How electricity works in Greece.
Greece electricity market 2026: colour-coded tariffs, HEDNO as the national DSO, the 11-digit supply number, net billing for rooftop solar, IPTO balancing and storage reforms.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Euro (EUR) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Greece energy at a glance.
Key figures for households in Greece. Each one links to its source on the full overview below.
Electricity price.
0.238 EUR per kWh for households, including taxes. Figures for 2025-H2.
Household use.
4,233 kWh a year for a typical household. Figures for 2024.
Renewable share.
47.8% of electricity from renewable sources. Figures for 2025.
Selling back to the grid.
Can homes export electricity? Yes. Details are in the export section below.
Four things to check in Greece.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Greece below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Greece requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Greece.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Greece, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Greece, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Greece.
The energy market in Greece, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 1 October 2026.
On this page22 sections
Greece has a fully liberalised electricity market in law, but the former state monopoly, Public Power Corporation (PPC, ΔΕΗ), still supplied 70.98% of all metering points in April 2026, and 69.88% of household low-voltage supplies. Twenty-two suppliers were active, five of them also acting as universal-service suppliers. The Hellenic Electricity Distribution Network Operator (HEDNO, ΔΕΔΔΗΕ) runs the distribution network for the whole country, including the non-interconnected islands. The Independent Power Transmission Operator (IPTO, ΑΔΜΗΕ) owns and operates the high-voltage grid. The regulator is the Regulatory Authority for Waste, Energy and Water (RAAEY, ΡΑΑΕΥ), as the former Regulatory Authority for Energy (RAE) was renamed in 2023.
Household prices are market-based and sold under a colour code set by the regulator: blue for fixed prices, green for prices fixed on the first day of each month, yellow for variable prices linked to the wholesale market, and orange for dynamic hourly prices, which households have been able to take since 1 April 2026. Eurostat puts the average household price, including network charges and taxes, at €0.2381/kWh in the second half of 2025, among the higher prices in southern Europe.
Solar and wind now provide about two-fifths of Greek generation, and renewables as a whole provided 47.8% in 2025 on Ember’s figures. Greece became a net exporter of electricity in 2024 and 2025, but rapid solar growth has brought curtailment and negative prices. Rooftop solar has been on net billing since late 2024: what is used on site is offset in each 15-minute period and surplus is paid at the day-ahead market price. Battery storage is being added quickly from a low base.
Energy snapshot.
Headline figures for electricity in Greece. Each shows its data year and links to its source.
- Population10,366,586 peopleSource 21 Jan 2026
- Households4,055,400 householdsSource 32025
- Average household size2.4 people/householdSource 42025
- Electricity use per household4,233 kWh/yrSource 52024
- Household price (EUR)0.238 EUR/kWhSource 12025-H2
- Renewable electricity share47.8%Source 122025
- Solar capacity11.1 GWSource 122025
- Wind capacity5.71 GWSource 122025
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter share20.8%Source 19June 2026
- Market structure
- Fully liberalised
- Homes can export to the grid
- Yes
- Home equipment in grid services
- Restricted
- Regulator
- Regulatory Authority for Waste, Energy and Water (RAAEY)
- System operator
- IPTO (Independent Power Transmission Operator, ΑΔΜΗΕ)
- Distribution networks
- One national DSO, HEDNO (ΔΕΔΔΗΕ), 51% owned by PPC and 49% by Macquarie; it also operates the non-interconnected island systems
- Currency
- Euro (EUR)
- Voltage and frequency
- 230 V / 50 Hz
Electricity prices in Greece.
- Household price (EUR)
- 0.238 EUR/kWh (2025-H2)Source 1Eurostat average household price for the 2,500–4,999 kWh/yr band, all taxes and levies included (€0.2247 excluding VAT; €0.1953 excluding all taxes and levies). The average across all household bands was €0.2554/kWh.
- Typical annual electricity bill
- 1,008 EUR/yr (2024–2025)Source 1Derived, not an official statistic: the Eurostat 2025-H2 price for the 2,500–4,999 kWh band (€0.2381/kWh) multiplied by the derived average household consumption of 4,233 kWh (2024). Actual bills depend on tariff colour, supplier and region.
Household price trend (EUR per kWh).Source 1
| 2019-H1 | 0.1595 EUR/kWh |
|---|---|
| 2019-H2 | 0.1551 EUR/kWh |
| 2020-H1 | 0.1674 EUR/kWh |
| 2020-H2 | 0.1641 EUR/kWh |
| 2021-H1 | 0.168 EUR/kWh |
| 2021-H2 | 0.1974 EUR/kWh |
| 2022-H1 | 0.2101 EUR/kWh |
| 2022-H2 | 0.2438 EUR/kWh |
| 2023-H1 | 0.2327 EUR/kWh |
| 2023-H2 | 0.2309 EUR/kWh |
| 2024-H1 | 0.2218 EUR/kWh |
| 2024-H2 | 0.2311 EUR/kWh |
| 2025-H1 | 0.2305 EUR/kWh |
| 2025-H2 | 0.2381 EUR/kWh |
A Greek household bill has three parts. The competitive charge (ανταγωνιστικές χρεώσεις) is the supplier’s energy price and standing charge. The regulated charges (ρυθμιζόμενες χρεώσεις) are the same whoever supplies the customer: transmission and distribution use-of-system charges, public service obligations (ΥΚΩ) and the special levy for reducing gas emissions (ΕΤΜΕΑΡ). The third part is taxes and fees collected with the bill, including the special consumption tax, VAT and, historically, municipal charges.
The ΥΚΩ charge pays for the higher cost of supplying the non-interconnected islands, which therefore pay the same retail prices as the mainland, and for the KOT social tariff. It is tiered by consumption over four-month periods, so heavy users pay more per kWh. VAT on electricity is charged at the super-reduced rate of 6%.
Price level and trend
Eurostat’s 2025 annual price breakdown for the 2,500–4,999 kWh band shows energy and supply at €0.1611/kWh, network charges at €0.0334/kWh and taxes, fees and levies at €0.0393/kWh. The levies included €0.017/kWh for renewables and €0.0134/kWh of VAT, less €0.004/kWh of allowances. Energy is therefore a much larger share of the Greek bill than in many EU countries, so retail prices track wholesale gas and power prices closely.
The average household price was about €0.16/kWh in 2019–2020, rose to €0.2438/kWh in the second half of 2022 during the energy crisis, and has stayed between €0.22 and €0.24/kWh since. In the first seven months of 2026, yellow tariffs gave the lowest average charge for 300 kWh a month (€49.99, against €55.86 on blue and €56.06 on green). In 2025 fixed tariffs had been cheapest.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Fixed | Yes | Blue (σταθερά) tariffs: a fixed price per kWh for the contract term, typically 6 to 24 months. 1,871,421 household meters (31.53%) were on fixed tariffs in April 2026, up from 28.57% in January (RAAEY). |
| Variable | Yes | Green (ειδικά) tariffs: the supplier announces the price on the first day of each month, with no lock-in, so customers can leave at any time. They are the most common type, with 3,231,219 household meters (54.43%) in April 2026. |
| Variable | Yes | Yellow (κυμαινόμενα) tariffs: the price is linked to the wholesale market by a published formula. Some are set before the month (ex-ante) and others only after it (ex-post). 833,534 household meters (14.04%) used them in April 2026, about half of them ex-post. |
| Dynamic | Limited | Orange (δυναμικά) tariffs, introduced by ministerial decision: 24 hourly prices a day that follow the day-ahead market, announced by 17:00 the day before. They became available to larger customers from 1 February 2026 and to households and small businesses from 1 April 2026, and need a HEDNO smart meter. Only 6 household meters were on a dynamic tariff in April 2026. |
| Off-peak | Yes | The dual-zone reduced-rate tariff (διζωνικό, formerly the night tariff) needs a two-register or smart meter. Since 1 February 2025 the cheap hours have been 11:00–15:00 and 02:00–04:00 in summer (April–October), and 12:00–15:00 and 02:00–05:00 in winter (November–March), seven days a week. The midday window reflects solar output. |
| Regulated | Limited | The Social Household Tariff (Κοινωνικό Οικιακό Τιμολόγιο, KOT) gives reduced charges to vulnerable households and is funded through public-service-obligation charges. 444,531 low-voltage supplies were on KOT in April 2026. Universal service is a regulated fallback for small customers up to 25 kVA, and 77,567 supplies were on it. |
Household prices compared with neighbouring countries (EUR per kWh).
- Italy€0.316
- Cyprus€0.277
- Greece€0.238
- Bulgaria€0.136
- North Macedonia€0.116
- Egypt€0.02
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- 4,233 kWh/yr (2024)Source 5Derived: Eurostat household final electricity consumption of 17,243.5 GWh (2024) divided by 4,073.4 thousand private households (Eurostat LFS, 2024). Not a published per-household statistic.
- Average daily use per household
- 11.6 kWh/day (2024)Source 5Derived: 4,233 kWh/yr (see household consumption) divided by 365.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 1,662 kWh/person/yr (2024)Source 5Residential only. Derived: household electricity consumption of 17,243.5 GWh divided by the population on 1 January 2024 (10,375,764). The World Bank puts all-sector consumption at 4,686 kWh per person in 2024.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- 30,108 battery-electric passenger cars (2025)Source 9Stock of battery-electric cars out of 6,188,525 registered passenger cars (Eurostat), up from 17,987 in 2024. A further 38,323 were petrol plug-in hybrids.
- Electric cooking
- Not identified from a reliable public source.
Greek households used 17,244 GWh of electricity in 2024 (Eurostat energy balance), roughly 4,200 kWh per occupied household. Household use swings with the weather: it fell to 15,129 GWh in the mild year of 2023. Air conditioning drives summer use, and electricity is also used for water heating, cooking and space heating.
Summer air conditioning now sets the national peak. During the July 2025 heatwave IPTO recorded a record load of 10,798 MW on 24 July, and demand was expected to stay above 10,000 MW for 5.5 hours in a row on 25 July. On the interconnected system, total market demand was 51.4 TWh in 2025, 0.77% lower than in 2024 (IPTO).
Electric vehicles are still few, but the battery-electric fleet grew from 12,315 in 2023 to 30,108 in 2025. That is still less than 0.5% of registered cars.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- 69.4 % of population (2025)Source 660.4% own outright and 8.9% have a mortgage or loan.
- Private rented
- 24.1 % of population (2025)Source 6Tenants paying market rent.
- Social or public housing
- 6.6 % of population (2025)Source 6Tenants paying reduced rent or living rent-free (Eurostat category). Greece has very little public social housing, so this mostly reflects family arrangements.
- Houses
- 40.1 % of population (2025)Source 730.4% detached and 9.7% semi-detached or terraced.
- Apartments and flats
- 59.8 % of population (2025)Source 7
- Urban population
- 79.2 % of population (2025)Source 11
Most Greeks live in flats: 59.8% of the population in 2025, rising to a large majority in Athens and Thessaloniki, where the typical building is the multi-storey πολυκατοικία with a flat roof shared by the co-owners. Each flat normally has its own HEDNO supply and meter, while lifts, stairwell lighting and shared heating are on a separate common-areas supply.
Home ownership is high, at 69.4% of the population, but nearly a quarter of people rent at market rates, more than in most southern EU countries. For rooftop solar on a shared roof, the law requires the written consent of all co-owners. It also allows collective self-consumption, in which at least two self-consumers in the same building share a plant through virtual net billing, and common-area consumption can be included.
Detached houses, which 30.4% of people live in, are concentrated in suburbs, smaller towns, rural areas and the islands, where single-supply rooftop systems are simplest. Many holiday and second homes have their own supply, which is why HEDNO has many more household supplies than there are households.
How the grid works in Greece.
- TransmissionIPTO (Independent Power Transmission Operator, ΑΔΜΗΕ)
- DistributionOne national DSO, HEDNO (ΔΕΔΔΗΕ), 51% owned by PPC and 49% by Macquarie; it also operates the non-interconnected island systems
- MeteringNot identified from a reliable public source.
- Supply6 or more retail suppliers
Electricity flows from gas plants, the remaining lignite units, hydro, and a fast-growing fleet of wind and solar farms through IPTO’s 400 kV and 150 kV transmission grid. HEDNO then takes it down to medium voltage (mainly 20 kV) and to low voltage (230/400 V). About 7.66 million of the 7.68 million metering points in the retail market are on low voltage.
Many Aegean and Ionian islands were historically supplied by local oil-fired stations as non-interconnected islands (ΜΔΝ). IPTO has been linking them to the mainland: the Cyclades programme is in its last phase (Santorini–Naxos expected in the third quarter of 2026), and the high-voltage DC link between Attica and Crete (Ariadne) entered operation in 2025. The Dodecanese and North Aegean links are planned for 2030.
Commercially, generators, suppliers and aggregators trade on HEnEx, which is coupled with Italy and Bulgaria in the EU single day-ahead market, and IPTO settles imbalances and runs the balancing market. In 2025 Greece imported 3.41 TWh and exported 6.41 TWh. For a household almost everything goes through HEDNO: it builds the connection, issues the supply number, fits and reads the meter and approves any solar system. The supplier only bills and sells the energy.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry of Environment and Energy (ΥΠΕΝ) | Sets energy policy and the National Energy and Climate Plan, and issues ministerial decisions such as the self-consumption framework, the dynamic-tariff decision and the rules of subsidy programmes such as Photovoltaics on the Roof. |
| Regulator | Regulatory Authority for Waste, Energy and Water (RAAEY, ΡΑΑΕΥ) | Independent regulator, renamed from RAE under Law 5037/2023. It issues producer certificates, supply, trading and aggregation licences, approves network and market codes and tariffs, oversees the tariff colour code and publishes monthly retail market reports. |
| TSO | IPTO (Independent Power Transmission Operator, ΑΔΜΗΕ) | Owns and operates the Hellenic Electricity Transmission System (HETS) and runs the balancing market. It is also building the island interconnections, including the Crete–Attica link, which entered operation in 2025. ADMIE Holding owns 51%, the Hellenic Republic 25% and State Grid of China 24%. |
| DSO | Hellenic Electricity Distribution Network Operator (HEDNO, ΔΕΔΔΗΕ) | The only DSO, created in 2011 from PPC’s distribution department and now 51% PPC and 49% Macquarie. It has more than 7.6 million customers and about 242,000 km of lines. It connects customers, owns and reads meters, issues supply numbers, approves rooftop solar and runs the smart-meter rollout. It is also the system operator for the non-interconnected islands. |
| Exchange | Hellenic Energy Exchange (HEnEx) and EnEx Clearing House | HEnEx runs the day-ahead and intraday markets, which are coupled with EU markets, and EnEx Clearing House clears them. Under net billing the day-ahead clearing price is the reference for paying household solar surplus. |
| Settlement | DAPEEP (Renewable Energy Sources and Guarantees of Origin Operator) | Manages renewable support payments and guarantees of origin. It is also the aggregator (Φορέας Σωρευτικής Εκπροσώπησης) for household net-billing systems up to 10.8 kW, paying their surplus energy, and the aggregator of last resort. |
| Supplier | Public Power Corporation (PPC, ΔΕΗ) | The incumbent supplier, with 70.98% of all metering points and 69.88% of household low-voltage supplies in April 2026. It is one of five universal-service suppliers. |
Compared with the UK system.
| UK concept | Greece equivalent | How it works |
|---|---|---|
| DNO | ΔΕΔΔΗΕ / HEDNO (Διαχειριστής Δικτύου) | Greece has one distribution operator for the whole country instead of regional DNOs. HEDNO runs the mainland medium- and low-voltage network and also operates the separate electricity systems of the non-interconnected islands, where it dispatches local power stations. |
| National Grid/NESO | IPTO / ΑΔΜΗΕ | One company owns the transmission grid and operates the system, combining the roles split in Great Britain between National Grid Electricity Transmission and NESO. IPTO also runs the balancing market and develops subsea interconnections to the islands and neighbouring countries. |
| MPAN | Αριθμός Παροχής (supply number) | An 11-digit number issued by HEDNO, printed on the first page of every bill and stamped on a metal plate in the meter box. The first nine digits identify the supply and do not change. The last two are a succession number that increases when the holder or supplier changes. It is the key for switching supplier, solar applications and meter-data access. |
| MPRN | Gas supply point (separate system) | Natural gas is distributed by separate gas distribution companies with their own supply-point codes. The electricity supply number has nothing to do with gas. |
| Meter operator | HEDNO | There is no competitive metering market. HEDNO owns, installs, reads and replaces consumption meters. For a solar self-consumer it fits the bidirectional supply meter, while the customer buys a separate production meter of a type HEDNO accepts, which is certified in HEDNO’s laboratories and sealed by HEDNO staff. |
| Supplier | Προμηθευτής (supplier) / Προμηθευτής Καθολικής Υπηρεσίας | Households choose among 17 commercial suppliers, each selling colour-coded tariffs. Five of them (PPC, Metlen, Heron, Enerwave and NRG) are also universal-service suppliers for small customers who have not chosen a supplier or cannot find one. |
| Smart-meter infrastructure | HEDNO telemetry and smart-meter programme (no DCC equivalent) | There is no central communications body like the DCC. HEDNO runs the meters, the head-end and meter-data systems, and passes certified data to suppliers, aggregators and DAPEEP. Customers see their data through HEDNO web applications and the myDEDDIE app. |
How a supply point is identified.
3 41526378-01 (fictional)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Αριθμός Παροχής (supply number) |
| Who issues it? | HEDNO (ΔΕΔΔΗΕ), the national distribution network operator |
| Format | Written as 1 + 8 digits + a 2-digit suffix, for example 1 23456789-02. The first digit is a code for the area where the meter is. The next eight digits are the number stamped on the metal plate in the meter box. The last two digits are the succession number (αριθμός διαδοχής), which rises when the holder or supplier changes. Some bills print an additional final coding digit with no practical meaning. |
| Length | 11 digits (the first 9 are permanent; the last 2 change with each new holder or supplier) |
| Stays with the property when you switch supplier? | Yes |
| Where to find it | On the first page of the electricity bill, top right, labelled Αριθμός Παροχής, and on the silver metal plate in or on the meter box. |
| Electronic access | Customers can register supplies in the myDEDDIE app and HEDNO web services. For telemetered and smart meters, HEDNO’s data platform (apps.deddie.gr) gives consumption, production and export data, using the 9-digit supply number together with the customer’s tax number (ΑΦΜ) and an access token. Medium-voltage customers log in with their tax number and see 15-minute or hourly data for up to two years. |
| Third-party access | A new supplier quotes the supply number to HEDNO to switch the customer. Installers and electricians use it in the HEDNO solar-application portal (ape.deddie.gr) and when submitting the installer’s declaration (ΥΔΕ). Under net billing, HEDNO sends certified 15-minute data to the supplier and to the aggregator (DAPEEP for households up to 10.8 kW). |
| Who keeps the register | HEDNO keeps the register of all distribution supply points and their meters, as network operator and sole meter operator, and provides the supply counts per supplier used in RAAEY’s retail reports. |
| Register scope | National |
Every electricity connection in Greece is a παροχή (supply), identified by HEDNO’s αριθμός παροχής. The first nine digits identify the physical supply and meter position and stay with the property. The two-digit succession number changes whenever a new person takes over the supply or the supply contract moves, which lets HEDNO and suppliers tell one contract period from the next. For this reason government services usually ask only for the first nine digits, for example when checking eligibility for subsidies or the social tariff.
What it is used for
The supply number links the customer, the supplier and the network. Households quote it to switch supplier, to report a meter reading, to apply for the dual-zone tariff, to connect a solar system and to claim state electricity support. A solar system under net billing is matched to the supply number of the consumption it offsets. Under virtual net billing one plant can be matched to several supply numbers, even ones at other addresses, as long as they are on the same electrical system.
Metering data
For net billing, HEDNO collects energy taken from the grid and energy fed in by the solar plant for each 15-minute imbalance settlement period, from certified meters. It sends these data to the supplier and the aggregator, which value the surplus. Older electromechanical and non-telemetered meters are read manually, while smart meters installed since 2023 report remotely. HEDNO’s supply records also provide the meter counts per supplier and per tariff type used in RAAEY’s monthly retail reports.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Yes |
| Net metering | No |
| Net billing | Yes |
| How exported electricity is paid | Net billing (ταυτοχρονισμένος συμψηφισμός): production and consumption are offset in each 15-minute period, and surplus fed into the grid is paid for 20 years at the day-ahead market clearing price for the hours of injection. On the non-interconnected islands it is paid at the special market price for renewables published by DAPEEP. Households up to 10.8 kW are represented by DAPEEP, and any credit on the bill goes to the customer. |
| Is net metering still available? | Not for new systems. Law 5106/2024 restricted net metering and, from 31 October 2024, HEDNO has issued connection offers for self-consumption only under net billing or virtual net billing. Existing net-metering systems continue under their original contracts. |
| What size of system can a household connect? | Up to 100% of the supply’s agreed power in kVA. Existing single-phase supplies are limited to 5 kWp. HEDNO reserves 3 MW per substation for household self-consumption, with a cap of 10.8 kW per supply, and the household programme covers systems up to 10.8 kW. On the non-interconnected islands lower caps apply per island system, for example 20 kW for ordinary self-consumers on smaller islands. |
| How is exported energy valued? | At the day-ahead market clearing price in the hours of injection, calculated by the aggregator for each 15-minute period and settled monthly. Because solar output pushes midday prices down, sometimes below zero, the value of surplus is usually well below the retail price. |
| Are network charges paid on self-consumed energy? | No. Regulated charges (ΕΤΜΕΑΡ, system and network use charges, ΥΚΩ) are calculated only on energy taken from the grid. Energy produced and used in the same 15-minute period is not charged. |
| Can I install solar in a saturated network area? | Zero-export (zero feed-in) systems are examined with absolute priority and can be connected in areas declared saturated because of thermal or voltage limits. In the saturated networks of the Peloponnese, Evia, Crete and the interconnected Cyclades, net-billing systems are capped at 1 MWp. |
| Do households pay tax on surplus payments? | No. Household self-consumers are not treated as businesses and have no tax obligations for the energy they inject under net billing. |
| Can neighbours in a block of flats share solar? | Yes. At least two self-consumers in the same building can share a plant through virtual net billing, including common-area consumption. The plant is connected through a new HEDNO supply. |
Connecting a home system.
- Check that the supply can take the planned system. Under net billing the PV capacity (kWp) can be up to 100% of the supply’s agreed power (kVA), but an existing single-phase low-voltage supply is limited to 5 kWp and must be upgraded to three-phase for more.
- Submit the connection application online on HEDNO’s renewable-energy portal (ape.deddie.gr), with proof of ownership or legal use of the roof and, for shared roofs, the written consent of all co-owners.
- HEDNO issues a connection offer or connection contract and charges the connection fee. If no network works are needed, this is €370 plus VAT for a single-phase system up to 10.8 kWp and €390 for three-phase up to 55 kWp.
- Sign the net-billing contract (Σύμβαση Ταυτοχρονισμένου Συμψηφισμού) with the supplier and the aggregator, which is DAPEEP for households up to 10.8 kW. It runs for 20 years from activation. A zero-export system does not need this contract.
- Install the system, including a production meter of a type HEDNO accepts, certified in HEDNO’s laboratories, and the telemetry needed to record production, export and consumption in real time.
- Submit a readiness declaration with the required documents. HEDNO replaces the supply meter with a bidirectional one if needed, tests the installation, seals both meters and activates the connection.
Greece ran a generous net-metering scheme for rooftop solar for several years. Law 5106/2024 replaced it with net billing as the main tool for self-consumption, and the implementing ministerial decision (ΥΠΕΝ/ΔΑΠΕΕΚ/93976/2772, ΦΕΚ 5074Β/5.9.2024) took effect for new connection offers from 31 October 2024. Under net billing, energy produced and consumed in the same 15-minute period is free of energy and regulated charges, while surplus is sold at the wholesale price.
The main subsidy for household solar, Photovoltaics on the Roof, required a battery with every household system and was run under net billing. Its final deadlines (applications by 20 May 2026, programme completion by 30 June 2026) have passed. Parliamentary questions in 2026 complained about long delays in making net-billing settlement work in practice. Households considering solar should therefore check how their supplier and DAPEEP are actually paying surplus.
Third-party ownership is allowed: a self-consumer’s plant may belong to or be operated by a third party acting on the consumer’s instructions, but the value of the surplus must go to the consumer. Self-consumers or plant owners may also sell surplus under bilateral PPAs, and suppliers or aggregators may guarantee a fixed price for it.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity | No producer certificate, installation permit or operation permit for PV up to 1 MW, wind up to 60 kW, biomass, biogas, geothermal, solar thermal and CHP up to 1 MW, other renewables up to 50 kW, or self-producers that do not export (Law 4951/2022, Art. 33). Larger plants need a RAAEY Producer Certificate (Βεβαίωση Παραγωγού), environmental licensing, a connection offer, installation and operation permits. | RAAEY; HEDNO / IPTO (connection) | Rooftop PV on buildings and other structures, with or without storage, is exempt from the Producer Certificate whatever its size. |
| Store electricity | Storage stations with injection power below 1 MW are exempt from licensing. Larger standalone storage needs a RAAEY licence or Producer Certificate for Special Projects (Βεβαίωση Ειδικών Έργων) under Law 4951/2022, valid for up to 25 years (35 for pumped storage). | RAAEY; IPTO / HEDNO (connection) | Hybrid RES-plus-storage projects that also charge from the grid need a Special Projects certificate. Behind-the-meter household batteries with net-billing solar need no licence. |
| Export to the grid | No licence for self-consumers. A HEDNO connection contract and a 20-year net-billing contract with the supplier and aggregator are needed. | HEDNO; supplier; DAPEEP (households up to 10.8 kW) | Non-household self-consumers selling surplus need the relevant business activity code for electricity production and sale. |
| Sell / supply electricity to consumers | RAAEY supply licence (άδεια προμήθειας), granted under Law 4001/2011. | RAAEY | Universal service for customers up to 25 kVA is assigned by ministerial decision to the largest suppliers (currently PPC, Metlen, Heron, Enerwave and NRG). |
| Wholesale trading | RAAEY trading licence (άδεια εμπορίας) under Law 4001/2011, plus registration as a HEnEx member and in IPTO’s balance-responsible-party registry. | RAAEY; HEnEx; IPTO | Participants must settle imbalances with IPTO. |
| Aggregate | Aggregators of renewable plants (Φορείς Σωρευτικής Εκπροσώπησης) and demand-response aggregators are licensed by RAAEY. Demand-response aggregator licences follow RAE Decision 233/2022 and require minimum capital of €60,000, for up to 20 years. | RAAEY; IPTO (registration) | DAPEEP is the aggregator for household net-billing systems up to 10.8 kW and the aggregator of last resort. |
| Balancing / grid services | Registration in IPTO’s Balancing Service Providers registry and prequalification of each unit or portfolio (dispatchable load portfolios, dispatchable RES portfolios, storage). | IPTO | Since the 2026 balancing-rules revision, storage of 10 MW or more must take part as an individual unit and not within an aggregated portfolio. |
| Virtual power plant / remote control of assets | No separate licence beyond an aggregation licence, but the portfolio must be registered and prequalified with IPTO. | RAAEY; IPTO | Self-consumers may let a third party install and operate their plant, including metering and maintenance, on their instructions. |
| Energy community / energy sharing | Energy communities are legal entities under Greek law. Law 5037/2023 transposed the EU rules on renewable and citizen energy communities. Community plants use virtual net billing for members, including vulnerable households. | Ministry of Environment and Energy; RAAEY; HEDNO | HEDNO reserves 3.8 MW per substation for business self-consumers and energy communities, with a cap of 200 kW per plant. |
Greek electricity licensing rests on Law 4001/2011, which makes RAAEY responsible for producer certificates and for supply, trading and other licences. Law 4951/2022 reformed renewable and storage licensing and introduced special-project certificates for storage and hybrids. Law 5037/2023 renamed the regulator and transposed the EU directives on renewables (2018/2001) and the electricity market (2019/944).
For small assets the key thresholds are the 1 MW exemptions for PV and for storage injection power, and the rule that rooftop PV with or without storage needs no producer certificate. Self-consumption is governed by Law 5106/2024 and the September 2024 ministerial decision. Households therefore deal almost entirely with HEDNO and their supplier.
Flexibility and grid services.
Aggregation of home equipment: Yes
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Manual Frequency Restoration Reserve (mFRR) | Yes | — | Yes | IPTO. Open to demand response through licensed aggregators. In October 2024 Optimus Energy and Sympower added more than 230 MW of industrial demand response to IPTO’s balancing market, with loads reducing consumption within 15 minutes of an IPTO signal. |
| Automatic Frequency Restoration Reserve (aFRR) | Yes | — | Limited | IPTO. Procured by IPTO. Operational integration into the European aFRR platform PICASSO was scheduled for 18 March 2025. |
| Storage participation in balancing | Yes | 10 MW for individual participation | Limited | IPTO. RAAEY’s February 2026 revision of the balancing-market rules cut the threshold between large and small storage from 40 MW to 10 MW. Larger units must participate individually, submit charging and discharging schedules on strict deadlines and follow state-of-charge restoration rules. |
| Day-ahead and intraday wholesale | Restricted | — | Yes | HEnEx. Open to licensed participants and aggregators. Household solar surplus reaches the market indirectly through DAPEEP as aggregator. Negative-price hours rose from 11 in 2024 to 115 in 2025 and 382 by mid-September 2026. |
| Household demand response | Developing | — | Limited | Households can now choose orange hourly tariffs and the dual-zone tariff with midday cheap hours, but only 6 household meters were on dynamic tariffs in April 2026. No DSO local flexibility market was identified. |
Flexibility in Greece is mainly bought by IPTO through its balancing market, which is open to generators, storage, dispatchable renewable portfolios and demand response through licensed aggregators. Industrial demand response became an active part of mFRR from 2024. Storage is now changing the market: the first of 900 MW of subsidised batteries chosen in RAAEY auctions began operating in 2026, and the balancing rules were revised in February 2026 to integrate them.
The need for flexibility is clear in the price data. Rapid solar growth produced 382 negative-price hours by mid-September 2026, and renewable curtailment rose from 899 GWh in 2024 to an estimated 2 TWh in 2025. Household assets are not yet a meaningful source of flexibility. Smart meters reach only about a fifth of supplies, dynamic tariffs are barely used, and no aggregator was identified offering household batteries or heat pumps to IPTO’s markets.
Flexibility and aggregation platforms.
| Platform or aggregator | What it does |
|---|---|
| PICASSO | European aFRR energy platform. IPTO scheduled operational integration for 18 March 2025. |
| HEnEx | Greek day-ahead and intraday markets, coupled with EU markets. |
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | HEDNO-led rollout from 2023, part-financed by the EIB and EU funds; target of 7.7 million smart meters by 2030 |
| Reading interval | 15-minute data for net billing and telemetered meters; hourly or 15-minute data shown to customers |
| Smart meters installed (June 2026) | More than 1.6 million (85,000 before the programme) |
| Target end 2026 | 2.37 million |
| Target 2030 | 7.7 million (all supplies) |
| First phase (EIB-financed) | 3.12 million meters, 2023–2026 |
| Network losses | 10.8% (2024), 10.4% (2025); theft 5.1% of consumption in 2025 |
| Meter owner | HEDNO |
Smart metering is entirely HEDNO’s responsibility. After years in which only about 85,000 meters had been fitted, HEDNO started a mass rollout in 2023. The EIB-financed first phase covers 3.12 million meters, and the full programme aims at about 7.7 million meters, covering every supply, by 2030. More than 1.6 million had been installed by June 2026, with 2.37 million expected by the end of the year.
One main driver is electricity theft and losses. HEDNO put total losses at 10.4% in 2025 and theft at 5.1% of consumption, costing honest customers more than €450 million a year. Smart meters are also needed for the orange dynamic tariffs, for 15-minute net-billing settlement and to replace estimated bills. RAAEY has also given HEDNO a six-month deadline to resolve problems with some installed meters.
Renewable electricity.
Electricity generation mix (2025).
- Gas: 40.3%
- Wind: 20.9%
- Solar: 19.8%
- Other fossil (oil): 7.2%
- Hydro: 5.9%
- Coal (lignite): 4.7%
- Bioenergy: 1.2%
- Renewable electricity share
- 47.8% (2025)Source 12Share of domestic generation (wind 20.86%, solar 19.79%, hydro 5.90%, bioenergy 1.23%). IPTO reports a 54.33% renewable share of production on the interconnected system. The EU directive-based RES-E share of consumption was 60.9% in 2025 (Eurostat).
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- 2.25 GW (2025)Source 12Derived: Ember solar capacity of 11.08 GW (2025) minus 8.83 GW (2024).
- Solar
- 11.1 GW (2025)Source 12
- Gas
- 6.97 GW (2025)Source 12
- Wind
- 5.71 GW (2025)Source 12
- Hydro
- 3.49 GW (2025)Source 12
- Coal (lignite)
- 1.65 GW (2025)Source 12
- Other fossil
- 1.44 GW (2025)Source 12Ember category for fossil capacity other than coal and gas, mainly oil-fired units on the non-interconnected islands.
- Bioenergy
- 0.18 GW (2025)Source 12
Targets.
- Final revised NECP (submitted October 2024): renewables to supply 75.7% of electricity production by 2030, with 4,325 MW of batteries and 1,928 MW of pumped storage.
- NECP capacity targets for 2030 of 13.5 GW solar, 8.9 GW onshore wind and 1.9 GW offshore wind, and lignite phased out before 2030.
Greek generation has shifted from lignite to gas and renewables within a decade. In 2025 gas supplied 40.3% of generation, wind 20.9%, solar 19.8%, oil-fired island plants 7.2%, hydro 5.9% and lignite only 4.7% (Ember). Solar capacity grew from 8.83 GW to 11.08 GW in 2025, and trade data put it at 11.6 GW by the end of May 2026, already close to the 2030 NECP target.
The speed of solar growth has outrun grid and storage capacity. Curtailment of renewables rose from 899 GWh (3.5% of renewable output) in 2024 to about 2 TWh (around 7.5%) in 2025, according to an academic estimate, and could reach 3.3–3.7 TWh in 2026. Interconnections help: Greece was a net exporter in 2024 and 2025. The 1 GW Crete–Attica link now lets Crete use mainland renewables in place of local oil plants.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
Greece had almost no grid-scale batteries until 2025. Negative prices, curtailment and evening price peaks have since made storage a priority, and the energy ministry was reported to expect installed battery capacity of about 1 GW by the end of 2026, 1.5 GW by mid-2027 and 3 GW by 2028. The NECP targets 4,325 MW of batteries and 1,928 MW of pumped storage by 2030. Industry forecasts for 2030 range from 4–5 GW (Aurora) to 8.6 GW (HELAPCO).
Storage below 1 MW injection power needs no licence, and behind-the-meter batteries with net-billing solar need no producer certificate. Under net billing a household battery raises the share of solar used on site, which avoids buying at retail prices and selling surplus at low midday wholesale prices. Photovoltaics on the Roof made a battery compulsory for households and subsidised it at 90–100%, but the programme has closed. No new household battery grant was open in October 2026.
Storage projects.
- RAAEY standalone storage auctions: 900 MW of front-of-the-meter batteries supported through competitive auctions, of which 711 MW are two-hour and 189 MW four-hour systems. Projects from the first auctions began energising in 2026, and all are expected to operate by the end of 2026.
- Merchant battery pipeline: Investors have applied to connect about 12.15 GW of standalone merchant batteries, far more than the 4.7 GW the government plans to approve.
- €200 million storage support scheme: Announced in September 2026 and still being designed: four €50 million actions for municipalities, businesses, batteries with renewables and standalone batteries. Households are not direct beneficiaries.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| PPC (ΔΕΗ) | 70.98% of all metering points and 69.88% of household LV supplies (April 2026) | Unknown | Yes | Unknown | Limited |
| Protergia (Metlen Energy & Metals) | 8.52% of metering points (April 2026) | Unknown | Unknown | Unknown | Limited |
| Zenith | 4.73% of metering points (April 2026) | Unknown | Unknown | Unknown | Limited |
| Heron (ΗΡΩΝ) | 4.69% of metering points (April 2026) | Unknown | Unknown | Unknown | Limited |
| Enerwave | 4.26% of metering points (April 2026) | Unknown | Unknown | Unknown | Limited |
| NRG | 2.46% of metering points (April 2026) | Unknown | Unknown | Unknown | Limited |
RAAEY counted 22 active suppliers in April 2026, five of them universal-service suppliers. The market remains concentrated: PPC served 5.45 million of the 7.68 million metering points, and the next largest suppliers, Protergia, Zenith, Heron and Enerwave, each had between 4% and 9%. Other active suppliers included Fysiko Aerio (1.70%) and Volton (1.49%).
All suppliers sell under the regulator’s colour code, which makes it easier to compare offers. Under net billing, suppliers bill the energy taken from the grid. Surplus from household systems up to 10.8 kW is valued by DAPEEP, not by the supplier, so supplier-specific export tariffs are limited.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Ministry of Environment and Energy (ΥΠΕΝ) | Government | Energy policy and legislation | Issues the self-consumption and dynamic-tariff decisions, the NECP and the subsidy programmes. |
| RAAEY (ΡΑΑΕΥ) | Regulator | Energy, waste and water regulator | Licences, producer certificates, tariffs, balancing rules, the tariff colour code and monthly retail market reports. |
| IPTO (ΑΔΜΗΕ) | Transmission | Transmission owner and system operator | Balancing market, market-participant registries, interconnections and system data. |
| HEDNO (ΔΕΔΔΗΕ) | Distribution | National DSO, meter operator and island system operator | Connections, supply numbers, smart meters, solar applications (ape.deddie.gr) and metering data. |
| Hellenic Energy Exchange (HEnEx) | Market | Power exchange | Day-ahead and intraday markets whose prices set the value of solar surplus. |
| DAPEEP | Renewable Energy | RES and guarantees-of-origin operator | Renewable support payments, guarantees of origin, and aggregator for household net billing. |
| HELAPCO (Hellenic Association of Photovoltaic Companies, ΣΕΦ) | Solar | Solar industry association | Publishes practical guides to self-consumption, net billing and storage, and market statistics. |
| Consumer Ombudsman (Συνήγορος του Καταναλωτή) | Consumer | Independent consumer authority | Handles disputes between households and energy suppliers. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Grid connection (generators) | EU Regulation 2016/631 (RfG); HEDNO Network Code (Κώδικας Διαχείρισης ΕΔΔΗΕ, ΦΕΚ Β 78/2017, as amended) | European Commission; HEDNO with RAAEY approval | Set connection, protection and metering requirements for generators on the distribution network. The connection point for low-voltage self-consumers is upstream of the main distribution board. |
| Self-consumption metering | HEDNO requirements for production meters and telemetry under net billing (Ministerial Decision ΥΠΕΝ/ΔΑΠΕΕΚ/93976/2772/2024) | HEDNO; Ministry of Environment and Energy | The customer’s production meter must be of a HEDNO-accepted type and certified in HEDNO laboratories. HEDNO seals both meters at activation. |
| Zero export | Energy-flow direction sensor scheme (HEDNO technical description) | HEDNO | Zero-export systems need a technical description, wiring diagram and manufacturer manuals, plus a solemn declaration that settings will not be changed. HEDNO may disconnect systems that export. |
| Electrical installations | ΕΛΟΤ 60364 (replacing ΕΛΟΤ HD 384 from 1 January 2024) | Hellenic Organisation for Standardisation (ΕΛΟΤ) | The national wiring standard for low-voltage installations, including PV and battery systems in buildings. |
| Installer accreditation | Licensed electrician and Installer’s Declaration (Υπεύθυνη Δήλωση Εγκαταστάτη, ΥΔΕ) | Licensed electrical installers; HEDNO | A licensed electrician must certify the installation in a ΥΔΕ, submitted through HEDNO’s online application, before HEDNO energises a supply or activates a solar connection. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| HEDNO connection offer / connection contract | Yes | National | Online application at ape.deddie.gr. Fees without network works run from €370 to €1,500 plus VAT depending on voltage and size. |
| Net-billing contract | Limited | National | A 20-year contract with the supplier and aggregator (DAPEEP for households up to 10.8 kW) where the system exports. Not needed for zero-export systems. |
| Producer Certificate | No | National | Not required for rooftop PV with or without storage, for PV up to 1 MW, or for self-producers that do not export. |
| Building and planning rules | Limited | Local | Rooftop, pergola, canopy and façade installations follow the building regulations of Law 4067/2012. Heritage areas and traditional settlements may impose extra restrictions. |
| Co-owners’ consent | Limited | Local | Written consent of all co-owners is needed to use a common roof, which is common in blocks of flats. A tenant needs the owner’s written consent. |
| Installer’s declaration (ΥΔΕ) | Yes | National | Issued by a licensed electrician and submitted to HEDNO before activation. |
For a household, the process is mostly technical and handled by HEDNO: an online application, a connection offer, the net-billing contract and an activation visit at which HEDNO tests the system and seals the meters. Rooftop systems are exempt from the RAAEY Producer Certificate and from installation and operation permits.
Capacity, not paperwork, is often the main constraint. Parts of the network have been declared saturated, notably in the Peloponnese, Evia, Crete and the Cyclades. HEDNO keeps an extra 10 MW of hosting capacity in every substation for self-consumers, and zero-export systems are processed with absolute priority.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Net billing for self-consumers | Active | Net billing | Self-consumption is offset in each 15-minute period with no regulated charges on it, and surplus is paid at the day-ahead price for 20 years. Households have no tax obligations on the surplus. | New connection offers from 31 October 2024 |
| Social Household Tariff (KOT) | Active | Social tariff | Reduced charges for vulnerable households, funded through public-service-obligation charges. 444,531 supplies were on KOT in April 2026. | — |
| Dual-zone reduced-rate tariff | Active | Time-of-use tariff | Reduced charges in a midday window (11:00–15:00 in summer, 12:00–15:00 in winter) and a night window (02:00–04:00 in summer, 02:00–05:00 in winter) for households with a suitable meter. | New schedule from 1 February 2025 |
| €200 million energy storage support programme | Scheduled | Grant / tender | Four €50 million actions: 50% subsidy for municipalities, 30–40% for businesses, and competitive tenders for batteries combined with renewables and for standalone batteries. Households are not direct beneficiaries. First calls are expected by the end of 2026. | Calls expected late 2026 |
| Photovoltaics on the Roof (Φωτοβολταϊκά στη Στέγη) | Closed | Grant | A €238 million Recovery and Resilience Facility programme for households and farmers. It paid 45–75% of household solar costs (up to €16,000) for systems up to 10.8 kWp, with a compulsory battery subsidised at 90–100%. Applications closed on 20 May 2026 and the programme ended on 30 June 2026. | 2024 – 30 June 2026 |
| Net metering (ενεργειακός συμψηφισμός) | Closed | Net metering | Closed to new systems: connection offers have been issued only for net billing since 31 October 2024. Existing systems keep their contracts. | — |
Data and connectivity.
- Fixed broadband
- 88.7 % of households (2025)Source 8Households with internet access (Eurostat). Fibre-to-the-premises coverage was 59.8% (Digital Decade 2026).
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- 99.5 % of population (2025)Source 395G coverage reported in the European Commission’s Digital Decade 2026 country report.
Mobile coverage is near universal, with 5G reaching 99.5% of the population, while fibre has grown from almost nothing in 2019 to 59.8% coverage. This supports app-based monitoring of inverters and batteries even on islands. Net billing depends on telemetry: self-consumers must install a system that records production, export and consumption in real time, and HEDNO collects certified 15-minute data. HEDNO’s meter-data system is designed to handle close to a million NB-IoT cellular smart meters.
Grid conditions.
- National peak demand
- 10.8 GW (2025)Source 27Record peak load on 24 July 2025 during a heatwave (IPTO data).
- Annual electricity demand
- 51.4 TWh (2025)Source 26Total market demand on the interconnected system (IPTO), 0.77% lower than in 2024. Ember reports 55.39 TWh including the islands, on its own basis.
- Generation capacity
- 30.5 GW (2025)Source 12Ember total: 20.46 GW clean and 10.06 GW fossil.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- 2 TWh (2025)Source 30Estimate by Prof. Pantelis Biskas (Aristotle University of Thessaloniki), about 7.5% of renewable output. Not an official IPTO statistic. Green Tank put 2024 curtailment at 899 GWh.
The Greek system is now shaped by midday solar surpluses and summer evening peaks. Demand peaks in heatwaves (10,798 MW in July 2025), while spring middays bring curtailment and negative prices. Exports to neighbours have become an important outlet: Greece exported 6.41 TWh and imported 3.41 TWh in 2025.
The network is the main constraint on new solar. Saturated areas limit new connections, and HEDNO reserves part of each substation’s capacity for self-consumers. IPTO is investing heavily in interconnections, including the remaining Cyclades links, the Dodecanese and North Aegean projects for 2030, and a second link with Italy planned for 2033. A Greece–Cyprus–Israel link (the Great Sea Interconnector) is supported by €657 million of EU funding.
Grid and capacity maps.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Net billing replaces net metering | Current | 31 October 2024 | Under Law 5106/2024 and Ministerial Decision ΥΠΕΝ/ΔΑΠΕΕΚ/93976/2772/2024, new self-consumption connections use 15-minute net billing, with surplus paid at the day-ahead price for 20 years. |
| New dual-zone tariff hours | Current | 1 February 2025 | The reduced-rate window moved to midday and early-morning hours to match solar output. |
| Orange dynamic tariffs for households | Current | 1 April 2026 | Hourly prices linked to the day-ahead market, announced by 17:00 the day before, for customers with a HEDNO smart meter (larger customers from 1 February 2026). |
| Balancing-market rules revised for storage | Current | February 2026 | RAAEY lowered the large-storage threshold from 40 MW to 10 MW and set scheduling and state-of-charge rules for batteries. |
| €200 million storage support programme | Upcoming | Late 2026 | First calls and tenders for municipal, business, hybrid and standalone storage are expected by the end of 2026. |
| Cyclades interconnection completed | Upcoming | Q3 2026 | IPTO expects the Santorini–Naxos link, the final element of phase D, to be completed in the third quarter of 2026. |
| Smart meters at all supplies | Upcoming | 2030 | HEDNO targets 2.37 million smart meters by the end of 2026 and 7.7 million by 2030. |
| Dodecanese and North Aegean interconnections | Upcoming | 2030 | IPTO plans to connect the Dodecanese (€2.9 billion) and North Aegean islands to the mainland grid by 2030. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Medium | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | Medium | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | Medium | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | Low | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Medium | Rooftop solar is well established after years of net metering, and Photovoltaics on the Roof funded household PV with batteries. However, there is no official household capacity figure, 60% of people live in flats with shared roofs, and the main subsidy closed in June 2026. |
| Distributed energy market | Medium | Large distributed solar fleet and net billing with 15-minute settlement, but smart meters reach only about 21% of supplies, there are few EVs (30,108 battery-electric cars in 2025) and household batteries are estimated at about 100 MW. |
| Grid flexibility market | Medium | IPTO balancing markets are open to aggregated demand response (more than 230 MW in mFRR since 2024) and to batteries under the 2026 rules, but there is no household flexibility market and only 6 household meters were on dynamic tariffs in April 2026. |
| Energy storage adoption | Medium | 900 MW of auctioned batteries coming online through 2026, with about 400–600 MW reported operating, a 12 GW merchant pipeline and a 4,325 MW NECP target. Still small relative to 11 GW of solar. |
| Renewable growth environment | High | Solar capacity rose from 8.83 GW to 11.08 GW in 2025 (Ember), and the EU RES-E share of consumption rose from 51.2% in 2024 to 60.9% in 2025 (Eurostat). |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 41 sources
- Electricity prices for household consumers – bi-annual data (nrg_pc_204) and price components (nrg_pc_204_c). Eurostat, 2025. accessed 1 October 2026.
- Population on 1 January (tps00001). Eurostat, 2026. accessed 1 October 2026.
- Number of private households by household composition (lfst_hhnhtych). Eurostat, 2025. accessed 1 October 2026.
- Average household size (ilc_lvph01). Eurostat, 2025. accessed 1 October 2026.
- Complete energy balances (nrg_bal_c) – final consumption, households, electricity. Eurostat, 2024. accessed 1 October 2026.
- Distribution of population by tenure status (ilc_lvho02). Eurostat, 2025. accessed 1 October 2026.
- Distribution of population by dwelling type (ilc_lvho01). Eurostat, 2025. accessed 1 October 2026.
- Level of internet access – households (isoc_ci_in_h). Eurostat, 2025. accessed 1 October 2026.
- Passenger cars by type of motor energy (road_eqs_carpda). Eurostat, 2025. accessed 1 October 2026.
- Share of energy from renewable sources (nrg_ind_ren). Eurostat, 2025. accessed 1 October 2026.
- Urban population (% of total population) – Greece. World Bank, 2025. accessed 1 October 2026.
- Yearly electricity data (generation, capacity, demand) – Greece. Ember, 2025. accessed 1 October 2026.
- Έκθεση Λιανικής Αγοράς Ηλεκτρικής Ενέργειας – Απρίλιος 2026. Ρυθμιστική Αρχή Αποβλήτων, Ενέργειας και Υδάτων (RAAEY), 2026. accessed 1 October 2026.
- Αυτοκατανάλωση ενέργειας (net-billing & zero feed-in) με ή χωρίς αποθήκευση. HELAPCO (Σύνδεσμος Εταιριών Φωτοβολταϊκών), 2024. accessed 1 October 2026.
- Διαδικασία πρόσβασης στο Δίκτυο ΜΔΝ για σταθμούς ΑΠΕ/ΣΗΘΥΑ που εξαιρούνται από Βεβαίωση Παραγωγού (άρθρο 33 ν. 4951/2022). ΔΕΔΔΗΕ (HEDNO), 2025. accessed 1 October 2026.
- Law 4951/2022 – Modernization of the licensing process for RES projects and licensing of energy storage. EY Greece, 2022. accessed 1 October 2026.
- Ο αριθμός παροχής ηλεκτρικού ρεύματος και πού βρίσκεται. Οδηγός του Πολίτη. accessed 1 October 2026.
- deddie-metering: integration for HEDNO metering-data platform (supply number, tax number and token access). GitHub (mike81gr). accessed 1 October 2026.
- ΔΕΔΔΗΕ: 7,7 εκατ. έξυπνοι μετρητές κόντρα στις ρευματοκλοπές. Τα Νέα, 2026. accessed 1 October 2026.
- HEDNO Smart Meters I. European Investment Bank, 2023. accessed 1 October 2026.
- Ποια τιμολόγια ρεύματος συμφέρουν και ποια κρύβουν ρίσκο. Τα Νέα, 2026. accessed 1 October 2026.
- Ξεκινά η εφαρμογή του δυναμικού «πορτοκαλί» τιμολογίου. Powergame, 2025. accessed 1 October 2026.
- Ποιες είναι οι ώρες του νυχτερινού (διζωνικού) τιμολογίου ρεύματος για την χειμερινή περίοδο. Οδηγός του Πολίτη, 2025. accessed 1 October 2026.
- Τροποποιήσεις και παρατάσεις στο Πρόγραμμα «Φωτοβολταϊκά στη Στέγη». Οδηγός του Πολίτη, 2026. accessed 1 October 2026.
- ΥΠΕΝ ανακοινώνει επιδότηση μπαταριών 200 εκατ. ευρώ. SBC TV, 2026. accessed 1 October 2026.
- ADMIE Holding – Investor Presentation FY2025. ADMIE (IPTO) Holding, 2026. accessed 1 October 2026.
- Heatwave pushes Greece’s power demand and prices to record highs. OT.gr (English edition), 2025. accessed 1 October 2026.
- Greece can install 8.6 GW of batteries by 2030. pv magazine, 2026. accessed 1 October 2026.
- Greece added 724 MW of solar energy in May despite curtailments and low prices. Balkan Green Energy News, 2026. accessed 1 October 2026.
- Greek PV producers fret 3.5 TWh of curtailments in 2026. pv magazine, 2026. accessed 1 October 2026.
- Green power wasted: Greece sees record renewable energy cuts in 2025. To Vima (citing Green Tank), 2025. accessed 1 October 2026.
- Greece adjusts goals for renewables, pumped hydropower, hydrogen in final NECP. Balkan Green Energy News, 2024. accessed 1 October 2026.
- Greece’s revised NECP targets 81% renewables in its power mix by 2030. Enerdata, 2024. accessed 1 October 2026.
- PPC agrees sale of 49 per cent of HEDNO to Macquarie Asset Management. Macquarie, 2021. accessed 1 October 2026.
- Optimus Energy, Sympower add over 230 MW to Greece’s balancing market. Balkan Green Energy News, 2024. accessed 1 October 2026.
- The Greek case – demand response and market integration (RAEWW presentation). ERRA / RAAEY, 2024. accessed 1 October 2026.
- Greek regulator opens balancing market to large-scale battery storage. dnews.gr, 2026. accessed 1 October 2026.
- Start of simulation tests and scheduling of operational integration into the European platform PICASSO. IPTO (ΑΔΜΗΕ), 2025. accessed 1 October 2026.
- State of the Digital Decade 2026 – Greece country report. European Commission (Council document ST-10476-2026-ADD-13), 2026. accessed 1 October 2026.
- Ηλεκτρικές εγκαταστάσεις χαμηλής τάσης – γενικές και ειδικές απαιτήσεις. Οδηγός του Πολίτη. accessed 1 October 2026.
- Hellenic Parliament document on reduced VAT rates for electricity. Hellenic Parliament. accessed 1 October 2026.
Questions about energy in Greece.
Eurostat puts the average household price at €0.2381/kWh in the second half of 2025, including network charges, levies and 6% VAT, for households using 2,500–4,999 kWh a year. Prices depend on the tariff colour: in January–July 2026 the average charge for 300 kWh a month was €49.99 on yellow (variable) tariffs, €55.86 on blue (fixed) and €56.06 on green.
The αριθμός παροχής (supply number), an 11-digit number issued by HEDNO and printed at the top right of the first page of the bill and on a metal plate at the meter. The first nine digits identify the supply and stay with the property. The last two are a succession number that changes with a new holder or supplier.
Yes, under net billing. Energy you produce and use in the same 15-minute period is free of energy and regulated charges, and surplus fed into the grid is paid at the day-ahead market price for 20 years. For households up to 10.8 kW, DAPEEP handles the payment. Net metering has been closed to new systems since 31 October 2024.
IPTO (ΑΔΜΗΕ) owns and operates the transmission grid and runs the balancing market. HEDNO (ΔΕΔΔΗΕ) is the single distribution operator for the whole country, including the non-interconnected islands, and also owns and reads the meters. RAAEY regulates both.
No. Rooftop PV with or without storage is exempt from the RAAEY Producer Certificate, and storage below 1 MW needs no licence. You need a HEDNO connection contract, a net-billing contract if you export, and an installer’s declaration (ΥΔΕ) from a licensed electrician.
Not at present. Photovoltaics on the Roof, which subsidised household solar with a compulsory battery, closed on 30 June 2026. A €200 million storage programme announced in September 2026 targets municipalities and businesses, not households, and new household programmes through the Social Climate Fund had not been launched by October 2026.
They are the regulator’s colour code. Blue tariffs have a fixed price for the contract term. Green tariffs have a price set on the first day of each month. Yellow tariffs have a variable price linked to the wholesale market. Orange tariffs are dynamic, with hourly prices published the day before, and need a smart meter.
The rollout is under way. HEDNO had installed more than 1.6 million smart meters by June 2026, about a fifth of supplies, and aims for 2.37 million by the end of 2026 and 7.7 million, covering all supplies, by 2030.