How electricity works in Tajikistan.
Tajikistan electricity 2026: 93% hydropower, Barqi Tojik generation, SIB transmission and STB distribution, a 0.4137 TJS/kWh household tariff and the Rogun dam.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Tajikistani somoni (TJS) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Tajikistan energy at a glance.
Key figures for households in Tajikistan. Each one links to its source on the full overview below.
Electricity price.
0.414 TJS per kWh for households, including taxes. Figures for From 1 January 2026.
Renewable share.
92.5% of electricity from renewable sources. Figures for 2024.
Selling back to the grid.
Can homes export electricity? No. Details are in the export section below.
Four things to check in Tajikistan.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Tajikistan below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Tajikistan requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Tajikistan.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Tajikistan, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Tajikistan, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Tajikistan.
The energy market in Tajikistan, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 10 October 2026.
On this page21 sections
Tajikistan generates almost all of its electricity from hydropower. The World Bank puts hydro at 92.5% of generation in 2024, with the rest from fossil-fuelled plants. The Vakhsh river cascade, which includes the Nurek dam, produces about 95% of the country’s hydroelectricity, and the 3,780 MW Rogun hydropower plant is under construction upstream of Nurek, with completion now expected in 2033.
The sector was historically run by one state holding company, Barqi Tojik. Under Government Decree No. 330 of 22 June 2019 it was unbundled into three state-owned companies: Barqi Tojik, which keeps generation and the market-operator function; Shabakahoi Intiqoli Barq (SIB), the national transmission company; and Shabakahoi Taqsimoti Barq (STB), the national distribution company. Policy is set by the Ministry of Energy and Water Resources, and tariffs are reviewed by a tariff unit within the Antimonopoly Service. In the Gorno-Badakhshan Autonomous Region (GBAO), the private Pamir Energy Company generates and supplies electricity under a 25-year concession that expires in 2027.
Electricity is cheap but the sector is financially weak. Households pay a single regulated tariff of 0.4137 somoni per kWh including VAT from 1 January 2026. The World Bank estimated in April 2024 that end-user tariffs covered about 60% of the costs of the three state companies, and the government has committed to cost-recovery tariffs by 2027. Winter shortages are a recurring problem because river flows fall just as heating demand peaks.
Energy snapshot.
Headline figures for electricity in Tajikistan. Each shows its data year and links to its source.
- Population10,786,734 peopleSource 12025
- HouseholdsNot identified from a reliable public source.
- Average household sizeNot identified from a reliable public source.
- Electricity use per householdNot identified from a reliable public source.
- Household price (TJS)0.414 TJS/kWhSource 3From 1 January 2026
- Household price (EUR)0.04 EUR/kWhSource 6From 1 January 2026
- Renewable electricity share92.5 % of generationSource 22024
- Solar capacityNot identified from a reliable public source.
- Wind capacityNot identified from a reliable public source.
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Single buyer
- Homes can export to the grid
- No
- Home equipment in grid services
- No
- Regulator
- Ministry of Energy and Water Resources (policy); tariff unit of the Antimonopoly Service (tariff review). No independent energy regulator yet.
- System operator
- Shabakahoi Intiqoli Barq (SIB) OJSC — state transmission company; Barqi Tojik retains a market-operator directorate
- Distribution networks
- One national state distribution company, Shabakahoi Taqsimoti Barq (STB); Pamir Energy serves GBAO under a concession
- Currency
- Tajikistani somoni (TJS)
- Voltage and frequency
- Not verified from an official source
Electricity prices in Tajikistan.
- Household price (TJS)
- 0.414 TJS/kWh (From 1 January 2026)Source 3Single household tariff including VAT, applicable nationwide (tariffs announced 29 December 2025). No seasonal or block structure is shown. GBAO, served by Pamir Energy, may differ.
- Household price (EUR)
- 0.04 EUR/kWh (From 1 January 2026)Source 6Converted from 0.4137 TJS/kWh at the National Bank of Tajikistan official rate of TJS 10.3582 per euro (rate dated 12 October 2026, published on the NBT website when accessed on 10 October 2026).
- Typical annual electricity bill
- Not identified from a reliable public source.
Retail electricity prices in Tajikistan are set by the government rather than by a market. The tariff unit of the Antimonopoly Service reviews tariffs and makes recommendations, using a Tariff Methodology for the Electric Energy Sector approved by government decree on 22 June 2019. The current schedule, published by Barqi Tojik and in force from 1 January 2026, applies to consumers throughout the republic and includes VAT.
At 0.4137 somoni per kWh — about €0.04 at the National Bank’s October 2026 rate — household electricity is inexpensive by international standards. Industry pays more than twice as much per kWh. The aluminium smelter TALCO, historically the largest single consumer, has its own tariff: the World Bank reports that it rose by 50% in January 2023 and a further 16% in January 2024, to an average of about US 1.7 cents per kWh.
Tariff reform
Tariffs have been rising steadily under a World Bank-supported recovery programme. End-user tariffs more than doubled after 2017, and weighted average tariffs rose by 64% between 2020 and late 2024; the most recent increase reported by the World Bank, 16% across all customer categories, took effect on 1 January 2024. Even so, the World Bank estimated that tariffs covered about 60% of the sector’s costs in April 2024 (20% in 2018). The government has committed to reach full cost recovery by 2027.
Losses and collection
The World Bank put average losses at about 23% in 2024 and reports transmission and distribution losses of 16.2% of output for 2024 in its development indicators. Its 2020 technical assessment found a bill collection rate of 84% for 2018 and commercial losses of around 8%.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | A single national household rate of 0.4137 TJS/kWh including VAT from 1 January 2026. The same rate applies to budget-funded institutions; industrial enterprises pay 0.9465 TJS/kWh and water-supply companies 0.1967 TJS/kWh. |
| Time-of-use | No | No time-of-use, seasonal or dynamic household tariff is shown in the published tariff schedule. |
Household prices compared with neighbouring countries (EUR per kWh).
- Pakistan€0.106
- Kazakhstan€0.076
- China€0.065
- Uzbekistan€0.049
- Tajikistan€0.04
- Afghanistan€0.034
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- Not identified from a reliable public source.
- Average daily use per household
- Not identified from a reliable public source.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 1,558.9 kWh/person/yr (all sectors) (2024)Source 1
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- Not identified from a reliable public source.
According to the World Bank, 99.9% of the population had access to electricity in 2024, and average electricity consumption was about 1,559 kWh per person across all sectors. Domestic demand reached 14,420 GWh in 2020, having grown by an average of 2.9% a year between 2014 and 2020.
Demand peaks in winter, just as hydropower output falls with low river flows. The World Bank describes electricity shortages as increasingly recurrent and expects Rogun to help meet winter peak demand.
Heavy industry is a smaller share of demand than in the past. TALCO used about 12% of total electricity in 2023 — 1.7 billion kWh, down from 5.5–6.3 billion kWh a year in 2009–13.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- Not identified from a reliable public source.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- Not identified from a reliable public source.
- Apartments and flats
- Not identified from a reliable public source.
- Urban population
- 26.2 % of population (2025)Source 1World Bank estimate.
Tajikistan is mainly rural: the World Bank estimates that only about 26% of people live in towns. The 2020 Population and Housing Census (reference date 1 October 2020) includes volumes on household size and on housing type and tenure, but these are published as PDF tables that could not be read for this profile, so housing figures are left blank.
How the grid works in Tajikistan.
- TransmissionShabakahoi Intiqoli Barq (SIB) OJSC, Barqi Tojik OJSHC — market operator directorate
- DistributionOne national state distribution company, Shabakahoi Taqsimoti Barq (STB); Pamir Energy serves GBAO under a concession
- MeteringNot identified from a reliable public source.
- Supply2 or more retail suppliers
Physical flow
Barqi Tojik reports total installed capacity of about 6 GW, and a 2021 World Bank document gives 6,058 MW, 88% of it hydropower. The 3,000 MW-class Nurek plant on the Vakhsh produced about half of annual energy, and Barqi Tojik lists Nurek at 3,160 MW. Other major hydropower plants include Sangtuda-1 and Sangtuda-2, commissioned in 2006 and 2011, and Rogun, which is being built in stages to 3,780 MW. Barqi Tojik also operates thermal plants, including Dushanbe-2 and Yovon.
Because generation depends on river flow, the system has a summer surplus and a winter deficit. Tajikistan has completed resynchronisation with the Central Asian Power System (CAPS), allowing exports to Uzbekistan and Kazakhstan, and the CASA-1000 project is designed to carry summer exports to Pakistan via Afghanistan.
Commercial flow
Barqi Tojik generates and buys electricity from other generators, including the Sangtuda plants and Rogun OJSC, and the power is delivered through SIB’s transmission network and STB’s distribution network to customers at regulated tariffs. Inter-company debts are large: the World Bank reports that Barqi Tojik owed more than US$500 million to the Sangtuda plants and more than US$60 million to Rogun OJSC at the end of 2023. There is no wholesale market or retail competition.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry of Energy and Water Resources (MEWR) | Sets energy and water policy and oversees the state power companies, including Barqi Tojik, SIB and STB, and the reform programme. |
| Regulator | Antimonopoly Service — electricity tariff unit | Reviews tariffs and recommends them to the government under the 2019 Tariff Methodology. The World Bank notes it still needs support to become a fully independent regulator. |
| TSO | Shabakahoi Intiqoli Barq (SIB) OJSC | National transmission company created through the 2019 unbundling. Its projects include CASA-1000, a 500 kV line in Sughd and an automated metering system (ASKUE). |
| System operator | Barqi Tojik OJSHC — market operator directorate | Barqi Tojik remains the main generator, operating hydropower plants including Nurek and Kairakkum and the Dushanbe-2 and Yovon thermal plants, and keeps a market-operator directorate. It buys power from other generators such as Sangtuda-1 (2,384 GWh reported by the World Bank in April 2024). |
| DSO | Shabakahoi Taqsimoti Barq (STB) OJSC | National distribution company created through the 2019 unbundling, covering the whole country outside GBAO. |
| DSO | Pamir Energy Company | Private company that generates and supplies electricity in GBAO under a 25-year concession agreement expiring in 2027. |
Compared with the UK system.
| UK concept | Tajikistan equivalent | How it works |
|---|---|---|
| DNO | Shabakahoi Taqsimoti Barq (STB); Pamir Energy in GBAO | A single state company operates the distribution network across most of the country. In GBAO, Pamir Energy runs both generation and the local network under a concession. |
| National Grid/NESO | Shabakahoi Intiqoli Barq (SIB) | SIB owns and operates the high-voltage transmission network, including links to the Central Asian Power System, which Tajikistan has resynchronised with to export to Uzbekistan and Kazakhstan. |
| MPAN | Customer account with the distribution company | A connection is identified by the customer’s account and meter with the distribution company. No public specification of a standardised national supply-point number was identified. |
| MPRN | No equivalent identified | No gas supply-point register for households was identified in the sources consulted. |
| Meter operator | STB (and Pamir Energy in GBAO) | Meters are installed and read by the network company; there is no separate metering market. Meter reading and billing data transfer were carried out manually in the cities assessed by the World Bank in 2020. |
| Supplier | No retail competition | Households cannot choose a supplier. Everyone pays the nationally set tariff published by Barqi Tojik. |
| Smart-meter infrastructure | Donor-funded AMI and billing projects | No national data hub. Smart meters with two-way communication and automated billing were introduced in selected cities under the World Bank programme. |
How a supply point is identified.
| Question | Answer |
|---|---|
| What is it called? | Distribution company customer account and meter number |
| Who issues it? | Shabakahoi Taqsimoti Barq (STB), or Pamir Energy in GBAO, when a connection is made |
| Format | Not published. Neither STB nor Barqi Tojik documents the structure of customer account or meter numbers on pages that could be read. |
| Length | Not verified |
| Stays with the property when you switch supplier? | Not identified from a reliable public source. |
| Where to find it | On the electricity bill and on the meter. |
| Electronic access | Not verified — STB’s website did not return readable content when this profile was prepared. |
| Third-party access | No framework for third-party access to metering or customer data was identified. |
| Who keeps the register | STB’s customer and billing records (Pamir Energy in GBAO) |
| Register scope | Per DSO |
A household connection in Tajikistan is identified by the account the distribution company opens and the meter it installs. Because STB is the only distribution company outside GBAO, its customer and billing database is in practice the register of supply points for most of the country; Pamir Energy holds the equivalent records in GBAO. There is no independent data hub and no supplier switching, so no separate national supply-point number is needed.
The World Bank’s 2020 technical assessment of three cities in Sughd — Istaravshan (39,502 residential customers), Isfara (40,469 residential customers) and Konibodom (45,301) — found that around 90% of meters in Istaravshan were indoors, and that meter reading and data transfer for billing were done manually. The programme it supports introduces smart meters with two-way communication and automated billing, first in those cities and later in eight large cities accounting for about half of electricity consumption.
The structure and length of account and meter numbers are not published, so no example is shown here. Whether an account stays with a property when the occupant changes is not documented in the sources consulted.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Unknown |
| Net metering | Unknown |
| Net billing | Unknown |
| How exported electricity is paid | Not identified. No published net-metering, net-billing or feed-in arrangement for household systems was found in accessible sources. |
| Can households sell solar power to the grid? | No household export or net-metering scheme was identified. Tajikistan has a Law on the Use of Renewable Energy Sources, but its text (PDF) could not be read for this profile. |
| How do larger solar projects sell power? | Through power purchase agreements with the state sector. The World Bank’s 2021 Sughd solar concept notes that the 2012 Public–Private Partnership Law (No. 907) was virtually untested by the market. |
Connecting a home system.
- No published procedure for connecting a household solar system and exporting to the grid was identified; contact STB (or Pamir Energy in GBAO) and the Ministry of Energy and Water Resources.
Accessible official sources do not describe any scheme allowing households to export surplus solar electricity or be paid for it. With household tariffs of about €0.04 per kWh, the financial case for grid-tied rooftop solar is limited. The Ministry of Energy and Water Resources notes more than 200 days a year of strong sunshine, and a World Bank document cites 2,100–3,000 hours of sunshine a year and a solar potential of about 25 billion kWh a year.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity for sale (IPP) | Contracted with the state sector; legal basis includes the Law on Energy, the Law on the Use of Renewable Energy Sources and the 2012 PPP Law (No. 907); thresholds not verified | Ministry of Energy and Water Resources; Government | Sangtuda-1 and Sangtuda-2 sell to Barqi Tojik; a 200 MW private solar plant in Sughd was prepared with World Bank support. |
| Generate for own use (rooftop solar) | No published threshold or exemption identified | Ministry of Energy and Water Resources; STB | Not addressed in the sources consulted. |
| Export / sell surplus to the grid | No household export regime identified | STB; Barqi Tojik | No net-metering or feed-in tariff found. |
| Transmit electricity | Carried out by state-owned SIB | Government (Decree No. 330 of 22 June 2019) | No other transmission operators. |
| Distribute and supply to end customers | State-owned STB nationally; Pamir Energy in GBAO under a concession expiring in 2027 | Government; Ministry of Energy and Water Resources | No retail competition; tariffs set by the government. |
| Wholesale purchase and dispatch | Barqi Tojik market-operator directorate | Ministry of Energy and Water Resources | No organised wholesale market. |
| Store electricity | No specific storage licensing regime identified | — | Not addressed in the sources consulted. |
| Aggregate, trade, balancing, grid services, VPP, remote control of assets | No regime identified | — | There is no organised wholesale or flexibility market in which these activities exist. |
The legal framework consists of the Law on Energy, the Law on the Use of Renewable Energy Sources and the Law on Energy Saving and Energy Efficiency, all listed by the Ministry of Energy and Water Resources, together with the 2012 Public–Private Partnership Law. The texts are published as PDFs that could not be read for this profile, so activity thresholds and exemptions are not stated.
The main structural change has been the unbundling of Barqi Tojik under Decree No. 330 of 22 June 2019 into generation (Barqi Tojik), transmission (SIB) and distribution (STB) companies, followed by a reorganisation of Barqi Tojik under Decree No. 18 of 18 January 2023. Building an independent regulator from the Antimonopoly Service’s tariff unit is still in progress.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Energy, balancing and ancillary services | No | — | No | Barqi Tojik / SIB. The state companies balance the system mainly with the large hydropower reservoirs. No market for distributed resources, demand response or aggregation was identified. |
Tajikistan has no domestic wholesale or flexibility market. Its main flexibility resource is reservoir hydropower: the World Bank expects Rogun to provide reserve and balancing services that help neighbouring countries integrate solar and wind. Cross-border trade runs under long-term agreements with Uzbekistan and Kazakhstan through the Central Asian Power System; SIB also lists a project on REMIT (regional market transparency).
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | Project-based: smart meters and automated billing in selected cities under the World Bank Power Utility Financial Recovery programme |
| Reading interval | Not published |
| Meter ownership | Distribution company (STB) |
| First AMI cities | Istaravshan, Isfara and Konibodom (Sughd), about 8% of consumption |
| Extension | Billing systems and meters for eight large cities, about 50% of consumption (2022 additional financing) |
| Transmission metering | SIB automated metering project (ASKUE) |
Smart metering in Tajikistan is driven by loss reduction. The World Bank programme for the power utility, approved in 2020, introduces advanced metering infrastructure — smart meters with two-way remote communication — and automated billing in three Sughd cities, replacing manual meter reading. Additional financing in 2022 extended the work to billing systems and meters for eight large cities accounting for about half of electricity consumption.
No national figure for smart-meter coverage and no data-access rules for consumers or third parties were identified.
Renewable electricity.
Electricity generation mix (2024).
- Hydropower: 92.5%
- Fossil fuels (oil, gas, coal): 7.5%
- Renewable electricity share
- 92.5 % of generation (2024)Source 2World Bank share of electricity produced from hydroelectric sources; the remaining 7.46% is from oil, gas and coal. Tajikistan is a net exporter in summer, so generation share is used.
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- Not identified from a reliable public source.
- Total installed (all sources)
- 6,058 MW (2021)Source 1388% hydropower. Barqi Tojik describes total installed capacity as about 6 GW.
- Nurek hydropower plant
- 3,160 MWSource 4Capacity given by Barqi Tojik; the World Bank refers to it as the 3,000 MW Nurek HPP producing about half of annual generation.
- Rogun hydropower plant (planned total)
- 3,780 MWSource 8Under construction; completion expected in 2033 and full reservoir impoundment not before 2039.
Targets.
- National Development Strategy: diversify power generation with 10% from non-hydro renewables, and about 1,000 MW of new solar PV capacity by 2035 (as cited by the World Bank, 2021).
- Rogun hydropower plant: 3,780 MW when complete (expected 2033).
Tajikistan’s electricity is already overwhelmingly renewable because of hydropower: 92.5% of generation in 2024 according to the World Bank. The Ministry of Energy and Water Resources puts economically usable hydropower potential at 527 billion kWh a year and says the country ranks eighth in the world for hydropower potential.
The policy challenge is seasonal. Hydropower plants lose generating capability in winter, which is why the National Development Strategy calls for diversification into solar, with about 1,000 MW of new solar PV needed by 2035. Rogun’s large reservoir is intended to shift water, and so generation, from summer into winter.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
Energy storage in Tajikistan means hydropower reservoirs, chiefly Nurek and, in future, Rogun. No official statistics or rules for battery storage were identified.
Storage projects.
- Rogun hydropower plant: Large reservoir hydropower project (3,780 MW planned) providing seasonal water storage and balancing services; World Bank financing approved in December 2024.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Shabakahoi Taqsimoti Barq (STB) | National distribution company outside GBAO | No | No | No | No |
| Pamir Energy Company | Sole supplier in GBAO (concession to 2027) | No | No | No | No |
There is no retail competition. Outside GBAO, households are served by the state distribution company STB at the nationally set tariff; in GBAO, Pamir Energy generates and supplies electricity under a 25-year concession agreement that expires in 2027.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Ministry of Energy and Water Resources | Government | Energy and water policy | Oversees the state power companies and publishes the main energy laws. |
| Antimonopoly Service — electricity tariff unit | Regulator | Tariff review | Reviews and recommends electricity tariffs under the 2019 Tariff Methodology. |
| Barqi Tojik OJSHC | Market | Main generator and market operator | Operates most power plants and publishes the national tariff schedule. |
| Shabakahoi Intiqoli Barq (SIB) | Transmission | National transmission company | Operates the high-voltage grid and cross-border links, including CASA-1000. |
| Shabakahoi Taqsimoti Barq (STB) | Distribution | National distribution company | Connects and meters households outside GBAO. |
| Agency on Statistics under the President of the Republic of Tajikistan | Government | National statistics office | Publishes population, census and electricity output statistics. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Sector law | Law on Energy; Law on the Use of Renewable Energy Sources; Law on Energy Saving and Energy Efficiency | Republic of Tajikistan | Listed by the Ministry of Energy and Water Resources; texts are PDF. |
| Tariff setting | Tariff Methodology for the Electric Energy Sector (government decree, 22 June 2019) | Government of Tajikistan | Applied by the Antimonopoly Service’s tariff unit. |
| Grid connection (inverter / interconnection technical rules) | No published grid code for small generators identified | — | Not found in accessible official sources. |
| Installer accreditation | No national scheme identified | — | No certification scheme for solar installers was verified. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Distribution company connection | Yes | National | Grid connections are made by STB (or Pamir Energy in GBAO). The procedure for small generators was not verified. |
| Authorisation for generation | Limited | National | Generation is governed by the Law on Energy and the Law on the Use of Renewable Energy Sources; thresholds for small systems were not verified. |
Accessible sources do not set out a permitting route specific to rooftop solar or home batteries. Anyone planning a grid-connected installation should confirm the requirements with STB (or Pamir Energy in GBAO) and the Ministry of Energy and Water Resources.
Data and connectivity.
- Fixed broadband
- 55.8 % of population using the internet (2024)Source 1
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
About 56% of the population used the internet in 2024 (World Bank). The communication technology used by the smart meters installed under the World Bank programme has not been published.
Grid conditions.
- National peak demand
- Not identified from a reliable public source.
- Annual electricity demand
- 14.4 TWh (2020)Source 13Total domestic demand of 14,420 GWh, as given by the World Bank.
- Generation capacity
- 6.058 GW (2021)Source 1388% hydropower. Barqi Tojik gives about 6 GW.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
The grid is dominated by the Vakhsh cascade in the south, which produces about 95% of hydroelectricity. SIB’s projects include a 500 kV line in Sughd and the CASA-1000 export line.
Reliability has been improving under the World Bank programme: equipment failures in transmission and distribution networks fell from 2,417 in 2018 to about 1,900 by April 2024, against a target of 1,400 by 2032. Winter supply remains the main constraint.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Cost-recovery tariffs | Upcoming | 2027 | The government has committed to reach full cost recovery in electricity tariffs by 2027, continuing the increases of recent years (the latest schedule took effect on 1 January 2026). |
| Pamir Energy concession expiry | Upcoming | 2027 | The 25-year concession under which Pamir Energy supplies GBAO expires in 2027; arrangements after expiry were not verified. |
| Rogun hydropower plant | Upcoming | Completion expected 2033 | 3,780 MW plant financed in part by a World Bank programme approved in December 2024; expected to ease winter shortages and support exports. |
| Independent regulator | Upcoming | Not scheduled | The tariff unit of the Antimonopoly Service has been established but, according to the World Bank, still needs support to become an independent regulator. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Low | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | — | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | High | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Low | No official residential solar statistics, no household export or net-metering scheme identified, and household tariffs of about €0.04/kWh. |
| Distributed energy market | Low | State companies dominate generation, transmission and distribution; no published framework for small distributed generation was found. |
| Grid flexibility market | Low | No wholesale or flexibility market; balancing is done by state companies with reservoir hydropower. |
| Energy storage adoption | Low | No official statistics or regulatory framework for battery storage identified. |
| Renewable growth environment | Medium | Rogun (3,780 MW planned) is under construction, and the National Development Strategy calls for about 1,000 MW of new solar PV by 2035; no official data on solar additions were found. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 16 sources
- World Development Indicators: population, urban population, access to electricity, internet users, electric power consumption — Tajikistan. World Bank, 2025. accessed 10 October 2026.
- World Development Indicators: electricity from hydroelectric and fossil sources, T&D losses — Tajikistan. World Bank, 2024. accessed 10 October 2026.
- Тарифҳо (electricity tariffs from 1 January 2026). Barqi Tojik OJSHC, 2026. accessed 10 October 2026.
- Barqi Tojik — company overview. Barqi Tojik OJSHC. accessed 10 October 2026.
- Barqi Tojik — history (unbundling decrees). Barqi Tojik OJSHC. accessed 10 October 2026.
- Official exchange rate of foreign currencies against the somoni. National Bank of Tajikistan, 2026. accessed 10 October 2026.
- Agency on Statistics — resident population on 1 January 2026. Agency on Statistics under the President of the Republic of Tajikistan, 2026. accessed 10 October 2026.
- Tajikistan — Sustainable Financing for Rogun Hydropower Project (P181029): Project Appraisal Document. World Bank, 2024. accessed 10 October 2026.
- Disclosable Restructuring Paper — Program for the Recovery of the Electricity Sector in Tajikistan (P168211). World Bank, 2024. accessed 10 October 2026.
- Implementation Status and Results Report, Sequence 07 — Tajikistan Power Utility Financial Recovery (P168211). World Bank, 2024. accessed 10 October 2026.
- Tajikistan — Power Utility Financial Recovery Program-for-Results: Additional Financing (Program Paper). World Bank, 2022. accessed 10 October 2026.
- Final Technical Assessment — Tajikistan Power Utility Financial Recovery (P168211). World Bank, 2020. accessed 10 October 2026.
- Concept Project Information Document — Sughd Private Solar Power Project (P176602). World Bank, 2021. accessed 10 October 2026.
- Energy resources of Tajikistan. Ministry of Energy and Water Resources. accessed 10 October 2026.
- Legislation. Ministry of Energy and Water Resources. accessed 10 October 2026.
- Population and Housing Census 2020. Agency on Statistics under the President of the Republic of Tajikistan, 2020. accessed 10 October 2026.
Questions about energy in Tajikistan.
From 1 January 2026, households pay a single national tariff of 0.4137 somoni per kWh including VAT — about €0.04 per kWh. Industrial enterprises pay 0.9465 somoni per kWh.
Almost entirely from hydropower: 92.5% of generation in 2024 according to the World Bank, mostly from the Vakhsh river cascade including the Nurek dam. The rest comes from fossil-fuelled plants.
The state distribution company Shabakahoi Taqsimoti Barq (STB) serves customers across most of the country, with power generated mainly by Barqi Tojik and carried by the transmission company SIB. In Gorno-Badakhshan, Pamir Energy supplies electricity under a concession.
Policy is set by the Ministry of Energy and Water Resources. Tariffs are reviewed by a tariff unit within the Antimonopoly Service and approved by the government; an independent regulator has not yet been fully established.
There is no published national supply-point number. A connection is identified by the customer account and meter with the distribution company — STB, or Pamir Energy in GBAO.
No household net-metering or feed-in scheme was identified. Tajikistan has a Law on the Use of Renewable Energy Sources, but rules for small rooftop systems were not found; check with STB and the Ministry of Energy and Water Resources.
A hydropower plant under construction on the Vakhsh river, planned at 3,780 MW. The World Bank expects completion in 2033; it is intended to ease winter shortages and increase exports.