How electricity works in Algeria.
Algeria electricity market 2026: CREG tariff 54M bands, the 15-digit Sonelgaz client reference, Sonelgaz grid and distribution, self-production rules and solar plans.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Algerian dinar (DZD) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Algeria energy at a glance.
Key figures for households in Algeria. Each one links to its source on the full overview below.
Electricity price.
4.658 DZD per kWh for households, including taxes. Figures for 2026.
Renewable share.
1.1% of electricity from renewable sources. Figures for 2024.
Selling back to the grid.
Can homes export electricity? No. Details are in the export section below.
Four things to check in Algeria.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Algeria below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Algeria requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Algeria.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Algeria, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Algeria, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Algeria.
The energy market in Algeria, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 9 October 2026.
On this page22 sections
Algeria’s electricity sector is run almost entirely by the state-owned Sonelgaz group. Its subsidiaries generate most of the country’s electricity (Sonelgaz-Production de l’Électricité), own and operate the transmission grid and the national dispatch (Sonelgaz-Transport de l’Électricité et Opérateur Système, S-TOS), and distribute and sell electricity and gas to every connected customer (Sonelgaz-Distribution). In 2025 the group served 12.62 million electricity customers and 8.50 million gas customers, and reports an electrification rate of 99%.
The legal framework is Law 02-01 of 5 February 2002 on electricity and the distribution of gas by pipeline. It opened generation to competition, created the Electricity and Gas Regulatory Commission (CREG) and made distribution a concession, but in practice Sonelgaz remains the single distributor and supplier and independent producers sell to it. CREG sets the regulated tariffs, which have been unchanged since 1 January 2016 and are uniform across the country. Since September 2025 the sector has been overseen by the Ministry of Energy and Renewable Energies (MEER).
Generation is almost entirely gas-fired: renewables produced about 1% of electricity in 2024 according to Ember. The government’s programme is to build 15,000 MW of solar photovoltaics, of which a first tranche of 3,200 MW in 12 southern and High Plateaux provinces is under construction. Demand is growing quickly and peaks in summer: the system reached a record 20,628 MW on 23 July 2025.
Energy snapshot.
Headline figures for electricity in Algeria. Each shows its data year and links to its source.
- Population47,435,312 peopleSource 142025
- HouseholdsNot identified from a reliable public source.
- Average household sizeNot identified from a reliable public source.
- Electricity use per householdNot identified from a reliable public source.
- Household price (DZD)4.658 DZD/kWhSource 22026
- Household price (EUR)0.031 EUR/kWhSource 172026
- Renewable electricity share1.07%Source 122024
- Solar capacity0.462 GWSource 13End 2024
- Wind capacity0.01 GWSource 13End 2024
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Vertically integrated
- Homes can export to the grid
- No
- Home equipment in grid services
- No
- Regulator
- Commission de Régulation de l’Électricité et du Gaz (CREG)
- System operator
- Sonelgaz-Transport de l’Électricité et Opérateur Système (S-TOS)
- Distribution networks
- Sonelgaz-Distribution holds the electricity and gas distribution concessions for the whole country
- Currency
- Algerian dinar (DZD)
- Voltage and frequency
- 220 V single-phase / 380 V three-phase, 50 Hz
Electricity prices in Algeria.
- Household price (DZD)
- 4.658 DZD/kWh (2026)Source 2Derived from CREG’s published household tariff 54M (in force since 1 January 2016) for an illustrative household using 500 kWh in a quarterly billing period on a 6 kW connection: 125 kWh at 1.7787 + 125 kWh at 4.1789 + 250 kWh at 4.8120 DA/kWh = 1,947.70 DA, plus the fixed charge of 4.37 DA/kW/month × 6 kW × 3 months = 78.66 DA, plus VAT at 9% on bands 1–2 and the fixed charge and 19% on band 3 (302.67 DA). Total 2,329.03 DA ÷ 500 kWh. The radio/television duty (droit fixe, 100 DA per bill at this consumption), the housing tax collected on the bill and the stamp duty on cash payments are excluded. The average price varies sharply with consumption because of the rising bands.
- Household price (EUR)
- 0.031 EUR/kWh (2026)Source 17Converted from DZD 4.658/kWh at the Bank of Algeria opening rate of 9 October 2026 (EUR 1 = DZD 150.9119).
- Typical annual electricity bill
- 9,316 DZD/yr (2026)Source 2Illustrative, derived for a household using 500 kWh a quarter (2,000 kWh a year) on a 6 kW connection: 4 × 2,329.03 DA including VAT. The radio/television duty (4 × 100 DA), the housing tax and any stamp duty are excluded. Not an official average bill.
How the household tariff works
Every household on tariff 54M pays the same progressive prices wherever it lives. The bands apply to the consumption on each bill, and meters are read every three months, so the cheapest band covers the first 125 kWh of a quarter. A household that uses more moves into the 4.18, 4.81 and 5.48 DA/kWh bands, so its average price climbs quickly: in the example used above, 500 kWh in a quarter costs on average 4.66 DA/kWh including VAT. The fixed charge depends on the power the distributor makes available, which is 4, 6 or 12 kW for single-phase homes and 20 to 80 kW for three-phase connections.
Taxes and charges on the bill
VAT is charged at 9% on the first two household bands and on the fixed charge, and at 19% on bands 3 and 4. Each bill also carries a fixed duty for radio and television of 25, 50 or 100 DA depending on consumption, and Sonelgaz collects the housing tax on behalf of the state: 300 to 1,200 DA a year in ordinary municipalities and 600 to 2,400 DA in daïra capitals and in all municipalities of Algiers, Annaba, Constantine and Oran. Stamp duty is added when a bill is paid in cash.
Regional support
Tariffs excluding tax are identical across the country, but the state pays part of the bill in the south. Households and farmers in 20 southern wilayas (including Adrar, Béchar, Tamanrasset, Ouargla, Illizi, Tindouf, El Oued and Ghardaïa) receive a 65% reduction, other economic activities there 25%, and low- and medium-voltage customers in Djelfa, El Bayadh and Naâma 10%. Under the 2017 Finance Law the household reduction applies up to 12,000 kWh a year.
Price level and trend
The tariff grid has not changed since 2016. Sonelgaz’s average selling price to low-voltage customers was 433.0 centimes (4.33 DA) per kWh excluding tax in 2025, against 435.3 centimes in 2024. At the official exchange rate the household price is around EUR 0.03 per kWh, among the lowest in the Mediterranean region, reflecting cheap domestic gas.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | Households (“ménages”) are billed on CREG tariff 54M, set by Decision D/22-15/CD of 29 December 2015 and in force since 1 January 2016. Energy prices excluding tax rise by band: 1.7787 DA/kWh up to 125 kWh, 4.1789 DA/kWh from 125 to 250 kWh, 4.8120 DA/kWh from 250 to 1,000 kWh and 5.4796 DA/kWh above 1,000 kWh. A fixed charge of 4.37 DA per kW of connected power per month is added. Non-household low-voltage customers use tariff 54NM, which has three bands starting at 4.1789 DA/kWh. |
| Time-of-use | Limited | Low-voltage customers can choose two- or three-period tariffs instead of the progressive tariff: 52 (peak 8.1147 and off-peak 1.7807 DA/kWh), 53 (day 4.8698 and night 1.2050 DA/kWh) and 51 (peak 8.1147, standard 2.1645 and night 1.2050 DA/kWh), each with a higher fixed charge. CREG lists them for both household (M) and non-household (NM) customers. |
| Dynamic | No | There is no organised wholesale market and no wholesale-linked retail price. |
| Fixed | No | There is no supplier choice. The regulated tariff applies to all households and changes only by CREG decision. |
| Prepayment | No | No prepayment tariff was identified. Bills follow quarterly meter readings and can be paid at Sonelgaz commercial agencies, any post office, by transfer or online with the Edahabia or CIB card, WIMPAY-BNA or BaridiMob. |
Household prices compared with neighbouring countries (EUR per kWh).
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- Not identified from a reliable public source.
- Average daily use per household
- Not identified from a reliable public source.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 1,888 kWh/person/yr (all sectors) (2025)Source 8Derived: Sonelgaz electricity sales on the national territory of 89,552 GWh in 2025 divided by the World Bank 2025 population estimate of 47,435,312.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- Not identified from a reliable public source.
Electricity demand is growing fast. Sonelgaz sold 89,552 GWh on the national territory in 2025, 7.6% more than in 2024. Low-voltage customers, mostly households, took 49,058 GWh (55%), medium-voltage customers 22,104 GWh (25%) and high-voltage industrial customers 18,390 GWh (20%). The number of electricity customers rose by 3% to 12.62 million.
Demand peaks in summer, not winter. Successive heatwaves in July 2025 pushed the maximum demand to a record 20,628 MW on 23 July, 5.6% above the 2024 peak of 19,543 MW, and on 21 and 23 July Sonelgaz operated with zero reserve. The ministry, CREG, the energy-efficiency agency APRUE and Sonelgaz run annual campaigns asking households to limit consumption at peak times.
Natural gas, not electricity, is the main heating and cooking fuel in towns: Sonelgaz reports a gas penetration rate of 75% and 14,491 million m³ of low-pressure gas sales in 2025.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- Not identified from a reliable public source.
- Private rented
- Not identified from a reliable public source.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- Not identified from a reliable public source.
- Apartments and flats
- Not identified from a reliable public source.
- Urban population
- 75.8 % of population (2025)Source 15World Bank estimate.
About three-quarters of Algerians live in urban areas, concentrated along the Mediterranean coast and in the northern High Plateaux, while the vast Saharan south is thinly populated and partly served by isolated diesel and gas-turbine networks. Housing statistics from the national statistics office were not available online, so tenure and dwelling-type shares are not given here.
Each connection is opened in the name of the occupier on proof of the right to occupy (title deed, allocation decision or lease), so both owners and tenants hold supply contracts directly with Sonelgaz-Distribution.
How the grid works in Algeria.
- TransmissionSonelgaz-Transport de l’Électricité et Opérateur Système (S-TOS), S-TOS (national dispatch)
- DistributionSonelgaz-Distribution holds the electricity and gas distribution concessions for the whole country
- MeteringSonelgaz-Distribution
- Supply1 or more retail suppliers
Physical flow
Almost all electricity is produced in gas-fired combined-cycle, steam and gas-turbine plants, most of them operated by Sonelgaz-Production de l’Électricité. Total installed capacity was 26,706 MW in 2025, of which 25,134 MW belonged to Sonelgaz’s production and renewables subsidiaries and 1,572 MW to other producers. Power flows over S-TOS’s 400, 220 and 60 kV network, which grew by 976 km in 2025, to Sonelgaz-Distribution’s medium- and low-voltage networks. Transmission losses were 3.58% and distribution losses 7.44% in 2025.
Sonelgaz sells electricity to the Tunisian utility STEG, worth 33.1 billion DA in 2025. Ember data show Algeria as a small net exporter (2.52 TWh in 2024). Parts of the far south are supplied by isolated networks fed by local gas turbines and diesel sets, and a north–south interconnection is under construction.
Commercial flow
Law 02-01 provides for producers to sell by bilateral contract or through a market operator, but no organised wholesale market operates. Sonelgaz-Distribution buys from the group’s producers and from independent producers, and sells to final customers at CREG’s regulated tariffs. CREG fixes the remuneration of transmission and distribution and the transmission use-of-system tariff. Contributions included in tariffs fund tariff equalisation between concessions and the extra costs of renewable and cogeneration production.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry of Energy and Renewable Energies (MEER) | Created in the government reshuffle of 14 September 2025. Sets energy policy, oversees Sonelgaz and the renewable programme, and is the supervising ministry for Sonelgaz-Énergies Renouvelables and the equipment maker SAIEG since their transfer from the group in 2025. |
| Regulator | Commission de Régulation de l’Électricité et du Gaz (CREG) | Independent regulator created under Law 02-01 (operating since January 2005). Sets electricity and gas tariffs and network remuneration, grants or registers generation authorisations and declarations, supervises the distribution concessionaire and handles consumer appeals. Its president since 22 December 2025 is Baya Chekired Hammat. |
| TSO | Sonelgaz-Transport de l’Électricité et Opérateur Système (S-TOS) | Owns and operates the high- and very-high-voltage transmission network (36,513 km at the end of 2025, at 60, 220 and 400 kV) and combines the former transmission company GRTE with the system operator. |
| System operator | S-TOS (national dispatch) | Balances generation and demand in real time, forecasts demand, schedules the generating fleet and reserves, manages international exchanges and prepares the transmission development plan, under rules approved by CREG. |
| DSO | Sonelgaz-Distribution | Holds the electricity and gas distribution concessions for the whole country under Executive Decree 08-114. Operates 201,603 km of medium-voltage and 232,871 km of low-voltage lines (2025) through regional directorates and local commercial agencies. |
| Supplier | Sonelgaz-Distribution | Sole retail supplier to 12.62 million electricity customers at CREG’s regulated tariffs. Only very large customers above 4 GWh a year are legally eligible to choose a supplier. |
| Metering | Sonelgaz-Distribution | Owns, installs and reads all customer meters; CREG states that the meter is the distributor’s property and that tampering is treated as theft. |
Compared with the UK system.
| UK concept | Algeria equivalent | How it works |
|---|---|---|
| DNO | Sonelgaz-Distribution (concessionaire) | One company holds every distribution concession in the country. Its regional directorates and commercial agencies handle connections, meters, faults and billing, the roles a DNO and a supplier share in Britain. |
| National Grid/NESO | S-TOS | Transmission ownership and system operation sit in one Sonelgaz subsidiary. There is no balancing market; S-TOS dispatches Sonelgaz plants, independent producers and the interconnections under CREG-approved operating procedures. |
| MPAN | Référence client / PDL (15 digits) | Each supply contract has a 15-digit client reference printed on the bill next to the label “Référence / PDL” (point de livraison). It identifies the customer account at the consumption address and is what customers quote to their agency or the 3303 call centre. |
| MPRN | Separate gas contract with Sonelgaz-Distribution | Sonelgaz-Distribution also distributes natural gas, billed on the same document under gas tariff 23M/23NM with its own meter number and subscribed flow rate (6 to 40 m³/h). |
| Meter operator | Sonelgaz-Distribution | The distributor owns, installs, seals and reads the meter; there is no competitive metering market. |
| Supplier | Sonelgaz-Distribution (no choice) | Households cannot switch. Customers using at least 4 GWh a year are legally “eligible” to leave the tariff system, but CREG notes that this right depends on competing suppliers existing. |
| Smart-meter infrastructure | None identified | There is no national smart-meter data hub comparable to the DCC. Consumption is read manually every quarter, and bills show whether a reading was real (R), estimated (E) or special (M). |
How a supply point is identified.
051407238816290 (fictional)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Référence client (référence / point de livraison) (Référence / PDL) |
| Who issues it? | Sonelgaz-Distribution, when a supply contract is opened at the local commercial agency |
| Format | Numeric client reference shown in the bill’s “Informations sur la facture” block, labelled “Référence / PDL”. CREG describes it as 15 digits; the internal structure is not published. The bill also shows a separate 12-digit invoice number, the meter number and the tariff code. |
| Length | 15 digits |
| Stays with the property when you switch supplier? | Not identified from a reliable public source. |
| Where to find it | On every electricity and gas bill, in the invoice-information block alongside the invoice number, issue date, consumption address and expected date of the next meter reading. |
| Electronic access | Bills can be paid online with the Edahabia or CIB card, WIMPAY-BNA and BaridiMob. Sonelgaz reports that a Sonelgaz-Distribution customer portal was in a test phase on its intranet in 2025, and that the national identification number (NIN) has been added to its customer system for ordinary low-voltage and low-pressure customers. |
| Third-party access | No regulated third-party data access exists. There are no competing suppliers, and consumption data stay with Sonelgaz-Distribution. |
| Who keeps the register | Sonelgaz-Distribution customer relationship management system (CRMS) |
| Register scope | National |
How a supply point is created
To be connected, the occupier submits a written request to the Sonelgaz-Distribution commercial agency with an identity document and legal proof of occupation (title deed, lease or allocation decision); non-household customers also show their trade or professional registration. The agency checks the file, fills in the standard supply application form set by CREG Decision D/03-23/CD, which becomes the supply contract once signed, and gives a receipt with a file number. A technical team visits if needed and a quote based on the ministerial price schedule is issued; the applicant has two months to pay it.
A simple connection (branchement) applies for up to 40 kVA where the property is less than 25 m from the network; longer or more powerful connections need a network extension. Once the works are done and a certificate of conformity for the internal installation is presented, the supply is energised and billing starts. CREG’s consumer guidance gives lead times of 7 days for a low-voltage connection and 40 days for a low-voltage extension.
The client reference
The 15-digit reference is the identifier a customer quotes for any account matter: paying a bill, reporting a fault to the 3303 call centre, contesting a bill or appealing to CREG. It is printed with the label “Référence / PDL”, linking the account to the delivery point at the consumption address. The meter has its own number, printed separately on the bill.
Change of occupant and corrections
Personal details on the contract are changed at the commercial agency on presentation of supporting documents such as a deed, an acquisition decision, a lease or an identity card. Sonelgaz does not publish whether the reference is kept or reissued when a new occupant takes over a supply point.
Connected power
Each contract specifies the power made available (puissance mise à disposition): 4, 6 or 12 kW for single-phase 220 V homes and 20, 40, 60 or 80 kW for three-phase 380 V connections. The fixed charge on the bill is calculated from this figure.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Limited |
| Net metering | No |
| Net billing | No |
| How exported electricity is paid | No household export tariff, net metering or net billing scheme was identified. Renewable plants are paid a guaranteed purchase price only under the “special regime”, which is open exclusively through tenders. |
| Can a household sell surplus solar electricity? | No retail scheme exists. CREG’s rules allow self-producers to connect after declaring their installation, but payment for injected electricity is only provided for plants selected under the special regime, which is accessed by tender. |
| Which size thresholds apply? | Self-production below 25 MW (ISO conditions) is subject to declaration; 25 MW and above, or an extension of more than 10%, needs an operating authorisation. Back-up generators below 1 MW and plants below 15 MW serving the isolated southern networks are excluded. |
| Can a producer connect to the grid? | Yes. Producers have free access to the transmission and distribution networks on presentation of a CREG authorisation or declaration certificate, and the distribution concessionaire must connect licensed renewable and cogeneration plants. |
| Are guarantees of origin available? | Yes. CREG Decision D/04-23/CD of 14 May 2023 sets the procedure for issuing guarantee-of-origin certificates for photovoltaic installations. |
Connecting a home system.
- Small self-production systems below 25 MW are not licensed but must be declared in advance to CREG, under the ministerial order of 2 April 2007 and CREG Decision D/01-23/CD on processing declarations.
- CREG checks that the declaration complies with Law 02-01 and issues a declaration certificate.
- The producer applies to the network operator (Sonelgaz-Distribution or S-TOS) for connection, producing the CREG authorisation or declaration certificate.
- The installation must be fitted with metering that records electricity injected into and withdrawn from the network.
Algeria has no rooftop solar export scheme for households. Law 02-01 allows anyone to generate electricity, and CREG treats installations whose output is for self-production and below 25 MW as declarable rather than licensable, but there is no published tariff, credit or offset for surplus fed into the low-voltage network. Very cheap regulated tariffs also give households little financial reason to self-generate.
Grid-connected renewable generation is developed through tenders. Executive Decree 17-98 (amended in 2017 and 2021) sets the tender procedure for renewable and cogeneration production, and Executive Decree 13-218 (amended by Decree 21-431 in 2021) sets the premiums paid to cover diversification costs. Winners connect under the special regime with priority dispatch and a guaranteed purchase price.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity | Operating authorisation from CREG for plants of 25 MW and above (Executive Decree 06-428); prior declaration to CREG for self-production below 25 MW | CREG | Back-up generators below 1 MW and plants below 15 MW serving isolated southern networks are excluded. CREG publishes the main characteristics of authorised plants. |
| Generate from renewables or cogeneration with guaranteed price | Special regime, accessible only by winning a tender under Executive Decree 17-98 | CREG / Ministry of Energy and Renewable Energies | Gives priority dispatch and a guaranteed purchase tariff under Executive Decree 13-218. |
| Store electricity | No specific storage licence or regime identified | — | Storage is not defined as a separate activity in the CREG regulations reviewed. |
| Export to the grid | CREG authorisation or declaration certificate needed to connect; no retail export scheme | CREG; Sonelgaz-Distribution or S-TOS for connection | Metering of injected and withdrawn energy is required. |
| Transmit electricity | Natural monopoly; operating authorisation from the energy ministry after CREG opinion | Ministry of Energy and Renewable Energies / CREG | Held by the Sonelgaz transmission and system-operator subsidiary (formerly GRTE). |
| Distribute electricity | Concession granted by the state (Executive Decree 08-114) | State / CREG supervision | All concessions are held by Sonelgaz-Distribution with exclusive rights in their areas. |
| Supply or sell electricity to households | Reserved to the distribution concessionaire at regulated tariffs | CREG | Customers using 4 GWh a year or more are “eligible” and may negotiate with another supplier if one exists (Executive Decree 07-310). |
| Aggregate, trade or operate a VPP | No framework identified | — | There is no wholesale market or aggregator licence. |
| Provide balancing or grid services | Producers must provide frequency/voltage control and black-start if CREG requires it | CREG / S-TOS | Producer rights include payment for secondary and tertiary frequency control and black-start; there is no market for third-party flexibility. |
Algeria’s licensing rules are set by Law 02-01 and its implementing decrees. Generation is formally open to competition: any public or private person may build a plant with a CREG operating authorisation (large plants) or a declaration (self-production below 25 MW). Transmission and system operation are a single regulated monopoly, distribution is a state concession held by Sonelgaz-Distribution, and supply to ordinary customers is reserved to the concessionaire.
There is no licence category for storage, aggregation or demand response, and no organised market in which such services could be sold.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Wholesale energy market | No | — | No | Law 02-01 provides for a market operator, but no organised wholesale market operates; Sonelgaz-Distribution buys power for all regulated customers. |
| Frequency control and black-start | Restricted | — | No | S-TOS. Provided by large generators under their CREG cahier des charges, with remuneration for secondary and tertiary control and black-start. Not open to distributed assets. |
| Demand response | No | — | No | No demand-response programme was identified. Peak management relies on public awareness campaigns and two- and three-period tariffs. |
Distributed energy resources cannot take part in any energy or flexibility market. System balancing is carried out by S-TOS using Sonelgaz and independent power plants, and in July 2025 the system ran at zero reserve on two days of record demand. The main levers for household demand are the time-of-use tariff options and national campaigns asking customers to reduce consumption at peak times.
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | No national smart-meter rollout identified |
| Reading interval | Quarterly manual reading |
| Meter owner | Sonelgaz-Distribution |
| Reading frequency | Every three months |
| Reading types on the bill | R (actual), E (estimated), M (special reading) |
| Data hub | None |
CREG states that meters are read every three months on a schedule set by the distributor, and the date of the next reading is printed on the bill. If the meter is inaccessible, quarterly consumption is estimated from the customer’s history, and later corrected by a catch-up bill (facture de rattrapage). No official smart-meter rollout programme or penetration figure was identified in Sonelgaz’s 2025 activity report or on CREG’s site.
Renewable electricity.
Electricity generation mix (2024).
- Gas: 98.6%
- Other fossil: 0.3%
- Solar: 1%
- Wind: 0%
- Hydro: 0%
- Renewable electricity share
- 1.07% (2024)Source 12Share of electricity generation: solar 1.03%, wind 0.02% and hydro 0.02% of 96.36 TWh. Algeria is a net exporter of electricity (net exports 2.52 TWh in 2024), so the generation share is used.
- Home solar
- Not identified from a reliable public source.
- Solar added each year
- 0 MW (2024)Source 13IRENA records no net solar additions in 2024.
- Solar PV
- 0.462 GW (End 2024)Source 13
- Wind
- 0.01 GW (End 2024)Source 13
- Hydro
- 0.129 GW (End 2024)Source 13
Targets.
- 15,000 MW of solar photovoltaic capacity under the government programme assigned to Sonelgaz, with a first tranche of 3,200 MW in 12 southern and High Plateaux provinces (plants of 80 to 220 MW) under implementation.
- Policy objectives of the Ministry of Energy and Renewable Energies include increasing renewables in national production and directing renewable output toward export to Africa and Europe.
Algeria has one of the world’s best solar resources but almost no renewable electricity: gas supplied 98.6% of generation in 2024. Sonelgaz built about 343 MW of photovoltaic plants on sites in the Grand Sud and High Plateaux, the 10 MW Kaberten wind farm in Adrar, and earlier electrified 18 remote villages with solar systems. Sonelgaz-Énergies Renouvelables produced 616 GWh in 2025.
The current programme aims at 15,000 MW of solar PV. Its first 3,200 MW tranche consists of utility-scale plants of 80 to 220 MW in 12 provinces, built by Sonelgaz with contractors; the ministry described it as under implementation in October 2026, and Sonelgaz’s 2025 report mentions plants in the Béchar and Ghardaïa provinces. Renewable plants are owned by the state group rather than by households or private investors.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
No grid-scale battery or pumped-storage capacity was identified in official sources, and storage has no specific regulatory status. Flexibility on the Algerian system comes from gas-fired plants, which make up almost all capacity.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Sonelgaz-Distribution | 100% of regulated retail customers (12.62 million electricity customers, 2025) | No | Yes | No | No |
There is a single supplier. Sonelgaz-Distribution sells electricity and gas to all low-, medium- and high-voltage customers at CREG’s tariffs. CREG publishes each year the list of customers whose consumption reached the eligibility threshold of 4 GWh of electricity or 140 million thermies of gas, but it notes that eligibility only becomes meaningful when several suppliers compete.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Ministry of Energy and Renewable Energies | Government | Energy policy and sector supervision | Responsible for the 15,000 MW solar programme and oversees Sonelgaz. |
| Commission de Régulation de l’Électricité et du Gaz (CREG) | Regulator | Electricity and gas regulator | Sets tariffs, registers generation, publishes consumer rules and handles appeals. |
| Sonelgaz group | Transmission | State energy group (generation, transmission, distribution) | Parent of S-TOS, Sonelgaz-Distribution and Sonelgaz-Production de l’Électricité; publishes the annual activity report. |
| Sonelgaz-Distribution | Distribution | National distribution concessionaire and supplier | Connects, meters and bills every household. |
| APRUE (Agence nationale pour la promotion et la rationalisation de l’utilisation de l’énergie) | Consumer | Energy-efficiency agency | Runs consumption-rationalisation campaigns with Sonelgaz under the ministry. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Grid connection (transmission) | Ministerial order of 21 February 2008 on technical rules for connection to the transmission network and system operation | Ministry of Energy | Applies to producers and large consumers connected to the transmission grid. |
| Transmission network design and operation | Executive Decree 06-430 and the 2015 technical regulations on transmission works | Government / Ministry of Energy | Design, construction and operating specifications for transmission assets. |
| System operation | CREG Decision D/04-17/CD (operating procedure) and D/03-21/CD (defence and restoration plan) | CREG | Roles of the system operator, transmission operator, producers and connected customers. |
| Guarantees of origin | CREG Decision D/04-23/CD of 14 May 2023 | CREG | Procedure for certifying electricity produced by PV installations. |
| Internal installations | Certificate of conformity of the internal installation | Sonelgaz-Distribution / CREG rules | Required before a new connection is energised. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| CREG declaration (self-production below 25 MW) | Yes | National | Prior declaration to CREG; a declaration certificate is needed to connect to the network. |
| CREG operating authorisation | Limited | National | Needed for plants of 25 MW and above and for extensions of more than 10% or that move a plant into the authorisation regime. |
| Network operator connection approval | Yes | National | Connection request to Sonelgaz-Distribution or S-TOS with technical study and quote. |
| Planning permission for rooftop solar | Unknown | Local | No specific national rule for rooftop PV was identified. |
The permissions regime was designed for power plants rather than rooftop systems. A household installation would fall into CREG’s declaration regime for self-production, and connecting it to the network requires the network operator’s agreement. No simplified procedure for small residential systems has been published.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| State support for southern and High Plateaux wilayas | Active | Bill reduction | 65% reduction for households and farmers and 25% for other economic activities in 20 southern wilayas; 10% for low- and medium-voltage customers in Djelfa, El Bayadh and Naâma. The household reduction is capped at 12,000 kWh a year (2017 Finance Law). | — |
| Special regime premiums for renewables and cogeneration | Active | Guaranteed purchase price (tender) | Executive Decree 13-218, amended by Decree 21-431 of 4 November 2021, sets premiums covering diversification costs for plants selected by tender under Decree 17-98. Not available to households. | — |
Data and connectivity.
- Fixed broadband
- 13.3 fixed subscriptions per 100 people (2024)Source 16
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
Internet use is widespread (77.4% of the population in 2024, World Bank) but fixed broadband is limited at 13.3 subscriptions per 100 people. Sonelgaz runs its own fibre-optic telecoms network along the transmission grid, which reached 23,589 km at the end of 2025, and has digitised payment through BaridiMob and card payments, but no communicating-meter network was identified.
Grid conditions.
- National peak demand
- 20.6 GW (23 July 2025)Source 8Record maximum demand; 19.543 GW on 31 July 2024.
- Annual electricity demand
- 93.8 TWh (2024)Source 12Ember electricity demand. Sonelgaz reports 101,692 GWh of total production and 89,552 GWh of sales on the national territory in 2025.
- Generation capacity
- 26.7 GW (2025)Source 825,134 MW Sonelgaz production and renewables subsidiaries plus 1,572 MW other producers (excluding SPP1).
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
The main constraint is summer peak demand. Availability of the generating fleet rose to 91.68% in 2025, but reserves fell to zero on the two peak days of July 2025. In 2025 Sonelgaz added 688.8 MW of capacity, mainly a steam unit at the Kais combined-cycle plant and two gas turbines at the new Mostaganem combined-cycle plant, and commissioned 11 new 220 kV and 15 new 60 kV substations and 1,094 km of lines.
Supply interruptions to customers fell from 1.32% in 2024 to 1.15% in 2025 by Sonelgaz’s measure, and distribution losses (technical and commercial) fell from 7.78% to 7.44%.
Grid and capacity maps.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Ministry of Energy and Renewable Energies created | Current | September 2025 | The government reshuffle of 14 September 2025 created a ministry combining energy and renewable energies; Sonelgaz was attached to it, and Sonelgaz-Énergies Renouvelables and SAIEG were moved directly under the ministry. |
| New CREG president | Current | 22 December 2025 | Baya Chekired Hammat replaced Wassila Betata Atimene as president of CREG. |
| 3,200 MW solar programme | Upcoming | Under implementation (2026) | First tranche of the 15,000 MW PV programme: plants of 80 to 220 MW in 12 southern and High Plateaux provinces. |
| Adapting the sector’s regulatory framework | Upcoming | No date set | The ministry’s national energy policy lists adapting the regulatory framework, integrating Algeria into the European electricity market and directing renewable output to export as objectives; no specific legal text had been published. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Low | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | — | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | Low | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Low | No household export scheme or residential solar statistic exists; regulated tariffs are among the lowest in the region. |
| Distributed energy market | Low | Self-production is possible only through a CREG declaration designed for plants; no retail compensation for surplus. |
| Grid flexibility market | Low | No wholesale, balancing or demand-response market; ancillary services come from large generators. |
| Energy storage adoption | Low | No grid-scale or residential storage capacity identified. |
| Renewable growth environment | Medium | Renewables were about 1% of generation in 2024, but a 3,200 MW utility solar tranche of a 15,000 MW programme is under construction. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 17 sources
- Pricing (tariff decision D/22-15/CD and electricity tariff table). CREG, 2026. accessed 9 October 2026.
- Facturation et tarifs — FAQ (bill explanation, tariff bands, VAT, client reference). CREG, 2026. accessed 9 October 2026.
- Raccordement au réseau — FAQ. CREG, 2026. accessed 9 October 2026.
- State Support. CREG, 2026. accessed 9 October 2026.
- Production de l’électricité (authorisation, declaration, network access). CREG, 2026. accessed 9 October 2026.
- Distribution de l’électricité et du gaz. CREG, 2026. accessed 9 October 2026.
- La CREG publie la liste des clients ayant atteint le seuil d’éligibilité au 31 décembre 2025. CREG, 2026. accessed 9 October 2026.
- Rapport d’activités 2025. Sonelgaz, 2026. accessed 9 October 2026.
- Foire aux questions. Sonelgaz, 2026. accessed 9 October 2026.
- Renewable Energies (RE). Ministry of Energy and Renewable Energies, 2026. accessed 9 October 2026.
- National Energy Policy. Ministry of Energy and Renewable Energies, 2026. accessed 9 October 2026.
- Yearly electricity data (global release, Algeria rows). Ember, 2025. accessed 9 October 2026.
- Energy Profile: Algeria. IRENA, 2025. accessed 9 October 2026.
- Population, total — Algeria (SP.POP.TOTL). World Bank, 2025. accessed 9 October 2026.
- Urban population (% of total population) — Algeria (SP.URB.TOTL.IN.ZS). World Bank, 2025. accessed 9 October 2026.
- Fixed broadband subscriptions (per 100 people) — Algeria (IT.NET.BBND.P2). World Bank, 2024. accessed 9 October 2026.
- Taux de change journalier. Banque d’Algérie, 2026. accessed 9 October 2026.
Questions about energy in Algeria.
Household prices are set by CREG and have not changed since 2016. Tariff 54M charges 1.7787 DA/kWh for the first 125 kWh of a billing period, then 4.1789, 4.8120 and 5.4796 DA/kWh in higher bands, plus 4.37 DA per kW per month and VAT of 9% or 19%. A household using 500 kWh a quarter pays about 4.66 DA/kWh including VAT, roughly EUR 0.03.
Sonelgaz-Distribution, a subsidiary of the state group Sonelgaz, is the only supplier to households and holds every distribution concession. Customers cannot switch supplier.
The 15-digit client reference printed on the Sonelgaz bill under “Référence / PDL” (point de livraison). It identifies the supply account at the consumption address; the meter number and a 12-digit invoice number are printed separately.
There is no net metering or export tariff for households. Self-production systems below 25 MW must be declared to CREG and can be connected, but payment for exported electricity is available only to plants selected by tender under the special regime.
The Electricity and Gas Regulatory Commission (CREG), created under Law 02-01 of 2002. The Ministry of Energy and Renewable Energies sets policy.
About 1% of generation came from renewables in 2024, almost all solar; natural gas supplied 98.6%. A 3,200 MW solar tranche of a 15,000 MW programme is under construction.
Every three months. The bill shows whether the reading was actual (R), estimated (E) or a special reading (M), and the expected date of the next reading.