Countries

Energy in Cyprus, explained.

How electricity works in Cyprus: prices, the grid and local rules. Olmack status: Not yet available. Information last checked 1 October 2026.

Olmack in Cyprus: Not yet available.Olmack is not offered in Cyprus yet. The market information on this page is provided for reference. Information last checked 1 October 2026.
Energy-market overview

How electricity works in Cyprus.

Cyprus electricity market 2026: an isolated oil-fired grid, EAC tariffs, the 10-digit premises number, net billing for new solar, heavy curtailment and smart meters.

This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Euro (EUR) where they relate to prices.

Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.

At a glance

Cyprus energy at a glance.

Key figures for households in Cyprus. Each one links to its source on the full overview below.

  • Electricity price.

    0.277 EUR per kWh for households, including taxes. Figures for 2025-H2.

  • Household use.

    4,877 kWh a year for a typical household. Figures for 2024.

  • Renewable share.

    27.8% of electricity from renewable sources. Figures for 2025.

  • Selling back to the grid.

    Can homes export electricity? Yes. Details are in the export section below.

Before you start

Four things to check in Cyprus.

Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.

  1. Check the local rules.

    Read the connection, export and permission rules for Cyprus below, and ask your local grid operator if anything is unclear.

  2. Choose a qualified installer.

    Look for an installer listed on an official register, with the certifications Cyprus requires for the work.

  3. Look at current schemes.

    Check which support schemes are open now. Closed or scheduled schemes are labelled as such.

  4. Talk to your energy supplier.

    Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.

Local detail

Schemes, rules and certifications in Cyprus.

The full detail sits in the sections below. Each item shows its status and links to the official source.

  • Support schemes.

    Grants, tax relief and export payments in Cyprus, each labelled Active, Scheduled or Closed.

  • Connection and export.

    How equipment is connected to the grid in Cyprus, and the steps to export electricity.

  • Standards and certifications.

    The technical standards and installer certifications that apply to energy equipment in Cyprus.

Full overview

The energy market in Cyprus, in detail.

Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.

Profile last updated 1 October 2026.

On this page22 sections

Cyprus runs one of the few electricity systems in the EU with no interconnection to any other country. Every kilowatt-hour has to be generated on the island at the moment it is used, mostly by the oil-fired power stations of the state-owned Electricity Authority of Cyprus (EAC) at Vasiliko, Dhekelia and Moni. The rest comes from a fast-growing fleet of solar systems and a small amount of wind and biogas. Renewables supplied 27.75% of generation in 2025, according to Ember.

EAC remains vertically integrated but operationally unbundled. It owns the transmission network, owns and operates the single nationwide distribution network through its Distribution System Operator (DSO), runs EAC Generation, and supplies most customers through EAC Supply. A separate public-law body, the Transmission System Operator Cyprus (TSOC), operates the transmission system and, since 1 October 2025, the competitive wholesale market. The Cyprus Energy Regulatory Authority (CERA) regulates the sector.

Rooftop solar is widespread: by the end of 2025 about 95,600 self-consumption systems, around 600 MW, were connected to the distribution network. Net metering closed to new applicants at the end of 2025, and systems applying from 1 January 2026 are settled under net billing. Because the island cannot export surplus power, solar output is frequently curtailed. An estimated 306 GWh of distribution-connected renewable output was curtailed in 2025, and the first grid-scale batteries are only now being procured.

Energy snapshot.

Headline figures for electricity in Cyprus. Each shows its data year and links to its source.

  • Population996,571 peopleSource 21 Jan 2026
  • Households390,100 householdsSource 32025
  • Average household size2.5 people/householdSource 42025
  • Electricity use per household4,877 kWh/yrSource 52024
  • Household price (EUR)0.277 EUR/kWhSource 12025-H2
  • Renewable electricity share27.8%Source 122025
  • Solar capacity0.86 GWSource 122025
  • Wind capacity0.17 GWSource 122025
  • Energy storage capacityNot identified from a reliable public source.
  • Smart-meter share62%Source 20July 2026
Market structure
Partially liberalised
Homes can export to the grid
Yes
Home equipment in grid services
Developing
Regulator
Cyprus Energy Regulatory Authority (CERA)
System operator
Transmission System Operator Cyprus (TSOC)
Distribution networks
One nationwide DSO: the Distribution System Operator of the Electricity Authority of Cyprus (EAC)
Currency
Euro (EUR)
Voltage and frequency
230 V / 50 Hz

Electricity prices in Cyprus.

Household price (EUR)
0.277 EUR/kWh (2025-H2)Source 1Eurostat average household price for the 2,500–4,999 kWh/yr band, all taxes and levies included.
Typical annual electricity bill
1,353 EUR/yr (2025)Source 1Derived: average household consumption of 4,877 kWh (2024, see snapshot) multiplied by the Eurostat all-taxes price of €0.2774/kWh (2025-H2). Indicative only; not a published typical bill.

Household price trend (EUR per kWh).Source 1

0.170.2720.3742019-H12025-H2
Cyprus household electricity price, EUR per kWh
2019-H10.2203 EUR/kWh
2019-H20.2236 EUR/kWh
2020-H10.2133 EUR/kWh
2020-H20.1698 EUR/kWh
2021-H10.1976 EUR/kWh
2021-H20.2304 EUR/kWh
2022-H10.2607 EUR/kWh
2022-H20.3261 EUR/kWh
2023-H10.3739 EUR/kWh
2023-H20.3452 EUR/kWh
2024-H10.3241 EUR/kWh
2024-H20.3251 EUR/kWh
2025-H10.2932 EUR/kWh
2025-H20.2774 EUR/kWh

Household prices in Cyprus are set by CERA-approved EAC tariffs, because EAC Supply still holds the dominant share of the market (about 90%, according to EAC). Each bill is split into the unbundled charges of the four EAC activities: generation, network use (transmission, distribution and the TSOC charge), ancillary services, meter data management and supply. A public service obligation charge funds the code 08 vulnerable-customer tariff, and a charge for the Renewable Energy Sources and Energy Conservation Fund (shown as 0.5 c/kWh on EAC’s sample bill) is added outside VAT.

Fuel adjustment

Because almost all conventional power is generated from imported oil products, the largest variable element is the fuel adjustment. Tariffs are set at a basic fuel price that CERA raised from €300 to €600 per tonne for 2026. Each month EAC calculates a weighted average fuel price that includes the COSMOS stock-holding fee and the cost of EU emission allowances. For every cent the fuel price is above or below €600, a published coefficient is added to or taken off each kilowatt-hour. In EAC’s 2026 worked example, a fuel price of €701.72 per tonne adds 2.6695 c/kWh to the low-voltage energy charge.

Taxes

The standard VAT rate is 19%, but household electricity has been taxed at a reduced 9% since 2021 under a series of temporary measures. In February 2026 the government extended the 9% rate until the end of March 2027.

Price level and trend

Eurostat puts the average household price for the 2,500–4,999 kWh band at €0.2774/kWh in the second half of 2025, all taxes included, slightly below the EU average of €0.2896/kWh for the same band. Prices rose from about €0.22/kWh in 2019 to a peak of €0.3739/kWh in the first half of 2023, well above the EU average of €0.2887/kWh at the time. They have eased since, but they still track oil and carbon prices closely through the fuel adjustment, because the island depends on oil-fired generation and cannot import power. The reduced 9% VAT rate also lowers the all-taxes figure.

Tariff types.

Tariff types.
TariffAvailableDetail
RegulatedYesEAC Supply single-rate domestic tariff (code 01). From the 2026 tariff round (CERA Decision 105/2026) the energy charge is 17.89 c/kWh at the basic fuel price of €600 per tonne, plus a fuel adjustment (2.6695 c/kWh in EAC’s worked example), a network charge of 3.93 c/kWh, a supply charge of €8.00 and a meter-reading charge of €0.94 per two-monthly bill. Public service obligation and RES & ES Fund charges and VAT are added on top.
Time-of-useYesTwo-rate domestic tariff (code 02): standard period 09:00–23:00 and economy period 23:00–09:00. In 2026 the energy charges are 17.94 c/kWh and 17.86 c/kWh, so the two periods are now priced almost the same.
OtherLimitedSpecial domestic tariff for vulnerable customers (code 08), with prices that rise with consumption. It is open to 20 eligible categories and had 29,905 beneficiaries at the end of February 2026. Its extra cost is recovered from all customers through the public service obligation charge.
Off-peakYesStorage of thermal energy tariff (code 56) for storage heaters and water heaters on a separate circuit. Supply is available only in hours set by EAC through ripple control. Since the 2026 tariffs its price is roughly the same as the main domestic tariff, so EAC says customers may switch back to their standard tariff.
VariableLimitedLicensed independent suppliers can offer their own contracts since the competitive market opened on 1 October 2025. They have mostly targeted business customers, and EAC Supply still holds the dominant share of the market.

Household prices compared with neighbouring countries (EUR per kWh).

Household prices including taxes, converted to euros as stated on each country page.

Household electricity use.

Electricity use per household
4,877 kWh/yr (2024)Source 5Derived: Eurostat household final electricity consumption of 1,876.3 GWh (2024) divided by 384.7 thousand households (Eurostat LFS, 2024). Not a published per-household statistic.
Average daily use per household
13.4 kWh/day (2024)Source 5Derived: 4,877 kWh/yr (see household consumption) divided by 365.
Typical household peak demand
Not identified from a reliable public source.
Electricity use per person
1,942 kWh/person/yr (2024)Source 5Residential only. Derived: household electricity consumption of 1,876.3 GWh divided by the population on 1 January 2024 (966,365). Total electricity demand per capita (all sectors) was 4.31 MWh in 2025 (Ember).
Heat pumps
Not identified from a reliable public source.
Air conditioning
Not identified from a reliable public source.
Electric vehicles
5,244 battery-electric passenger cars (2025)Source 9Stock of battery-electric cars out of 667,841 registered passenger cars (Eurostat).
Electric cooking
Not identified from a reliable public source.

Cypriot households used 1,876 GWh of electricity in 2024, according to the Eurostat energy balance, up from 1,693 GWh in 2023. Across about 385,000 households that is roughly 4,900 kWh per household a year, Electricity is the main household energy source: in 2024 it made up 161 of the 348 ktoe of household final energy use. Solar thermal, mostly rooftop solar water heaters, supplied 67 ktoe, and LPG and other oil products most of the rest. Households used no natural gas. Air conditioning drives demand in the long, hot summers.

Demand peaks on summer afternoons. TSOC recorded an all-time high of 1,372 MW on 23 July 2026. EAC sold 4,053 GWh to all customers in 2025, 3.7% less than in 2024, partly because more consumers produce their own solar power.

Electric vehicles are still a small share of the car fleet, but the number of battery-electric cars almost tripled from 1,800 in 2023 to 5,244 in 2025.

Housing and households.

Dwellings
Not identified from a reliable public source.
Owner-occupied
69.2 % of population (2025)Source 650.4% own outright and 18.8% have a mortgage or loan.
Private rented
14.9 % of population (2025)Source 6Tenants paying market rent.
Social or public housing
15.9 % of population (2025)Source 6Tenants paying reduced rent or living rent-free (Eurostat category). This is not limited to social housing and includes people living rent-free in family-owned homes.
Houses
75 % of population (2025)Source 750.6% detached and 24.5% semi-detached or terraced.
Apartments and flats
23.9 % of population (2025)Source 79.4% live in buildings with 10 or more dwellings.
Urban population
66.7 % of population (2025)Source 11

Three-quarters of people in Cyprus live in houses, half of them in detached houses, and 69% live in a home their household owns. Flats are concentrated in Nicosia, Limassol, Larnaca and Paphos, and only 9% of people live in blocks of ten or more dwellings.

A high share of owner-occupied houses has made rooftop solar common on Cypriot homes, much of it backed by government grant schemes such as “Photovoltaics for All”.

How the grid works in Cyprus.

  1. TransmissionTransmission System Operator Cyprus (TSOC), EAC Transmission (Transmission System Owner)
  2. DistributionOne nationwide DSO: the Distribution System Operator of the Electricity Authority of Cyprus (EAC)
  3. MeteringRing-fenced Meter Register and Meter Reading Department (EAC DSO)
  4. Supply4 or more retail suppliers

Electricity is generated mainly at EAC’s three oil-fired power stations: Vasiliko, the largest, produced about 66% of EAC’s output in 2025, Dhekelia about 32% and Moni about 1%. It travels over the 132 kV transmission network to substations that step it down to 22 kV or 11 kV for the distribution network. Wind farms connect at transmission level. Most solar parks and all rooftop systems connect to the distribution network, which by the end of 2025 hosted about 97,600 renewable systems with more than 1,068 MW of capacity.

Commercially, Cyprus moved from EAC acting as single buyer to a net-pool market on 1 October 2025. Generators sell through bilateral contracts or the day-ahead market, which clears every half-hour, and imbalances are settled in TSOC’s balancing market. As the dominant generator, EAC Generation must make its output available to other suppliers at a regulated wholesale price. Each participant is responsible for its own imbalances, either directly or through a balancing responsible party.

With no interconnection, system security depends on keeping enough conventional plant running. When solar output exceeds demand, TSOC first reduces conventional units to their minimum, then curtails large wind and solar plants, and finally disconnects groups of smaller commercial and household systems in rotation. The DSO uses ripple-control receivers to do this.

Who does what.

Who does what.
RoleOrganisationWhat it does
MinistryMinistry of Energy, Commerce and Industry (MECI)Sets energy policy and runs grant schemes for solar, storage and energy efficiency, including through the Renewable Energy Sources and Energy Conservation Fund. It also leads on the Great Sea Interconnector.
RegulatorCyprus Energy Regulatory Authority (CERA)Independent regulator. It issues generation, supply, aggregation and storage licences under Law 130(I)/2021, approves EAC tariffs and the fuel-adjustment coefficients, approves the Transmission and Distribution Rules and market rules, and oversees the competitive market.
TSOTransmission System Operator Cyprus (TSOC)Public-law body set up in 2004 and independent of EAC. It operates the 132 kV transmission system (some 66 kV sections remain) and dispatches generation, including curtailment of renewables. It is also the market operator for the net-pool wholesale market launched on 1 October 2025.
System operatorEAC Transmission (Transmission System Owner)EAC owns the transmission network and carries out construction and maintenance under TSOC’s operational control. TSOC operates the network but does not own it.
DSOEAC Distribution System Operator (DSO)Single nationwide DSO and distribution network owner. It handles new connections, connection terms for solar and storage, meters and smart-meter rollout, ripple control of storage heaters and small PV, and curtailment at distribution level.
MeteringRing-fenced Meter Register and Meter Reading Department (EAC DSO)Unit reporting directly to the DSO. It is the only body that reads meters, loads readings into the Metering Data Management System (MDMS) and sends validated data to suppliers. Under CERA Regulatory Decision 04/2014 it is also solely responsible for processing supplier switches.
SupplierEAC SupplyEAC’s supply business. It holds the dominant market share (about 90%, according to EAC), supplies on CERA-regulated tariffs and is the supplier of last resort. Since 1 January 2026 it offers only net-billing contracts to new solar applicants.
ExchangeTSOC Market Management System (day-ahead and balancing markets)Producers, suppliers and aggregators submit half-hourly bids and offers to the day-ahead market, and TSOC runs the real-time balancing market. Bilateral forward contracts sit alongside them. An intraday market is planned but not yet operating.

Compared with the UK system.

Compared with the UK system.
UK conceptCyprus equivalentHow it works
DNOEAC Distribution System Operator (ΔΣΔ)One DSO for the whole island, part of the state-owned EAC. It owns and operates the medium- and low-voltage network (22 kV and 11 kV down to 230/400 V), connects homes and solar systems, and owns and reads every meter. Connection applications go through EAC customer centres or regional email addresses, and the work has to be done by a licensed electrician.
National Grid/NESOTSOC (ΔΣΜΚ) with EAC as transmission ownerTSOC operates the 132 kV system and runs the wholesale market, while EAC owns the transmission assets. Unlike Great Britain, Cyprus has no interconnectors, so TSOC must balance the island on its own, curtailing solar and wind when supply exceeds demand.
MPANΑριθμός Υποστατικού (Premise ID / premises number)A 10-digit number assigned by EAC to each premises. It stays the same when the tenant or the account number changes, and is printed on every bill alongside the account and meter numbers. Unlike the MPAN it has no published internal structure (no distributor ID or profile class).
MPRNNo equivalentEurostat records no natural gas use by Cypriot households, and natural gas is not yet available even for power generation, so there is no gas supply-point identifier. Households rely on electricity, solar water heating and LPG.
Meter operatorEAC DSOThere is no competitive metering market. The DSO owns, installs, replaces and reads meters through its ring-fenced Meter Register and Meter Reading Department, which also handles switching.
SupplierEAC Supply / licensed suppliersConsumers have been free to choose their supplier since 2014, but EAC Supply still supplies most households on regulated tariffs. Independent suppliers licensed under Law 130(I)/2021 compete mainly for business customers.
Smart-meter infrastructureEAC DSO advanced metering infrastructure (no DCC)There is no central communications body. The DSO runs its own smart-meter programme, partly funded by the EU Recovery and Resilience Facility, and its own MDMS. Meter information and reading data are available to registered users through the DSO’s MDMS web portal.

How a supply point is identified.

4012345678 (fictional)

Fictional example in the real format.

How a supply point is identified.
QuestionAnswer
What is it called?Αριθμός Υποστατικού (Premise ID) (Premises number)
Who issues it?The Electricity Authority of Cyprus (EAC), as owner and operator of the distribution system
FormatA purely numeric 10-digit number assigned to the premises (the physical supply point). EAC does not publish any internal structure such as region or check-digit positions. It is separate from the customer account number (Αρ. Λογαριασμού), which changes with each new account holder, from the meter number (Αρ. Μετρητή), which changes when a meter is replaced, and from the three check digits used with the account number for online payment.
Length10 digits
Stays with the property when you switch supplier?Yes
Where to find itIn the header of every EAC bill, labelled “Αρ. Υποστατικού” (Premise ID), directly below the account number and meter number and next to the load entitlement or fuse rating, tariff code and, for codes 56 and 46, the ripple-control receiver group.
Electronic accessCustomers quote the premises number when submitting a meter reading online, reporting a fault or applying for services. Meter information and reading data are available through the DSO’s MDMS portal (meterreading-dso.eac.com.cy) after registration. Smart meters give access to daily consumption data.
Third-party accessThe ring-fenced Meter Register and Meter Reading Department sends validated meter data to all suppliers and network users, and only this department processes supplier-switch applications. A new supplier submits the switch on the customer’s behalf, using the premises and account details from the bill.
Who keeps the registerEAC DSO, through its ring-fenced Meter Register and Meter Reading Department (CERA Regulatory Decision 04/2014)
Register scopeNational

In Cyprus a household supply point is identified by its premises number (αριθμός υποστατικού, called the Premise ID in EAC’s English material). EAC describes it as unique for each premises and says it stays the same even when the tenancy or the account number changes. That makes it the closest equivalent to a UK MPAN: it belongs to the property, not to the occupier or the supplier.

How it differs from the other numbers on a bill

An EAC bill carries several identifiers. The account number (αριθμός λογαριασμού) belongs to the contract between the customer and the supplier and changes with each new account holder. The meter number identifies the physical meter, so it changes when the DSO replaces it, for example with a smart meter. The three check digits are used only with the account number to pay online. The premises number links all of these to one physical connection. EAC asks for the 10-digit premises number, for example, when a customer submits a meter reading through its website.

Who keeps the register

Because Cyprus has one DSO, there is a single national register. It is kept by the DSO’s ring-fenced Meter Register and Meter Reading Department, which is deliberately separated from EAC Supply. The department alone reads meters, validates the data in the MDMS and passes it to suppliers. Under CERA Regulatory Decision 04/2014 it is also the only body that processes supplier switches, so an independent supplier gets data on equal terms with EAC Supply. Unlike the UK, Cyprus has no separate central switching service or meter operator market.

Sending electricity to the grid.

Sending electricity to the grid.
QuestionAnswer
Can homes export electricity?Yes
Net meteringLimited
Net billingYes
How exported electricity is paidFor solar connection applications made from 1 January 2026, the supplier settles under net billing. Imports and exports are offset and any surplus is credited as a monetary amount on the next bill, at compensation rates published by the supplier that reflect wholesale rather than retail prices. Self-consumers may instead sell surplus through an aggregator or choose not to export. Systems whose DSO application was made by 31 December 2025 can still sign net-metering contracts, under which credits are carried forward for up to 36 months.
Who can still use net metering?Only systems whose connection application was submitted to the DSO by 31 December 2025. Net metering covers household and non-household PV systems of up to 10 kW, and virtual net metering covers domestic systems of up to 10.4 kWp. The government self-consumption scheme behind these contracts expired on 31 December 2025.
What size limits apply under net billing?EAC offers net billing for own-use systems of up to 8 MW, including houses. Virtual net billing, where generation is offset against a consumption bill elsewhere, is limited to 150 kWp of PV per consumption bill and per beneficiary, and up to 500 kWp for energy storage systems.
What happens to accumulated net-metering credits?Under the 2023 amendment to the scheme, surplus production is carried forward for a total of 36 months and then reset to zero. The first reset was applied to bills in February and March 2026.
Can export be curtailed?Yes. The Transmission and Distribution Rules allow TSOC and the DSO to limit renewable feed-in at any time to keep the system stable. Small PV systems are disconnected in rotating groups through ripple control, and EAC publishes notices of these disconnections.
Does a household system need a generation licence?No individual licence. Under article 27 of Law 130(I)/2021, self-consumption systems of up to 30 kW and renewable plants of up to 50 kW are covered by a general licence, and larger self-consumption systems of up to 1 MW are exempt.

Connecting a home system.

  1. Check the network: the DSO and TSOC publish an indicative RES hosting-capacity map, although each connection request is assessed individually.
  2. Submit an application for connection of the PV system to the EAC DSO, prepared by a licensed electrician or installer.
  3. The DSO issues connection terms. These include its technical connection requirements for small PV and, for systems of up to 20 kW, a ripple-control receiver so that the DSO can disconnect the system remotely.
  4. Install the system with a compliant inverter, then have the installation tested and inspected by the DSO.
  5. Sign a self-consumption contract: since 1 January 2026, EAC Supply offers only net-billing or virtual net-billing contracts for new applicants. Alternatively, sign with another supplier or an aggregator, or operate without export.
  6. The DSO connects the system and configures the meter to record imports and exports separately.

Until the end of 2025, household solar in Cyprus was built on net metering. Each kilowatt-hour exported cancelled one imported later, with only network-related charges payable, and grant schemes such as “Photovoltaics for All” helped households install systems. Virtual net metering also allowed domestic systems of up to 10.4 kWp to be offset against a bill at another premises.

Net metering closed with the end of the government self-consumption scheme on 31 December 2025, three months after the competitive market opened. From 1 January 2026 new systems are settled under net billing. Imports and exports are measured separately and offset in money terms, with exports valued at wholesale-based rates rather than the retail tariff. CERA’s framework gives self-consumers three routes: a bilateral agreement with a supplier, selling surplus through an aggregator, or not exporting at all.

The value of exported solar is also limited by curtailment. Because surplus cannot be exported, small systems are regularly disconnected on sunny, low-demand days, especially in spring. That makes self-consumption, load-shifting and batteries more valuable than export.

Licensing and approvals.

Requirements depend on the activity. The table sets out what each activity needs and who grants it.

Licensing and approvals.
ActivityLicence or registrationAuthorityNotes
Generate electricityGeneral licence (no individual application) for off-grid plants, plants of up to 20 kW, self-consumption systems of up to 30 kW and renewable plants of up to 50 kW (article 27(1), Law 130(I)/2021). Exemptions apply to self-consumption systems above 30 kW and up to 1 MW, and renewable plants above 50 kW and up to 8 MW (article 27(4)). Larger plants need a CERA generation licence and a construction licence.CERAEvery grid-connected system also needs DSO or TSOC connection terms. Larger projects need planning and building permits.
Store electricityStand-alone storage is licensed by CERA: 33 private companies held battery storage licences for more than 1,000 MW in early 2026. The DSO and TSOC may not own or operate storage, except for fully integrated network components approved by CERA.CERANo separate licensing threshold for behind-the-meter household batteries was identified. They are connected under DSO terms as part of a self-consumption arrangement, and virtual net billing allows storage of up to 500 kWp.
Export to the gridNo licence for small self-consumers. Payment for export requires a net-billing contract with a supplier or an agreement with an aggregator.DSO (connection); supplier or aggregator (contract)Export may be curtailed by TSOC or the DSO at any time.
Sell / supply electricity to consumersSupply licence under article 34 of Law 130(I)/2021 and the licensing regulations, with compliance with the market rules.CERAEAC Supply is the supplier of last resort. Suppliers must take part in the TSOC market and bear balancing responsibility.
Wholesale tradingRegistration as a market participant in TSOC’s Market Management System, holding a CERA licence (generation, supply or aggregation), with balancing responsibility either held directly or through a balancing responsible party.TSOC (market operator); CERATrading takes place through the half-hourly day-ahead market, the balancing market and bilateral forward contracts. There is no intraday market yet.
AggregateAggregator licence granted by CERA under article 26(1) of Law 130(I)/2021, with standard conditions requiring compliance with the Transmission and Distribution Rules and the market rules.CERARenewable aggregators can represent small installations collectively in the market. Since 2026 they are one of the routes for selling self-consumers’ surplus.
Balancing / grid servicesRegistration with TSOC as a balancing service provider for the balancing market. Ancillary services are procured as a separate market from eligible generators’ capacity offers.TSOCNo published minimum bid size for distributed assets was identified for this profile.
Virtual power plant / remote control of assetsNo separate VPP licence identified. Market participation of a portfolio is through an aggregator licence. Remote control of small PV (up to 20 kW), storage heaters, water pumps and central air-conditioning compressors is reserved to the DSO, which uses ripple-control receivers under Directive Ο-ΔΔ-517.CERA; DSOThird-party control must not conflict with the DSO’s curtailment and connection terms.

Licensing is governed by the Law Regulating the Electricity Market of 2021 (Law 130(I)/2021) and administered by CERA. The thresholds that matter to households are low: a typical rooftop system falls under the general licence or the exemptions in article 27, so the practical approvals are the DSO’s connection terms and the supply contract.

At market level CERA licenses generators, suppliers, aggregators and storage operators separately. EU unbundling rules prevent the network operators from owning storage, which is why the role of EAC and TSOC in grid-scale batteries has been contested. EAC is developing storage at its power stations through its generation business, and TSOC has procured a 120 MW system to reduce curtailment.

Flexibility and grid services.

Aggregation of home equipment: Yes

Flexibility and grid services.
Market or serviceAccess for home equipmentMinimum sizeVia an aggregatorDetail
Day-ahead marketRestricted—YesTSOC. Half-hourly bids and offers from licensed producers, suppliers, storage operators and aggregators, live since 1 October 2025. Households take part only through their supplier or an aggregator.
Balancing market (integrated scheduling and real-time)Developing—LimitedTSOC. Run by TSOC with balancing service providers and balancing responsible parties. Distributed assets are not yet a significant source of balancing services.
Ancillary servicesRestricted—UnknownTSOC. Procured as a separate market based on capacity offers from eligible generators, in practice mainly EAC’s conventional units.
Intraday marketNo—UnknownTSOC. Planned but not yet operating.
DSO load control (ripple control)Restricted—NoEAC DSO. The DSO switches storage heaters (code 56), water pumps (code 46) and central air-conditioning compressors, and disconnects small PV systems in rotating groups. This is network control, not a paid flexibility market.

Flexibility markets in Cyprus are at an early stage. The net-pool market that started in October 2025 gives aggregators, storage operators and balancing service providers a formal place for the first time, but there is no intraday market. The most important source of flexibility is still EAC’s conventional fleet, backed by direct DSO control of selected loads and of small solar systems.

Paid household flexibility does not yet exist. The tools that will make it possible are being put in place: smart meters on most premises, licensed aggregators that can sell self-consumers’ surplus, and storage subsidies. Time-of-use tariffs linked to smart meters are being prepared by EAC but need CERA approval.

Flexibility and aggregation platforms.

Flexibility and aggregation platforms.
Platform or aggregatorWhat it does
TSOC Market Management SystemPlatform for day-ahead bids and offers and balancing-market operation.
EAC PV forecast and production dashboardReal-time and historical distributed PV generation, demand and curtailment on the distribution network.

Smart meters.

Smart meters.
FactValue
Smart-meter rolloutDSO-led national rollout, partly funded by the EU Recovery and Resilience Facility: about 390,000 installed by July 2026, with a target of 500,000 by June 2027
Reading intervalNot published by the DSO; conventional profiled meters are read every two months
Installed (July 2026)About 390,000
Target500,000 by June 2027, covering every consumer
Installation rateAbout 16,000 a month (mid-2026)
EU funding€29.6 million certified under the RRF (up to €35 million secured)
Cost to consumerNone
Meter owner / data managerEAC DSO (ring-fenced Meter Register and Meter Reading Department)

EAC’s DSO began the mass rollout of smart meters in urban areas in early 2025, replacing conventional meters at premises billed every two months, including homes and small businesses. Installation is free, and EAC says the supply is interrupted for no more than about 20 minutes. The Recovery and Resilience Facility project first covered 400,000 meters; EAC reports that by July 2026 about 390,000 were installed and the programme is on track for 500,000 by June 2027.

EAC lists the benefits as daily consumption data for customers, bills based on actual rather than estimated readings, faster fault detection, prepaid options for short-term rentals and tariffs that vary by time of day. Readings are managed in the DSO’s Metering Data Management System. In 2026 CERA fined EAC over problems with the MDMS after the market opened, and EAC says it is putting corrective measures in place.

Renewable electricity.

Electricity generation mix (2025).

  • Other fossil (mainly oil): 72.3%
  • Solar: 23.2%
  • Wind: 3.6%
  • Bioenergy: 1%
Source 12
Renewable electricity share
27.8% (2025)Source 12Share of domestic generation: solar 23.18%, wind 3.55%, bioenergy 1.02%. The EU directive-based RES-E share of electricity consumption was 27.5% in 2025 (Eurostat).
Home solar
600 MW (End 2025)Source 20About 95,600 self-consumption PV systems under net metering and net billing connected to the distribution network. This includes some non-household self-consumers, so it is an upper bound for residential solar.
Solar added each year
159 MW (2024)Source 33Of which about 100 MW were self-consumption systems.
Other fossil (oil-fired)
1.85 GW (2025)Source 12
Solar
0.86 GW (2025)Source 12
Wind
0.17 GW (2025)Source 12
Bioenergy
0.01 GW (2025)Source 12

Targets.

  • Renewables: 33% of gross final energy consumption by 2030 under the National Energy and Climate Plan (20.21% in 2023).
  • Distribution network: a further 1,000 MW of renewable capacity expected to be connected by 2030 (EAC).

Cyprus generates almost all its conventional electricity from oil products. Natural gas is not yet available: EAC has converted the Vasiliko station to burn gas and completed a new combined-cycle unit there, but both are waiting until natural gas becomes available at Vasiliko. Oil-fired plant produced 72.25% of electricity in 2025.

Solar is the main renewable source: it produced 1.37 TWh, or 23.18% of generation, in 2025, up from 1.11 TWh in 2024. Wind farms of about 170 MW supply most of the rest. Growth now depends less on new panels than on the system’s ability to absorb them. An estimated 47% of distribution-connected renewable output was curtailed in 2025, and new connections face delays.

Energy storage.

Home batteries
Not identified from a reliable public source.
Grid-scale storage
Not identified from a reliable public source.

Storage is the missing piece of the Cypriot system. With no interconnection, surplus midday solar can only be stored or curtailed. In June 2026 about 925 MW of storage was registered across 36 applications, and CERA had licensed more than 1,000 MW of private battery projects, but only state-led projects were moving to construction.

Household batteries have become more attractive since net billing reduced the value of exported solar. They are eligible under the Save – Upgrade in Residences 2026 scheme. A separate storage grant scheme for businesses was announced in August 2026.

Storage projects.

  • TSOC central storage system (120 MW): Awarded through an international tender for about €50 million, with contracts announced in June 2026. Equipment is due in January 2027 and operation is targeted for summer 2027, mainly to reduce solar curtailment.
  • EAC Dhekelia battery (80 MW / 160 MWh): Being installed at Dhekelia power station (EAC, July 2026). EAC has also applied for a 100 MW / 200 MWh system at Moni and for battery storage at Vasiliko.
  • Grant Scheme for Energy Storage Systems in Combination with RES: A €35 million scheme funded by the EU Just Transition Fund (applications February–March 2025), expected to add about 150 MW / 350 MWh of batteries at existing renewable plants. Funding agreements have been signed and projects are obtaining permits.

Electricity suppliers.

Electricity suppliers.
SupplierMarket shareRenewable tariffTime of useDynamicExport tariff
EAC SupplyAbout 90% (EAC); supplier of last resortUnknownYesNoYes
Petrolina Electric Ltd—UnknownUnknownUnknownUnknown
Synenergia Ltd—UnknownUnknownUnknownUnknown
Abio Power Ltd—UnknownUnknownUnknownUnknown

In practice most households are supplied by EAC Supply on CERA-regulated tariffs. CERA lists several active independent suppliers, including Bioland Promithia, Evergy, Abio Power, Petrolina Electric, Energy & Beyond, Synenergia, First Electric Supply and Eko Energy Cyprus. They have concentrated on business customers, whose larger loads are cheaper to serve; household offers remain limited. Segments shown for independent suppliers reflect that focus, not a published restriction.

All suppliers rely on the same DSO network, meters and meter data. Switches are processed only by the DSO’s ring-fenced Meter Register and Meter Reading Department.

Key organisations.

Key organisations.
OrganisationCategoryWhat it doesWhy it matters
Ministry of Energy, Commerce and IndustryGovernmentEnergy policy and grant schemesSelf-consumption schemes, storage grants, the Great Sea Interconnector and the National Energy and Climate Plan.
Cyprus Energy Regulatory Authority (CERA)RegulatorEnergy regulatorLicensing, tariff and fuel-adjustment approvals, market rules and the list of active suppliers.
Transmission System Operator Cyprus (TSOC)TransmissionTransmission system and market operatorSystem demand data, the day-ahead and balancing markets, storage procurement and curtailment instructions.
Electricity Authority of Cyprus — Distribution System OperatorDistributionSole DSO and meter operatorPV connection terms, ripple control, curtailment reports, hosting-capacity map, smart meters and the MDMS portal.
EAC SupplyConsumerDominant supplier and supplier of last resortRegulated household tariffs, the fuel adjustment and net-billing contracts.
Renewable Energy Sources and Energy Conservation FundRenewable EnergyAdministers household grant schemesRuns the 2024–2025 home solar and insulation grants, including “Photovoltaics for All”.
Cyprus Energy AgencyRenewable EnergyEnergy agencyInformation and projects on renewables and energy efficiency.
The Cyprus Institute — Energy, Environment and Water Research CenterRenewable EnergyResearch instituteIndependent analysis of the competitive market and the energy transition.

Technical standards.

Technical standards.
AreaStandardIssued byNotes
Grid codeTransmission and Distribution RulesTSOC and EAC DSO, approved by CERASet connection requirements and give TSOC and the DSO the right to limit renewable feed-in at any time for system security.
Grid connection (generators)EU Regulation 2016/631 (RfG); DSO Technical Connection Guidelines for RES systemsEuropean Commission; EAC DSODSO Information Bulletin 001/2024 changed the requirements for small PV of up to 10.4 kW, including limits on installed capacity (kWp) and inverter power (kVA).
InvertersEN 50549-1 with the Cyprus EAC settingsCENELEC; EAC DSOInverter manufacturers publish Cyprus-specific parameter sets for the EAC requirements (separate settings below and above 10.4 kW).
Remote control / curtailmentDirective Ο-ΔΔ-517 (ripple-control receivers)EAC DSOCovers control of storage heaters, water pumps, central air-conditioning compressors and small PV of up to 20 kW. Exemptions are available for siting the PV receiver outside the meter room.
Installation and inspectionLicensed electrician; DSO installation inspectionEAC DSOEvery connection must be carried out under the responsibility of an electrician licensed in Cyprus, and new or altered installations are inspected before connection.
Connection procedureConnection Process to the Distribution System (CERA Decision 134/2024)CERA; EAC DSOApproved but not yet in force. It takes effect once the tasks in Regulatory Decisions 01/2022 and 02/2022 are completed.

Permissions.

Permissions.
PermissionRequiredLevelDetail
DSO connection termsYesNationalEvery PV or storage system connected to the grid needs connection terms from the EAC DSO, followed by inspection and connection.
Generation licenceNoNationalHousehold systems fall under the general licence (self-consumption up to 30 kW, RES up to 50 kW) or the exemption for self-consumption up to 1 MW.
Ripple-control receiverYesNationalSmall PV systems of up to 20 kW are fitted with a DSO-controlled receiver used for curtailment. Exemptions may be granted for its location.
Supply contract for exportYesNationalA net-billing contract with a supplier, or an aggregator agreement, is needed to be paid for exports. Otherwise the system must run without export.
Planning and building permitsLimitedLocalGeneration stations need a planning permit and a building permit. Whether a household rooftop system needs them was not verified from an official source for this profile.

For a household, the DSO is the main point of contact. It assesses the connection, sets the terms, fits the ripple-control receiver, inspects the installation and configures the meter. The commercial side is a separate contract with the supplier, which since 2026 means net billing. Grant schemes have usually required DSO approval before the grant application, which is why the May 2026 reopening of the home solar grant was limited to people who had applied to the DSO by the end of 2025.

Support schemes, taxes and incentives.

Support schemes, taxes and incentives.
SchemeStatusTypeDetailPeriod
Grant scheme for RES and energy saving in homes 2024–2025 (including “Photovoltaics for All”)ClosedGrantPV grants of €375/kW (maximum €1,500) for the general category and €1,250/kW (maximum €6,250) for vulnerable households. “Photovoltaics for All” paid €250/kW (maximum €1,000) and also financed up to €1,000/kW, repaid through €150 charges on each two-monthly bill. Roof-insulation grants were also available. Budget €90 million. The PV categories reopened from 18 to 31 May 2026, only for applicants who had applied to the DSO before 31 December 2025.Feb 2024 – Dec 2025; reopened 18–31 May 2026
Save – Upgrade in Residences 2026 (THALEIA 2021–2027)ScheduledGrantA €20 million scheme for deep renovation of homes first connected to the grid before 2008, with at least 60% primary energy savings. It offers up to €32,000 (type A) or €24,000 (type B) and covers insulation, windows, heat pumps, solar water heating, PV under net billing and battery storage. The call was expected in September 2026.Call expected September 2026
Grant Scheme for Energy Storage Systems in Combination with RESClosedGrantA €35 million scheme funded by the Just Transition Fund for adding batteries to existing renewable plants, including €5 million for self-consumption (net-billing) systems at €75,000/MWh up to 70% of cost. Batteries may draw no more than 25% of their annual charging from the grid.Applications 14 Feb – 28 Mar 2025
Reduced VAT on household electricityActiveVAT reliefVAT of 9% instead of 19% on household electricity consumption.Extended to 31 Mar 2027
Special domestic tariff for vulnerable customers (code 08)ActiveSocial tariffReduced, consumption-scaled tariff for 20 eligible categories, with 29,905 beneficiaries at the end of February 2026. It is funded through the public service obligation charge.—
Income tax deduction for home energy systemsActiveTax deductionA deduction of up to €1,000 for installing energy-efficiency systems, renewable energy systems and batteries in a primary residence, as described in the Chambers 2026 Cyprus renewable energy guide.—
Net metering and virtual net meteringClosedNet meteringClosed to new applicants: available only to systems whose DSO application was submitted by 31 December 2025. Existing contracts continue, with credits reset after 36 months.Until 31 Dec 2025 for new applications
Business energy storage grant schemeScheduledGrantAnnounced by the Energy Minister in August 2026 to reduce curtailment. Budget and launch date had not been published.—

Data and connectivity.

Fixed broadband
97.5 % of households (2025)Source 8Households with internet access (Eurostat).
4G coverage
Not identified from a reliable public source.
5G coverage
Not identified from a reliable public source.

Nearly all Cypriot households have internet access, which supports app-based monitoring of inverters, batteries and smart-meter data. Grid-side control of small distributed assets does not rely on household broadband: the DSO uses ripple-control signals over the power network to switch storage heaters and disconnect small PV systems.

Grid conditions.

National peak demand
1.372 GW (23 Jul 2026)Source 37All-time record demand reported by TSOC, at 14:45. The previous record was 1,321 MW on 21 July 2026.
Annual electricity demand
5.91 TWh (2025)Source 12
Generation capacity
2.89 GW (2025)Source 12Derived: sum of Ember fossil (1.85 GW) and clean (1.04 GW) capacity.
Interconnection
0 GW (2026)Source 32Cyprus is a non-interconnected system. The planned Great Sea Interconnector to Greece (1 GW initially) is not expected before 2030.
Curtailment
306 GWh (2025)Source 34Estimate by the CyprusGrid analytics platform: 47.44% of output from distribution-connected renewables, up from 167 GWh (29%) in 2024. A further 9.5 GWh of transmission-connected wind was curtailed.

As an isolated island system, Cyprus has two recurring stress points. On hot summer afternoons air-conditioning demand pushes the system close to the limits of its conventional fleet. On 23 July 2026 demand reached a record 1,372 MW, and earlier in that heatwave TSOC warned that losing one large unit would leave demand uncovered. After sunset solar output falls to zero, so evening demand has to be met entirely by thermal plant.

In spring and on mild sunny days the problem reverses: solar output exceeds what the system can absorb while keeping enough conventional units online for stability. TSOC then orders curtailment, which falls first on large plants and then, in rotation, on small rooftop systems. The DSO reports curtailed energy per renewable system to the market operator each month (CERA Decision 189/2023).

The planned remedies are storage, starting with TSOC’s 120 MW system and EAC’s Dhekelia battery, and in the longer term the Great Sea Interconnector, a 1,208 km HVDC link to Greece via Crete. Meridiam took a majority stake in the interconnector’s developer in August 2026, but completion is now expected after the original 2029–2030 target.

Grid and capacity maps.

Regulatory changes.

Regulatory changes.
ChangeStatusDateDetail
Competitive wholesale marketCurrent1 October 2025Net-pool market run by TSOC replaced EAC’s single-buyer role: half-hourly day-ahead market, balancing market and bilateral contracts.
Net billing for new self-consumption systemsCurrent1 January 2026Net metering closed to new applicants. EAC Supply now offers only net-billing and virtual net-billing contracts, and self-consumers can also use aggregators or not export.
2026 tariffs and higher basic fuel priceCurrentBills from end of April / May 2026CERA Decisions 105/2026 and 129/2026 set new tariffs on a basic fuel price of €600 per tonne (previously €300). The thermal-storage tariff (code 56) is now priced close to standard tariffs.
Time-of-use tariffs linked to smart metersUpcomingNot announcedEAC is preparing time-varying household tariffs as smart meters reach most premises (500,000 by June 2027). They need CERA approval.
First grid-scale batteriesUpcomingFrom summer 2027TSOC’s 120 MW system is due to operate in summer 2027, and EAC is installing 80 MW / 160 MWh at Dhekelia.
Natural gas for power generationUpcomingWhen gas reaches VasilikoVasiliko units have been converted and a new combined-cycle unit (No. 6) is complete and preserved, ready to run once natural gas becomes available.
New Connection Process to the Distribution SystemUpcomingAfter CERA decisionApproved by CERA Decision 134/2024. It takes effect once the tasks in Regulatory Decisions 01/2022 and 02/2022 are completed.
Intraday marketUpcomingNot announcedProvided for in the market design but not yet operating.
Great Sea Interconnector (Greece–Cyprus)UpcomingAfter 2030A 1,208 km, 1 GW (expandable to 2 GW) HVDC cable costing about €1.9 billion, with €657 million of EU funding. It would end Cyprus’s electrical isolation.
Reduced household VAT expiryUpcoming31 March 2027The 9% rate on household electricity is due to end unless extended again.

Market indicators.

Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.

Market indicators.
IndicatorLevelBasis
Electricity costMediumLow below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros).
Household electricity useMediumLow below 2,500 kWh a year, high at 5,000 kWh or more (average use per household).
Renewable shareLowLow below 30%, high at 60% or more (renewable share of electricity).
Smart-meter adoptionMediumLow below 30%, high at 80% or more (share of meters that are smart).
Home solar adoptionHighAbout 95,600 self-consumption PV systems (about 600 MW) were connected by the end of 2025, for about 390,000 households, and 75% of people live in houses.
Distributed energy marketMediumRooftop solar is widespread, but net metering has closed, about 47% of distribution-connected renewable output was curtailed in 2025, and storage and EV numbers are small.
Grid flexibility marketLowThe wholesale market started only in October 2025, with no intraday market. Aggregators are licensed but household flexibility is limited to DSO ripple control, and time-of-use tariffs are still being prepared.
Energy storage adoptionLowNo large-scale batteries were operating in early 2026. The first 120 MW (TSOC) and 80 MW (EAC) systems are due from 2027, and no household storage statistic exists.
Renewable growth environmentMediumThe renewable share of generation rose from 24.0% to 27.75% between 2024 and 2025, but heavy curtailment and the lack of storage and interconnection limit further gains.

Sources.

Public sources used for this profile, with the date each was accessed.

Show all 50 sources
  1. Electricity prices for household consumers — bi-annual data (nrg_pc_204). Eurostat, 2025. accessed 1 October 2026.
  2. Population change — demographic balance (demo_gind). Eurostat, 2026. accessed 1 October 2026.
  3. Number of households by household composition (lfst_hhnhtych). Eurostat, 2025. accessed 1 October 2026.
  4. Average household size (ilc_lvph01). Eurostat, 2025. accessed 1 October 2026.
  5. Complete energy balances (nrg_bal_c) — household electricity. Eurostat, 2024. accessed 1 October 2026.
  6. Distribution of population by tenure status (ilc_lvho02). Eurostat, 2025. accessed 1 October 2026.
  7. Distribution of population by degree of urbanisation and dwelling type (ilc_lvho01). Eurostat, 2025. accessed 1 October 2026.
  8. Level of internet access — households (isoc_ci_in_h). Eurostat, 2025. accessed 1 October 2026.
  9. Passenger cars by type of motor energy (road_eqs_carpda). Eurostat, 2025. accessed 1 October 2026.
  10. Share of energy from renewable sources (nrg_ind_ren). Eurostat, 2025. accessed 1 October 2026.
  11. Urban population (% of total population) — Cyprus. World Bank, 2025. accessed 1 October 2026.
  12. Yearly electricity data (generation, capacity, demand, imports) — Cyprus. Ember, 2025. accessed 1 October 2026.
  13. kWh price calculation (tariff codes 01 and 02). Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  14. EAC – New EAC tariff charges for the year 2026. Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  15. EAC – New fuel adjustment coefficients for tariffs and RES from April–June 2026. Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  16. Bill explanation (Premise ID, tariffs, charges, VAT). Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  17. Register meter readings (10-digit premises number). Electricity Authority of Cyprus — DSO, 2026. accessed 1 October 2026.
  18. Meter reading – consumption (Ring-fenced Meter Register and Meter Reading Department, MDMS portal). Electricity Authority of Cyprus — DSO, 2026. accessed 1 October 2026.
  19. Electricity market. Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  20. EAC’s Review of Activities – 23 July 2026. Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  21. EAC in the era of smart meters. Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  22. Mass installation and operation of smart metering infrastructure by the DSO (RRF project). Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  23. Photovoltaic systems – RES schemes (households). Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  24. EAC – Net billing and virtual net billing. Electricity Authority of Cyprus, 2025. accessed 1 October 2026.
  25. Ripple control (Directive Ο-ΔΔ-517). Electricity Authority of Cyprus — DSO, 2026. accessed 1 October 2026.
  26. EAC – Changes in requirements for small PV systems up to 10.4 kW. Electricity Authority of Cyprus — DSO, 2024. accessed 1 October 2026.
  27. Renewable energy sources (hosting capacity, curtailed energy, curtailments). Electricity Authority of Cyprus — DSO, 2026. accessed 1 October 2026.
  28. Distribution network applications. Electricity Authority of Cyprus — DSO, 2026. accessed 1 October 2026.
  29. Network user connection (CERA Decision 134/2024). Electricity Authority of Cyprus — DSO, 2026. accessed 1 October 2026.
  30. Existing transmission system. Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  31. EAC – Notification for disconnection of PV systems from the distribution network (7 May 2026). Electricity Authority of Cyprus, 2026. accessed 1 October 2026.
  32. The launch of the electricity market in Cyprus on 1 October 2025 — its operation and implications for consumers. The Cyprus Institute, 2025. accessed 1 October 2026.
  33. Cyprus to replace net metering with new self-consumption regime. pv magazine, 2025. accessed 1 October 2026.
  34. Cyprus solar curtailment hits 47% in 2025. pv magazine (CyprusGrid data), 2026. accessed 1 October 2026.
  35. Cyprus households left in the dark over solar credits reset. Cyprus Mail, 2026. accessed 1 October 2026.
  36. Reduced VAT on electricity bills extended for another year. Cyprus Mail, 2026. accessed 1 October 2026.
  37. Electricity demand easing as temperatures fall, grid operator says. Cyprus Mail (TSOC data), 2026. accessed 1 October 2026.
  38. Blackout risk rises as heatwave pushes demand to record levels. Cyprus Mail (TSOC data), 2026. accessed 1 October 2026.
  39. Smart meters to bring time-based electricity tariffs in Cyprus. Politis, 2026. accessed 1 October 2026.
  40. Energy storage grants planned to ease solar curtailments. Politis, 2026. accessed 1 October 2026.
  41. Agreements expected for the first 120MW electricity storage batteries. Sigmalive, 2026. accessed 1 October 2026.
  42. Σχέδιο Χορηγιών ΑΠΕ και ΕΞΕ σε κατοικίες 2024–2025 — τροποποίηση (13/05/2026). Renewable Energy Sources and Energy Conservation Fund, 2026. accessed 1 October 2026.
  43. Grant scheme to encourage the use of renewable energy sources and energy saving in homes (2024–2025). Funding Programmes Portal, Republic of Cyprus, 2025. accessed 1 October 2026.
  44. Grants up to €32,000 for homes – who can enter the new €20M scheme. Fast Forward (Cyprus), 2026. accessed 1 October 2026.
  45. Cyprus grant scheme for energy storage systems combined with RES. Balkan Green Energy News, 2025. accessed 1 October 2026.
  46. Renewable Energy 2026 — Cyprus (Papakyriacou LLC). Chambers and Partners, 2026. accessed 1 October 2026.
  47. Aggregator licence (standard terms). Cyprus Energy Regulatory Authority. accessed 1 October 2026.
  48. Consumers — active electricity suppliers. Cyprus Energy Regulatory Authority, 2026. accessed 1 October 2026.
  49. Meridiam buys majority stake in Greece-Cyprus power interconnection project. Enerdata, 2026. accessed 1 October 2026.
  50. Europe’s environment 2025 — Cyprus: renewable energy sources. European Environment Agency, 2025. accessed 1 October 2026.

Questions about energy in Cyprus.

Talk to us about Olmack in Cyprus.Tell us about your home, housing portfolio or school estate in Cyprus. We'll explain what is possible there now.