Countries

Energy in Kyrgyzstan, explained.

How electricity works in Kyrgyzstan: prices, the grid and local rules. Olmack status: Not yet available. Information last checked 10 October 2026.

Olmack in Kyrgyzstan: Not yet available.Olmack is not offered in Kyrgyzstan yet. The market information on this page is provided for reference. Information last checked 10 October 2026.
Energy-market overview

How electricity works in Kyrgyzstan.

Kyrgyzstan electricity 2026: hydro-led supply, state-owned EEP and NEGK, Ministry of Energy regulation, annual tariff rises, 501,000 smart meters and winter imports.

This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Kyrgyz som (KGS) where they relate to prices.

Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.

At a glance

Kyrgyzstan energy at a glance.

Key figures for households in Kyrgyzstan. Each one links to its source on the full overview below.

  • Renewable share.

    75% of electricity from renewable sources. Figures for 2025.

  • Selling back to the grid.

    Can homes export electricity? Limited. Details are in the export section below.

Before you start

Four things to check in Kyrgyzstan.

Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.

  1. Check the local rules.

    Read the connection, export and permission rules for Kyrgyzstan below, and ask your local grid operator if anything is unclear.

  2. Choose a qualified installer.

    Look for an installer listed on an official register, with the certifications Kyrgyzstan requires for the work.

  3. Look at current schemes.

    Check which support schemes are open now. Closed or scheduled schemes are labelled as such.

  4. Talk to your energy supplier.

    Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.

Local detail

Schemes, rules and certifications in Kyrgyzstan.

The full detail sits in the sections below. Each item shows its status and links to the official source.

  • Support schemes.

    Grants, tax relief and export payments in Kyrgyzstan, each labelled Active, Scheduled or Closed.

  • Connection and export.

    How equipment is connected to the grid in Kyrgyzstan, and the steps to export electricity.

  • Standards and certifications.

    The technical standards and installer certifications that apply to energy equipment in Kyrgyzstan.

Full overview

The energy market in Kyrgyzstan, in detail.

Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.

Profile last updated 10 October 2026.

On this page22 sections

Kyrgyzstan’s electricity system is dominated by hydropower and run by state-owned companies. The World Bank reports that hydropower supplied 75% of generation in 2025, with coal at about 25%, mostly from the Bishkek combined heat and power plants. IRENA’s statistics record 13,839 GWh of generation in 2023, 87% of it hydro, and no grid-connected solar or wind capacity at the end of 2024.

After a restructuring, the four regional distribution companies were merged with the transmission company, leaving two main state companies: Electric Power Plants (EEP), which runs the large hydropower plants and the Bishkek CHPs, and the National Electric Grid of Kyrgyzstan (NEGK), which runs transmission and distribution. The Ministry of Energy, re-established in 2021, sets policy and houses the tariff and licensing regulator.

Household tariffs have long been among the lowest in the world and below cost. The residential tariff rose from 0.77 to 1.00 som per kWh on 1 May 2023, by about 11% on 1 May 2024, and again on 1 May 2025 and 1 May 2026 under a Medium-Term Tariff Plan approved in April 2025. Demand in winter is two to three times that in summer, which leaves the country dependent on winter imports.

Energy snapshot.

Headline figures for electricity in Kyrgyzstan. Each shows its data year and links to its source.

  • Population7,343,064 peopleSource 12025
  • HouseholdsNot identified from a reliable public source.
  • Average household sizeNot identified from a reliable public source.
  • Electricity use per householdNot identified from a reliable public source.
  • Household price (KGS)Not identified from a reliable public source.
  • Household price (EUR)Not identified from a reliable public source.
  • Renewable electricity share75%Source 82025
  • Solar capacity0 GWSource 22024
  • Wind capacity0 GWSource 22024
  • Energy storage capacityNot identified from a reliable public source.
  • Smart-meter shareNot identified from a reliable public source.
Market structure
Single buyer
Homes can export to the grid
Limited
Home equipment in grid services
No
Regulator
Ministry of Energy, through its tariff and licensing regulator (described by the World Bank as the State Regulatory Agency for Energy and Fuel, mapped under the Ministry)
System operator
National Electric Grid of Kyrgyzstan (NEGK), the state transmission and distribution company
Distribution networks
Single national network company: the four former regional distribution companies (Severelectro, Vostokelectro, Oshelectro, Jalalabadelectro) were merged with transmission into NEGK
Currency
Kyrgyz som (KGS)
Voltage and frequency
Not confirmed from an official source in this research

Electricity prices in Kyrgyzstan.

Household price (KGS)
Not identified from a reliable public source.
Household price (EUR)
Not identified from a reliable public source.
Typical annual electricity bill
Not identified from a reliable public source.

Household price trend (KGS per kWh).Source 4

0.770.8851Before May 2023May 2023
Kyrgyzstan household electricity price, KGS per kWh
Before May 20230.77 KGS/kWh
May 20231 KGS/kWh

Low, regulated tariffs

Electricity in Kyrgyzstan is sold to households at a single regulated price. The World Bank described tariffs in 2023 as among the lowest in the world, recovering only about half the cost of supply; it estimated cost recovery at about 65% and projected a fall to 46% by 2030 without reform. Budget organisations pay more than households: their tariff rose from 2.52 to 3.40 som/kWh in January 2022.

Tariff reform since 2023

A new tariff-setting methodology based on full cost recovery was approved on 6 October 2023. The residential tariff rose by 30% to 1.00 som/kWh on 1 May 2023 and by about 11% on 1 May 2024, indexed to inflation. An updated Medium-Term Tariff Plan was approved by the Chairman of the Cabinet of Ministers on 24 April 2025, and tariffs were adjusted on 1 May 2025 and 1 May 2026 in line with it. Across the sector, cash collected per kWh rose from 1.37 som in September 2022 to 2.16 som in May 2026, which the World Bank attributes to the annual adjustments.

Protecting vulnerable households

Since January 2022 families earning below the guaranteed minimum income have paid 0.50 som/kWh for up to 700 kWh a month. The World Bank project supporting the reform also funds work on social protection systems so that tariff increases can be offset for poorer households.

Tariff types.

Tariff types.
TariffAvailableDetail
RegulatedYesA single regulated residential tariff set by the state. It was 1.00 som/kWh from 1 May 2023, up from 0.77; it has since been adjusted each May (2024, 2025, 2026) under the Medium-Term Tariff Plan.
OtherYesA reduced tariff for low-income households: in January 2022 it was cut from 0.77 to 0.50 som/kWh for consumption up to 700 kWh a month for families earning below the guaranteed minimum income, and it was unchanged at 0.50 in May 2023 (World Bank).
Time-of-useUnknownNo household time-of-use tariff was confirmed from the sources read.
DynamicNoThere is no competitive retail market, so no market-linked household tariff exists.

Household prices compared with neighbouring countries (EUR per kWh).

Household prices including taxes, converted to euros as stated on each country page.

Household electricity use.

Electricity use per household
Not identified from a reliable public source.
Average daily use per household
Not identified from a reliable public source.
Typical household peak demand
Not identified from a reliable public source.
Electricity use per person
2,168 kWh/person/yr (all sectors) (2024)Source 1World Bank indicator EG.USE.ELEC.KH.PC (2,167.6 kWh).
Heat pumps
Not identified from a reliable public source.
Air conditioning
Not identified from a reliable public source.
Electric vehicles
Not identified from a reliable public source.
Electric cooking
Not identified from a reliable public source.

Everyone in Kyrgyzstan has access to electricity (World Bank, 2024), and consumption per person was about 2,168 kWh in 2024. Use is strongly seasonal: demand in winter is two to three times that in summer, while over 70% of river flow arrives in four to five summer months (World Bank, 2023).

The World Bank reported that electricity consumption grew by more than 70% over the decade to 2023 and that domestic demand rises by about 3% a year, while no major new power plants were built in decades. Households accounted for 37% of renewable final energy consumption in 2022 (IRENA).

Housing and households.

Dwellings
Not identified from a reliable public source.
Owner-occupied
Not identified from a reliable public source.
Private rented
Not identified from a reliable public source.
Social or public housing
Not identified from a reliable public source.
Houses
Not identified from a reliable public source.
Apartments and flats
Not identified from a reliable public source.
Urban population
34.7 % of population (2025)Source 1

About a third of the population (34.7% in 2025) lives in towns and cities, mainly Bishkek and Osh; the rest live in rural villages. The National Statistical Committee publishes housing-stock tables by form of ownership and type, and ran a Population and Housing Census in 2022, but the detailed results could not be read for this profile.

Much of the urban housing stock dates from the Soviet era. The World Bank estimates the energy-saving potential of residential and commercial buildings at about 15%. In Bishkek, the two CHP plants supply about 70% of the country’s heat demand, so electricity and district heating are closely linked.

How the grid works in Kyrgyzstan.

  1. TransmissionNational Electric Grid of Kyrgyzstan (NEGK OJSC), Electric Power Plants (EEP OJSC)
  2. DistributionSingle national network company: the four former regional distribution companies (Severelectro, Vostokelectro, Oshelectro, Jalalabadelectro) were merged with transmission into NEGK
  3. MeteringNot identified from a reliable public source.
  4. Supply1 or more retail suppliers

Physical system

Installed capacity was about 4.2 GW at the end of 2024, 78% of it renewable (hydro), according to IRENA, which recorded 115 MW of new hydro capacity in 2024. Much of the untapped hydropower potential lies in the Naryn basin, where the World Bank lists 33 projects totalling 6,170 MW. The Bishkek CHP plants burn mainly coal, with gas as backup. The World Bank reported in 2022 that about half of generation capacity and 60–70% of distribution assets were beyond their useful lives, and that losses were about 20% of net generation in 2020.

Seasonal imbalance and trade

Most river flow arrives in summer, but demand peaks in winter. Kyrgyzstan traditionally exports to Kazakhstan and Uzbekistan in spring and summer and imports in winter; net imports rose from 53 GWh in 2020 to 1,120 GWh in 2021 and 2,485 GWh in 2022 (World Bank). Regional projects aim to change this: the planned 1,860 MW Kambarata-1 hydropower plant on the Naryn, the CASA-1000 line to export summer surplus to Afghanistan and Pakistan, and a new 220 kV Kristall–Yulduz line to Uzbekistan financed under the World Bank’s regional electricity market programme approved in December 2025.

Commercial flow

EEP generates most electricity and sells it to NEGK, which transmits, distributes and bills customers at regulated tariffs set by the regulator under the Ministry of Energy. Under the 2023 Renewable Energy Law, NEGK is the single buyer of power from renewable projects. There is no competitive wholesale or retail market.

Who does what.

Who does what.
RoleOrganisationWhat it does
MinistryMinistry of Energy of the Kyrgyz RepublicRe-established in 2021 to consolidate policy-making, long-term planning and oversight of the energy sector. Leads energy reforms and the energy subsidy reform agenda (World Bank).
RegulatorEnergy regulator under the Ministry of EnergyRegulates domestic electricity, gas and heating tariffs and performs licensing functions. The World Bank refers to it as the State Regulatory Agency for Energy and Fuel, mapped under the Ministry of Energy.
TSONational Electric Grid of Kyrgyzstan (NEGK OJSC)State-owned transmission company, which absorbed the four regional distribution companies. Designated in the updated Renewable Energy Law (August 2023) as the renewable energy off-taker and single buyer. Implementing agency for World Bank grid and regional interconnection projects.
DSONEGK (former Severelectro, Vostokelectro, Oshelectro and Jalalabadelectro)The four regional distribution companies were merged with the transmission company; the World Bank reported in 2026 that only two major companies, EEP and NEGK, remain in the power sector.
System operatorElectric Power Plants (EEP OJSC)State generation company operating seven large hydropower plants with 3,030 MW of capacity (World Bank, 2023) and the Bishkek combined heat and power plants.

Compared with the UK system.

Compared with the UK system.
UK conceptKyrgyzstan equivalentHow it works
DNONEGK (merged regional distribution companies)Instead of 14 regional DNOs, Kyrgyzstan now has one state network company. The former regional companies (Severelectro, Vostokelectro, Oshelectro and Jalalabadelectro) were merged into NEGK.
National Grid/NESONEGKNEGK runs the transmission network as well as distribution, and is the single buyer for renewable power. Kyrgyzstan is part of the Central Asian power system and a founding member of the regional Coordinating Dispatch Center.
MPANCustomer account with the network companyThere is no national supply-point number comparable to an MPAN. A household connection is identified by the customer account and meter records held by the distribution business.
MPRNGas account with the gas companyGas is supplied separately; no national gas supply-point identifier was identified.
Meter operatorNEGKMeters are installed and owned by the network company. Smart meters are being fitted under a World Bank-financed programme.
SupplierNEGK (state, regulated)Households cannot choose a supplier. The state network company bills customers at the regulated tariff.
Smart-meter infrastructureUtility AMI systems501,000 advanced meters were installed by May 2026 under the World Bank project, following an earlier KfW-supported AMI and billing system in Bishkek. There is no independent data hub like the DCC.

How a supply point is identified.

Fictional illustration, not a real format: account 0412-3365897, single-phase smart meter, Bishkek.

Fictional example in the real format.

How a supply point is identified.
QuestionAnswer
What is it called?Customer account and meter number (no national supply-point identifier)
Who issues it?The state network company (NEGK, formerly the regional distribution companies)
FormatNo published national numbering standard was found. Account and meter numbers are assigned in the network company’s own billing system.
LengthNot publicly documented
Stays with the property when you switch supplier?Not identified from a reliable public source.
Where to find itOn electricity bills and receipts issued by the network company, and on the meter itself. No official description of the format was found.
Electronic accessNo regulated national service for consumers to download their consumption data was identified.
Third-party accessNo regulated data-sharing scheme exists; third parties rely on the customer’s own account details.
Who keeps the registerKept by the network company in its billing system. No independent central register of supply points was identified.
Register scopePer DSO

How a connection is identified

Kyrgyzstan has no independent, national supply-point register of the kind used in liberalised European markets. Because the network company is also the only electricity seller, a household connection exists as a customer account in its billing system, linked to a meter at the property. Before the merger these records sat with the four regional distribution companies; they now belong to NEGK. No official document setting out the account-number format, or what happens to the account when a property changes hands, was found for this profile.

Billing and metering

Billing has been modernised with donor support: KfW financed an advanced metering programme and a billing system in Bishkek, and the World Bank’s Electricity Sector Modernization and Sustainability Project (2022–2027) has installed 501,000 single- and three-phase smart meters, all of those in its original scope, by May 2026. The project targets 590,000 advanced metering systems by September 2027.

Why no supplier switching register exists

With no retail competition, there is no need for a switching register or settlement data hub. Any change of account holder is handled as a customer-service matter with the network company.

Sending electricity to the grid.

Sending electricity to the grid.
QuestionAnswer
Can homes export electricity?Limited
Net meteringUnknown
Net billingUnknown
How exported electricity is paidRenewable generators sell to NEGK as single buyer. The World Bank reported in 2023 that cost-recovering feed-in tariffs were being introduced for small solar projects (generally 30 MW and below), with auctions for larger plants. Household-scale rules were not confirmed.
Can households sell solar power to the grid?Not confirmed. The Renewable Energy Law provides for purchase of renewable power by NEGK, but no household-specific net-metering or export procedure was confirmed from the sources read.
Who buys power from renewable generators?NEGK, designated as renewable energy off-taker and single buyer by the updated Renewable Energy Law adopted in August 2023 (World Bank).
How are larger solar plants procured?The World Bank reported in 2023 that the government intended to use auctions for large solar projects and feed-in tariffs for projects of generally 30 MW and below.

Connecting a home system.

  1. Renewable projects sell their output to NEGK, which the 2023 Renewable Energy Law designates as single buyer.
  2. A grid connection is arranged with NEGK as network owner.
  3. Tariffs and licences are handled by the regulator under the Ministry of Energy.
  4. No published step-by-step procedure for household rooftop solar export was found for this profile.

Kyrgyzstan has started to open its hydro-dominated system to private renewable generation. A Renewable Energy Law passed in 2022 and updated in August 2023 makes NEGK the single buyer, and the World Bank notes the introduction of feed-in tariffs for small solar projects and auctions for larger ones. IRENA records no grid-connected solar capacity at the end of 2024, so these rules are at an early stage. The World Bank also noted in 2023 a legal gap around public–private partnerships and competitive auctions.

Licensing and approvals.

Requirements depend on the activity. The table sets out what each activity needs and who grants it.

Licensing and approvals.
ActivityLicence or registrationAuthorityNotes
Generate electricity for own use (household solar)No household licence requirement was confirmed from the sources read.Regulator under the Ministry of EnergyThresholds could not be verified.
Generate electricity for saleLicensing is performed by the regulator; renewable output is sold to NEGK as single buyer under the Renewable Energy Law.Regulator under the Ministry of EnergyFeed-in tariffs for small solar (generally ≤30 MW) and auctions for larger plants (World Bank, 2023).
Transmit and distribute electricityState monopoly held by NEGK.Ministry of Energy / regulatorThe four regional distribution companies were merged into NEGK.
Supply (sell) electricity to consumersPerformed by the state network company at regulated tariffs; no competitive retail supply.Regulator under the Ministry of Energy
Store electricity (batteries)No specific rule was identified.None identified
Export electricity to the gridSale to NEGK as single buyer for renewable generators; household procedure not confirmed.NEGK / regulatorSee the export section.
Wholesale trading, aggregation and virtual power plantsNo framework; there is no competitive wholesale market or aggregator role.NoneCross-border trade is conducted by state companies.
Balancing, grid services and remote control of assetsNot open to third parties.NEGK / EEPNo rules for third-party distributed assets were identified.

The regulator under the Ministry of Energy sets electricity, gas and heating tariffs and issues licences, but the detailed licensing thresholds could not be confirmed from the official legal database during this research. Electricity is generated, transmitted, distributed and sold by state-owned companies; the main route for private participation is renewable generation sold to NEGK under the Renewable Energy Law.

Flexibility and grid services.

Aggregation of home equipment: No

Flexibility and grid services.
Market or serviceAccess for home equipmentMinimum sizeVia an aggregatorDetail
Wholesale energy marketNo—NoThere is no competitive wholesale market; power flows from EEP and renewable producers to NEGK at regulated prices.
Balancing and reservesNo—NoNEGK / EEP. Balancing is provided mainly by EEP’s large hydropower plants.
Regional electricity tradeDeveloping—NoState companies; Coordinating Dispatch Center Energia. Regional trade is about 1–2% of demand across Central Asia; a World Bank programme approved in 2025 aims to build a regional electricity market (state entities only).

There is no route for distributed energy resources, demand response or aggregators to sell flexibility in Kyrgyzstan. System flexibility comes from reservoir hydropower and from cross-border exchanges with neighbouring Central Asian systems, coordinated through the regional dispatch centre in which Kyrgyzstan is a founding member.

Smart meters.

Smart meters.
FactValue
Smart-meter rollout501,000 advanced meters installed under a World Bank project by May 2026; target 590,000 by September 2027
Reading intervalNot published
Meter ownerNEGK (state network company)
Installed (May 2026)501,000 advanced meters
Target (Sept 2027)590,000 advanced metering systems
Earlier programmeKfW-supported AMI and billing in Bishkek
Data hubNone

Smart metering is utility-led and donor-financed. The World Bank Electricity Sector Modernization and Sustainability Project (US$58 million, closing December 2027) aims to improve the financial performance and reliability of the sector. Its smart-meter procurement was launched in February 2024, no meters had been fitted by October 2024, and by May 2026 all 501,000 meters in the original scope, both single- and three-phase, were installed in large cities. The aim is to cut commercial losses and improve billing and collection rather than to support consumer services such as time-of-use tariffs.

Renewable electricity.

Electricity generation mix (2025).

  • Hydropower: 75%
  • Coal and other fossil fuels: 25%
Source 8
Renewable electricity share
75% (2025)Source 8Hydropower share of electricity generation (World Bank, 2026). IRENA puts the renewable share at 87% of 2023 generation. Kyrgyzstan imports electricity in winter (net imports of 2,485 GWh in 2022), so the share of consumption is lower.
Home solar
Not identified from a reliable public source.
Solar added each year
0 MW (2024)Source 2
Total (all technologies)
4.2 GW (2024)Source 2Renewable (hydro) share of capacity 78%.
Large hydropower (EEP)
3,030 MW (2023)Source 4Seven large HPPs operated by Electric Power Plants.
Small hydropower (Chakan HPP)
38 MW (2023)Source 4Nine small HPPs.
Solar PV
0 MW (2024)Source 2

Targets.

  • Updated NDC: unconditional greenhouse-gas reduction of 18% by 2030 and 16% by 2035; conditional on international support, 30% by 2030 and 39% by 2035 (World Bank, 2026).
  • Kambarata-1 hydropower plant (1,860 MW) on the Naryn, with launch of the project expected by 2027 (World Bank, 2026).

Kyrgyzstan’s electricity is already mostly renewable because of hydropower: 87% of generation in 2023 (IRENA) and 75% in 2025 (World Bank). The rest comes mainly from coal at the Bishkek CHPs. The World Bank estimates the technical solar potential at about 650 GW and solar yields at around 1,200 kWh/kWp a year, yet no grid-connected solar or wind capacity was recorded by IRENA at the end of 2024.

Diversification is a government and donor priority because droughts and winter shortages expose the system. The World Bank-financed Kyrgyz Renewable Energy Development Project (approved 2023) targets 20 MW of rehabilitated or new hydropower, 105.5 km of transmission lines and 100 MW of variable renewable energy enabled by June 2028, though progress was rated moderately unsatisfactory in March 2026.

Energy storage.

Home batteries
Not identified from a reliable public source.
Grid-scale storage
Not identified from a reliable public source.

Energy storage in Kyrgyzstan is essentially reservoir hydropower. No battery storage projects or statistics were identified from official sources.

Storage projects.

  • Kambarata-1 hydropower plant: Planned 1,860 MW reservoir hydropower plant on the Naryn, about 14 km upstream of the 120 MW Kambarata-2; feasibility study reviewed by Kyrgyzstan, Kazakhstan and Uzbekistan.

Electricity suppliers.

Electricity suppliers.
SupplierMarket shareRenewable tariffTime of useDynamicExport tariff
National Electric Grid of Kyrgyzstan (NEGK)State network company serving all grid customers after the merger of the four regional distribution companiesNoUnknownNoUnknown

There is no supplier choice. Households buy electricity at the regulated tariff from the state network company. The websites of the Ministry of Energy, NEGK and the former distribution companies could not be reached for this research, so the World Bank project report is given as the reference.

Key organisations.

Key organisations.
OrganisationCategoryWhat it doesWhy it matters
Ministry of Energy of the Kyrgyz RepublicGovernmentEnergy policy, planning and oversightSets energy policy and oversees state energy companies and tariff reform.
Energy regulator under the Ministry of EnergyRegulatorTariff regulation and licensingSets electricity, gas and heating tariffs and issues licences.
National Electric Grid of Kyrgyzstan (NEGK)TransmissionTransmission, distribution and single buyerOwns the grid, serves customers and buys renewable power.
Electric Power Plants (EEP)Renewable EnergyState generation companyRuns the large hydropower plants and the Bishkek CHPs.
National Statistical Committee of the Kyrgyz RepublicGovernmentOfficial statisticsPublishes population, housing and price statistics.

Technical standards.

Technical standards.
AreaStandardIssued byNotes
Energy efficiency of appliancesRegulation EAEU 048/2019Eurasian Economic UnionListed by IRENA as a current regulation on energy-efficiency requirements for energy-consuming devices (2025).
Sector lawRenewable Energy Law (2022, updated August 2023)Government of the Kyrgyz RepublicDesignates NEGK as single buyer of renewable power.
Grid connectionNot confirmedNEGK / Ministry of EnergyNo grid-connection or inverter standard for small generators could be confirmed from the sources read.

Permissions.

Permissions.
PermissionRequiredLevelDetail
Electricity licence for household solarLimitedNationalLicensing is carried out by the regulator under the Ministry of Energy; thresholds for small installations were not confirmed.
Grid connection approvalYesNationalAny grid connection is arranged with NEGK, the network owner.
Building or planning permissionLimitedLocalNo specific rule for rooftop solar was identified.

Detailed permitting rules for household solar could not be confirmed from official sources during this research. Anyone planning an installation should check with NEGK and the regulator under the Ministry of Energy.

Support schemes, taxes and incentives.

Support schemes, taxes and incentives.
SchemeStatusTypeDetailPeriod
Feed-in tariffs for small renewable projectsActiveFeed-in tariffThe World Bank reported in 2023 that cost-recovering feed-in tariffs were being introduced for small solar PV projects (generally 30 MW and below), with NEGK as single buyer. Tariff levels were not confirmed.—
Reduced electricity tariff for low-income familiesActiveSocial tariff0.50 som/kWh for up to 700 kWh a month for families earning below the guaranteed minimum income (from January 2022; unchanged in May 2023).—

Data and connectivity.

Fixed broadband
92 % of population using the internet (2024)Source 1
4G coverage
Not identified from a reliable public source.
5G coverage
Not identified from a reliable public source.

Internet use is high: 92% of people in 2024, with 107.5 mobile subscriptions per 100 people (World Bank). The communications technology used by the new smart meters was not published in the sources read.

Grid conditions.

National peak demand
Not identified from a reliable public source.
Annual electricity demand
15.7 TWh (2024)Source 1Derived: World Bank consumption per capita (2,167.6 kWh) × population (7,221,868) for 2024. Generation was 13.84 TWh in 2023 (IRENA).
Generation capacity
4.2 GW (2024)Source 2
Interconnection
Not identified from a reliable public source.
Curtailment
Not identified from a reliable public source.

The main constraint is seasonal adequacy rather than curtailment. Winter demand is two to three times summer demand while river flows are lowest, so the country imports electricity in winter. Network losses remain high: the World Bank reported about 20% of net generation in 2020, and the IEA has cited losses above 20%. A World Bank project has upgraded 296 km of distribution lines and 291 transformer substations by May 2026.

Regulatory changes.

Regulatory changes.
ChangeStatusDateDetail
Annual tariff adjustments under the Medium-Term Tariff PlanCurrentPlan approved 24 April 2025; adjustments 1 May 2025 and 1 May 2026Tariffs are being raised annually towards cost recovery under a methodology approved on 6 October 2023.
Merger of distribution into NEGKCurrentCompleted by 2026The four regional distribution companies were merged with the transmission company, leaving EEP and NEGK as the two main power companies.
Kambarata-1 hydropower plantUpcomingProject launch expected by 20271,860 MW plant on the Naryn, prepared with World Bank technical assistance and reviewed with Kazakhstan and Uzbekistan.
Regional electricity market and Kristall–Yulduz lineUpcomingProgramme approved December 2025World Bank programme (US$40 million IDA for Kyrgyzstan) to build the Kyrgyz section of a 220 kV line to Uzbekistan and modernise the Kristall and Torobaeva substations.
Smart-meter programme completionUpcomingSeptember 2027Target of 590,000 advanced metering systems.

Market indicators.

Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.

Market indicators.
IndicatorLevelBasis
Electricity cost—Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros).
Household electricity use—Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household).
Renewable shareHighLow below 30%, high at 60% or more (renewable share of electricity).
Smart-meter adoption—Low below 30%, high at 80% or more (share of meters that are smart).
Home solar adoptionLowIRENA records no grid-connected solar capacity at end-2024; household export rules were not confirmed.
Distributed energy marketLowState-owned generation and networks dominate; private renewables limited to sales to the single buyer NEGK.
Grid flexibility marketLowNo wholesale, balancing or demand-response market exists.
Energy storage adoptionLowNo battery storage statistics; storage is provided by reservoir hydropower.
Renewable growth environmentLowRenewable capacity changed little (–11% 2019–24, +115 MW hydro in 2024, IRENA); no solar or wind added by end-2024.

Sources.

Public sources used for this profile, with the date each was accessed.

Show all 16 sources
  1. World Development Indicators: population, urban population, internet use, electricity access and consumption per capita (Kyrgyz Republic). World Bank, 2025. accessed 10 October 2026.
  2. Energy Profile: Kyrgyzstan. IRENA, 2025. accessed 10 October 2026.
  3. Project Appraisal Document: Kyrgyz Republic Electricity Sector Modernization and Sustainability Project (P177871). World Bank, 2022. accessed 10 October 2026.
  4. Project Appraisal Document: Kyrgyz Republic Renewable Energy Development Project (P178286). World Bank, 2023. accessed 10 October 2026.
  5. Electricity Sector Modernization and Sustainability Project: Support Mission Aide Memoire (February 2024). World Bank, 2024. accessed 10 October 2026.
  6. Implementation Status and Results Report, Sequence 5: Electricity Sector Modernization and Sustainability Project. World Bank, 2024. accessed 10 October 2026.
  7. Implementation Status and Results Report, Sequence 8: Electricity Sector Modernization and Sustainability Project. World Bank, 2026. accessed 10 October 2026.
  8. Appraisal Project Information Document: Innovative Finance for Resilient and Sustainable Energy Transition (P512264). World Bank, 2026. accessed 10 October 2026.
  9. Implementation Status and Results Report, Sequence 6: Kyrgyz Renewable Energy Development Project. World Bank, 2026. accessed 10 October 2026.
  10. Project Appraisal Document: Central Asia Regional Electricity Market Interconnectivity and Trade Program. World Bank, 2025. accessed 10 October 2026.
  11. Implementation Status and Results Report, Sequence 5: Technical Assistance for Kambarata 1 Hydropower Plant Project. World Bank, 2026. accessed 10 October 2026.
  12. Project Paper: Technical Assistance for Kambarata 1 Hydropower Plant Project, Additional Financing. World Bank, 2024. accessed 10 October 2026.
  13. Implementation Completion Report Review: CASA-1000 Community Support Project, Kyrgyz Republic. World Bank, 2025. accessed 10 October 2026.
  14. Promoting Green Growth in Kyrgyz Republic. World Bank, 2026. accessed 10 October 2026.
  15. Official exchange rates of the som (daily). National Bank of the Kyrgyz Republic, 2026. accessed 10 October 2026.
  16. Housing fund statistics. National Statistical Committee of the Kyrgyz Republic, 2026. accessed 10 October 2026.

Questions about energy in Kyrgyzstan.

Talk to us about Olmack in Kyrgyzstan.Tell us about your home, housing portfolio or school estate in Kyrgyzstan. We'll explain what is possible there now.