How electricity works in Saint Martin.
Saint-Martin electricity 2026: isolated French island grid run by EDF, energy powers held by the Collectivité since 2012, local energy code, PPE still pending.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Euro (EUR) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Saint Martin energy at a glance.
Key figures for households in Saint Martin. Each one links to its source on the full overview below.
Selling back to the grid.
Can homes export electricity? Limited. Details are in the export section below.
Four things to check in Saint Martin.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Saint Martin below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Saint Martin requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Saint Martin.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Saint Martin, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Saint Martin, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Saint Martin.
The energy market in Saint Martin, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 10 October 2026.
On this page22 sections
The Collectivité de Saint-Martin is the French part of the island of Saint-Martin/Sint Maarten in the northern Lesser Antilles. It left Guadeloupe and became a separate overseas collectivity under an organic law of February 2007; its first Territorial Council president was elected on 15 July 2007. The Dutch side, Sint Maarten, is a separate country within the Kingdom of the Netherlands with its own utility, and this profile does not cover it.
French energy law classes Saint-Martin as a “zone non interconnectée” (ZNI): its grid has no link to mainland France, so electricity is produced on the island. EDF, through its island systems division (EDF SEI, which runs Saint-Martin from its Guadeloupe organisation, EDF Archipel Guadeloupe), produces, transports, distributes and supplies electricity, and the Commission de régulation de l’énergie (CRE) regulates the public-service costs this involves.
What sets Saint-Martin apart from Guadeloupe or Martinique is that energy has been a competence of the Collectivité since 2012. The Territorial Council has adopted its own Code de l’énergie, which the Collectivité describes as mandatory for keeping national price equalisation (péréquation tarifaire). Several national schemes therefore do not apply as they do elsewhere: Saint-Martin is outside the national solar feed-in order of January 2024, and its public-service charges are excluded from the excise-based funding mechanism used for the other ZNI since August 2025. Its multi-year energy plan (PPE) was still being drawn up in 2026, and the island has faced a generation shortfall since September 2024.
Energy snapshot.
Headline figures for electricity in Saint Martin. Each shows its data year and links to its source.
- PopulationNot identified from a reliable public source.
- HouseholdsNot identified from a reliable public source.
- Average household sizeNot identified from a reliable public source.
- Electricity use per householdNot identified from a reliable public source.
- Household price (EUR)Not identified from a reliable public source.
- Renewable electricity shareNot identified from a reliable public source.
- Solar capacityNot identified from a reliable public source.
- Wind capacityNot identified from a reliable public source.
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Vertically integrated
- Homes can export to the grid
- Limited
- Home equipment in grid services
- No
- Regulator
- Commission de régulation de l’énergie (CRE), alongside the Collectivité de Saint-Martin, which holds energy competence
- System operator
- EDF SEI (EDF Archipel Guadeloupe), which runs and balances the island’s isolated system
- Distribution networks
- Single network operator: EDF SEI runs the whole distribution network on the French side; there is no interconnection with the Dutch side’s utility system recorded in official French sources.
- Currency
- Euro (EUR)
- Voltage and frequency
- 230 V / 50 Hz
Electricity prices in Saint Martin.
- Household price (EUR)
- Not identified from a reliable public source.
- Typical annual electricity bill
- Not identified from a reliable public source.
Electricity in Saint-Martin is sold by EDF under the French system of price equalisation. The CRE explains that consumers in the ZNI pay an electricity bill, before taxes, at the same level as in mainland France, and that the structural extra costs between production costs and tariff revenue are compensated to the historic supplier as public-service charges (charges de service public de l’énergie, SPE). Across all ZNI, production cost an average of €369/MWh in 2025, up from €362/MWh in 2024.
Saint-Martin’s different funding and tax position
Since August 2025, under article 7 of the 2025 Finance Act, SPE charges in the ZNI have been compensated from a surcharge on excise duty. The CRE states explicitly that this applies to all ZNI except Saint-Martin and Saint-Barthélemy. Saint-Martin also levies its own taxes under its own tax code (Code général des impôts de Saint-Martin), so the tax lines on a Saint-Martin bill are not the same as in Guadeloupe or the mainland. The exact tax-inclusive kWh price could not be confirmed from an accessible source.
Why the local energy code matters for prices
Because energy is a competence of the Collectivité, national equalisation does not apply automatically. The Collectivité presents its Code de l’énergie as a mandatory document for keeping péréquation, and the June 2025 joint statement by the Collectivité, the State and EDF tied the maintenance of equalisation to the signature of the territory’s PPE.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | Households are supplied by EDF at the regulated tariff. Under national price equalisation the pre-tax bill level is the same as in mainland France (CRE). The Collectivité states that its local energy code is required to keep this equalisation in place. Current Saint-Martin unit prices could not be verified. |
| Off-peak | Unknown | EDF offers a peak/off-peak option in the overseas regions; whether and on what hours it applies in Saint-Martin could not be confirmed from an accessible Saint-Martin page. |
| Dynamic | No | EDF is the only supplier and no market-indexed offer exists in a ZNI without a wholesale market. |
| Fixed | No | There are no competing suppliers offering fixed-price contracts; the regulated tariff applies. |
Household prices compared with neighbouring countries (EUR per kWh).
- Saint Kitts and Nevis€0.513
- France€0.2
- Martinique€0.19
- Guadeloupe€0.189
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- Not identified from a reliable public source.
- Average daily use per household
- Not identified from a reliable public source.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- Not identified from a reliable public source.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- Not identified from a reliable public source.
Official consumption statistics for Saint-Martin are sparse. The most recent official statement found is from the joint EDF–State–Collectivité press conference of 13 June 2025, which reported that electricity consumption had risen by 7% over the preceding months, at a time when production capacity was reduced by engine failures.
Demand is shaped by a hot climate all year, a large tourism and hospitality sector and air-conditioning. EDF’s Agir Plus programme, cited by the Collectivité in 2025, encourages households and businesses to switch to less energy-intensive equipment. Saint-Martin was included in the CRE’s territorial compensation frameworks for small demand-reduction (MDE) actions for 2019–2024 and in the renewed frameworks adopted by the CRE in December 2024.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- Not identified from a reliable public source.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- Not identified from a reliable public source.
- Apartments and flats
- Not identified from a reliable public source.
- Urban population
- Not identified from a reliable public source.
Census housing data for Saint-Martin is produced by INSEE but could not be read from the pages available for this profile, so no tenure or dwelling-type figures are given.
Building and planning rules are set locally. The Collectivité applies its own Code de l’urbanisme (updated in December 2025) and a local planning document, the PADSM. Changes to a façade or roof that alter a building’s external appearance require a prior declaration (déclaration préalable), decided within one month of a complete application, or two months in a protected area.
How the grid works in Saint Martin.
- TransmissionEDF SEI – EDF Archipel Guadeloupe
- DistributionSingle network operator: EDF SEI runs the whole distribution network on the French side; there is no interconnection with the Dutch side’s utility system recorded in official French sources.
- MeteringEDF SEI
- Supply1 or more retail suppliers
Saint-Martin’s grid is small and isolated. The CRE lists the territory among the overseas collectivities that form part of France’s non-interconnected zones, alongside Saint-Barthélemy, Saint-Pierre-et-Miquelon and Wallis and Futuna. No interconnection with the Dutch side of the island is recorded in the French official sources consulted.
Generation is mainly from diesel-type engines grouped in units (“tranches”). In June 2025 the Collectivité, the State and EDF reported that the territory had faced an electricity production crisis since September 2024, caused by the failure of an engine in unit 1 and weakened engines in unit 2, at the same time as consumption was rising. Mobile generators were brought in as an interim measure. The parties said that a new power plant, with a strong renewable component, depended on the signature of the PPE, which was blocked at State level at the time.
Commercially, the chain is short: EDF produces or buys electricity, runs the network and supplies every customer at the regulated tariff, and the CRE assesses the extra costs that are compensated as public-service charges.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Collectivité de Saint-Martin (with the State for the PPE) | Holds energy competence since 2012 and has adopted a local Code de l’énergie. Under a 2021 framework convention it is drawing up the multi-year energy plan (PPE) jointly with the State. |
| Regulator | Commission de régulation de l’énergie (CRE) | Calculates the public-service charges that compensate EDF for the extra cost of island supply and runs the territorial demand-reduction (MDE) frameworks, which include Saint-Martin. |
| System operator | EDF SEI – EDF Archipel Guadeloupe | Balances generation and demand on the isolated island grid. During the 2024–2025 shortfall it deployed mobile generators alongside the island’s engine-based plant. |
| DSO | EDF SEI | The CRE describes EDF SEI as producer, network operator and supplier in the ZNI it serves. In Saint-Martin it operates the whole network on the French side. |
| Supplier | EDF (sole supplier) | Supplies all customers as the historic supplier and is compensated for the gap between costs and tariff revenue. |
| Metering | EDF SEI | Meters belong to the network operator’s activity; there is no separate meter operator. Saint-Martin-specific meter information could not be accessed. |
Compared with the UK system.
| UK concept | Saint Martin equivalent | How it works |
|---|---|---|
| DNO | EDF SEI (network operator for the French side) | One operator runs all distribution on the French side of the island. It is part of EDF’s island systems division, organised from Guadeloupe. Enedis, the mainland distribution operator, does not operate here. |
| National Grid/NESO | EDF SEI as system operator | The same company dispatches the island’s generation and keeps the system in balance. There is no independent system operator, balancing market or capacity market, and no link to mainland France. |
| MPAN | Delivery point reference held by EDF (not confirmed for Saint-Martin) | Each connection is identified by EDF as a delivery point on the customer’s bill and in EDF’s systems. The exact format used in Saint-Martin could not be confirmed from an accessible page; see the supply-point section. |
| MPRN | No equivalent identified | No mains gas network was identified on the official pages consulted, so there is no gas supply-point identifier. |
| Meter operator | EDF SEI | The network operator owns and maintains meters; customers do not choose a meter operator. |
| Supplier | EDF (regulated supply only) | Households cannot switch supplier. EDF supplies everyone as the historic operator of a small isolated system. |
| Smart-meter infrastructure | EDF’s own systems (not documented for Saint-Martin) | There is no central data company like the DCC. Any remote reading is handled inside EDF’s own systems; the extent of smart-meter roll-out in Saint-Martin was not found in an accessible source. |
How a supply point is identified.
30081749562013 (fictional, French 14-digit PRM format)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Delivery point (point de livraison) reference on the EDF contract (PDL / PRM (format not confirmed for Saint-Martin)) |
| Who issues it? | EDF SEI, as network operator, when a connection is created |
| Format | In the French system a delivery point is identified by a 14-digit Point de Référence Mesure (PRM). Whether EDF uses the same 14-digit number on Saint-Martin bills, or a separate local reference, could not be confirmed from an accessible Saint-Martin source. |
| Length | Not confirmed (14 digits in the French PRM format) |
| Stays with the property when you switch supplier? | Not identified from a reliable public source. |
| Where to find it | On the EDF bill and contract. Saint-Martin-specific guidance could not be accessed. |
| Electronic access | EDF provides online customer accounts in its island territories; the Saint-Martin service could not be verified. |
| Third-party access | No third-party consumer data platform was identified. EDF’s open-data portals cover Corsica, Guadeloupe, French Guiana, Martinique, Réunion, the Ponant islands and Saint-Pierre-et-Miquelon, but not Saint-Martin. |
| Who keeps the register | EDF SEI’s own customer and network systems; there is no independent national data hub in the ZNI. |
| Register scope | Regional |
Because one company is network operator, system operator and sole supplier, the delivery-point reference in Saint-Martin is not used for switching supplier, as it would be in a competitive market. It identifies the connection for EDF’s own purposes: connection works, meter interventions, billing and social schemes.
In mainland France and the overseas regions, each delivery point carries a 14-digit PRM that stays with the connection when occupants change. EDF SEI’s Saint-Martin documentation could not be accessed for this profile, so the format and practice are not confirmed here; customers should use the reference printed on their EDF bill.
Moving home or a new connection
A new occupant opens a contract with EDF. A new building needs planning consent from the Collectivité under its Code de l’urbanisme before it can be connected. The detailed connection procedure for Saint-Martin was not available on an accessible official page.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Unknown |
| Net metering | Unknown |
| Net billing | Unknown |
| How exported electricity is paid | Not confirmed. The national rooftop-solar purchase order of 5 January 2024 (S24 PV ZNI) does not list Saint-Martin among the territories it covers, and no local purchase tariff could be verified. |
| Does the national solar feed-in tariff apply? | No. Article 1 of the order of 5 January 2024 covers Corsica, Guadeloupe, French Guiana, Martinique, Mayotte, Réunion, Wallis and Futuna, Saint-Pierre-et-Miquelon and certain Ponant islands. Saint-Martin and Saint-Barthélemy are not listed. |
| Who sets the rules for solar in Saint-Martin? | Energy has been a competence of the Collectivité since 2012, and the Territorial Council has adopted a local Code de l’énergie. The published version is a scanned document that could not be read for this profile, so its export provisions are not summarised here. |
| Can grid-scale solar or storage win national ZNI support? | No Saint-Martin projects were identified in the CRE’s ZNI storage windows. Larger renewable capacity is expected to follow from the PPE, which was still being drawn up in 2026. |
Connecting a home system.
- Check planning requirements with the Collectivité: roof changes that alter a building’s external appearance need a déclaration préalable.
- Contact EDF (EDF Archipel Guadeloupe, Saint-Martin) before installing any grid-connected system; the network operator must approve any connection to its network.
- Confirm with the Collectivité’s environment department whether its Code de l’énergie provides a purchase or self-consumption scheme for the planned installation.
Rules for selling solar power in Saint-Martin differ from those in Guadeloupe and Martinique. The national purchase order that sets rooftop feed-in tariffs in the other ZNI does not cover Saint-Martin, because energy is a local competence. Whatever export arrangement applies therefore comes from the Collectivité’s Code de l’énergie and EDF’s connection terms, neither of which could be read in detail from an accessible source.
Anyone planning a grid-connected system should confirm the current position with EDF and the Collectivité’s environment department (guichet-environnement) before investing.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity (rooftop solar) | Governed by the Collectivité’s Code de l’énergie and EDF’s connection approval; thresholds could not be verified. A déclaration préalable is needed where roof work changes the building’s appearance. | Collectivité de Saint-Martin; EDF SEI | The national S24 feed-in order does not apply to Saint-Martin. |
| Generate electricity (power plants) | New capacity is planned through the PPE, co-written by the State and the Collectivité under articles L141-1 to L141-6 of the national energy code. A new plant was said in June 2025 to depend on the PPE being signed. | State and Collectivité (PPE); CRE (cost assessment) | The PPE was still being drawn up in 2026. |
| Store electricity (household battery) | No specific licensing regime identified; a battery connected to the network requires the network operator’s agreement. | EDF SEI; Collectivité | No support scheme for home storage was identified. |
| Store electricity (grid-scale) | No Saint-Martin storage window has been opened by the CRE. | CRE; EDF SEI | Recent CRE windows covered other ZNI only. |
| Export / sell to the grid | Only to EDF, as the single buyer and operator; terms not confirmed for Saint-Martin. | EDF SEI; Collectivité | There is no market in which to sell to third parties. |
| Supply electricity to consumers | Not open to competitors in practice; EDF is the historic sole supplier. | Collectivité; State; CRE | Price equalisation depends on the local energy code and PPE. |
| Aggregate / operate a VPP | No framework; there is no market for flexibility. | — | Flexibility is managed by EDF as system operator. |
| Trade / wholesale | No wholesale market exists. | — | EDF’s costs are assessed by the CRE. |
| Balancing and ancillary services | Provided by EDF-dispatched generation, including mobile generators during the 2024–2025 shortfall. No open procurement. | EDF SEI | — |
| Remote control of customer assets | No retail demand-response scheme identified. | EDF SEI | Demand reduction is pursued through MDE subsidies (Agir Plus) rather than control of assets. |
Licensing in Saint-Martin sits at the junction of national and local law. The State keeps responsibility for parts of the framework, such as the PPE (which it co-writes with the Collectivité) and the CRE’s role in public-service charges. The Collectivité, which has held energy competence since 2012, sets local energy rules through its Code de l’énergie. Planning rules come from the Collectivité’s own Code de l’urbanisme.
For a small installation the practical steps are planning clearance from the Collectivité and connection approval from EDF. Detailed thresholds in the local energy code could not be verified because the published code is a scanned document.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Balancing / reserves | No | — | No | EDF SEI. Reserves come from EDF-dispatched engines and, during the shortfall, mobile generators. There is no market for distributed assets. |
| Demand-side management (MDE) | Restricted | — | No | EDF / CRE territorial frameworks. Efficiency subsidies for small actions are compensated under the CRE’s territorial frameworks, which include Saint-Martin (deliberation 2024-237 of 19 December 2024, amended on 7 May 2025). |
Saint-Martin has no flexibility market. EDF runs the small isolated system directly, and in the 2024–2025 shortfall it relied on mobile generators to cover the gap. Households interact with the system mainly through EDF’s Agir Plus energy-efficiency programme rather than through any payment for flexibility.
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | Not documented for Saint-Martin on an accessible official page |
| Reading interval | Not identified |
| Meter owner / operator | EDF SEI |
| Roll-out data | Not identified |
EDF has rolled out its “compteur numérique” in its overseas regions, but no figures or programme details specific to Saint-Martin were found on an accessible official page. Customers should ask EDF whether their connection has a remotely read meter.
Renewable electricity.
- Renewable electricity share
- Not identified from a reliable public source.
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- Not identified from a reliable public source.
- Solar PV
- Not identified from a reliable public source.
Targets.
- National energy-code objective for the ZNI: 100% renewable electricity and energy autonomy by 2030 (CRE).
- Saint-Martin PPE: being drawn up jointly by the State and the Collectivité under a framework convention signed in 2021; not adopted as of 2026.
- A new power plant with a strong renewable component was announced in June 2025 as dependent on the PPE.
No official generation mix or renewable capacity figures were found for Saint-Martin. The island’s electricity comes mainly from engine-based thermal units, which is why engine failures in 2024–2025 caused a supply crisis.
The legal objective for all French non-interconnected zones is 100% renewable electricity by 2030, but Saint-Martin has no adopted PPE to translate this into capacity targets. In June 2025 the Collectivité said it had met the CRE’s chair in Paris to press for the PPE’s signature, which would allow a new plant with a strong renewable share.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
No storage projects in Saint-Martin were identified in official sources. In the other ZNI, storage is mainly centralised, selected through CRE windows and dispatched by EDF; none of the windows open in 2024–2026 covered Saint-Martin.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| EDF (EDF Archipel Guadeloupe – Saint-Martin) | 100%: sole historic supplier | No | Unknown | No | Unknown |
There is no supplier competition. EDF supplies all customers on the French side of the island as the historic operator of an isolated system, and is compensated for the extra cost of supply through public-service charges assessed by the CRE.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Collectivité de Saint-Martin – Direction de l’Environnement | Government | Energy competence, local Code de l’énergie, PPE (with the State), planning | Sets local energy and planning rules and is the contact for energy questions (guichet-environnement). |
| Commission de régulation de l’énergie (CRE) | Regulator | National energy regulator | Assesses public-service charges for the ZNI and runs the MDE frameworks that include Saint-Martin. |
| EDF SEI – EDF Archipel Guadeloupe | Distribution | Producer, network and system operator, sole supplier | Handles generation, connections, meters and bills on the French side. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Local energy rules | Code de l’énergie de Saint-Martin | Collectivité de Saint-Martin | Adopted by the Territorial Council; published as a scanned PDF. Content not summarised here. |
| Planning | Code de l’urbanisme de Saint-Martin (2025) and PADSM | Collectivité de Saint-Martin | Façade or roof changes altering external appearance need a déclaration préalable. |
| Grid connection | Not identified for Saint-Martin | EDF SEI | EDF SEI’s technical references could not be accessed for this profile. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Planning: déclaration préalable for roof/façade changes | Yes | Local | Required where works change the external appearance of a façade or roof. Decision within one month (two in a protected area); valid for three years. |
| Network operator approval | Yes | Regional | Any connection to the public network is arranged with EDF SEI; the Saint-Martin procedure could not be verified. |
| Local energy-code requirements | Unknown | Local | The Collectivité’s Code de l’énergie may impose requirements; its text could not be read for this profile. |
Permissions are local. The Collectivité controls planning through its own Code de l’urbanisme and the PADSM, and energy through its own Code de l’énergie. EDF controls connection to the network.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| National price equalisation (péréquation tarifaire) | Active | Tariff support | Pre-tax bill levels match mainland France; extra island costs are compensated as public-service charges. In Saint-Martin these charges are outside the excise-funded mechanism used for other ZNI since August 2025. | — |
| MDE territorial compensation framework (small actions) | Active | Grant | Energy-efficiency subsidies for small actions, delivered through EDF’s Agir Plus programme and compensated under the CRE frameworks that include Saint-Martin (deliberation 2024-237, amended 7 May 2025). Saint-Martin amounts not verified. | — |
Data and connectivity.
- Fixed broadband
- Not identified from a reliable public source.
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
No official data on broadband or mobile coverage, or on the communications used by meters in Saint-Martin, was identified.
Grid conditions.
- National peak demand
- Not identified from a reliable public source.
- Annual electricity demand
- Not identified from a reliable public source.
- Generation capacity
- Not identified from a reliable public source.
- Interconnection
- 0 GWSource 1Listed by the CRE as a non-interconnected zone: no link to mainland France.
- Curtailment
- Not identified from a reliable public source.
Security of supply is the main issue. Since September 2024 the island has had an electricity production crisis: an engine in unit 1 failed and the unit 2 engines were weakened, while consumption rose by about 7%. Mobile generators were used as a stop-gap, and the long-term fix — a new plant with a large renewable component — was tied to the signature of the PPE.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Saint-Martin PPE | Upcoming | Not adopted as of 2026 | Being drawn up by the State and the Collectivité under a 2021 framework convention. Its signature is expected to unlock a new power plant and secure price equalisation. |
| New power plant | Upcoming | Dependent on PPE | Announced in June 2025 as a plant with a strong renewable component, to replace failing engine capacity. |
| SPE charges outside the excise mechanism | Current | August 2025 | Since August 2025, ZNI public-service charges are funded by an excise surcharge, except in Saint-Martin and Saint-Barthélemy. |
| Renewed MDE frameworks | Current | 19 December 2024 (amended 7 May 2025) | CRE deliberation 2024-237 adopted new territorial frameworks for small demand-reduction actions, including Saint-Martin. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | — | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | — | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | — | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Low | Saint-Martin is outside the national S24 rooftop feed-in order, and no local purchase tariff or residential PV statistics could be verified. |
| Distributed energy market | Low | Generation is dominated by engine-based thermal units; no official distributed-generation figures were found. |
| Grid flexibility market | Low | No balancing, capacity or flexibility market and no aggregator framework; EDF dispatches all resources. |
| Energy storage adoption | Low | No grid-scale storage identified and Saint-Martin was not included in CRE ZNI storage windows 2024–2026. |
| Renewable growth environment | Low | No adopted PPE; new renewable-heavy capacity depends on the plan being signed. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 10 sources
- Transition énergétique dans les zones non interconnectées (ZNI). Commission de régulation de l’énergie, 2026. accessed 10 October 2026.
- Délibération 2024-237 – Cadres territoriaux de compensation pour les petites actions de MDE (incl. Saint-Martin). Commission de régulation de l’énergie, 2024. accessed 10 October 2026.
- Guichets de saisine pour les ouvrages de stockage d’électricité dans les ZNI. Commission de régulation de l’énergie. accessed 10 October 2026.
- Arrêté du 5 janvier 2024 fixant les conditions d’achat de l’électricité produite par les installations photovoltaïques sur bâtiment, hangar ou ombrière (ZNI). Légifrance, 2024. accessed 10 October 2026.
- Le code de l’énergie. Collectivité de Saint-Martin. accessed 10 October 2026.
- Programmation pluriannuelle de l’énergie. Collectivité de Saint-Martin. accessed 10 October 2026.
- Conférence de presse conjointe EDF-État-COM : point de situation énergie à Saint-Martin. Collectivité de Saint-Martin, 2025. accessed 10 October 2026.
- Déclaration préalable – constructions et travaux. Collectivité de Saint-Martin. accessed 10 October 2026.
- Codes et règlements. Collectivité de Saint-Martin, 2025. accessed 10 October 2026.
- Histoire de la Collectivité. Collectivité de Saint-Martin. accessed 10 October 2026.
Questions about energy in Saint Martin.
EDF, through its island systems division (EDF SEI, organised as EDF Archipel Guadeloupe), produces, distributes and supplies electricity on the French side of the island. Households cannot choose another supplier.
Households pay EDF’s regulated tariff under national price equalisation, so the pre-tax bill level matches mainland France. Saint-Martin applies its own taxes, and the current tax-inclusive price could not be verified from an accessible official source.
Not under the national scheme: the 5 January 2024 rooftop-solar purchase order used in Guadeloupe and other ZNI does not cover Saint-Martin. Energy is a competence of the Collectivité, so any arrangement comes from its Code de l’énergie and EDF’s connection terms. Check with EDF and the Collectivité before installing.
Since September 2024 the island has had a production shortfall after an engine in unit 1 failed and unit 2 engines weakened, while demand rose by about 7%. EDF brought in mobile generators, and a new plant depends on the territory’s energy plan (PPE) being signed.
The CRE classes Saint-Martin as a non-interconnected zone with no link to mainland France. No interconnection with the Dutch side’s utility is recorded in the French official sources consulted.
The CRE regulates the public-service costs of supply, while the Collectivité de Saint-Martin has held energy competence since 2012 and has adopted its own Code de l’énergie. The State and the Collectivité are jointly drawing up the PPE.