How electricity works in Italy.
Italy electricity market 2026: ARERA prices, Terna and e-distribuzione, the POD code, 2G smart meters, GSE export rules, energy communities, licensing and reforms.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Euro (EUR) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Italy energy at a glance.
Key figures for households in Italy. Each one links to its source on the full overview below.
Electricity price.
0.316 EUR per kWh for households, including taxes. Figures for Jul–Sep 2026.
Household use.
2,128 kWh a year for a typical household. Figures for 2024.
Renewable share.
47.7% of electricity from renewable sources. Figures for 2025.
Selling back to the grid.
Can homes export electricity? Yes. Details are in the export section below.
Four things to check in Italy.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Italy below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Italy requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Italy.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Italy, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Italy, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Italy.
The energy market in Italy, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 1 October 2026.
On this page22 sections
Italy has a fully liberalised electricity market regulated by ARERA (Autorità di Regolazione per Energia Reti e Ambiente). Regulated “maggior tutela” prices ended for non-vulnerable households on 1 July 2024. Households that had not chosen a supplier were moved to the Servizio a Tutele Graduali (STG), which runs until 31 March 2027. Only vulnerable customers, such as people over 75 or those receiving the social bonus, can still choose the regulated service. In 2025, 79.7% of the 30.5 million household supply points were on free-market contracts.
From 1 July 2026, ARERA’s reference price for a typical vulnerable household (2,000 kWh a year, 3 kW) was 31.63 euro cents per kWh including taxes. Eurostat put the average price for mid-sized households at €0.2966/kWh in the second half of 2025, slightly above the EU average. Terna owns and operates the national transmission grid and runs the electricity system. Distribution is handled by 114 companies, with e-distribuzione (Enel group) carrying 85.1% of the volumes distributed.
Electricity demand was 311.3 TWh in 2025. Renewables met 41.1% of demand and produced 47.7% of net domestic generation, with natural gas still the largest single source. Solar capacity reached 47.3 GW and battery storage 19.4 GWh by the end of July 2026. Major changes since 2024 include the end of net metering (scambio sul posto) for new systems, a new single law on renewable permits (Legislative Decree 190/2024), the TIDE dispatching reform that opens balancing markets to aggregated distributed resources, and the first MACSE auction for long-term storage contracts.
Energy snapshot.
Headline figures for electricity in Italy. Each shows its data year and links to its source.
- Population58,943,000 peopleSource 181 Jan 2026
- Households26,600,000 householdsSource 182024–2025
- Average household size2.2 people/householdSource 182024–2025
- Electricity use per household2,128 kWh/yrSource 32024
- Household price (EUR)0.316 EUR/kWhSource 1Jul–Sep 2026
- Renewable electricity share47.7%Source 122025
- Solar capacity47.3 GWSource 1331 Jul 2026
- Wind capacity14 GWSource 1331 Jul 2026
- Energy storage capacity19.4 GWhSource 1331 Jul 2026
- Smart-meter share87%Source 42023–2024
- Market structure
- Fully liberalised
- Homes can export to the grid
- Yes
- Home equipment in grid services
- Yes
- Regulator
- ARERA (Autorità di Regolazione per Energia Reti e Ambiente)
- System operator
- Terna
- Distribution networks
- 114 distribution companies under concession; e-distribuzione (Enel) carries 85.1% of volumes, and the ten largest serve 98.3% of customers
- Currency
- Euro (EUR)
- Voltage and frequency
- 230 V / 50 Hz
Electricity prices in Italy.
- Household price (EUR)
- 0.316 EUR/kWh (Jul–Sep 2026)Source 1ARERA reference price including taxes for the typical vulnerable customer in maggior tutela (2,000 kWh/yr, 3 kW). The Q4 2026 update had not been published when this was checked. Most households are on free-market contracts; Eurostat’s 2025-S2 all-taxes price for 2,500–4,999 kWh was €0.2966/kWh.
- Typical annual electricity bill
- 591.9 EUR/yr (Oct 2025 – Sep 2026)Source 1Rolling 12-month spend for ARERA’s typical vulnerable customer in maggior tutela (2,000 kWh/yr, 3 kW), down 0.9% from €597.30. Customers using more, or on free-market offers, pay more.
Household price trend (EUR per kWh).Source 15
| 2019-S1 | 0.2301 EUR/kWh |
|---|---|
| 2019-S2 | 0.2341 EUR/kWh |
| 2020-S1 | 0.2226 EUR/kWh |
| 2020-S2 | 0.2153 EUR/kWh |
| 2021-S1 | 0.2259 EUR/kWh |
| 2021-S2 | 0.236 EUR/kWh |
| 2022-S1 | 0.3115 EUR/kWh |
| 2022-S2 | 0.3641 EUR/kWh |
| 2023-S1 | 0.3782 EUR/kWh |
| 2023-S2 | 0.3347 EUR/kWh |
| 2024-S1 | 0.3274 EUR/kWh |
| 2024-S2 | 0.3111 EUR/kWh |
| 2025-S1 | 0.3291 EUR/kWh |
| 2025-S2 | 0.2966 EUR/kWh |
An Italian bill has four regulated blocks plus energy. The energy block (spesa per la materia energia) covers wholesale purchase and retail costs. The network block (trasporto e gestione del contatore) covers transmission, distribution and metering. System charges (oneri di sistema) are mainly the ASOS component, which funds renewable incentives and relief for energy-intensive industry. The fourth block is taxes. For the typical vulnerable customer in Q3 2026 the split was 16.92 c€ energy procurement, 2.11 c€ retail, 6.18 c€ network, 3.32 c€ system charges and 3.10 c€ taxes per kWh. Renewable incentives cost about €9.3 billion in 2025.
Network and system charges are set nationally by ARERA. Household network charges are the same everywhere in Italy and are paid partly per kWh, partly per kW of contracted power (potenza impegnata, typically 3 kW) and partly as a fixed charge. Excise duty is €0.0227/kWh, but residents with up to 3 kW pay none on their first 150 kWh a month (the relief tapers above 220 kWh a month). VAT on domestic supply is 10%.
Price trend
Italian household prices rose sharply during the 2022 gas crisis, which hit Italy hard because gas sets the wholesale price for most hours. Eurostat’s all-taxes price for mid-sized households peaked at €0.3782/kWh in the first half of 2023 and was €0.2966/kWh in the second half of 2025. That was above the EU average (€0.2896), France (€0.2561) and Spain (€0.2669), but well below Germany (€0.3869). ARERA notes that the free market remained more expensive than maggior tutela for every consumption class in 2025.
Since 1 January 2025 the old single national price (PUN) has been replaced by the PUN Index GME. GME calculates it in the same way, as a weighted average of zonal day-ahead prices, but energy purchases are now settled at zonal prices with an equalisation component. Retail offers that were indexed to the PUN now reference the PUN Index GME.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Limited | Maggior tutela is now only for vulnerable domestic customers (about 3 million). ARERA updates its prices every quarter, and Acquirente Unico buys the energy. The STG, which covers non-vulnerable households that did not choose a supplier, applies conditions set by competitive auction until 31 March 2027. |
| Time-of-use | Yes | Most contracts can be single-rate (monorario), two-rate (F1 / F23) or three-rate (F1, F2, F3). F1 covers weekdays 08:00–19:00. F2 covers weekdays 07:00–08:00 and 19:00–23:00, plus Saturdays 07:00–23:00. F3 covers nights, Sundays and public holidays. |
| Fixed | Yes | Fixed-price offers usually fix the energy price for 12–24 months. In 2025, 51% of household free-market contracts were fixed-price, with an average supply component of €236.69/MWh. |
| Variable | Yes | Variable offers are usually indexed monthly to the PUN Index GME wholesale reference price plus a supplier spread. In 2025, 49% of household contracts were variable, averaging €232.35/MWh. |
| Dynamic | Limited | Under Legislative Decree 210/2021, any customer with a smart meter can ask a supplier with more than 200,000 customers for a dynamic-price contract. Hourly-indexed offers exist, but most indexed household offers are priced monthly by time band. |
Household prices compared with neighbouring countries (EUR per kWh).
- Austria€0.327
- Italy€0.316
- Switzerland€0.292
- Greece€0.238
- Slovenia€0.212
- France€0.2
- Croatia€0.166
- Malta€0.128
- Tunisia€0.059
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- 2,128 kWh/yr (2024)Source 3Derived from ARERA figures: resident households (78.7% of 30.3 million household supply points) used 86.6% of the 58.6 TWh distributed to households. ARERA’s own reference “average” customer uses 2,700 kWh a year at 3 kW.
- Average daily use per household
- 5.8 kWh/day (2024)Source 3Derived by dividing the derived 2,128 kWh/yr resident-household figure by 365.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 5,137 kWh/person/yr (2024)Source 21All sectors (World Bank, electric power consumption per capita).
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- 400,000 vehicles (Mar 2026)Source 32About 400,000 battery-electric light passenger vehicles on the road (+32% year on year). Battery-electric cars took 7.8% of registrations in Q1 2026.
- Electric cooking
- Not identified from a reliable public source.
Italian homes use little electricity by European standards. Most heat their homes and water with gas, and 83.5% of household connections have a contracted power of 1.5–3 kW. With a standard 3 kW limit, running several large appliances at once can trip the meter, so heat pumps, induction hobs and EV chargers usually need a contract upgrade to 4.5 or 6 kW. Non-resident and second homes are numerous and pull the average consumption per supply point down further.
Demand is increasingly driven by summer cooling. July 2026 set a monthly record of 32.5 TWh (+8.3% year on year), and the annual peak reached about 58 GW on 15 July 2026, during a heatwave. Electric cars are growing from a low base: about 400,000 battery-electric cars were on the road in March 2026. The Conto Termico 3.0 scheme supports heat pumps, but no official count of residential heat pumps or air-conditioned homes was found from a reliable public source.
Housing and households.
- Dwellings
- 35,271,829 dwellings (2021)Source 19Permanent census. 25.69 million (72.8%) are occupied by at least one resident; 27.2% are empty or used only by non-residents.
- Owner-occupied
- 77.1% (2025)Source 16Share of population living in owner-occupied housing (59.9% outright, 17.3% with a mortgage).
- Private rented
- 13.6% (2025)Source 16Share of population renting at market price. A further 9.3% rent at a reduced price or live rent-free.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- 42% (2025)Source 17Share of population living in houses (21.2% detached, 20.7% semi-detached or terraced).
- Apartments and flats
- 57.8% (2025)Source 17Share of population living in flats; 27.2% live in buildings with ten or more dwellings.
- Urban population
- 69.7 % of population (2025)Source 20
Italy has very high home ownership: 77.1% of people live in a home their household owns, and most own it outright. Most people live in flats, typically in condominiums (condomini). This matters for rooftop solar and building upgrades, because shared roofs and façades need a decision by the condominium assembly. Collective self-consumption groups (gruppi di autoconsumatori) let residents of one building share the output of a common system.
Italy also has a large stock of under-used dwellings: more than a quarter of homes are empty or used only by non-residents, especially in the south, the islands and mountain areas. Detached and semi-detached houses, which are common in the north-east and in smaller towns, account for most small rooftop PV and home battery installations.
How the grid works in Italy.
- TransmissionTerna
- Distribution114 distribution companies under concession; e-distribuzione (Enel) carries 85.1% of volumes, and the ten largest serve 98.3% of customers
- MeteringAcquirente Unico – Sistema Informativo Integrato (SII), Distribution companies
- Supply8 or more retail suppliers
Electricity reaches homes in three steps. Large gas-fired, hydro, wind and solar plants feed Terna’s high-voltage network, which is linked to France, Switzerland, Austria, Slovenia, Greece, Montenegro and Malta. In winter, imports from the northern border can exceed 11 GW. At substations, a distribution company takes over and carries power at medium and low voltage to about 37.4 million users. Italy is a structural net importer: domestic production covered about 85% of demand in 2025.
Commercially, the household has a contract only with its supplier. The supplier holds a transport contract with the DSO and a dispatching contract with Terna, either directly or through a balance-responsible party. It buys energy on GME’s markets or bilaterally. Imbalances are settled by Terna using metering data that DSOs send through the SII. The wholesale market is split into bidding zones (Nord, Centro-Nord, Centro-Sud, Sud, Calabria, Sicilia and Sardegna). Since 2025, purchases have been settled at zonal prices rather than one national price.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministero dell’Ambiente e della Sicurezza Energetica (MASE) | Sets energy policy and the national energy and climate plan (PNIEC). Keeps the list of authorised electricity sellers (Elenco Venditori, EVE), authorises large plants and issues incentive decrees such as the CACER, FER X and Conto Termico decrees. |
| Regulator | ARERA | Independent regulator for energy, networks and environment. Sets network tariffs and system charges, connection rules (TICA), dispatching rules (TIDE), metering and smart-meter rules, regulated prices for vulnerable customers, and consumer-protection rules. |
| TSO | Terna | Owns most of the high-voltage grid and is the national system operator. Runs dispatching, the balancing and ancillary-services market (MSD/MBR), the capacity market and MACSE storage auctions. Keeps Gaudì, the national register of generation and storage plants. |
| DSO | e-distribuzione | Enel group distribution company carrying 85.1% of distributed volumes (2024). Owns and reads the Open Meter 2G smart meters in its area and processes connection requests and Modello Unico submissions for small PV. |
| DSO | Other distribution companies | There were 114 DSOs at the end of 2024. Large city and regional operators include Areti (Rome, Acea), Unareti (Milan and Brescia, A2A), Ireti (Turin, Parma and others, Iren), Edyna (South Tyrol), Deval (Aosta Valley) and Inrete (Bologna area, Hera). Many small municipal companies serve the rest. |
| Data hub / registry | Acquirente Unico – Sistema Informativo Integrato (SII) | Central hub created by Law 129/2010. Its Registro Centrale Ufficiale (RCU) lists every withdrawal point (POD) and customer. It runs switching, contract changes and the distribution of settlement and metering data, and feeds the Portale Consumi. |
| Supplier | Venditori (retail suppliers) | There were 769 active electricity sellers in 2025, 710 of them on the free market. Retail sale requires registration in MASE’s Elenco Venditori. The largest groups across the whole market are Enel (22.3%), A2A (10%) and Edison (7.5%). |
| Metering | Distribution companies | Metering is a regulated DSO activity. The local DSO installs, owns and reads the meter and validates the data, which reach suppliers through the SII. |
| Exchange | Gestore dei Mercati Energetici (GME) | Runs the day-ahead (MGP) and intraday markets, coupled with European markets, and publishes zonal prices and the PUN Index GME. |
| Settlement | Gestore dei Servizi Energetici (GSE) | State-owned company that manages renewable incentives, buys exported energy under Ritiro Dedicato, and runs the CACER energy-community scheme and Conto Termico. It is the commercial counterparty for many small producers. |
| Flexibility market | Terna MSD/MBR, capacity market and MACSE | Since TIDE took effect on 1 January 2025, ancillary services are bought from Balancing Service Providers, which can include virtual units that aggregate distributed resources. Terna also runs capacity auctions and MACSE, which awards long-term contracts for new storage. |
Compared with the UK system.
| UK concept | Italy equivalent | How it works |
|---|---|---|
| DNO | Impresa distributrice (e-distribuzione, Areti, Unareti and others) | Distribution is run under state concessions for defined municipalities. One company, e-distribuzione, covers most of the country, while city operators such as Areti in Rome and Unareti in Milan serve large urban areas. The DSO connects customers and generators and is also the meter operator. |
| National Grid / NESO | Terna | Terna owns the transmission network and is also the system operator, so there is no owner/operator split as in Great Britain. It balances the system across seven bidding zones and procures reserves, capacity and long-term storage. |
| MPAN | POD (Point of Delivery / punto di prelievo) | A 14–15 character alphanumeric code starting with “IT”, followed by the distributor’s code, the letter E and the point number. It identifies the physical connection, not the customer, and does not change when the occupant or supplier changes. Unlike the MPAN, it carries no profile class or meter-timeswitch data. |
| MPRN | PDR (Punto di Riconsegna) for gas | Gas supply points have a separate 14-digit PDR code issued by the gas distribution company. It is shown on gas bills and registered in the same SII hub. |
| Meter operator | The DSO (no competitive meter operators) | The local DSO owns, installs, reads and replaces meters under ARERA rules. Customers and suppliers cannot appoint a separate meter operator. |
| Supplier | Venditore | Suppliers must be in MASE’s Elenco Venditori. They bill one amount covering energy, network charges, system charges and taxes, and pass the regulated parts through. Switching runs through the SII and is free. |
| Smart-meter infrastructure (DCC / SMETS2) | DSO-run 2G systems plus the SII data hub | There is no single meter-communications company like the DCC. Each DSO runs its own 2G system (e-distribuzione’s Open Meter, for example) and sends validated readings to the SII, which distributes them to suppliers and Terna. The SII also gives consumers their data through the Portale Consumi. |
How a supply point is identified.
IT001E73920481 (fictional)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Point of Delivery (punto di prelievo) (POD) |
| Who issues it? | The local distribution company (DSO) that owns the network at the address |
| Format | “IT” country code, a three-digit code for the distribution company, the letter “E” for electricity, and a progressive number for the point (typically eight digits; some codes carry an extra character). It identifies the physical delivery point, not the customer or contract. |
| Length | 14 or 15 alphanumeric characters |
| Stays with the property when you switch supplier? | Yes |
| Where to find it | On the first page of every electricity bill under “dati della fornitura”, in the supplier’s online account, and on many electronic meters (cycle through the display screens). The supplier’s customer service can also provide it. |
| Electronic access | Customers can log in with SPID to the free Portale Consumi (consumienergia.it), run by Acquirente Unico under ARERA rules. It shows POD details, contract and technical data, and historical consumption from the SII. Many DSOs also offer their own customer areas with 2G meter data. |
| Third-party access | The current supplier receives metering and contract data through the SII. A new supplier can run a pre-check that matches the POD with the customer’s tax code before switching. Other parties, such as energy-service companies, installers or energy communities, need the customer’s consent and the POD to obtain data or register the point in a configuration. |
| Who keeps the register | The Registro Centrale Ufficiale (RCU) of the Sistema Informativo Integrato, run by Acquirente Unico, lists all national withdrawal points with customer and technical data. Each DSO also keeps the technical records for its own network. |
| Register scope | National |
Every Italian electricity connection has one POD. The distribution company assigns it when the point is first connected, and it stays with that point for its whole life, through changes of occupant, supplier or contract type. The first three digits after “IT” show which distributor runs the network. In the fictional example IT001E73920481, “001” is the distributor code, “E” marks electricity and 73920481 identifies the point.
How it is used
The POD is needed to switch supplier, transfer a contract to a new occupant (voltura), take over an empty dwelling (subentro), change contracted power, register a solar system for Ritiro Dedicato, or include a home in an energy community or self-consumption group. For switching, the new supplier sends the request to the SII with the POD and the customer’s details. The hub checks them against the RCU and the switch takes effect without any action by the old supplier.
Who keeps the data
Unlike France or the UK, Italy has a single national hub. Since 2013 the SII has handled electricity switching and settlement data flows, and its RCU is the official list of every withdrawal point and its current holder. DSOs remain responsible for the meter and its readings, while ARERA sets the processes and data formats.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Yes |
| Net metering | No |
| Net billing | No |
| How exported electricity is paid | Ritiro Dedicato (RID) through GSE. Exported energy is paid at the hourly zonal market price or, for plants up to 1 MW, at least the ARERA minimum guaranteed price: €47.5/MWh for solar in 2026 on the first 1.5 GWh a year. Energy shared within an energy community or self-consumption group can also earn the CACER premium tariff. |
| Is net metering still available? | No, not for new systems. Scambio sul posto closed to plants entering service after 29 May 2025 (ARERA 78/2025/R/efr). Applications for earlier plants had to be made by 26 September 2025. Existing contracts continue until they expire. |
| What are the minimum guaranteed prices for 2026? | For plants up to 1 MW under Ritiro Dedicato: solar €47.5/MWh and wind €59.5/MWh on the first 1.5 GWh a year. Hydro has tiers from €180.9/MWh on the first 250 MWh. ARERA uprated the 2025 values by 1.4%. |
| Which technical rule applies to a home system? | CEI 0-21 for low-voltage connections. The consolidated 2026 edition (valid from August 2026) extends the rules on feed-in limitation systems (SLI). Medium-voltage plants follow CEI 0-16. |
| Is there a simplified route for small solar? | Yes. The Modello Unico was extended to PV up to 200 kW by DM 2 August 2022 n. 297 and ARERA 674/2022/R/efr. New templates came into use on 30 May 2025, after net metering closed. |
| Can a household share solar with neighbours? | Yes. Under DM 414/2023, renewable energy communities, collective self-consumption groups in one building and remote individual self-consumers can receive a 20-year premium on the energy they share. Plants are limited to 1 MW each and the national allocation is 5 GW, available until 31 December 2027. |
Connecting a home system.
- Check the permitting regime under Legislative Decree 190/2024. Most rooftop PV that follows the roof’s pitch is “attività libera” and needs no permit, but protected buildings and areas need a simplified procedure (PAS).
- For PV up to 200 kW, submit Part I of the Modello Unico to the DSO before installation. It acts as the connection request and, if chosen, the Ritiro Dedicato request.
- Have the system installed by a qualified installer to CEI 0-21, including the interface protection system (SPI) and any battery, and get a declaration of conformity under DM 37/2008.
- Submit Part II of the Modello Unico after completion. The DSO registers the plant in Terna’s Gaudì register, installs or reconfigures the bidirectional meter and activates the connection.
- Activate Ritiro Dedicato with GSE, or join a CACER configuration through GSE’s portal, to be paid for exported or shared energy.
Italy has moved from net metering to selling surplus energy. Scambio sul posto, which credited exported energy against later consumption, is closed to new systems. New home solar owners now either sell their surplus to GSE under Ritiro Dedicato or share it within a CACER configuration. GSE pays the hourly zonal price, with a floor for small plants. For solar that floor (€47.5/MWh in 2026) is below typical market prices, so it mainly protects against very low summer midday prices.
Because export is paid at roughly wholesale value while imports cost around 30 c€/kWh, the value of home solar comes mainly from self-consumption. This is why a large share of new residential systems include a battery. Energy communities add a premium of up to €120/MWh on shared energy for plants of 200 kW or less, plus an ARERA payment reflecting avoided network costs.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity | Permitting regime set by Legislative Decree 190/2024. Rooftop PV under 12 MW that follows the roof is attività libera (no permit). Other PV on buildings under 10 MW needs a PAS. Other PV of 1–300 MW needs a regional Autorizzazione Unica, and above 300 MW a state authorisation. | Municipality (PAS), Region or MASE (AU), via the GSE SUER platform | Protected heritage or landscape areas move a project to a stricter regime. All plants must be registered in Terna’s Gaudì register. |
| Self-consume generated electricity | No licence for renewable plants up to 20 kW, whose output is exempt from excise duty. Above 20 kW, an electricity workshop licence (licenza di officina elettrica) and excise returns to the customs agency are required for self-consumed energy. | Agenzia delle Dogane e dei Monopoli (ADM) | This is a tax registration, not an energy-market licence. |
| Store electricity | No separate licence. Batteries connected with PV follow the PV plant’s permitting regime and the CEI 0-21 / 0-16 connection rules. Stand-alone storage is authorised under Legislative Decree 190/2024 according to size and location. | DSO (connection); Municipality, Region or MASE (permit); Terna (Gaudì) | Storage can sell into the energy markets and provide balancing services once registered as a production unit or within a virtual unit. |
| Export to the grid | No licence. Requires a DSO connection (TICA / Modello Unico) and either a Ritiro Dedicato agreement with GSE or a dispatching contract with Terna, normally held through a trader. | DSO, GSE, Terna | Net metering is closed to new plants since 29 May 2025. |
| Sell or supply electricity to final customers | Registration in the Elenco Venditori di Energia Elettrica (EVE) is the enabling title for retail sale. It requires technical, financial and good-repute criteria under DM 25 August 2022 n. 164. | MASE, with ARERA monitoring | Removal from the list ends the right to sign or keep supply contracts. Energy communities sharing energy are not suppliers. |
| Aggregate distributed resources | No licence. An aggregator acts as a Balancing Service Provider (BSP) under TIDE, with a contract with Terna and qualification of each virtual unit (UVA). Under the earlier UVAM pilot each aggregate had to offer at least 1 MW. | Terna under ARERA rules (TIDE, 345/2023/R/eel) | From 1 February 2026 the BSP and BRP roles are fully separated, so an aggregator does not have to be the customer’s supplier. |
| Wholesale trading | Admission as a market participant on the GME markets, plus a dispatching contract with Terna or use of a dispatching user. Under REMIT, traders must also register with ARERA. | GME, Terna, ARERA | Bilateral trades are registered on GME’s PCE platform. |
| Balancing and grid services | Qualification of the unit or virtual unit with Terna as a BSP resource. Units must meet the technical requirements for each product (FCR, aFRR, mFRR/RR, congestion relief). | Terna | Local DSO flexibility is still at pilot stage: Edge (e-distribuzione), RomeFlex (Areti) and MindFlex (Unareti) were renewed for 2026. |
| Virtual power plant / remote control of assets | No specific licence. Remote control is allowed within a qualified virtual unit or a CACER configuration with the owner’s contract. MV PV and wind plants of 100 kW or more must have a Central Plant Controller (CCI) for DSO/Terna curtailment (ARERA 385/2025/R/eel). | Terna, DSO, ARERA | Existing MV plants have until 31 March 2028 to fit the CCI. |
Italy separates energy permitting from market roles. Building and operating a plant falls under Legislative Decree 190/2024, which reduced the many regional procedures to three national regimes: free activity, PAS and single authorisation. Applications go through GSE’s digital platform (SUER). Selling to households requires listing in MASE’s seller register. Aggregation, storage and grid services need no licence, but they do need market qualification with Terna under ARERA’s TIDE rules.
For a typical home system (a few kW of rooftop PV with a battery), there is no permit, no licence and no tax registration. The steps are connection under CEI 0-21 through the Modello Unico, registration in Gaudì by the DSO, and an export or sharing agreement with GSE.
Flexibility and grid services.
Aggregation of home equipment: Yes
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Balancing and redispatch market (MSD / MBR) | Yes | — | Yes | Terna. Under TIDE (in force since 1 January 2025), mFRR, aFRR, replacement reserve and congestion management are open, technology-neutral, to qualified units and virtual units, including demand, storage and small generation. |
| Frequency Containment Reserve (FCR) | Developing | — | Yes | Terna. TIDE version 4 (ARERA 227/2025/R/eel) introduced market-based FCR procurement, with auctions starting from the consolidation phase on 1 February 2026. |
| Capacity market | Yes | — | Yes | Terna. Auctions of reliability options for future delivery years. Demand response and storage can take part. Capacity costs are passed to consumers and rose in Q3 2026 because of July “critical hours”. |
| MACSE long-term storage contracts | Yes | Utility-scale projects | No | Terna. The first auction, on 30 September 2025, awarded 10 GWh of new storage in the south and the islands, for delivery in 2028, at a weighted average of €12,959/MWh-year, against a reserve price of €37,000. It was more than four times oversubscribed. |
| Flexible withdrawal modulation service | Yes | — | Yes | Terna. Pilot service extended for 2026 (ARERA 564/2025/R/eel) to pay for increases as well as reductions in consumption, absorbing surplus renewable output at low-demand times. |
| Local DSO flexibility | Developing | — | Yes | e-distribuzione, Areti, Unareti. Pilot local ancillary-service markets renewed for 2026: Edge (e-distribuzione), RomeFlex (Areti, Rome) and MindFlex (Unareti, Milan). |
Italy has opened its balancing markets to distributed resources in stages. The UVAM pilot, launched under ARERA 300/2017/R/eel, first let aggregated loads, small generators and batteries offer balancing in aggregates of at least 1 MW. TIDE replaced it from 2025 with a permanent framework. Balancing Service Providers offer services from qualified units or virtual units, separately from the balance-responsible party that schedules energy. Full separation of these roles began on 1 February 2026.
Home batteries are numerous: almost all of the 948,154 storage systems are small units coupled with PV. However, most are not yet aggregated into markets, and energy communities are the most common way households take part collectively. The settlement reform to 15-minute energy accounting, which matters for flexibility, has been postponed to 1 January 2027.
Flexibility and aggregation platforms.
| Platform or aggregator | What it does |
|---|---|
| Terna – Mercato dei servizi di dispacciamento | Rules, qualification of units and virtual units, and auction results. |
| GME | Day-ahead and intraday energy markets and the PUN Index GME. |
| GSE – CACER portal | Registration of energy communities and self-consumption groups that receive the shared-energy premium. |
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | Second national rollout (2G) under way, after almost universal first-generation remote reading from the 2000s |
| Reading interval | 15 minutes (2G meters) |
| Responsible party | The local DSO (regulated activity) |
| 2G meters installed | About 34.8 million installed by the ten DSOs with over 100,000 points (end-2023), with a stock of about 32.7 million |
| Regulatory framework | ARERA functional specifications for 2G meters and rollout plans (PMS2) with cost-recognition rules (306/2019/R/eel, updated by 724/2022/R/eel) |
| Main system | e-distribuzione Open Meter |
| Data hub | SII (Acquirente Unico); consumer access through the Portale Consumi |
| Customer device link | A dedicated channel from 2G meters to in-home devices (“Chain 2”) for near-real-time data |
Italy was among the first countries to install remotely read meters for almost every household. Enel’s Telegestore programme began in the early 2000s, and other DSOs followed under ARERA obligations. The current second-generation (2G) rollout replaces those meters with devices that record 15-minute data and can send it to customer devices, with its timetable and costs set by ARERA plans for each DSO.
Meters belong to the DSO, not the supplier, so changing supplier never means changing meter. The DSO collects and validates readings and sends them to the SII, which distributes them to suppliers and to Terna for settlement. Customers can see their data through the Portale Consumi or the DSO’s portal. ARERA reported that the ten largest DSOs had installed about 34.8 million 2G meters by the end of 2023, and ARERA’s 2019 rules set the end of the massive replacement phase at 2026.
Renewable electricity.
Electricity generation mix (2025 (provisional, net generation)).
- Natural gas and other fossil thermal: 50.1%
- Solar: 16.5%
- Hydro: 15.4%
- Wind: 8%
- Bioenergy: 5.8%
- Geothermal: 2%
- Coal: 1.1%
- Pumped storage: 0.6%
- Battery storage (stand-alone): 0.5%
- Renewable electricity share
- 47.7% (2025)Source 12Derived from Terna’s provisional 2025 balance: 127,978 GWh of renewable generation out of 268,496 GWh of total net generation. Measured against total demand, including imports, renewables covered 41.1%. ARERA reports 48% of gross production.
- Home solar
- 1.245 GW added in 2025 (systems up to 20 kW) (2025)Source 23Residential additions are falling: 556 MW in H1 2026 against 725 MW in H1 2025 (−23%, Italia Solare). No reliable cumulative residential total was identified.
- Solar added each year
- 6.437 GW (2025)Source 12Net change in operating capacity (Terna). ANIE Rinnovabili reports 5.6 GW of new installations on a different basis.
- Solar PV
- 47.3 GW (31 Jul 2026)Source 13
- Wind
- 14 GW (31 Jul 2026)Source 13
- All renewables
- 87.7 GW (31 Jul 2026)Source 13
- Hydro
- 21.4 GW (end 2025)Source 23ANIE Rinnovabili, based on Terna Gaudì data.
- Bioenergy
- 5.1 GW (end 2025)Source 23
Targets.
- PNIEC (2024): about 131 GW of renewable capacity by 2030 (ANIE Rinnovabili calculation from the plan), including about 28 GW of wind.
- Legislative Decree 199/2021 and 190/2024: transpose RED II and accelerate permits through “suitable areas” (aree idonee) and the SUER platform.
- CACER: 5 GW of new renewable capacity in energy-sharing configurations by 31 December 2027.
- MACSE: long-term contracts for new storage, starting with 10 GWh for delivery in 2028.
Natural gas remains the backbone of Italian generation, at 45.7% of production in 2025 according to ARERA. Renewables produced 47.7% of net generation, but output fell in 2025 because hydro dropped by about 21% in a dry year, while solar output rose by about 25%. Coal is now marginal at about 1% of generation. Hydro and geothermal give Italy a long-established renewable base in the Alps and Tuscany.
Solar is the growth engine. Capacity grew by 6.4 GW in 2025 and 3.8 GW in the first seven months of 2026, and output reached 44.3 TWh in 2025. Growth has shifted from homes to commercial and utility-scale plants: residential additions fell to 1.2 GW in 2025 and 556 MW in H1 2026 as tax incentives were reduced. Wind has grown slowly (+0.6 GW in 2025) because of long permit processes, and Italy is behind its PNIEC path.
Energy storage.
- Home batteries
- 11.9 GWh (30 Jun 2026)Source 22Capacity of storage coupled with PV plants (all sizes, mostly residential). 914 MWh was added in H1 2026, of which 651 MWh in systems up to 20 kW.
- Grid-scale storage
- 7.336 GWh (30 Jun 2026)Source 22Stand-alone storage.
Italy has one of Europe’s largest fleets of small batteries. At the end of July 2026 there were 948,154 systems with 19.43 GWh of capacity and 8.0 GW of power. Most are home batteries installed with rooftop PV, encouraged by tax relief and by the gap between import prices and export payments. Stand-alone grid-scale storage is now growing quickly: its output rose from 131 GWh in 2024 to 1,459 GWh in 2025.
The next phase is driven by Terna’s MACSE mechanism, which gives new storage long-term capacity-style payments in the zones where solar surplus is largest. Storage can also earn revenue on the capacity market, in balancing under TIDE, and from wholesale price spreads on GME.
Storage projects.
- MACSE first auction (Terna): 10 GWh of lithium-ion storage in the Centro-Sud, Sud and Calabria, Sicily and Sardinia zones, for delivery in 2028.
- Pumped hydro fleet: Existing pumped-storage plants produced 1.6 TWh in 2025 (Terna provisional balance).
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Enel Energia | Enel group 22.3% of total electricity sales (2025) | Yes | Yes | Limited | No |
| A2A Energia | A2A group 10% of total electricity sales (2025) | Yes | Yes | Limited | No |
| Edison Energia | Edison group 7.5% of total electricity sales (2025) | Yes | Yes | Limited | No |
| Plenitude (Eni) | — | Yes | Yes | Limited | No |
| Hera Comm | — | Yes | Yes | Limited | No |
| Iren Luce Gas e Servizi | — | Yes | Yes | Limited | No |
| Acea Energia | — | Yes | Yes | Limited | No |
| Sorgenia | — | Yes | Yes | Limited | No |
The retail market is crowded but concentrated at the top: 769 sellers were active in 2025, and the three largest groups (Enel, A2A and Edison) held 38.6% of total sales. Enel’s share has fallen steadily, from 33.5% in 2023 to 22.3% in 2025. Household switching remained high at 20.8% of customers in 2025, partly because the end of maggior tutela prompted many to compare offers.
Suppliers do not normally buy exported solar power: households sell it to GSE under Ritiro Dedicato or share it in an energy community. “Smart meters: Yes” means the supplier’s customers have DSO-owned electronic meters and billing on actual readings, not that the supplier owns them. Time-band (F1/F23) pricing is offered widely. Hourly dynamic offers are less common, although larger suppliers must offer them on request under Legislative Decree 210/2021.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Ministero dell’Ambiente e della Sicurezza Energetica (MASE) | Government | Energy ministry | Publishes the PNIEC, incentive decrees and the seller register (EVE). |
| ARERA | Regulator | Energy, networks and environment regulator | Source for tariffs, connection rules, consumer prices and market reports. |
| Terna | Transmission | TSO and system operator | Grid data, monthly system reports, Gaudì, capacity market and MACSE. |
| e-distribuzione | Distribution | Largest DSO | Connections, Modello Unico submissions and Open Meter data for most of Italy. |
| GME – Gestore dei Mercati Energetici | Market | Power exchange | Zonal prices, PUN Index GME and market rules. |
| Acquirente Unico | Metering | SII data hub and Portale Consumi | Runs the national register of withdrawal points and consumer access to consumption data. |
| GSE – Gestore dei Servizi Energetici | Renewable Energy | Incentives and Ritiro Dedicato | Manages RID, CACER energy communities, Conto Termico and the SUER permit platform. |
| Italia Solare | Solar | Solar and storage association | Quarterly statistics on PV and storage connections based on Terna data. |
| Elettricità Futura | Renewable Energy | Electricity industry association | Represents generators, renewable developers and suppliers. |
| ANIE Rinnovabili | Storage | Manufacturers’ association for renewables and storage | Publishes the Osservatorio FER on installations by technology and size. |
| RSE – Ricerca sul Sistema Energetico | Flexibility | Public energy-system research company | Research on flexibility, distributed resources and network integration. |
| Sportello per il Consumatore Energia e Ambiente | Consumer | ARERA consumer helpdesk (run by Acquirente Unico) | Complaints, conciliation and information for household energy customers. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Grid connection (low voltage) | CEI 0-21:2026-07 | Comitato Elettrotecnico Italiano (CEI) | Reference technical rule for active and passive users on LV networks. The consolidated 2026 edition replaces the 2022 edition and its variants and extends the rules on feed-in limitation systems (SLI). |
| Grid connection (medium/high voltage) | CEI 0-16 | CEI | Rule for connecting users to HV and MV networks; variant V5 published October 2025. |
| Inverters and anti-islanding | CEI 0-21 interface protection (SPI) and CEI EN 50549-1 | CEI / CENELEC | Inverters must have type-tested interface protection to CEI 0-21. Plants are registered in Gaudì with their protection data. |
| Connection procedure | TICA (Testo Integrato Connessioni Attive) | ARERA | Sets timelines and fees for generator connections, including the Modello Unico for PV up to 200 kW. |
| Remote curtailment | Central Plant Controller (CCI), ARERA 385/2025/R/eel | ARERA / Terna | Required on MV-connected PV and wind plants of 100 kW or more, replacing GSM/GPRS devices. Existing plants have until 31 March 2028. |
| Installer qualification | DM 22 January 2008 n. 37 | Ministry (now MIMIT) | Electrical work must be carried out by a qualified firm, which issues a declaration of conformity (dichiarazione di conformità) for the installation. |
| Smart meters | ARERA 2G functional specifications | ARERA | 15-minute measurement and data provision to customers’ devices. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Building permit for rooftop PV | No | National | Attività libera under Legislative Decree 190/2024, Annex A, for rooftop PV that follows the roof’s pitch and orientation and does not extend beyond the roof. No communication to the municipality is needed. |
| Heritage or landscape consent | Limited | Mixed | Buildings and areas protected under the cultural heritage and landscape code, and Natura 2000 or protected natural areas, move the project to a PAS or stricter procedure. |
| DSO connection approval | Yes | National | Every exporting or grid-parallel system needs a connection under TICA. For PV up to 200 kW, this is done through the two-part Modello Unico. |
| Condominium approval | Limited | Local | Systems on shared roofs of apartment buildings need the agreement of the condominium assembly. |
| Customs (excise) registration | Limited | National | Only for renewable plants above 20 kW that self-consume, which need an officina elettrica licence from ADM. |
| Ground-mounted or large PV | Yes | Regional | PAS at the municipality, or Autorizzazione Unica from the Region (1–300 MW) or the State (above 300 MW), submitted through SUER. |
For a home on a normal roof in an unprotected area, there is no building permit. The paperwork is the Modello Unico submitted to the DSO, the installer’s declaration of conformity, and the GSE agreement for selling or sharing exported energy. Regions still influence larger projects through their “suitable area” rules and their role in single authorisations.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Bonus ristrutturazioni (home renovation tax credit) | Active | Income-tax deduction | For 2026, a deduction of 50% for the main home and 36% for other homes, on up to €96,000 per dwelling, spread over 10 years. It covers PV and batteries as energy-saving works. In 2027 it falls to 36% for the main home and 30% for other homes. | 2026 (reduced rates scheduled for 2027) |
| Ritiro Dedicato (GSE) | Active | Export payment | GSE buys exported energy at the hourly zonal price, with a 2026 minimum guaranteed price of €47.5/MWh for solar plants up to 1 MW on the first 1.5 GWh a year. | — |
| CACER – energy communities and self-consumption (DM 414/2023) | Active | Premium tariff | 20-year premium on shared energy: a fixed part of €60–80/MWh depending on plant size, plus a variable part of up to €40/MWh when zonal prices are low (caps of €100–120/MWh). It also includes an ARERA payment for avoided network costs. Plants must be up to 1 MW and new since 16 December 2021, with a 5 GW allocation. | Until 31 Dec 2027 or until 5 GW is reached |
| PNRR capital grant for energy communities | Active | Grant | Up to 40% of eligible costs for CACER plants in municipalities with fewer than 50,000 inhabitants. The budget was cut to €795.5 million in November 2025 against 48,750 applications (3.3 GW). Concession agreements had to be signed by 30 June 2026, and new applications are effectively closed. | 2024–2026 |
| Conto Termico 3.0 | Active | Grant | Grants for heat pumps, solar thermal and building efficiency (DM 7 August 2025). The GSE portal opened on 2 February 2026, was suspended on 3 March after about €1.3 billion of applications, and reopened for direct applications from all beneficiaries on 13 April 2026. | — |
| Scambio sul posto (net metering) | Closed | Net metering | Closed to plants entering service after 29 May 2025. Existing contracts continue until they expire. | Closed to new plants from 30 May 2025 |
Data and connectivity.
- Fixed broadband
- 77.6 % of households (FTTP coverage) (2025)Source 33Fibre-to-the-premises coverage; EU average 74.13%.
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- 99.8 % coverage (2025)Source 33Basic 5G coverage; EU average 96.79%.
Smart-meter data travels over the DSOs’ own systems, mainly power-line communication from the meter to the concentrator, with mobile or fibre backhaul, and not over the customer’s broadband. Home batteries, inverters and EV chargers usually connect to manufacturers’ clouds over home Wi-Fi or cellular links. Medium-voltage plants are moving to the Central Plant Controller standard for remote curtailment. Italy’s near-universal 5G and fast-growing fibre coverage support remote monitoring and aggregation of distributed assets.
Grid conditions.
- National peak demand
- 58 GW (15 Jul 2026)Source 13About 58 GW, 4.5% above the 2025 peak, during a heatwave.
- Annual electricity demand
- 311.3 TWh (2025)Source 12Provisional (311,324 GWh), −0.2% on 2024. Demand rose 5% in January–August 2026.
- Generation capacity
- Not identified from a reliable public source.
- Interconnection
- 11.2 GW (2023 (winter))Source 11Total import capacity in winter (11,235 MW; 9,705 MW in summer). Export capacity is about 5.7 GW.
- Curtailment
- Not identified from a reliable public source.
The Italian grid runs mainly from north to south, which creates internal bottlenecks between bidding zones. The south and the islands have the most solar and wind, while demand is concentrated in the north. In 2025, about 15% of demand was met by imports, mostly across the northern border from France and Switzerland.
The main stresses are summer peaks from air conditioning, record midday solar output that pushes prices down at weekends and on holidays, and the need for more storage and network capacity in the south. Terna’s response includes MACSE storage auctions, interconnector and HVDC projects, and the flexible withdrawal modulation service that pays consumers to increase demand when renewable output is in surplus.
Grid and capacity maps.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Net metering closed to new plants | Current | 30 May 2025 | New systems sell surplus energy through Ritiro Dedicato or share it in CACER configurations. Existing SSP contracts continue until they expire. |
| TIDE dispatching reform | Current | 1 Jan 2025; consolidation 1 Feb 2026 | Technology-neutral balancing markets open to BSPs and virtual units, with separate BSP and BRP roles and market-based FCR from 2026. |
| PUN replaced by PUN Index GME | Current | 1 Jan 2025 | Purchases on the day-ahead market are settled at zonal prices with an equalisation component. The national reference for retail offers is now the PUN Index GME. |
| Single law on renewable permitting | Current | 30 Dec 2024 | Legislative Decree 190/2024 introduced three regimes (free activity, PAS, single authorisation) and the GSE SUER digital platform. |
| New CEI 0-21 edition | Current | Aug 2026 | The consolidated 2026 edition of the LV connection rule extends the requirements for feed-in limitation systems. |
| Quarter-hourly settlement | Upcoming | 1 Jan 2027 | Settlement reform with 15-minute energy accounting and new rules for residual energy and losses, postponed from earlier dates by ARERA 430/2025/R/eel. |
| End of the Servizio a Tutele Graduali | Upcoming | 31 Mar 2027 | The current assignment period for households placed in the STG ends. Vulnerable customers remain eligible for maggior tutela. |
| Lower home-renovation tax rates | Upcoming | 1 Jan 2027 | Bonus ristrutturazioni falls to 36% for the main home and 30% for other homes, which affects the payback on home PV and batteries. |
| Central Plant Controller retrofit deadline | Upcoming | 31 Mar 2028 | Existing MV-connected PV and wind plants of 100 kW or more must fit the CCI for remote curtailment. |
| First MACSE storage enters service | Upcoming | 2028 | 10 GWh of storage contracted in the September 2025 auction is due to start delivery. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | High | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | Low | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | Medium | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | High | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | High | 2.26 million PV plants and 46.6 GW at mid-2026 (Italia Solare/Terna), with 1.2 GW of systems up to 20 kW added in 2025, although residential additions fell 23% in H1 2026 and net metering has closed. |
| Distributed energy market | Medium | Almost 950,000 small battery systems and CACER energy-sharing configurations, but low household electrification (mostly 3 kW contracts, gas heating) and about 400,000 battery-electric cars. |
| Grid flexibility market | Medium | TIDE opened balancing markets to aggregated virtual units from 2025, with a capacity market, MACSE storage contracts and demand modulation, but FCR auctions and local DSO markets are still being phased in. |
| Energy storage adoption | High | 19.43 GWh and 8.0 GW of electrochemical storage at the end of July 2026 (Terna), mostly coupled with PV, plus 10 GWh awarded in the first MACSE auction. |
| Renewable growth environment | Medium | 7.2 GW of renewable capacity added in 2025, almost all solar, but wind growth was slow (+0.6 GW), renewable output fell in a dry year, and capacity is behind the PNIEC 2025 path. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 33 sources
- Elettricità: Maggior Tutela +4,6% nel III trimestre 2026 per i clienti vulnerabili. ARERA, 2026. accessed 1 October 2026.
- ARERA in breve: Relazione Annuale sullo stato dei servizi 2025. ARERA, 2026. accessed 1 October 2026.
- Summary of the Annual Report on the State of Services 2024. ARERA, 2025. accessed 1 October 2026.
- Smart metering – area operatori. ARERA. accessed 1 October 2026.
- Sistema Informativo Integrato (SII). ARERA. accessed 1 October 2026.
- Glossario della bolletta – POD. ARERA. accessed 1 October 2026.
- Cosa sono i prezzi per fasce?. ARERA. accessed 1 October 2026.
- Aggiornamento dei prezzi minimi garantiti per l’anno 2026. ARERA, 2026. accessed 1 October 2026.
- Deliberazione 674/2022/R/efr – Modello unico per impianti fotovoltaici fino a 200 kW. ARERA, 2022. accessed 1 October 2026.
- Superamento del prezzo unico nazionale e relativa componente perequativa. ARERA. accessed 1 October 2026.
- Capacità di interconnessione con l’estero. ARERA, 2023. accessed 1 October 2026.
- Rapporto mensile sul sistema elettrico – dicembre 2025. Terna, 2026. accessed 1 October 2026.
- A luglio consumi elettrici sostenuti dalle temperature elevate: +8,3% rispetto al 2025. Terna, 2026. accessed 1 October 2026.
- Terna, conclusa la prima asta MACSE: assegnati 10 GWh di capacità di accumulo. Teleborsa (Terna press release), 2025. accessed 1 October 2026.
- Electricity prices for household consumers – bi-annual data (nrg_pc_204). Eurostat, 2026. accessed 1 October 2026.
- Distribution of population by tenure status (ilc_lvho02). Eurostat, 2025. accessed 1 October 2026.
- Distribution of population by dwelling type (ilc_lvho01). Eurostat, 2025. accessed 1 October 2026.
- Indicatori demografici – Anno 2025. ISTAT, 2026. accessed 1 October 2026.
- Censimento permanente 2021: caratteristiche delle abitazioni. ISTAT, 2024. accessed 1 October 2026.
- Urban population (% of total population) – Italy. World Bank, 2025. accessed 1 October 2026.
- Electric power consumption (kWh per capita) – Italy. World Bank, 2024. accessed 1 October 2026.
- Fotovoltaico e accumuli: nel primo semestre 2026 connessi 3,1 GW di nuova potenza solare e 1,35 GWh di storage. Italia Solare, 2026. accessed 1 October 2026.
- Osservatorio FER 2025: installazioni in calo per fotovoltaico ed eolico (ANIE Rinnovabili). Infobuildenergia, 2026. accessed 1 October 2026.
- Ritiro dedicato. GSE. accessed 1 October 2026.
- CACER: bilancio e prospettive alla luce della revisione del PNRR. GSE (Unioncamere), 2026. accessed 1 October 2026.
- Fonti rinnovabili, nuovi regimi amministrativi e procedure digitali di autorizzazione. ANCE, 2024. accessed 1 October 2026.
- Elenco Venditori di Energia Elettrica – decreto direttoriale e indicazioni operative. MASE, 2023. accessed 1 October 2026.
- Agevolazioni per le ristrutturazioni edilizie. Agenzia delle Entrate, 2026. accessed 1 October 2026.
- Conto Termico 3.0, ufficiale la riapertura dello sportello GSE dal 13 aprile 2026. Edotto, 2026. accessed 1 October 2026.
- CEI 0-21 – Regola tecnica di riferimento per la connessione di utenti attivi e passivi alle reti BT. CEI, 2026. accessed 1 October 2026.
- Imposte sulle forniture di energia elettrica. Enel Energia. accessed 1 October 2026.
- Libro Bianco 2026 sulla mobilità elettrica. Motus-E, 2026. accessed 1 October 2026.
- Digital Decade: Italy above EU average on public services, 5G, eHealth and fibre connectivity. Dipartimento per la trasformazione digitale, 2026. accessed 1 October 2026.
Questions about energy in Italy.
ARERA’s reference price for a typical vulnerable household in maggior tutela was 31.63 c€/kWh including taxes from 1 July 2026, about €592 a year for 2,000 kWh. Most households are on free-market offers. Eurostat put the average price for mid-sized households at €0.2966/kWh in the second half of 2025.
The POD (Point of Delivery) code. It has 14–15 characters starting with “IT”, followed by the distributor’s code, the letter E and the point number, for example IT001E73920481 (fictional). It is printed on every bill, stays with the connection when you move or switch supplier, and is registered in the national SII hub run by Acquirente Unico.
Yes. Since net metering closed to new systems on 29 May 2025, surplus energy is sold to GSE under Ritiro Dedicato at the hourly zonal price, with a 2026 floor of €47.5/MWh for solar plants up to 1 MW. Alternatively, it can be shared within an energy community for a 20-year premium of up to €120/MWh.
It ended for non-vulnerable households on 1 July 2024. Those who had not chosen a supplier were moved to the Servizio a Tutele Graduali, which runs until 31 March 2027. Vulnerable customers, including people over 75, social-bonus recipients and people with disabilities, can still choose maggior tutela.
Usually not. Under Legislative Decree 190/2024, rooftop PV that follows the roof’s pitch is free activity with no permit or communication, unless the building or area is protected. You still need a DSO connection, which for systems up to 200 kW is done through the Modello Unico.
Terna owns the transmission network and runs the national system. Distribution is handled by 114 companies, led by e-distribuzione (Enel), which carries 85.1% of volumes, with Areti in Rome, Unareti in Milan and Brescia and others in their concession areas. ARERA regulates all of them.
The home renovation deduction (bonus ristrutturazioni) gives 50% for the main home and 36% for other homes, on up to €96,000 per dwelling over 10 years. From 2027 these rates are scheduled to fall to 36% and 30%.