How electricity works in Cape Verde.
Cape Verde electricity 2026: EDEC tariffs and prepaid meters, ONSEC system operation, ARME regulation, island grids, microproduction rules and storage projects.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Cape Verdean escudo (CVE) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Cape Verde energy at a glance.
Key figures for households in Cape Verde. Each one links to its source on the full overview below.
Electricity price.
36.39 CVE per kWh for households, including taxes. Figures for 2026.
Renewable share.
16% of electricity from renewable sources. Figures for 2023.
Selling back to the grid.
Can homes export electricity? Limited. Details are in the export section below.
Four things to check in Cape Verde.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Cape Verde below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Cape Verde requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Cape Verde.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Cape Verde, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Cape Verde, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Cape Verde.
The energy market in Cape Verde, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 10 October 2026.
On this page22 sections
Cape Verde (Cabo Verde) is an Atlantic archipelago of ten islands, nine of them inhabited, with no fossil-fuel resources and no electrical connection to the African mainland or between islands. Each inhabited island runs its own grid, supplied mainly by diesel and fuel-oil power stations, with wind farms and solar parks on the larger islands. According to IRENA, the country generated 483 GWh in 2023, of which 16% came from renewable sources — almost all of it wind.
The sector was restructured in 2024. Decree-Law 34/2022 authorised the break-up of the former public utility Electra, and from mid-2024 its electricity activities passed to three companies: EPEC (thermal generation), EDEC (distribution and retail supply across the archipelago) and ONSEC (the state-owned national system operator, which buys power from EPEC and independent producers and supplies it to EDEC). Electra itself continues as a water company. The government has said that EPEC and EDEC are to be privatised; ONSEC stays public.
Tariffs are regulated by the Agência Reguladora Multissetorial da Economia (ARME). Government policy targets more than 50% renewable electricity by 2030 and close to 100% by 2040, supported by battery storage on several islands and a 20 MW / 179 MWh pumped-storage plant planned on Santiago. According to the World Bank, 98.4% of the population had access to electricity in 2024.
Energy snapshot.
Headline figures for electricity in Cape Verde. Each shows its data year and links to its source.
- Population527,326 peopleSource 122025
- HouseholdsNot identified from a reliable public source.
- Average household sizeNot identified from a reliable public source.
- Electricity use per householdNot identified from a reliable public source.
- Household price (CVE)36.4 CVE/kWhSource 12026
- Household price (EUR)0.33 EUR/kWhSource 322026
- Renewable electricity share16%Source 112023
- Solar capacityNot identified from a reliable public source.
- Wind capacityNot identified from a reliable public source.
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Single buyer
- Homes can export to the grid
- Limited
- Home equipment in grid services
- No
- Regulator
- Agência Reguladora Multissetorial da Economia (ARME)
- System operator
- Operador Nacional do Sistema Elétrico de Cabo Verde (ONSEC) — state-owned system operator and central buyer
- Distribution networks
- A single national distribution concessionaire, EDEC, on separate island grids (payments split into EDEC Norte and EDEC Sul)
- Currency
- Cape Verdean escudo (CVE)
- Voltage and frequency
- Not verified from an official source
Electricity prices in Cape Verde.
- Household price (CVE)
- 36.4 CVE/kWh (2026)Source 1EDEC low-voltage normal (BT) tariff for monthly consumption above 60 kWh, including 15% VAT, as published on EDEC’s tariff page (accessed October 2026). The first 60 kWh a month cost 30.60 CVE/kWh. Excludes the monthly meter rental (47.61–425.37 CVE depending on installed power). The government announced that 2026 tariffs are about 7% lower than in 2025; whether EDEC’s page already reflects every 2026 adjustment was not confirmed.
- Household price (EUR)
- 0.33 EUR/kWh (2026)Source 32Converted from 36.39 CVE/kWh at the fixed parity of 110.265 CVE per euro (rate unchanged since 1999; checked 10 October 2026). The government confirms the escudo is pegged to the euro, backed by a Portuguese credit line, but the numerical parity was taken from a secondary reference. Includes VAT; excludes meter rental.
- Typical annual electricity bill
- Not identified from a reliable public source.
Electricity prices are set nationally under ARME’s oversight and are the same on every island served by EDEC. Household (BT normal) customers pay a two-band rising-block tariff: a lower rate for the first 60 kWh a month and a higher rate for everything above. All published rates include 15% VAT, which has applied to the full taxable value of electricity since Law 23/VIII/2013.
Recent trend
Tariffs rose after 2022, when the government adopted measures to cushion the effect of the war in Ukraine on fuel-based electricity costs. In January 2026 the government announced a second consecutive reduction, of about 7%, saying tariffs were 27% lower than in 2024. For comparison, the tariff in force from March 2017 was 26.09 CVE/kWh up to 60 kWh and 33.98 CVE/kWh above, VAT included.
Fixed charges and other items
Instead of a standing charge per kVA, domestic bills carry a monthly meter rental that rises with installed power. EDEC also collects the audiovisual contribution from customers using more than 40 kWh a month. New connections cost 169 CVE (single-phase) or 339 CVE (three-phase), plus line-extension costs that depend on distance and power.
Social tariff
A social electricity tariff, approved in 2018, is available to families in groups 1 and 2 (very poor and poor) of the Cadastro Social Único; the state also pays connection costs for these households. The discount level was not verified from a primary source.
Tariff reform
On 30 June 2026 the Council of Ministers approved a draft resolution to update the legal framework for electricity tariffs, aiming at more predictability and transparency. It is to be submitted to Parliament.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | Low-voltage normal (BT): 30.60 CVE/kWh for the first 60 kWh a month and 36.39 CVE/kWh above 60 kWh, both including 15% VAT, plus a monthly meter rental of 47.61 CVE (up to 2.2 kW), 115.63 CVE (3.3–6.6 kW), 304.85 CVE (9.9 kW) or 425.37 CVE (over 9.9 kW). |
| Prepayment | Yes | EDEC offers prepaid metering on request. Credit is sold in EDEC shops, with the Vinti4 network (ATM, POS, home banking, web) being tested. Priority is given to emigrants’ homes, rented properties, public buildings, hard-to-reach locations and customers in financial difficulty. |
| Other | Yes | Special low voltage (BTE) and medium voltage (MT) are billed as a demand charge plus energy: BTE 317.63 CVE/kW and 24.56 CVE/kWh; MT 292.55 CVE/kW and 19.60 CVE/kWh (VAT included). Public lighting: 21.10 CVE/kWh. |
| Time-of-use | No | No time-of-use tariff for households was identified. |
Household prices compared with neighbouring countries (EUR per kWh).
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- Not identified from a reliable public source.
- Average daily use per household
- Not identified from a reliable public source.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- Not identified from a reliable public source.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- Not identified from a reliable public source.
Access to electricity is almost universal: 98.4% of the population in 2024, according to the World Bank, and IRENA shows about 84% of the population with access to clean cooking in 2023. EDEC serves about 160,000 customers.
IRENA records 483 GWh of generation in 2023, up from 430 GWh in 2018. No official breakdown of household consumption, air-conditioner ownership or electric-vehicle numbers was identified.
Where a meter cannot be read, EDEC estimates consumption for up to six months from the customer’s average, then adjusts once an actual reading is taken.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- Not identified from a reliable public source.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- Not identified from a reliable public source.
- Apartments and flats
- Not identified from a reliable public source.
- Urban population
- 77.6 % of population (2025)Source 13World Bank estimate.
More than three-quarters of the population lives in towns, according to the World Bank, with Praia on Santiago the largest urban area, followed by Mindelo on São Vicente.
Tenure and dwelling-type data come from INE Cabo Verde’s 2021 census, which could not be accessed for this profile, so these figures are left blank. To open an electricity contract, EDEC asks for a municipal habitability certificate and the property’s land-registry (matrix) certificate, and tenants must show a rental agreement or the owner’s authorisation.
How the grid works in Cape Verde.
- TransmissionOperador Nacional do Sistema Elétrico de Cabo Verde (ONSEC)
- DistributionA single national distribution concessionaire, EDEC, on separate island grids (payments split into EDEC Norte and EDEC Sul)
- MeteringEDEC
- Supply1 or more retail suppliers
Physical flow
Cape Verde has no cross-border or inter-island connections, so each inhabited island balances its own supply and demand. Thermal plants run by EPEC — 200 MW installed, of which 160 MW available in 2025 — supply most electricity. Wind farms run by the public–private company Cabeólica on Santiago, São Vicente, Sal and Boa Vista, plus solar parks and smaller private producers, provide the renewable share. IRENA reports that fossil fuels produced 406 GWh of the 483 GWh generated in 2023.
Santiago, home to Praia, is by far the largest system. A 60 kV line of about 18 km is planned to connect the future pumped-storage plant in Ribeira Grande de Santiago to the island grid.
Commercial flow
Before 2024 Electra was generator, network operator and supplier, buying wind power from Cabeólica and other producers. Under the restructuring authorised by Decree-Law 34/2022, ONSEC now buys electricity from EPEC and independent power producers and supplies it to EDEC, which sells to end customers at regulated tariffs. This is a single-buyer model.
Privatisation
The government has stated that EPEC and EDEC will be privatised through competitive tenders while ONSEC remains state-owned. The outcome of those processes by October 2026 was not verified.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministério do Ambiente, Ação Climática e Energia | The ministry responsible for energy in the government formed in 2026 (energy previously sat with the Ministry of Industry, Commerce and Energy). Sets policy, renewable targets and the tariff framework; production systems are licensed through the national energy information system (SGIE). |
| Regulator | Agência Reguladora Multissetorial da Economia (ARME) | Multi-sector economic regulator; electricity had been regulated since 2004 by its predecessor, the Agência de Regulação Económica (ARE). Oversees and adjusts electricity tariffs and was consulted on the standard contract for micro-producers. |
| System operator | Operador Nacional do Sistema Elétrico de Cabo Verde (ONSEC) | State-owned company created in the 2024 restructuring. Manages, coordinates and balances production, transmission and distribution in real time; buys power from EPEC and independent producers; operates transmission assets and supplies EDEC. Leads battery and pumped-storage projects. |
| DSO | Empresa de Distribuição de Eletricidade de Cabo Verde (EDEC) | Distribution and retail concessionaire for the whole archipelago since 1 July 2024, with about 160,000 customers, 400 staff and 24 shops. Due to be privatised. |
| Supplier | EDEC | Sole retail supplier at regulated tariffs; bills and payments are handled under two entities, EDEC Norte and EDEC Sul. |
| Metering | EDEC | Installs, rents out, reads and verifies meters (postpaid and prepaid). |
Compared with the UK system.
| UK concept | Cape Verde equivalent | How it works |
|---|---|---|
| DNO | EDEC | One distribution company serves all islands, but each island is a separate grid. There are no regional network companies; EDEC builds, maintains and extends the low- and medium-voltage networks everywhere. |
| National Grid/NESO | ONSEC | ONSEC combines the roles of system operator and central buyer. It dispatches thermal and renewable plants on each island grid in real time and passes the aggregated supply to EDEC. There is no national transmission network linking the islands. |
| MPAN | EDEC contract and invoice “Referência” | A supply point is identified by the EDEC contract at a consumption location, tied to a meter number. The monthly invoice carries a payment “Referência” used with the EDEC Norte or EDEC Sul entity at ATMs, in home banking and on payment portals. No public, standardised supply-point code was identified. |
| MPRN | No equivalent | No piped natural-gas network or gas supply-point register was identified; LPG is among the imported fuels used. |
| Meter operator | EDEC | The distributor owns the meters and charges a monthly meter rental. There is no competitive metering market. Customers can ask EDEC to test a meter; the test is free if the complaint is upheld and costs 651 CVE otherwise. |
| Supplier | EDEC | There is no retail competition: every grid customer buys from EDEC at regulated tariffs. Households that install their own solar can sell surplus under the microproduction regime. |
| Smart-meter infrastructure | Prepaid meters and early smart-meter deployment | Postpaid meters read by EDEC are the standard arrangement; prepaid meters are available on request. The government has reported a new national dispatch centre, SCADA and the introduction of smart meters, but no national data hub or rollout figures. |
How a supply point is identified.
| Question | Answer |
|---|---|
| What is it called? | Contrato de fornecimento / Referência (EDEC supply contract and payment reference) (Referência) |
| Who issues it? | EDEC, when a supply contract is signed for a consumption location |
| Format | Not published. The invoice shows a payment “Referência”, used together with the EDEC Norte or EDEC Sul payment entity; the contract is also linked to a meter number. |
| Length | Not published |
| Stays with the property when you switch supplier? | No |
| Where to find it | On the monthly EDEC invoice (both electricity-only and combined electricity-and-water invoices), which also shows the amount due and payment deadline. |
| Electronic access | Invoices are paid with the reference at Vinti4 ATMs, through home banking and on payment platforms (FAXI, PAGALI, LESTOPAY) or by QR code; no online customer account with consumption data was identified. |
| Third-party access | No framework for third-party access to metering or customer data was identified. |
| Who keeps the register | EDEC’s customer and contract database |
| Register scope | National |
In Cape Verde a household connection is administered as a supply contract between the customer and EDEC for a specific consumption location. For a new connection the applicant goes to an EDEC shop with an identity card or passport, a tax number (NIF), the municipal habitability certificate, the property’s land-registry certificate and an electrical project with a location plan. Where a contract existed before, the applicant must also prove the right to occupy (deed, purchase contract, inheritance papers, rental agreement or owner’s authorisation).
Before signing, EDEC inspects the site and checks that no active contract exists at the location, that there are no outstanding debts at the property or in the applicant’s name, and that a meter is available. The contract is executed on a receipt signed by both parties and the connection fee is paid on the spot.
The contract belongs to the holder, not the property: a new occupant takes over by requesting a change of holder (with ID, NIF and proof that all invoices are paid, plus the connection fee), and a holder ending a contract asks EDEC to disconnect and settles the final bill. If a meter has been removed, a new contract is needed, quoting the old meter number where available.
EDEC does not publish a standard format for its identifiers. The monthly invoice carries a payment “Referência” which, together with the EDEC Norte or EDEC Sul entity, is what customers enter to pay at ATMs or online. Because EDEC is the only distributor and supplier, its customer database is in practice the national register of supply points.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Yes |
| Net metering | Unknown |
| Net billing | Unknown |
| How exported electricity is paid | Microproducers sell surplus under a standard purchase-and-sale contract for micro-producer customers, approved by Order 43/2019 after consultation with ARME. The purchase tariff was not verified from a primary source. |
| Can households sell solar power to the grid? | Yes. Decree-Law 1/2011 created a microproduction regime under which low-voltage customers can generate from renewables and inject surplus into the public electricity network under a standard contract. |
| Is there a size limit? | Size limits for microproduction are set in Decree-Law 1/2011, but the exact thresholds were not verified for this profile. |
| How fast is self-generation growing? | The government reported 2 MW of microproduction in 2016 and 9 MW in 2023, about 13 MW licensed by late 2022, and 30 MW of self-consumption capacity by November 2025. |
| Are inspections required? | Yes. Microproduction installations are inspected before connection to protect network quality; CERMI has run training for these inspectors. |
Connecting a home system.
- Hold a low-voltage supply contract with EDEC; low-voltage customers may become microproducers under Decree-Law 1/2011.
- Have the installation designed and installed, and register/license the production system through the energy authorities’ licensing process.
- Have the installation inspected by a qualified inspector (CERMI has trained inspectors for microproduction installations).
- Sign the standard micro-producer electricity purchase-and-sale contract (Order 43/2019) and inject surplus into the public network.
Small-scale renewable generation is governed by Decree-Law 1/2011 of 3 January, which regulates independent production and microproduction from renewable sources. Low-voltage customers can become microproducers, use their own output and inject surplus into the public electricity network, provided the installation is inspected to protect network quality. Article 64 requires micro-producer sales contracts to follow an approved model, which Order 43/2019 provides.
Self-generation has grown quickly. The government reported 2 MW of microproduction in 2016 and 9 MW in 2023, and in November 2025 the energy minister said self-production for self-consumption had reached 30 MW, avoiding more than 5,000 tonnes of fuel imports a year. On Boa Vista alone microgeneration grew from 6 kW in 2016 to 4,020 kW by early 2026.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate for own use with surplus export (microproduction) | Registration/licensing and inspection under Decree-Law 1/2011; available to low-voltage customers; standard sale contract under Order 43/2019 | Energy directorate (ministry); ARME (contract model) | Size thresholds not verified. |
| Independent power production for sale | Licence and power purchase agreement under Decree-Law 54/99 (electricity system law) and Decree-Law 1/2011 | Ministry responsible for energy; ONSEC as buyer | Projects in the Renewable Energy Development Zones (ZDER) defined by the PESER are exempt from an environmental impact assessment for licensing. |
| Thermal generation for the public system | Carried out by EPEC | State | EPEC is to be privatised. |
| Transmission and system operation | Carried out by ONSEC | State | ONSEC stays state-owned. |
| Distribute and supply electricity | Public-service concession held by EDEC since 1 July 2024 | State; ARME (tariffs) | No retail competition. |
| Store electricity | No specific storage licensing regime identified | — | Grid-scale storage is procured by ONSEC and the state (BESS, pumped storage) or built by producers such as Cabeólica. |
| Aggregate, trade, balancing, grid services, VPP, remote control of assets | No regime identified | — | There is no wholesale or flexibility market. |
The basic law of the electricity system is Decree-Law 54/99 (updated to 2006), which covers production licensing, transmission and distribution, concessions, tariffs and the promotion of renewables. Decree-Law 1/2011 adds the regime for independent production and microproduction from renewable sources. Decree-Law 34/2022 authorised the restructuring that created EPEC, EDEC and ONSEC.
The Sistema de Gestão de Informação Energética, launched in 2021, handles registration of technical professionals and companies and the licensing of production systems in one place.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Energy, balancing and ancillary services | No | — | No | ONSEC. ONSEC balances each island grid by dispatching thermal plants, renewables and utility batteries. No market for distributed resources, demand response or aggregation was identified. |
Cape Verde has no wholesale or flexibility market. ONSEC buys electricity under contracts with EPEC and independent producers and balances the small island grids centrally, increasingly with utility-scale batteries that let more wind and solar be absorbed.
There is no time-of-use tariff for households; only larger customers on special low voltage or medium voltage pay a demand charge.
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | Smart meters introduced but no published rollout figures; prepaid meters available on request |
| Reading interval | Not published |
| Meter owner | EDEC (monthly meter rental) |
| Payment modes | Postpaid (monthly invoice) and prepaid |
| Estimated billing | Up to 6 months on average consumption if no reading |
| Meter test fee | 651 CVE if complaint unfounded |
| Smart-meter share | Not published |
Postpaid customers have meters read by EDEC and receive a monthly invoice; customers can also report readings by phone, email or in a shop. Prepaid metering is available on request, with credit sold in EDEC shops and payment through the Vinti4 network being tested.
The government lists a new national dispatch centre, a SCADA system and the introduction of smart meters among recent efficiency measures, and has earmarked €7 million to reduce technical and commercial losses, especially in Praia. No figures on the number of smart meters or reading intervals have been published.
Renewable electricity.
Electricity generation mix (2023).
- Fossil fuels: 84%
- Wind: 15%
- Solar: 1%
- Renewable electricity share
- 16% (2023)Source 1177 GWh of renewable generation (70 GWh wind, 7 GWh solar) out of 483 GWh in 2023, per IRENA. Cape Verde has no electricity imports. The Prime Minister put the share at 18–20% in May 2023, and government targets aim for over 35% by 2026.
- Home solar
- 30 MW (2025)Source 22Self-production for self-consumption across all customer types, as stated by the energy minister in November 2025; not residential only.
- Solar added each year
- 5 MW (2024)Source 11
- Total installed (all sources)
- 0.2 GW (2024)Source 11Rounded value in IRENA’s chart; renewables about 27% of capacity.
- Thermal (EPEC)
- 200 MW (2025)Source 9160 MW available.
- Wind — Cabeólica expansion (Santiago)
- 13.5 MW (2025)Source 35Three 4.5 MW turbines; not the national total.
- Solar added in 2024
- 5 MW (2024)Source 11
Targets.
- More than 35% of electricity from renewables by 2026 (as stated by the Prime Minister in February 2026).
- More than 50% renewable electricity by 2030.
- Close to 100% renewable electricity by 2040.
- Electricity Sector Master Plan 2018–2040 (Resolution 39/2019) sets the least-cost expansion path for all nine islands.
Wind is Cape Verde’s main renewable source. IRENA records 70 GWh of wind and 7 GWh of solar in 2023, 16% of generation. Cabeólica, a public–private partnership, began operating in 2009 with four wind farms on Santiago, São Vicente, Sal and Boa Vista (25.5 MW, 30 turbines) and says it supplies about 18% of the country’s electricity; its 2025 expansion added three 4.5 MW turbines on Santiago.
Solar is growing fastest through self-consumption: the government reported 30 MW of self-production by November 2025. Utility solar parks with storage have been contracted on Boa Vista, São Vicente and Sal, and a 5 MW solar park on Sal (2024) helped the island exceed 40% renewables.
Policy rests on the Strategic Plan for Renewable Energies (PESER, Resolution 7/2012), which defines Renewable Energy Development Zones on every island, the National Renewable Energy Action Plan 2015–2020/2030 and the Electricity Sector Master Plan 2018–2040.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- 26 MWh (2025)Source 35Cabeólica battery systems inaugurated in December 2025, expected to reach nearly 30 MWh on completion. Excludes other utility batteries for which no capacity was published.
Storage is central to raising renewable penetration on small isolated grids. Sal hosted the first grid-connected battery, 1 MW, announced in 2020. Cabeólica’s battery systems, financed with €55 million of bridge finance from the Africa Finance Corporation, were inaugurated in December 2025, and ONSEC is deploying batteries on six smaller islands.
The largest project is the 20 MW / 179 MWh pumped-storage plant on Santiago, which the government expects to cut fuel use substantially and which is due to start operating in late 2028 or early 2029.
Storage projects.
- Santiago pumped-storage plant: 20 MW / 179 MWh closed-loop pumped hydro in Ribeira Grande de Santiago, financed with the EIB and EU under Global Gateway; tender launched in 2026, operation expected late 2028 or early 2029.
- Cabeólica BESS: Batteries of 26 MWh (rising to about 30 MWh) at Cabeólica’s wind farms, inaugurated December 2025, including systems on Sal and Boa Vista (€6 million each, early 2026).
- ONSEC island BESS programme: Battery systems for Boa Vista, Santo Antão, São Nicolau, Maio, Fogo and Brava.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Empresa de Distribuição de Eletricidade de Cabo Verde (EDEC) | Sole supplier on all island grids (about 160,000 customers) | No | No | No | Yes |
EDEC is the only electricity supplier on the public grid, at nationally regulated tariffs. Households and businesses with their own solar can sell surplus under the standard micro-producer contract.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Ministério do Ambiente, Ação Climática e Energia | Government | Ministry responsible for energy | Sets energy policy, renewable targets and the tariff framework. |
| Agência Reguladora Multissetorial da Economia (ARME) | Regulator | Economic regulator | Oversees electricity tariffs and approved the micro-producer contract model. |
| ONSEC | Transmission | National system operator and central buyer | Dispatches every island grid, buys from producers and runs storage projects. |
| EDEC | Distribution | Distribution and supply concessionaire | Connects customers, signs supply contracts, supplies meters and publishes tariffs. |
| Cabeólica | Renewable Energy | Wind producer and storage operator | Largest renewable producer, with wind farms and batteries on four islands. |
| CERMI — Centro de Energias Renováveis e Manutenção Industrial | Renewable Energy | Renewable energy training centre (Decree-Law 29/2014) | Trains installers and inspectors of microproduction installations. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Electricity system framework | Decree-Law 54/99 (updated to 2006) | Government of Cabo Verde | Production licensing, networks, concessions, tariffs and quality of service. |
| Independent and microproduction | Decree-Law 1/2011; Order 43/2019 (micro-producer contract) | Government of Cabo Verde | Sets the regime for renewable self-generation and surplus sale. |
| Installation inspection | Inspection of microproduction installations by trained inspectors | Energy directorate; CERMI (training) | A 64-hour CERMI course qualifies electrical professionals to inspect microproduction installations. |
| Grid connection (inverter / interconnection technical rules) | No published grid code for small generators identified | — | Not found in the sources consulted. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| EDEC supply contract | Yes | National | Signed in an EDEC shop with ID, NIF, habitability certificate, land-registry certificate and an electrical project; site inspection first. |
| Municipal habitability certificate | Yes | Local | Issued by the municipality; needed for a new connection. |
| Microproduction registration, inspection and contract | Yes | National | Under Decree-Law 1/2011 and Order 43/2019 to connect and sell surplus. |
| Environmental impact assessment | Limited | National | Not required for projects inside the Renewable Energy Development Zones (ZDER). |
| Planning permission for rooftop solar | Unknown | Local | No national rule identified. |
For households the main relationship is with EDEC. Self-generation that exports to the grid goes through the microproduction regime: registration and licensing of the system, inspection, and the standard sale contract.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Interest-rate subsidy for microproduction loans | Active | Subsidised credit | State subsidy of interest on bank loans for renewable self-production by households, micro and small enterprises on low voltage, under a protocol signed with five banks (BCA, CECV, BI, IIB, BCN) on 29 November 2022. The 2025 budget extended it to special low-voltage (BTE) customers, including small and medium industries. | Nov 2022 – (continuing in the 2025 budget) |
| Fiscal and customs incentives for renewable equipment and EVs | Active | Tax and customs relief | The 2025 State Budget continued fiscal and customs incentives for renewable production equipment and electric vehicles. | — |
| Social energy tariff | Active | Social tariff | Reduced tariff and state-paid connection for families in groups 1 and 2 of the Cadastro Social Único (approved 2018). | — |
Data and connectivity.
- Fixed broadband
- 74.7 % of population using the internet (2024)Source 15Share of individuals using the internet (ITU via World Bank), not fixed-broadband coverage.
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
About three-quarters of the population used the internet in 2024, according to the World Bank.
Electricity bills are commonly paid electronically through the Vinti4 interbank network, home banking, payment platforms and QR codes. No information was identified on the communication technologies used by smart meters.
Grid conditions.
- National peak demand
- Not identified from a reliable public source.
- Annual electricity demand
- 0.483 TWh (2023)Source 11Total generation; with no imports, generation equals supply before losses.
- Generation capacity
- 0.2 GW (2024)Source 11Rounded value in IRENA’s installed-capacity chart.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
Running nine small isolated grids on imported fuel is costly and limits how much variable wind and solar each system can absorb. Storage, new dispatch and SCADA systems, and loss-reduction work in Praia are the main responses.
Reliability varies: in August 2025 the national civil protection service met EDEC to follow the restoration of supply on São Vicente after an outage.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| New legal framework for electricity tariffs | Upcoming | Approved by Council of Ministers 30 June 2026; to Parliament | Draft resolution to update the tariff regime for more predictability and transparency. |
| Santiago pumped-storage plant | Upcoming | Late 2028 / early 2029 | 20 MW / 179 MWh plant; operation and maintenance concession tendered in 2026. |
| Privatisation of EPEC and EDEC | Upcoming | Not confirmed | Generation and distribution companies to be privatised by tender; ONSEC stays public. |
| 2026 tariff reduction | Current | January 2026 | About 7% lower tariffs, the second consecutive annual cut (27% below 2024). |
| Sector unbundling (EPEC, EDEC, ONSEC) | Current | June–July 2024 | Electra’s electricity activities split into generation, distribution/supply and system operation under Decree-Law 34/2022. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | High | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | — | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | Low | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Medium | Microproduction regime with standard export contract since 2011/2019 and subsidised loans; self-consumption capacity reported at 30 MW in 2025 against ~0.2 GW total capacity. |
| Distributed energy market | Medium | Self-production grew from 2 MW (2016) to 30 MW (2025) per government statements. |
| Grid flexibility market | Low | Single-buyer model with no wholesale or flexibility market. |
| Energy storage adoption | Medium | Utility batteries of about 26–30 MWh inaugurated in 2025–26, batteries on six more islands and a 179 MWh pumped-storage plant tendered. |
| Renewable growth environment | Medium | Renewables 16% of generation in 2023 (IRENA); 13.5 MW wind and 5 MW solar added 2024–25; targets of over 50% by 2030. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 39 sources
- Tarifas. EDEC, 2026. accessed 10 October 2026.
- EDEC — Empresa de Distribuição de Eletricidade de Cabo Verde. EDEC. accessed 10 October 2026.
- Contrato de energia. EDEC. accessed 10 October 2026.
- Pré-pago. EDEC. accessed 10 October 2026.
- Fatura. EDEC. accessed 10 October 2026.
- Perguntas frequentes. EDEC. accessed 10 October 2026.
- ONSEC — Operador Nacional do Sistema Elétrico. ONSEC. accessed 10 October 2026.
- Projetos. ONSEC, 2026. accessed 10 October 2026.
- EPEC — Empresa de Produção de Eletricidade de Cabo Verde. EPEC, 2025. accessed 10 October 2026.
- Electra SA. Electra. accessed 10 October 2026.
- Energy Profile: Cabo Verde. IRENA, 2025. accessed 10 October 2026.
- Population, total — Cabo Verde. World Bank, 2025. accessed 10 October 2026.
- Urban population (% of total) — Cabo Verde. World Bank, 2025. accessed 10 October 2026.
- Access to electricity (% of population) — Cabo Verde. World Bank, 2024. accessed 10 October 2026.
- Individuals using the Internet (% of population) — Cabo Verde. World Bank, 2024. accessed 10 October 2026.
- “A Electra está preparada para a mudança” – Ministro Alexandre Monteiro. Governo de Cabo Verde, 2024. accessed 10 October 2026.
- Discurso de S.E. Primeiro Ministro no debate parlamentar Política de Privatizações. Governo de Cabo Verde, 2024. accessed 10 October 2026.
- Empresas e os cabo-verdianos vão pagar cerca de 7% menos na tarifa de eletricidade em 2026. Governo de Cabo Verde, 2026. accessed 10 October 2026.
- Conselho de Ministros aprova Programa do Governo para a XI Legislatura, Moção de Confiança e proposta sobre tarifas de eletricidade. Governo de Cabo Verde, 2026. accessed 10 October 2026.
- Governo assina com os bancos nacionais um protocolo para bonificação de taxas de juros para a microprodução de energias renováveis. Governo de Cabo Verde, 2022. accessed 10 October 2026.
- Ministro Alexandre Monteiro apresenta Orçamento de Estado para 2025 com foco na aceleração da Transição Energética. Governo de Cabo Verde, 2024. accessed 10 October 2026.
- Ministro Alexandre Monteiro preside abertura do XI Simpósio Germano-Cabo-Verdiano de energia. Governo de Cabo Verde, 2025. accessed 10 October 2026.
- Discurso do Primeiro Ministro no debate parlamentar sobre a Transição Energética. Governo de Cabo Verde, 2023. accessed 10 October 2026.
- Cabo Verde com mais Inspectores de Instalações de Microprodução com base em Energias Renováveis. Governo de Cabo Verde, 2019. accessed 10 October 2026.
- Sistema de Gestão de Informação Energética apresentado hoje aos stakeholders. Governo de Cabo Verde, 2021. accessed 10 October 2026.
- Reduzir a pobreza através da Tarifa Social de Energia. Governo de Cabo Verde, 2021. accessed 10 October 2026.
- Central de armazenamento de energia por bombagem hídrica de Santiago avança para fase de concurso. Governo de Cabo Verde, 2026. accessed 10 October 2026.
- Primeiro Ministro na Boa Vista: Inaugurado o Sistema de Armazenamento de Energia em Baterias. Governo de Cabo Verde, 2026. accessed 10 October 2026.
- Primeiro Ministro inaugura no Sal a Extensão da Central Elétrica e o Sistema de Armazenamento de energia em Baterias. Governo de Cabo Verde, 2026. accessed 10 October 2026.
- Energias Renováveis: Sal será primeira ilha a ter solução de armazenamento conectado a rede. Governo de Cabo Verde, 2020. accessed 10 October 2026.
- S&P eleva rating de Cabo Verde para ‘B+’. Governo de Cabo Verde, 2026. accessed 10 October 2026.
- Cape Verdean escudo (fixed parity 1 EUR = 110.265 CVE). Wikipedia. accessed 10 October 2026.
- Informações sobre o Setor da Energia em Cabo Verde. Cabo Verde TradeInvest, 2018. accessed 10 October 2026.
- Cabeólica — Projeto de Expansão. Cabeólica. accessed 10 October 2026.
- Angola, Cabo Verde inaugurate major co-located battery storage projects. ESS News, 2025. accessed 10 October 2026.
- Decree-Law No. 34/2022 authorizing Electra S.A. to proceed with the dissolution of Electra Sul and Electra Norte. ECOLEX (FAOLEX), 2022. accessed 10 October 2026.
- Order No. 43/2019 approving the draft Agreement for the Purchase and Sale of Electricity for micro-producer customers. ECOLEX (FAOLEX), 2019. accessed 10 October 2026.
- Decree-Law No. 54/99 establishing the basic law for the Electricity System of Cape Verde. ECOLEX (FAOLEX), 1999. accessed 10 October 2026.
- Resolution No. 39/2019 approving the Master Plan of the Electric Sector 2018-2040. ECOLEX (FAOLEX), 2019. accessed 10 October 2026.
Questions about energy in Cape Verde.
Household tariffs are regulated nationally. EDEC charges 30.60 CVE/kWh for the first 60 kWh a month and 36.39 CVE/kWh above that, VAT included, plus a monthly meter rental from 47.61 CVE. At the fixed rate of 110.265 CVE per euro, 36.39 CVE is about €0.33/kWh.
Since July 2024 the Empresa de Distribuição de Eletricidade de Cabo Verde (EDEC) has been the distribution and supply concessionaire for all islands. ONSEC operates the system and buys power from EPEC and independent producers such as Cabeólica.
Under Decree-Law 34/2022 Electra’s electricity activities were split in 2024 into EPEC (thermal generation), EDEC (distribution and supply) and ONSEC (system operation). Electra continues as a water company.
Yes. Under Decree-Law 1/2011 low-voltage customers can become microproducers and sell surplus to the grid under a standard contract approved by Order 43/2019. Installations must be inspected, and subsidised loans are available.
There is no published standard supply-point code. A connection is identified by the EDEC supply contract and meter at a consumption location, and the monthly invoice carries a payment “Referência” used with the EDEC Norte or EDEC Sul entity.
IRENA reports 16% renewable generation in 2023, mostly wind. The government targets over 50% by 2030 and close to 100% by 2040.
The Agência Reguladora Multissetorial da Economia (ARME) regulates tariffs; the ministry responsible for energy sets policy.
