system is isolated.
Curtailment
Not identified from a reliable public source.

Demand is small in absolute terms but has grown about 20% between 2016 and 2022, driven by Providenciales. Each island system must cover its own summer cooling peak, with July 2022 supply some 44% above February.

Regulatory changes.

Regulatory changes.
ChangeStatusDateDetail
Fortis disposes of its Turks and Caicos utilityCurrent2025Fortis Inc. reports that it sold its Turks and Caicos business in 2025. The utility continues as the territory’s sole electricity supplier.
Green Energy Task Force and Crown land for renewablesUpcomingFrom 2025The EUD is procuring support to identify and reserve Crown land for green energy projects and to set land allocation and leasing policy.
Strategic transition plan under RESEMBIDUpcomingOngoingAn EU-funded strategic transition plan and energy-efficiency market analysis have been prepared for the EUD to guide the move away from oil-fired generation.

Market indicators.

Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.

Market indicators.
IndicatorLevelBasis
Electricity cost—Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros).
Household electricity use—Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household).
Renewable shareLowLow below 30%, high at 60% or more (renewable share of electricity).
Smart-meter adoption—Low below 30%, high at 80% or more (share of meters that are smart).
Home solar adoptionLowEmber records no solar generation before 2024 and only about 0.01 TWh in 2024; three licensed solar installers listed by the EUD.
Distributed energy marketLowSingle integrated utility on isolated oil-fired grids; no published export or aggregation framework identified.
Grid flexibility marketLowNo wholesale, balancing or flexibility market exists.
Energy storage adoptionLowBattery storage identified only in a handful of government solar projects.
Renewable growth environmentLowRenewables about 3.7% of generation in 2024 (Ember), up from zero; no quantified national target identified.

Sources.

Public sources used for this profile, with the date each was accessed.

Show all 27 sources
  1. Statistics Authority – 2025 indicators. Turks and Caicos Islands Statistics Authority, 2025. accessed 10 October 2026.
  2. Electricity Consumption. Turks and Caicos Islands Statistics Authority, 2022. accessed 10 October 2026.
  3. Electricity supplied by island for the period (MWh): 2010–2022. Turks and Caicos Islands Statistics Authority, 2022. accessed 10 October 2026.
  4. Electricity sales in kWh for Providenciales 2016–2022. Turks and Caicos Islands Statistics Authority, 2022. accessed 10 October 2026.
  5. Electricity sales in kWh for Grand Turk 2016–2022. Turks and Caicos Islands Statistics Authority, 2022. accessed 10 October 2026.
  6. Electricity sales in kWh for North Caicos 2016–2022. Turks and Caicos Islands Statistics Authority, 2022. accessed 10 October 2026.
  7. Electricity sales in kWh for South Caicos 2016–2022. Turks and Caicos Islands Statistics Authority, 2022. accessed 10 October 2026.
  8. Electricity sales in kWh for Middle Caicos 2016–2022. Turks and Caicos Islands Statistics Authority, 2022. accessed 10 October 2026.
  9. Total energy consumption by month for Turks and Caicos Islands 2016–2022. Turks and Caicos Islands Statistics Authority, 2022. accessed 10 October 2026.
  10. Electricity production by source – Turks and Caicos Islands (Ember data). Our World in Data / Ember, 2024. accessed 10 October 2026.
  11. Population, total – Turks and Caicos Islands (SP.POP.TOTL). World Bank, 2025. accessed 10 October 2026.
  12. Urban population (% of total) – Turks and Caicos Islands (SP.URB.TOTL.IN.ZS). World Bank, 2024. accessed 10 October 2026.
  13. Energy and Utilities Department. Government of the Turks and Caicos Islands. accessed 10 October 2026.
  14. Mission, Vision & Structure. Energy and Utilities Department. accessed 10 October 2026.
  15. Functions. Energy and Utilities Department. accessed 10 October 2026.
  16. FAQs. Energy and Utilities Department. accessed 10 October 2026.
  17. Licensed Electricians. Energy and Utilities Department, 2026. accessed 10 October 2026.
  18. Licensed Solar PV Installers. Energy and Utilities Department. accessed 10 October 2026.
  19. Forms & Applications. Energy and Utilities Department. accessed 10 October 2026.
  20. Reports. Energy and Utilities Department. accessed 10 October 2026.
  21. Press Releases. Energy and Utilities Department, 2025. accessed 10 October 2026.
  22. Solar PV Projects Completed at Critical Turks and Caicos Islands Healthcare Facilities. Energy and Utilities Department, 2025. accessed 10 October 2026.
  23. Request for Proposal (RFP) for Green Energy Task Force Consultant. Energy and Utilities Department, 2025. accessed 10 October 2026.
  24. RESEMBID – Transitioning Towards Green Energy in the Turks and Caicos Islands. Energy and Utilities Department. accessed 10 October 2026.
  25. Fortis Inc. Releases Second Quarter 2026 Results. Fortis Inc., 2026. accessed 10 October 2026.
  26. Fortis companies. Fortis Inc., 2026. accessed 10 October 2026.
  27. Fuel Reports for September 1–7 & 15, 2026. Government of the Turks and Caicos Islands Press Office, 2026. accessed 10 October 2026.

Questions about energy in Turks and Caicos Islands.

Talk to us about Olmack in Turks and Caicos Islands.Tell us about your home, housing portfolio or school estate in Turks and Caicos Islands. We'll explain what is possible there now.