Countries

Energy in Brunei, explained.

How electricity works in Brunei: prices, the grid and local rules. Olmack status: Not yet available. Information last checked 10 October 2026.

Olmack in Brunei: Not yet available.Olmack is not offered in Brunei yet. The market information on this page is provided for reference. Information last checked 10 October 2026.
Energy-market overview

How electricity works in Brunei.

Brunei electricity 2026: DES and BPC as state-owned utilities, block tariffs unchanged since 2012, gas-fired supply, AENBD regulation and net metering for solar up to 1 MW.

This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Brunei dollar (BND) where they relate to prices.

Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.

At a glance

Brunei energy at a glance.

Key figures for households in Brunei. Each one links to its source on the full overview below.

  • Electricity price.

    0.038 BND per kWh for households, including taxes. Figures for Tariff in force since 1 January 2012.

  • Renewable share.

    0.1% of electricity from renewable sources. Figures for 2023.

  • Selling back to the grid.

    Can homes export electricity? Yes. Details are in the export section below.

Before you start

Four things to check in Brunei.

Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.

  1. Check the local rules.

    Read the connection, export and permission rules for Brunei below, and ask your local grid operator if anything is unclear.

  2. Choose a qualified installer.

    Look for an installer listed on an official register, with the certifications Brunei requires for the work.

  3. Look at current schemes.

    Check which support schemes are open now. Closed or scheduled schemes are labelled as such.

  4. Talk to your energy supplier.

    Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.

Local detail

Schemes, rules and certifications in Brunei.

The full detail sits in the sections below. Each item shows its status and links to the official source.

  • Support schemes.

    Grants, tax relief and export payments in Brunei, each labelled Active, Scheduled or Closed.

  • Connection and export.

    How equipment is connected to the grid in Brunei, and the steps to export electricity.

  • Standards and certifications.

    The technical standards and installer certifications that apply to energy equipment in Brunei.

Full overview

The energy market in Brunei, in detail.

Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.

Profile last updated 10 October 2026.

On this page22 sections

Brunei Darussalam’s electricity is generated almost entirely from fossil fuels, and is supplied by two state-controlled bodies. The Department of Electrical Services (DES), part of the Department of Energy at the Prime Minister’s Office, runs power stations at Gadong, Bukit Panggal, Lumut and Belingus and supplies customers across the country. Berakas Power Company Sdn Bhd (BPC), a government-linked company wholly owned by Darussalam Assets Sdn Bhd, runs the Berakas Power System in the Brunei-Muara district and says it serves about 40% of national power demand, including most strategic and critical loads.

Electricity is regulated by the Autoriti Elektrik Negara Brunei Darussalam (AENBD), appointed as the Authority under the Electricity Act (Chapter 223) on 2 January 2019. It sits inside the Department of Energy and handles electricity licensing, compliance and the codes of practice that govern connections. Household prices are very low: the residential block tariff, unchanged since 1 January 2012, charges B$0.01 per kWh for the first 600 kWh a month.

Renewables remain marginal. IRENA records 4 GWh of solar generation out of 4,461 GWh in 2023, and the country’s best-known solar plant, the 1.2 MW Tenaga Suria Brunei demonstration facility, dates from 2010. The Brunei National Climate Change Policy (2020) sets a target of 30% renewable energy in total installed capacity by 2035, and a net-metering programme for solar systems of 1 kW to 1 MW was rolled out in 2025. The main new investment is gas-fired: in August 2026 the government signed a contract for a 215 MW second phase of the Bukit Panggal combined-cycle power station.

Energy snapshot.

Headline figures for electricity in Brunei. Each shows its data year and links to its source.

  • Population458,600 peopleSource 132025
  • Households87,137 householdsSource 142021 (census)
  • Average household size5.1 people/householdSource 142021 (census)
  • Electricity use per householdNot identified from a reliable public source.
  • Household price (BND)0.038 BND/kWhSource 1Tariff in force since 1 January 2012
  • Household price (EUR)0.026 EUR/kWhSource 17Tariff in force since 1 January 2012
  • Renewable electricity share0.1%Source 152023
  • Solar capacity0.005 GWSource 152023
  • Wind capacity0 GWSource 152024
  • Energy storage capacityNot identified from a reliable public source.
  • Smart-meter shareNot identified from a reliable public source.
Market structure
Vertically integrated
Homes can export to the grid
Yes
Home equipment in grid services
No
Regulator
Autoriti Elektrik Negara Brunei Darussalam (AENBD)
System operator
Department of Electrical Services (DES); Berakas Power Company (BPC) for the Berakas Power System
Distribution networks
DES distributes nationwide; BPC distributes to mainly strategic and critical loads in Brunei-Muara
Currency
Brunei dollar (BND)
Voltage and frequency
230 V / 400 V

Electricity prices in Brunei.

Household price (BND)
0.038 BND/kWh (Tariff in force since 1 January 2012)Source 1Derived average price for a household using 1,000 kWh a month (the Department of Energy’s worked example): 600 kWh × B$0.01 + 400 kWh × B$0.08 = B$38.00, or B$0.038/kWh. The marginal rate is B$0.01/kWh up to 600 kWh, B$0.08 to 2,000 kWh, B$0.10 to 4,000 kWh and B$0.12 above. The DES tariff page shows no standing charge or tax on residential bills.
Household price (EUR)
0.026 EUR/kWh (Tariff in force since 1 January 2012)Source 17The Brunei dollar is pegged at par to the Singapore dollar (BDCB). Converted at the ECB reference rate of EUR 1 = SGD 1.4460 on 1 October 2026: 0.038 ÷ 1.4460 = EUR 0.026/kWh.
Typical annual electricity bill
Not identified from a reliable public source.

How prices are set

Tariffs are set by government and published by DES. The residential tariff is a rising block structure: the first 600 kWh a month cost one Brunei cent each, so a small household pays only a few dollars a month, while heavy users pay up to 12 cents for consumption above 4,000 kWh. The DES tariff page lists no standing charge or tax for residential customers, and the structure has applied since 1 January 2012.

What households actually pay

Because the first block is so cheap, the average price depends heavily on consumption. A household using 600 kWh a month pays B$6.00; one using 1,000 kWh pays B$38.00 (about 3.8 cents per kWh on average); one using 2,000 kWh pays B$118.00. The Department of Energy’s solar guidebook works through the same calculation to show that 907.2 kWh of solar generation would save a residential customer B$30.58 a month.

Commercial supply

Commercial customers are charged on a different basis. Tariff B links the price blocks to subscribed capacity in kVA, so the first units per kVA cost 20 cents and the rate falls to 5 cents for the remainder. DES notes that the commercial tariff does not cover heavy industries.

Comparison

At about EUR 0.026/kWh for a household using 1,000 kWh a month, Brunei’s residential electricity is very cheap by international standards, and the tariff has not been revised for more than a decade.

Tariff types.

Tariff types.
TariffAvailableDetail
RegulatedYesTariff A (residential), in force since 1 January 2012: B$0.01/kWh for 0–600 kWh a month, B$0.08 for 601–2,000 kWh, B$0.10 for 2,001–4,000 kWh and B$0.12 above 4,000 kWh. DES publishes a bill table running from B$0.50 for 50 kWh to B$498.00 for 5,500 kWh.
PrepaymentYesDES sells prepaid electricity meter tokens at its counters, through BIBD NEXGEN Wallet, Baiduri b.Digital, Standard Chartered and TAIB online banking, PowerKad and MyBillPayment, and DST’s USMS quick top-up.
OtherYesTariff B (commercial, excluding heavy industry) is based on subscribed capacity in kVA: the first 10 units per kVA at B$0.20, the next 100 units per kVA at B$0.07, the next 100 at B$0.06 and the remainder at B$0.05. Vacant shophouses pay a minimum of B$2 a month unless the owner notifies DES of closure.
Time-of-useNoNo time-of-use tariff is published by DES.
DynamicNoThere is no wholesale market, so no wholesale-indexed tariffs.
FixedNoThere is no competing retail supplier offering fixed-price contracts; the tariff itself has not changed since 2012.

Household prices compared with neighbouring countries (EUR per kWh).

Household prices including taxes, converted to euros as stated on each country page.

Household electricity use.

Electricity use per household
Not identified from a reliable public source.
Average daily use per household
Not identified from a reliable public source.
Typical household peak demand
Not identified from a reliable public source.
Electricity use per person
7,117 kWh/person/yr (2024)Source 13Derived, all sectors: electricity consumption of 3,242.0 GWh in 2024 ÷ population estimate of 455,500 (DEPS, Brunei Darussalam Key Indicators 2025).
Heat pumps
Not identified from a reliable public source.
Air conditioning
Not identified from a reliable public source.
Electric vehicles
Not identified from a reliable public source.
Electric cooking
Not identified from a reliable public source.

Brunei uses a lot of electricity per person. DEPS records consumption of 3,649.7 GWh in 2023 and 3,242.0 GWh in 2024, which works out at about 7,100 kWh per person in 2024 across all sectors. A provisional 2025 figure of 2,055.2 GWh appears in the same table, but it is marked provisional and is far below production of 4,447.7 GWh that year, so it should be treated with caution.

The climate is hot and humid all year (a mean daily maximum of 32.5°C and 83% relative humidity in 2025, according to DEPS), so cooling is the main household load. Households are large, averaging 5.1 people in the 2021 census, and the very cheap first tariff block gives little price signal to save. The Department of Energy runs energy-efficiency campaigns and administers the Energy Efficiency (Standards and Labelling) Order 2021, which requires registered suppliers of covered appliances.

Housing and households.

Dwellings
83,810 dwellings (2021 (census))Source 14Occupied living quarters or housing units; 59,472 (71.0%) were in the Brunei-Muara district.
Owner-occupied
Not identified from a reliable public source.
Private rented
Not identified from a reliable public source.
Social or public housing
Not identified from a reliable public source.
Houses
Not identified from a reliable public source.
Apartments and flats
Not identified from a reliable public source.
Urban population
75 % of population (2025)Source 18

The 2021 census counted 83,810 occupied housing units and 87,137 households, up from 68,237 households in 2011. Population is concentrated in the Brunei-Muara district, which held 72.3% of residents in 2021 and 72.5% of the 2025 estimate, followed by Belait (14.8%), Tutong (10.6%) and Temburong (2.1%).

Government housing is a visible part of the market. The most populous village in 2021 was Perumahan Negara Kampung Panchor in Brunei-Muara, a national housing scheme with 13,358 residents, and DEPS attributed much of the fastest local population growth to new resettlement areas.

How the grid works in Brunei.

  1. TransmissionDepartment of Electrical Services (DES), Berakas Power Company Sdn Bhd (BPC)
  2. DistributionDES distributes nationwide; BPC distributes to mainly strategic and critical loads in Brunei-Muara
  3. MeteringDES and DES-approved meter vendors
  4. Supply2 or more retail suppliers

Physical flow

Brunei’s power is generated almost entirely from fossil fuels; IRENA attributes 58% of electricity and heat emissions in 2023 to gas and 41% to coal. DES runs power stations at Gadong, Bukit Panggal, Lumut and Belingus; Bukit Panggal is a 116 MW combined-cycle plant commissioned in 2006. BPC runs the separate Berakas Power System in Brunei-Muara. DEPS records generation capacity of 1,048.4 MW and production of 4,617.5 GWh in 2024; IRENA counts 1,231 MW of capacity, including about 220 MW of fossil capacity added in 2020.

The government says average generation efficiency is below 30%. In August 2026 it signed a contract with Sinohydro Corporation for the 215 MW second phase of the Bukit Panggal combined-cycle station under the 12th National Development Plan, which it expects to lift national generation efficiency to at least 50%. Low-voltage networks run at 400 V three-phase and 230 V single-phase.

Commercial flow

There is no wholesale market or independent power purchase market for small generators. DES and BPC are each responsible for generation, network operation and supply on their own systems, and households buy from DES at government-set tariffs. Net-metering customers do not sell power: their exports are credited against their own bills.

Who does what.

Who does what.
RoleOrganisationWhat it does
MinistryDepartment of Energy, Prime Minister’s OfficeSets energy policy, runs the net-metering programme as implementing agency through its Energy Transition Division, registers solar PV suppliers and installers, and oversees DES.
RegulatorAutoriti Elektrik Negara Brunei Darussalam (AENBD)Appointed as the Authority under the Electricity Act (Chapter 223) on 2 January 2019. Its Compliance Unit manages electricity licensing and monitors compliance; its Strategic Unit develops regulations, codes and guidelines, including the Code of Practice for small-scale solar connection.
System operatorDepartment of Electrical Services (DES)Government department founded as the Electrical Office in 1921 and a department since 1953, under the Department of Energy at the Prime Minister’s Office since 2005. It has generation, transmission, distribution, relay protection and renewable-energy divisions.
TSOBerakas Power Company Sdn Bhd (BPC)Government-linked company set up in 1998, wholly owned by Darussalam Assets Sdn Bhd. Operates, maintains and expands the Berakas Power System in the Brunei-Muara district, serving about 40% of national demand.
DSODepartment of Electrical Services (DES)Distribution service provider for customers across all four districts, and the utility that net-metering applicants must already be customers of.
DSOBerakas Power Company (BPC)Distribution service provider for mostly strategic and critical loads in Brunei-Muara, such as government and health facilities.
SupplierDepartment of Electrical Services (DES)Bills residential and commercial customers at the published tariffs and sells prepaid meter tokens.
MeteringDES and DES-approved meter vendorsDES meters and bills its customers; for net metering, the customer buys an import/export meter approved by the distribution service provider from a registered meter vendor, who installs it.

Compared with the UK system.

Compared with the UK system.
UK conceptBrunei equivalentHow it works
DNODES and BPC (distribution service providers)There are two network operators rather than regional companies. DES covers the whole country; BPC runs a separate system in Brunei-Muara mainly for strategic loads. Both are owned by the state, and each is also the generator and seller of electricity on its own system.
National Grid/NESODES and BPCThere is no independent transmission or system operator. DES operates its own power stations and transmission network, and BPC operates the Berakas Power System; AENBD regulates both from inside the Department of Energy.
MPANDES meter accountA supply is identified by its account with DES, which is tied to the meter installed at the premises. There is no national supply-point number. The net-metering guideline requires each meter account to be unique to the consumer, and DES registers a new account when a net meter is installed.
MPRNNo equivalentNo piped household gas network or gas supply-point register was identified in the sources read.
Meter operatorDES and registered meter vendorsDES meters its customers and sells prepaid tokens. For net metering the customer buys an approved meter from a registered vendor at their own cost, and the contractor notifies DES of the meter type, location and account.
SupplierDES (no choice of supplier)Households cannot switch supplier. Tariffs are set by government and have not changed since January 2012.
Smart-meter infrastructurePrepaid meters; no national smart-meter data network identifiedDES sells prepaid tokens through counters, banking apps and agents. No national programme comparable to the UK’s DCC network was identified.

How a supply point is identified.

Account No. 0012345678 (fictional; illustrative only)

Fictional example in the real format.

How a supply point is identified.
QuestionAnswer
What is it called?DES meter account (Account No.)
Who issues it?Department of Electrical Services (DES), when a supply is connected
FormatAccount reference in DES’s billing system, linked to the meter at the premises. DES does not publish the length or structure of the account number, and the meter carries its own serial number.
LengthNot published by DES
Stays with the property when you switch supplier?Not identified from a reliable public source.
Where to find itOn the DES bill or prepaid token receipts; meter details can be updated through DES’s MeterKu online form.
Electronic accessBills can be paid through the DES Paybill e-service and banking apps, and prepaid tokens bought online. Government-sector customers can submit their own meter readings through DES’s “Read Our Own Meter” form.
Third-party accessNo regulated data-access scheme for third parties was identified. For net metering, the appointed contractor gives DES the meter type, location and account so DES can register the net-metering account.
Who keeps the registerDES customer and billing records
Register scopeNational

How a home is identified

In Brunei a household supply is identified by its account with DES, the department that bills it, and by the meter installed at the premises. There is no separate national supply-point register: DES’s customer records are the register for its customers, and BPC keeps its own for the loads it serves. DES does not publish the format of its account numbers, so the example above is illustrative only.

Meter details and updates

DES maintains a MeterKu online form for customers to update their meter profile. Prepaid customers buy tokens at DES counters, through banking apps and through retail agents. Under the net-metering guideline, when a household replaces its meter with an approved import/export meter, the contractor tells DES the type and location of the meter and the account it belongs to, which must be unique to that consumer; DES then registers a new net-metering account.

Change of occupier

The net-metering guideline says that when a property with a solar system is sold, the net-metering approval transfers to the new owner, who must notify the distribution service provider. Credits cannot be transferred to another account. DES does not state whether the account number itself stays with the property when the occupier changes, so this is not recorded here.

Sending electricity to the grid.

Sending electricity to the grid.
QuestionAnswer
Can homes export electricity?Yes
Net meteringYes
Net billingNo
How exported electricity is paidNet metering: exported energy is credited at the prevailing gazetted tariff and netted off the bill; surplus credits roll over for up to 12 months and are then forfeited. No cash payments.
What size of system qualifies?Solar PV of 1 kW up to 1 MW (1,000 kW), for residential, government, commercial and industrial customers. Only solar PV qualifies. The AENBD Code of Practice for low-voltage connection applies to small-scale systems below 0.9 MWac.
How are exports valued?Net charge = (energy imported × gazetted tariff) − (energy exported × gazetted tariff). Surplus credits carry forward for a maximum of 12 months, after which they are forfeited. The bill shows exports, imports, net billed energy and credits carried forward.
Is a licence needed?No. The net-metering guideline states that solar installations of not more than 1 MW under the programme are exempt from an electricity licence under the Act.
Which technical rules apply?AENBD’s Code of Practice for Small Scale Solar Photovoltaic System Connection to Low Voltage Network (issued 7 October 2020 under the Electricity Order 2017). It requires grid-following inverters with anti-islanding, IEC 61727 voltage trip settings, frequency in line with the National Grid Code and smart inverter features; inverters may not be used as an uninterruptible power supply on the grid.
What does it cost to join?The Department of Energy’s guidebook gives indicative costs per 1 kWp: net meter B$1,100–2,100, application fee B$5/kW and net-meter installation about B$150, plus structural assessment (B$300), electrical design (B$300) and testing and commissioning (B$200) at minimum capacity.
Can the network operator disconnect the system?Yes. The distribution service provider may disconnect supply at the point of common coupling if the system endangers safety, reliability or security, and must reconnect it once the risk has passed. The system must not be connected while the distribution service provider is supplying from standby generators.

Connecting a home system.

  1. Confirm eligibility: an existing DES customer with no arrears, installing solar PV of 1 kW to 1 MW on a roof, garage, car park or similar structure.
  2. Appoint a contractor or installer registered with the Department of Energy (at least ABCi category E01).
  3. The contractor checks the structural integrity of the roof and submits the assessment to the Building Authority, which issues an approval letter for construction.
  4. The contractor carries out a technical study with a professional electrical engineer and submits the net-metering assessment and application forms, endorsed drawings and structural approval to the Department of Energy as implementing agency, paying an application fee of B$5 per kW.
  5. A registered meter vendor installs an approved import/export net meter, paid for by the customer.
  6. The contractor installs, tests and commissions the system and sends the testing and commissioning report to the Department of Energy and the distribution service provider, which registers the net-metering account.

Brunei piloted net metering in 2020 with four houses and two government buildings, including a 100 kWp system on the Temburong District Office, the first and largest rooftop solar system on a government building, which cut its bill by about B$1,000 a month. The Department of Energy published the Solar PV Rooftop and Net-metering Programme Guidebook in March 2022 and rolled out the programme with Revision 01 of the net-metering guideline in February 2025.

Under the scheme the household keeps the environmental attributes of its generation, and pays for the solar system, the net meter and any check meter itself. Because the first 600 kWh a month cost only B$0.01/kWh, the value of solar depends on how much of a household’s use falls into the higher blocks: the guidebook’s example of a 7 kWp system for a 1,000 kWh-a-month home saves B$30.58 a month, with a payback of about 8 years on an assumed B$3,000 investment.

Licensing and approvals.

Requirements depend on the activity. The table sets out what each activity needs and who grants it.

Licensing and approvals.
ActivityLicence or registrationAuthorityNotes
Generate electricityElectricity licence under the Electricity Act (Chapter 223), administered by AENBD’s Compliance Unit. Size thresholds for licensing were not published on the sources read.Autoriti Elektrik Negara Brunei Darussalam (AENBD)The Act provides for the regulation and control of generation, transmission, distribution and use of electricity.
Generate on own premises (solar, up to 1 MW, net-metered)Exempt from an electricity licence under the net-metering programme; needs Department of Energy approval, Building Authority structural approval and installation by a registered contractor.Department of Energy (implementing agency); AENBDNet-metering guideline, Revision 01 (February 2025), section 8.4.
Store electricityNo separate storage licence identified. Net metering covers solar PV generation only; batteries are mentioned in the guidebook for off-grid and hybrid systems.—No storage-specific rules were identified in the sources read.
Export to the gridOnly through the net-metering programme, with an approved import/export meter and a commissioned system registered with the distribution service provider.Department of Energy; DESExports earn bill credits only; no cash payment.
Sell or supply electricity to othersLicence under the Electricity Act; in practice supply is carried out by DES and BPC.AENBDNo competitive retail market.
Transmission and distributionCarried out by DES and BPC under the Electricity Act.AENBDBoth act as distribution service providers under the Code of Practice.
Wholesale tradingNot applicable: there is no wholesale market or exchange.——
Aggregation / virtual power plantNo licence category for aggregators identified.—No market for aggregated distributed resources exists.
Balancing and grid servicesProvided by DES and BPC with their own plant.DES; BPCNo third-party procurement published.
Remote control of customer assetsNo dispatch or control right over household systems identified; the distribution service provider may disconnect a solar system at the point of common coupling for safety or security reasons.DES; BPCNet-metering guideline, chapter 4.
Install solar PVRegister with the Department of Energy as a solar PV supplier and/or installer, after first registering with ABCi under category P05 (suppliers) or E01 (installers). Net-metering work needs at least an E01 licence.Department of Energy; ABCiThe Department of Energy publishes the list of registered contractors (updated 30 September 2026).
Electrical installation workElectrical contractors and workers must be registered with DES; DES publishes lists of registered electrical companies and workers and issues worker pass cards.Department of Electrical ServicesPass Card Issuance Policy Rev 1 (28 February 2026).

Electricity in Brunei is governed by the Electricity Act (Chapter 223) (AENBD’s 2020 Code of Practice cites it as the Electricity Order 2017) and regulated by AENBD within the Department of Energy at the Prime Minister’s Office. Because the main utilities are a government department (DES) and a government-linked company (BPC), licensing matters mainly for independent and self-generation projects.

For households and businesses installing rooftop solar, the practical gateway is the net-metering programme rather than a licence: systems up to 1 MW are exempt from licensing, but the installer must be registered with the Department of Energy and the system must comply with AENBD’s Code of Practice.

Flexibility and grid services.

Aggregation of home equipment: No

Flexibility and grid services.
Market or serviceAccess for home equipmentMinimum sizeVia an aggregatorDetail
Frequency and reserveNo—NoDES; BPC. Provided by the utilities’ own gas-fired and diesel plant; no market is open to distributed assets.
Demand responseNo—NoNo demand-response programme or time-of-use tariff is published.
Net meteringRestricted1 kWNoDepartment of Energy. Solar PV of 1 kW to 1 MW can export for bill credits; this is a billing arrangement, not a flexibility service.

Brunei has no flexibility, balancing or capacity market, and no legal role for aggregators. DES and BPC balance their systems with their own gas-fired plant. The Code of Practice requires smart inverter features on net-metered systems, and DES has a Renewable Energy unit responsible for integrating solar, storage and distributed energy resources into the grid, but no programme that pays distributed assets for grid services was identified.

Smart meters.

Smart meters.
FactValue
Smart-meter rolloutNo national smart-meter rollout identified; prepaid metering widely available
Reading intervalNot published
Meter providerDES (standard meters); registered vendors for net meters
Prepaid tokensDES counters, BIBD NEXGEN, Baiduri b.Digital, Standard Chartered, TAIB, PowerKad, MyBillPayment and DST USMS
Net meterImport/export meter approved by the distribution service provider; B$1,100–2,100 per guidebook
Online servicesDES Paybill e-service; MeterKu meter profile form

DES offers both billed and prepaid supply. Prepaid tokens can be bought at DES counters, through bank apps and online banking, and through retail payment services. For net metering, the meter reading taken by the distribution service provider is the basis of settlement, and customers may add a check meter or a separate solar generation meter at their own cost. No official figure for the number of smart or prepaid meters was identified.

Renewable electricity.

Electricity generation mix (2023).

  • Fossil fuels (natural gas, coal, diesel): 99.9%
  • Solar: 0.1%
Source 15
Renewable electricity share
0.1% (2023)Source 15IRENA: 4 GWh of renewable (solar) generation out of 4,461 GWh in total, which IRENA rounds to 0% (4 ÷ 4,461 = 0.09%). No electricity imports were identified in the sources read.
Home solar
Not identified from a reliable public source.
Solar added each year
0 MW (2024)Source 15IRENA shows net renewable capacity change of about 0.1 MW in 2024.
Fossil fuels
1,231 MW (2024)Source 15IRENA total installed capacity, almost entirely fossil. DEPS gives 1,048.4 MW of generation capacity for 2024.
Solar PV
5 MW (2023)Source 15Derived from IRENA’s 11.0 W per person; approximate.
Wind
0 MW (2024)Source 15

Targets.

  • 30% renewable energy in total installed capacity by 2035 (Brunei National Climate Change Policy, 2020, Strategy 4)
  • National generation efficiency of at least 50% with Bukit Panggal phase 2 (Department of Energy, 2026)

Brunei’s electricity is almost entirely fossil-fuelled. IRENA’s emissions breakdown for electricity and heat in 2023 attributes 58% to gas and 41% to coal, and its capacity series shows about 220 MW of new fossil capacity in 2020. Solar generated 4 GWh in 2023, with a capacity utilisation of about 10%.

The 1.2 MW Tenaga Suria Brunei plant, commissioned by DES in 2010, was the first significant solar installation. Rooftop systems have since been added on government buildings, such as the 100 kWp Temburong District Office system (2021), and on BPC’s headquarters (191 kWp). DES now has a Renewable Energy unit, and the Department of Energy registers solar contractors and runs the net-metering programme. Solar resources are moderate: IRENA shows most of the country yielding 1.4–1.6 MWh per kWp a year, and wind resources are low.

Energy storage.

Home batteries
Not identified from a reliable public source.
Grid-scale storage
Not identified from a reliable public source.

No grid-scale battery storage project was identified. DES’s Renewable Energy unit is responsible for integrating storage alongside solar and distributed energy resources, and the Department of Energy’s guidebook describes batteries mainly for off-grid systems and as an option in hybrid systems. Net metering covers solar PV generation only.

Electricity suppliers.

Electricity suppliers.
SupplierMarket shareRenewable tariffTime of useDynamicExport tariff
Department of Electrical Services (DES)Supplies households nationwideNoNoNoLimited
Berakas Power Company Sdn Bhd (BPC)About 40% of national power demand (BPC)NoNoNoUnknown

Households buy electricity from DES, and cannot choose another supplier. BPC serves mostly strategic and critical loads in Brunei-Muara, such as government institutions, health facilities and some commercial and educational customers. Exports under net metering are credited on the DES bill rather than paid as a tariff.

Key organisations.

Key organisations.
OrganisationCategoryWhat it doesWhy it matters
Department of Energy, Prime Minister’s OfficeGovernmentEnergy policy; net-metering implementing agency; solar contractor registrationRuns the net-metering programme and keeps the list of registered solar PV contractors.
Autoriti Elektrik Negara Brunei Darussalam (AENBD)RegulatorElectricity Authority under the Electricity Act (Chapter 223)Issues electricity licences and the Code of Practice for connecting small-scale solar.
Department of Electrical Services (DES)DistributionGeneration, transmission, distribution and supplyThe national utility that connects and bills households and registers electrical workers.
Berakas Power Company Sdn Bhd (BPC)TransmissionOperator of the Berakas Power System in Brunei-MuaraServes about 40% of national demand, mainly strategic and critical loads.
Department of Economic Planning and Statistics (DEPS)GovernmentNational statistics officePublishes census, population and electricity production and consumption statistics.

Technical standards.

Technical standards.
AreaStandardIssued byNotes
Grid connection (small-scale solar)Code of Practice for Small Scale Solar Photovoltaic System Connection to Low Voltage Network (Rev 00, 7 October 2020)AENBDIssued under Part 3 of the Electricity Order 2017; applies to systems below 0.9 MWac on 400/230 V networks. Reproduced as Appendix A of the net-metering guideline.
Inverter voltage protectionIEC 61727 (voltage disturbance trip times)Referenced in the AENBD Code of PracticeContinuous operation between 85% and 110% of nominal voltage at the point of common coupling; trip within 0.1 s below 50% and 0.05 s at 135% or above.
Inverter fault currentIEEE 1547Referenced in the AENBD Code of PracticeUsed as the reference for inverter short-circuit contribution (typically 100–200% of rated current).
Anti-islandingCode of Practice section 7.5AENBDGrid-following, anti-islanding inverters only; must not energise the network during an outage or when the distribution service provider is supplying from generator sets.
FrequencyNational Grid Code section 2.5.5Referenced in the AENBD Code of PracticeThe distribution service provider maintains system frequency; small-scale PV must synchronise within 0.05 Hz, 2% voltage and 8 degrees.
Installer registrationABCi categories E01 (installer) and P05 (supplier); Department of Energy solar contractor registerABCi; Department of EnergyAt least E01 is required to take part in net metering.
Electrical installationElectrical Installation Requirements (2017) and ESCOM guidelinesDepartment of Electrical ServicesDES also runs product registration and keeps a list of approved electrical products.

Permissions.

Permissions.
PermissionRequiredLevelDetail
Net-metering approvalYesNationalApplication to the Department of Energy as implementing agency, with assessment and application forms, endorsed drawings and structural approval; fee B$5 per kW.
Building Authority approvalYesNationalApproval letter based on the contractor’s structural assessment of the roof before construction starts.
Professional engineer endorsementYesNationalTechnical study and drawings endorsed by a professional electrical engineer.
Electricity licenceNoNationalNet-metered solar up to 1 MW is exempt from an electricity licence.
Testing and commissioningYesNationalReport submitted to the Department of Energy and the distribution service provider before the net-metering account is registered.

A household wanting rooftop solar works through a registered contractor, who handles the structural check with the Building Authority, the engineering study, the application to the Department of Energy and the meter change. The guidebook describes three stages: appoint a contractor, submit documents for approval, then install once approved.

Support schemes, taxes and incentives.

Support schemes, taxes and incentives.
SchemeStatusTypeDetailPeriod
Net-metering programmeActiveNet meteringSolar PV of 1 kW to 1 MW can offset bills at the gazetted tariff, with credits rolled over for up to 12 months. No grant or cash export payment.Piloted 2020; rolled out February 2025

Data and connectivity.

Fixed broadband
22.5 % (fixed broadband subscriptions per 100 people) (2025)Source 13Fixed broadband penetration rate; mobile broadband penetration was 118.1%.
4G coverage
Not identified from a reliable public source.
5G coverage
Not identified from a reliable public source.

Brunei is highly connected: DEPS recorded 537,315 mobile subscribers and 645,103 internet subscribers in 2025, mostly mobile broadband, and 103,291 fixed broadband subscriptions. Electricity payments and prepaid top-ups are widely available through banking apps and the DST USMS service.

Grid conditions.

National peak demand
Not identified from a reliable public source.
Annual electricity demand
3.242 TWh (2024)Source 13Electricity consumption (DEPS). Production was 4,617.5 GWh in 2024; the 2025 provisional consumption figure (2,055.2 GWh) is not used.
Generation capacity
1.048 GW (2024)Source 13DEPS generation capacity 1,048.4 MW (1,050.3 MW provisional for 2025). IRENA gives 1,231 MW for 2024.
Interconnection
Not identified from a reliable public source.
Curtailment
Not identified from a reliable public source.

DEPS reports electricity supply coverage of 99.9% in 2023–2025, and IRENA records 100% access to electricity. Generation capacity has been stable at about 1 GW in DEPS data, while IRENA’s total of 1,231 MW includes capacity added in 2020.

The Bukit Panggal phase 2 project (215 MW) is the main planned addition. The government expects it to raise average generation efficiency from below 30% to at least 50%, reducing the gas burned per unit of electricity.

Regulatory changes.

Regulatory changes.
ChangeStatusDateDetail
AENBD appointed as Electricity AuthorityCurrent2 January 2019Licensing, compliance and codes under the Electricity Act (Chapter 223) handled by AENBD within the Department of Energy.
Net-metering programme rolled outCurrentFebruary 2025Revision 01 of the net-metering guideline and revised guidebook: solar PV of 1 kW to 1 MW, credits at the gazetted tariff for up to 12 months, licence exemption.
Bukit Panggal combined-cycle phase 2UpcomingContract signed 13 August 2026215 MW of new combined-cycle gas capacity built by Sinohydro Corporation under the 12th National Development Plan.
30% renewable capacity targetUpcoming2035Brunei National Climate Change Policy (2020) target for renewables in the total installed capacity mix.

Market indicators.

Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.

Market indicators.
IndicatorLevelBasis
Electricity costLowLow below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros).
Household electricity use—Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household).
Renewable shareLowLow below 30%, high at 60% or more (renewable share of electricity).
Smart-meter adoption—Low below 30%, high at 80% or more (share of meters that are smart).
Home solar adoptionLowSolar produced 4 GWh of 4,461 GWh in 2023 (IRENA); net metering only rolled out in 2025 after a six-site pilot, and the first tariff block of B$0.01/kWh limits savings.
Distributed energy marketLowNet metering is open to 1 kW–1 MW solar but requires structural, engineering and meter approvals; no other distributed-energy scheme identified.
Grid flexibility marketLowNo wholesale, balancing or flexibility market and no aggregator role.
Energy storage adoptionLowNo grid-scale battery storage or home-battery figure identified.
Renewable growth environmentLowIRENA shows almost no net renewable capacity added in 2022–2024, while the main new project is 215 MW of gas-fired capacity.

Sources.

Public sources used for this profile, with the date each was accessed.

Show all 18 sources
  1. Electricity tariff. Department of Electrical Services. accessed 10 October 2026.
  2. Organization overview. Department of Electrical Services. accessed 10 October 2026.
  3. Generation Division. Department of Electrical Services. accessed 10 October 2026.
  4. Department of Electrical Services home page (prepaid tokens and online services). Department of Electrical Services. accessed 10 October 2026.
  5. General documents (registered contractors and workers, installation requirements). Department of Electrical Services. accessed 10 October 2026.
  6. About BPC. Berakas Power Company Sdn Bhd. accessed 10 October 2026.
  7. Autoriti Elektrik Negara Brunei Darussalam (AENBD). Department of Energy, Prime Minister’s Office. accessed 10 October 2026.
  8. Net Metering Programme. Department of Energy, Prime Minister’s Office. accessed 10 October 2026.
  9. Net-metering Guideline, Revision 01 (incl. AENBD Code of Practice for Small Scale Solar PV System Connection to Low Voltage Network). Department of Energy, Prime Minister’s Office, 2025. accessed 10 October 2026.
  10. Guidebook: Solar PV Rooftop and Net-metering Programme (revised February 2025). Department of Energy, Prime Minister’s Office, 2025. accessed 10 October 2026.
  11. Registration as Solar PV Supplier / Contractor / Installer. Department of Energy, Prime Minister’s Office. accessed 10 October 2026.
  12. Contract signing for Bukit Panggal Combined Cycle Gas Turbines Power Station Phase 2 construction project. Department of Energy, Prime Minister’s Office, 2026. accessed 10 October 2026.
  13. Brunei Darussalam Key Indicators 2025. Department of Economic Planning and Statistics, 2026. accessed 10 October 2026.
  14. Media release: Report of the Population and Housing Census (BPP) 2021 — Demographic, Household and Housing Characteristics. Department of Economic Planning and Statistics, 2021. accessed 10 October 2026.
  15. Energy Profile: Brunei Darussalam. IRENA, 2025. accessed 10 October 2026.
  16. Monetary policy framework. Brunei Darussalam Central Bank. accessed 10 October 2026.
  17. ECB euro reference exchange rate: Singapore dollar (SGD). European Central Bank, 2026. accessed 10 October 2026.
  18. Urban population (% of total population) — Brunei Darussalam (SP.URB.TOTL.IN.ZS). World Bank, 2025. accessed 10 October 2026.

Questions about energy in Brunei.

Talk to us about Olmack in Brunei.Tell us about your home, housing portfolio or school estate in Brunei. We'll explain what is possible there now.