Energy-market overview

How electricity works in Austria.

Austria electricity market 2026: E-Control, APG, 117 DSOs, the 33-character Zählpunkt, smart meters, ElWG reform, energy communities, PV grants and export rules.

This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Euro (EUR) where they relate to prices.

Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.

At a glance

Austria energy at a glance.

Key figures for households in Austria. Each one links to its source on the full overview below.

  • Electricity price.

    0.327 EUR per kWh for households, including taxes. Figures for 2025-H2.

  • Household use.

    5,204 kWh a year for a typical household. Figures for Jul 2023–Jun 2024.

  • Renewable share.

    82.3% of electricity from renewable sources. Figures for 2025.

  • Selling back to the grid.

    Can homes export electricity? Yes. Details are in the export section below.

Before you start

Four things to check in Austria.

Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.

  1. Check the local rules.

    Read the connection, export and permission rules for Austria below, and ask your local grid operator if anything is unclear.

  2. Choose a qualified installer.

    Look for an installer listed on an official register, with the certifications Austria requires for the work.

  3. Look at current schemes.

    Check which support schemes are open now. Closed or scheduled schemes are labelled as such.

  4. Talk to your energy supplier.

    Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.

Local detail

Schemes, rules and certifications in Austria.

The full detail sits in the sections below. Each item shows its status and links to the official source.

  • Support schemes.

    Grants, tax relief and export payments in Austria, each labelled Active, Scheduled or Closed.

  • Connection and export.

    How equipment is connected to the grid in Austria, and the steps to export electricity.

  • Standards and certifications.

    The technical standards and installer certifications that apply to energy equipment in Austria.

Full overview

The energy market in Austria, in detail.

Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.

Profile last updated 1 October 2026.

On this page22 sections

Austria has a liberalised electricity market regulated by E-Control. Households can choose their supplier but not their network operator: the transmission grid is run by Austrian Power Grid (APG), and more than 100 distribution network operators (117 of them obliged to roll out smart meters) run regional and local networks, most of them owned by the nine Länder utilities or by municipal companies.

Electricity is largely renewable. Hydropower supplied 50.7% of generation in 2025, a dry year, and renewables 82.3% overall, with solar (13.4%) overtaking wind (11.7%) for the first time. Eurostat put the average household price at €0.327/kWh including taxes in the second half of 2025, above the EU average of €0.290/kWh.

The market is being reshaped by the Elektrizitätswirtschaftsgesetz (ElWG), Austria’s new electricity law, in force since 24 December 2025. It introduced a social tariff from April 2026, a right for network operators to cap PV feed-in, a controllability requirement for new generators, new rules for energy communities from October 2026, a levy on feed-in from 2027 and a new network-tariff structure from 2027. Smart meters, which record 15-minute values, reached 96.9% of metering points by the end of 2024, and Austria has more than 10,000 energy communities.

Energy snapshot.

Headline figures for electricity in Austria. Each shows its data year and links to its source.

  • Population9,215,956 peopleSource 11 Jan 2026
  • Households4,182,100 private householdsSource 22025
  • Average household size2.16 people/householdSource 22025
  • Electricity use per household5,204 kWh/yrSource 4Jul 2023–Jun 2024
  • Household price (EUR)0.327 EUR/kWhSource 32025-H2
  • Renewable electricity share82.3%Source 102025
  • Solar capacity9.94 GWSource 10end 2025
  • Wind capacity4.22 GWSource 10end 2025
  • Energy storage capacity6 GW (pumped hydro, approx.)Source 11end 2025
  • Smart-meter share96.9%Source 15end 2024
Market structure
Fully liberalised
Homes can export to the grid
Yes
Home equipment in grid services
Developing
Regulator
Energie-Control Austria (E-Control)
System operator
Austrian Power Grid (APG)
Distribution networks
Over 100 regional and local DSOs (117 with smart-meter duties), led by the nine Länder network companies and city utilities
Currency
Euro (EUR)
Voltage and frequency
230 V / 50 Hz

Electricity prices in Austria.

Household price (EUR)
0.327 EUR/kWh (2025-H2)Source 3Eurostat household price, consumption band 2,500–4,999 kWh, all taxes and levies included. The 2026 cut in electricity tax for households (from 1.5 to 0.1 c/kWh) is not yet in this figure.
Typical annual electricity bill
Not identified from a reliable public source.

Household price trend (EUR per kWh).Source 3

0.2030.2650.3272019-H12025-H2
Austria household electricity price, EUR per kWh
2019-H10.2034 EUR/kWh
2019-H20.2074 EUR/kWh
2020-H10.2111 EUR/kWh
2020-H20.2167 EUR/kWh
2021-H10.2216 EUR/kWh
2021-H20.2285 EUR/kWh
2022-H10.2249 EUR/kWh
2022-H20.237 EUR/kWh
2023-H10.2653 EUR/kWh
2023-H20.2748 EUR/kWh
2024-H10.2731 EUR/kWh
2024-H20.2437 EUR/kWh
2025-H10.2905 EUR/kWh
2025-H20.3272 EUR/kWh

Three blocks on the bill

An Austrian electricity bill has three parts. The energy price (a unit rate in c/kWh and often a fixed monthly fee) is set by the supplier. Network charges are set by E-Control for each network area and paid to the local DSO; they make up roughly a third of a household bill. Taxes and levies make up the rest: electricity tax (Elektrizitätsabgabe), the renewables support contribution and flat fee, municipal use fees (Gebrauchsabgabe) in some areas, and 20% VAT.

Taxes and levies in 2026

For 2026 the electricity tax for households was cut from 1.5 c/kWh to 0.1 c/kWh, saving a household about €50 a year according to the Parliament’s budget office. The cut is temporary and ends at the end of 2026. The renewables support contribution (Erneuerbaren-Förderbeitrag) was set at 7.32% of network usage and loss charges for 2026, about 22% lower for households than in 2025.

Network charges

Network charges rose sharply in January 2025, when E-Control began to include planned grid investment and falling low-voltage volumes caused by self-consumption. For 2026 household network charges rose by only about 1.3% on average, but with big regional differences: +15.9% in Burgenland, +10.9% in Tyrol and +6.9% in Lower Austria, while Salzburg fell by about 9% and Vienna, Styria, Carinthia and Vorarlberg fell slightly. The annual flat network fee for network-level-7 customers without demand metering rose from €48 to €54, and the old summer/winter split was abolished.

Prices and competition

Retail prices fell back during 2025 after the 2022–2023 crisis peak, when new-customer offers reached 65 c/kWh. In December 2025 the median new-customer energy price in the E-Control tariff calculator was about 16 c/kWh (energy only), and the weighted average of the main products of the 13 largest incumbent suppliers was about 14 c/kWh. Up to 40 suppliers were active nationwide, still below the pre-crisis 56. Incumbents keep high market shares in their home areas, and 5.4% of electricity customers switched in 2025. E-Control estimated the average maximum saving from switching at about €460 a year.

Trend

Eurostat’s all-in household price rose from about €0.20/kWh in 2019 to €0.27 in 2023. It dipped in the second half of 2024 and then rose to €0.327/kWh in the second half of 2025, after the federal electricity price brake (Strompreisbremse) expired at the end of 2024 and network charges rose in January 2025.

Tariff types.

Tariff types.
TariffAvailableDetail
FixedYesFixed-price products, with or without a price guarantee, made up about 90% of household contracts in April 2025 (E-Control price monitoring). Many now fix the price for 12 months and then switch to a monthly floating price.
VariableYesMonthly "floaters" adjust the energy price each month by a published formula linked to wholesale prices; just over 6% of household contracts in April 2025.
DynamicYesSpot-market products pass through day-ahead exchange prices plus a margin. Since the switch to quarter-hour exchange prices on 1 October 2025 some products change every 15 minutes. About 18 spot products were listed in the E-Control tariff calculator at the end of 2025; about 1% of households used one in April 2025. ElWG §22 gives customers a right to a dynamic contract.
Time-of-useYesSupplier time-of-use products covered just over 3% of household contracts in April 2025. Separately, the network tariff has a summer low-load rate from April 2026 (20% lower network energy price 10:00–16:00, April–September) for customers with quarter-hour data.
RegulatedLimitedEnergy prices are not regulated, but network charges are set by E-Control in the System Charges Ordinance (SNE-V). From April 2026 eligible low-income households get a social tariff: 6 c/kWh net for the first 2,900 kWh a year.
PrepaymentLimitedElWG §29 gives customers a right to use a prepayment meter function.

Household prices compared with neighbouring countries (EUR per kWh).

Household prices including taxes, converted to euros as stated on each country page.

Household electricity use.

Electricity use per household
5,204 kWh/yr (Jul 2023–Jun 2024)Source 4Derived: total household electricity use of 77,531 TJ (21,536 GWh) in the Statistik Austria microcensus divided by 4,138,794 main-residence dwellings. Includes electric heating, hot water and heat pumps, so a typical home without electric heating uses much less. The Rechnungshof uses a 3,500 kWh model household.
Average daily use per household
14.3 kWh/day (Jul 2023–Jun 2024)Source 4Derived from the 5,204 kWh per-dwelling average divided by 365; includes electric heating and hot water.
Typical household peak demand
Not identified from a reliable public source.
Electricity use per person
7,760 kWh/person/yr (all sectors) (2025)Source 10Derived: domestic electricity consumption of 71,516 GWh (excluding pumped storage) divided by the population of 9,215,956.
Heat pumps
536,963 heat pumps in operation (2024)Source 48All types, +9.7% on 2023; 55,367 installed in 2024. In the 2023/24 microcensus, 591,874 main-residence homes (14.3%) were heated mainly by heat pumps or solar.
Air conditioning
414,538 air-conditioning units in households (Jul 2023–Jun 2024)Source 5Number of units, not homes. Up from 314,572 in 2021/22 and 210,102 in 2019/20. 414,538 units against 4.14 million dwellings is about 10%.
Electric vehicles
257,717 battery-electric cars (31 Dec 2025)Source 84.9% of 5.29 million cars, +28.5% in a year. Electric cars took 21.3% of new registrations in 2025 (60,651).
Electric cooking
Not identified from a reliable public source.

Austrian households used 77,531 TJ (about 21.5 TWh) of electricity in the year to June 2024, according to the Statistik Austria microcensus on household energy use, which is carried out every two years. That works out at roughly 5,200 kWh per main-residence dwelling, but the average hides a wide spread: 6.2% of homes are heated mainly by direct electric heating and 14.3% by heat pumps (or solar), while most homes use district heating (32.2%), gas (20.4%), wood (16.2%) or heating oil (10.7%).

Electrification is under way. About 537,000 heat pumps were in operation in 2024, battery-electric cars reached 257,717 at the end of 2025, and the number of household air-conditioning units roughly doubled between 2019/20 and 2023/24 to about 415,000.

National electricity consumption rose by 2.3% to 71.5 TWh in 2025 (excluding pumped-storage pumping). E-Control notes that consumption has stopped falling after the crisis years, which spreads network costs over similar volumes.

Housing and households.

Dwellings
4,138,794 main-residence dwellings (Jul 2023–Jun 2024)Source 5Dwellings with a registered main residence in the household energy microcensus. Second homes and empty dwellings are excluded.
Owner-occupied
47.3 % of households (2025)Source 735.5% own a house and 11.8% own a flat.
Private rented
19.5 % of households (2025)Source 7Private main tenancies. A further 9.7% live rent-free, sub-let or in service dwellings.
Social or public housing
23.5 % of households (2025)Source 7Derived: limited-profit housing association (cooperative) flats 17.0% plus municipal flats 6.5%.
Houses
Not identified from a reliable public source.
Apartments and flats
Not identified from a reliable public source.
Urban population
69.7 % of population (2025)Source 51

Austria has a low home-ownership rate by European standards. In 2025, 47.3% of households owned their home: 35.5% a house and 11.8% a flat. 43.1% rented, of which 19.5% were private tenants, 17.0% lived in limited-profit cooperative housing (Genossenschaften) and 6.5% in municipal housing.

Tenure matters for energy projects. Owners of single-family houses can install PV, batteries and heat pumps on their own decision, subject to the local building code. In flats, PV on the shared roof needs the agreement of co-owners under the Condominium Act (Wohnungseigentumsgesetz), which is why collective models such as joint generation facilities (gemeinschaftliche Erzeugungsanlagen) and energy communities are popular.

District heating is the main heating system in about one in three homes, mostly in cities, which limits the scope for heat pumps in urban flats.

How the grid works in Austria.

  1. TransmissionAustrian Power Grid (APG)
  2. DistributionOver 100 regional and local DSOs (117 with smart-meter duties), led by the nine Länder network companies and city utilities
  3. MeteringDSOs as meter operators, EDA – Energiewirtschaftlicher Datenaustausch
  4. Supply9 or more retail suppliers

Physical flow

Austria’s grid is organised in seven network levels (Netzebenen) for charging purposes, from the 380/220 kV transmission grid (level 1) through the 110 kV and medium-voltage grids down to the low-voltage grid (level 7) that supplies homes; the even-numbered levels are the transformation between them. In 2025 the public grid had 274,416 km of lines, three quarters of it as underground cable. Network charges differ by network level and network area.

Generation is concentrated in the Alpine west and the Danube (hydro) and in the east (wind in Lower Austria and Burgenland, most new PV). APG notes that about 78% of PV and almost all wind capacity sit in eastern Austria, which drives grid congestion and redispatch. APG reported grid-access requests of about 32 GW in 2025, including about 12 GW of battery storage.

Commercial flow

Every consumption and feed-in point belongs to a balance group. Balance responsible parties register with the balance group coordinator APCS and must provide security of at least €50,000. Suppliers buy power on the exchanges (EXAA, EPEX SPOT) or bilaterally; APCS settles the difference between scheduled and metered volumes. Small customers are settled on standard load profiles unless 15-minute data are available (ElWG §109).

The DSO bills network charges through the supplier on a combined invoice or separately. Since 2025 Austria has been a net importer again: physical net imports were 4.1 TWh in 2025 because hydro output fell by about a quarter, after a net export year in 2024.

Switching

Supplier switching runs electronically through the EDA platform. EU rules require the technical switch to take no more than 24 hours; E-Control is preparing a switching ordinance under the ElWG to deliver this.

Who does what.

Who does what.
RoleOrganisationWhat it does
MinistryFederal Ministry of Economy, Energy and Tourism (BMWET)Lead ministry for electricity law (ElWG), sets the feed-in levy and reference plants for peak capping by ordinance, and oversees EAG support.
RegulatorEnergie-Control Austria (E-Control)Independent regulator. Sets network charges for every network area (SNE-V), issues market rules (Sonstige Marktregeln) and the technical rules (TOR) framework, monitors retail prices, runs the tariff calculator and supervises supplier risk management under the ElWG.
TSOAustrian Power Grid (APG)Owns and operates the 380/220/110 kV transmission grid (about 3,500 km of routes and 67 substations) and is the control area manager for almost all of Austria. Procures balancing reserve and redispatch; spent €87.2 million on redispatch in 2025.
DSODistribution network operators (Verteilernetzbetreiber)117 DSOs are obliged to roll out smart meters. The largest are Wiener Netze, Netz Niederösterreich, Netz Oberösterreich, Energienetze Steiermark, Netz Burgenland, Salzburg Netz, KNG-Kärnten Netz, TINETZ-Tiroler Netze and Vorarlberger Energienetze, plus city networks such as Linz and Graz. Each holds a Land concession for its area.
MeteringDSOs as meter operatorsMetering is a regulated DSO task. The DSO installs and reads the meter, assigns the Zählpunkt and sends the data to suppliers and other authorised parties. There is no competitive metering market.
SettlementAPCS Power Clearing and SettlementBalance group coordinator for the APG control area: registers balance responsible parties, calculates and settles imbalances and determines balancing-energy prices.
Data hub / registryEDA – Energiewirtschaftlicher DatenaustauschIndustry data-exchange platform used for supplier switching, metering data, and adding metering points to energy communities. Market participants register via ebUtilities. Each DSO keeps its own Zählpunkt master data; there is no single national meter register.
SupplierCompetitive electricity suppliersUp to 40 suppliers active nationwide in 2025, plus regional suppliers. Each supplier must belong to a balance group and sign data-exchange contracts with the balance responsible party, the DSO and the balance group coordinator (ElWG §78).
ExchangeEXAA and EPEX SPOT (Austrian bidding zone)Day-ahead and intraday trading for the Austrian bidding zone. The average spot price was €99/MWh in 2025.
Flexibility marketAPG balancing reserve tenders and the planned joint flexibility platformAPG procures FCR, aFRR and mFRR in market-based tenders. ElWG §142 requires APG and the larger DSOs to set up a joint digital platform to coordinate flexibility procurement.

Compared with the UK system.

Compared with the UK system.
UK conceptAustria equivalentHow it works
DNOVerteilernetzbetreiber (VNB)More than 100 DSOs, each with a Land concession for a defined area; nine large Länder network companies cover most customers. The DSO owns the connection and meter, handles new connections and generator notifications, and reads the meter.
National Grid/NESOAustrian Power Grid (APG)APG combines transmission ownership and system operation for almost all of Austria (corridors in Tyrol and Vorarlberg are handled differently). It balances the system, procures reserve and manages redispatch.
MPANZählpunktbezeichnung (Zählpunktnummer)33-character code starting with AT, assigned by the DSO for each meter and each energy-flow direction, so a PV home has separate consumption and feed-in Zählpunkte.
MPRNGas ZählpunktGas metering points also use a 33-character AT code, assigned by the gas network operator. Electricity and gas codes are separate.
Meter operatorDSO (regulated metering)Meters are owned, installed and read by the DSO and paid for through a regulated metering charge. Suppliers cannot appoint their own meter operator.
SupplierStromlieferantCompetitive supply with free switching. No supply licence: suppliers work inside a registered balance group. The ElWG adds basic-supply duties, social-tariff duties and supplier stress tests.
Smart-meter infrastructureDSO-run smart meters (no national DCC)Each DSO runs its own head-end system, mostly power-line carrier to data concentrators. Data reaches suppliers and authorised third parties through the EDA platform; customers see their data on the DSO web portal.

How a supply point is identified.

AT009999050200000000000000A123456 (fictional)

Fictional example in the real format.

How a supply point is identified.
QuestionAnswer
What is it called?Zählpunktbezeichnung (Zählpunktnummer) (ZP)
Who issues it?The local distribution network operator, for each meter and each energy-flow direction (ElWG §109)
FormatCountry code "AT" (2) + network operator number (6 digits) + postcode of the supply point (5 digits, may be all zeros) + metering point number (20 alphanumeric characters, A–Z and 0–9), allocated by the DSO.
Length33 characters
Stays with the property when you switch supplier?Yes
Where to find itOn the electricity bill (for example on the detail sheet under general data), on the network access contract and in the DSO’s smart-meter web portal. The DSO must give it to the customer within one working day on request.
Electronic accessSuppliers, aggregators and other market participants exchange Zählpunkt master data and meter readings electronically through the EDA platform. Customers see daily or 15-minute data in their DSO’s smart-meter web portal.
Third-party accessThere is no public look-up. A third party (new supplier, energy community, aggregator) needs the Zählpunkt from the customer and the customer’s consent, and is then connected to the metering point through EDA processes.
Who keeps the registerEach DSO keeps the master data for the Zählpunkte in its own area. EDA links the DSO systems with suppliers and other market participants.
Register scopePer DSO

What the Zählpunkt identifies

A Zählpunkt is the point at which energy is measured for settlement. Under ElWG §109 the network operator must assign one Zählpunkt per meter and per energy-flow direction, each with a unique Zählpunktbezeichnung. A home with rooftop PV that exports surplus therefore has two: one for consumption and one for feed-in. A household with a separate heat-pump meter has another. The number stays with the supply point when the occupant or supplier changes; replacing the meter does not change it.

How it is built

The 33 characters work much like an IBAN. "AT" is the country code; the next six digits identify the network operator; the next five are the postcode of the supply point (or zeros); and the last 20 characters, which can include letters, are the metering point number chosen by the DSO. A fictional example is AT009999050200000000000000A123456. Because the network-operator part is built in, the code shows which DSO is responsible.

Why households need it

The Zählpunkt is the reference for switching supplier, signing a feed-in contract, registering a PV system or battery with the DSO, joining an energy community, and applying for some subsidies. Suppliers ask for it when you sign a contract, and energy communities use it to add members to the community’s billing through EDA.

Small plug-in systems

Very small generators with a total capacity of up to 0.8 kW per connection (Kleinsterzeugungsanlagen, typically plug-in balcony PV) do not get their own Zählpunkt unless the customer asks for one (ElWG §77). They are exempt from balance-group duties.

Gas

Gas metering points use the same 33-character AT structure but are assigned by the gas network operator, so a home with both gas and electricity has separate codes for each.

Sending electricity to the grid.

Sending electricity to the grid.
QuestionAnswer
Can homes export electricity?Yes
Net meteringNo
Net billingNo
How exported electricity is paidMarket-based: a buy-back contract with a supplier or trader, sale to OeMAG at its published monthly market price, or sharing within an energy community. No net metering.
Is there net metering?No. Consumption and feed-in are metered at separate Zählpunkte and priced separately. Feed-in is sold under a separate contract.
What does a small PV system pay to connect?PV up to 15 kW connected through an existing consumption connection may feed in up to the agreed withdrawal capacity (maximum 15 kW) with no extra connection fee. For larger renewable plants on network levels 5–7, the fee applies only above 15 kW and is reduced by 85% (ElWG §96).
Can the DSO limit my feed-in?Yes. For new or changed PV connections the DSO may permanently limit grid-effective output, but not below 70% of the module peak power. This does not apply to systems with an agreed feed-in of 7 kW or less, or where the owner paid for an unrestricted connection (ElWG §101).
Do I need a controllable inverter?From 1 June 2026, new or substantially changed generation from 3.68 kW must have a controllability device with a standardised interface. DSOs must be able to control plants above 25 kW by June 2028 and 3.68–25 kW plants by June 2029 (ElWG §76).
Will generators pay network charges?From 1 January 2027 generators pay a supply infrastructure contribution (Versorgungsinfrastrukturbeitrag) of at most 0.05 c per kWh fed in. Plants up to 20 kW are exempt (ElWG §75a).
Is plug-in (balcony) solar allowed?Yes. Plug-in systems up to 0.8 kW per connection are legally "very small generators". They need no separate Zählpunkt or balance-group membership (ElWG §6, §77), although the DSO should be informed.
What does OeMAG pay?OeMAG publishes a monthly market price for buying electricity from renewable plants. For September 2026 it was 10.168 c/kWh for PV and other technologies apart from wind.

Connecting a home system.

  1. Plan the system with an electrical contractor and check grid capacity with the DSO. Rooftop PV for a home is normally exempt from Länder electricity-law permits but may need a building notification in protected zones.
  2. For renewable plants up to 20 kW of grid-effective capacity, notify the DSO (simplified connection). The DSO must confirm or give reasons for refusal within four weeks; if it does not respond, the connection is deemed allowed (ElWG §96).
  3. Larger systems apply for a network access contract with the DSO. From 1 June 2026, new generators of 3.68 kW or more must have a device that allows the DSO to control their output.
  4. Use an inverter certified as compliant with TOR Erzeuger Type A (verified under OVE Guideline R 25). The installer commissions the system and sends the completion notice to the DSO.
  5. The DSO sets up a feed-in Zählpunkt and configures the smart meter to record export.
  6. Sign a contract to sell the surplus: with a supplier or trader, with OeMAG at its monthly market price, or through an energy community.

Households in Austria can export surplus electricity and be paid for it, but there is no net metering or feed-in tariff for new small PV. Export is sold at market-linked prices: many suppliers and traders offer buy-back contracts, OeMAG (the green-power settlement agency) buys at a monthly market price, and energy communities let members share surplus locally at agreed prices, with reduced network charges for the shared energy.

Connection is straightforward for small systems. Renewable plants up to 20 kW connect on notification, and PV up to 15 kW on an existing connection pays no connection fee. The ElWG also gives DSOs new tools to manage grids with high PV density: permanent peak capping to not less than 70% of module power, flexible (partially firm) connection agreements, and from June 2026 a requirement that new generators of 3.68 kW and above can be remotely controlled.

Exported energy is measured at a separate feed-in Zählpunkt by the smart meter, which records 15-minute values. Feed-in up to 100,000 kWh a year or 50 kW is settled on a standard load profile unless quarter-hour data are used.

Licensing and approvals.

Requirements depend on the activity. The table sets out what each activity needs and who grants it.

Licensing and approvals.
ActivityLicence or registrationAuthorityNotes
Generate electricityNo federal generation licence. Permits for building and operating plants are set by each Land’s electricity act under federal framework law (ElWG §73). Household rooftop PV is generally exempt; electricity-law permit thresholds for PV vary between Länder, from about 100 kWp to more than 1,000 kWp.Land governments (Landesregierung, district authorities)Plants covered by the Trade Act (GewO 1994) are exempt from a separate electricity-law permit. Building, spatial-planning and nature-protection rules apply separately.
Store electricityNo licence. Storage is treated as a consumer when charging and a generator when discharging (ElWG §88). Länder rules on permits for larger battery installations vary.DSO (connection); Land authorities (permits)E-Control consulted on rules for storage and hybrid plants in 2025, including metering concepts for storage behind the meter. Network operators may own storage only under strict conditions (ElWG §89).
Export to the gridNo licence. Notification to the DSO up to 20 kW (ElWG §96); a network access contract above that. A feed-in Zählpunkt and an offtake contract are needed.DSOGenerators must belong to a balance group, usually through their offtaker. Very small plants up to 0.8 kW are exempt.
Supply (sell) electricity to consumersNo supply licence. The supplier must operate within a registered balance group and sign data-exchange contracts with the balance responsible party, the DSO and the balance group coordinator (ElWG §78).E-Control (supervision); APCSElWG duties include basic supply (§30), the supported price for eligible households (§36), customer-service and advice obligations (§35) and risk-management rules monitored by E-Control (§47–48).
Act as balance responsible partyRegistration with the balance group coordinator before starting, with proof of expertise, reliability and security of at least €50,000 (ElWG §14).APCS (balance group coordinator)The coordinator publishes the list of registered balance responsible parties.
Distribute electricityA concession from the Land is required to operate a distribution network (ElWG §113).Land governmentsClosed distribution networks for linked business sites become possible two years after the ElWG entered into force.
AggregateNo licence. Customers have a right to an aggregation contract in addition to their supply contract (ElWG §23), and independent aggregators need no consent from the supplier. Aggregator switching is regulated (§§25–26).E-Control (data-exchange and settlement rules)E-Control can set financial compensation between aggregators and suppliers by ordinance (§63).
Trade wholesale electricityNo specific energy licence. Trading parties need balance-group membership or exchange membership; financial instruments fall under financial-market rules.E-Control (REMIT monitoring); exchangesThe ElWG gave E-Control powers to prosecute REMIT breaches as administrative offences.
Balancing services (FCR, aFRR, mFRR)Prequalification with APG and a framework agreement. Open to generators, demand response, storage and aggregators (ElWG §147). Minimum bid 1 MW for mFRR, with pooling of units.APG (control area manager)aFRR and mFRR activation is optimised through the EU platforms PICASSO and MARI.
Grid services and local flexibility (DSO)No licence. DSOs may procure flexibility; a joint flexibility platform of APG and the larger DSOs is being set up (ElWG §142). Flexible connection agreements (§103) are a separate route.DSOs; APG; E-ControlE-Control’s 2024–2025 study found market-based procurement of non-frequency ancillary services not yet appropriate for any of the six services examined.
Energy community (EEG/BEG)A legal entity (association, cooperative, company) registered with the DSO for each participating Zählpunkt via EDA. Renewable energy communities must stay within the local area set in ElWG §70.DSO; E-Control (oversight)From 1 October 2026 communities above certain size thresholds take on supplier-type information and billing duties.
Remote control of assets / VPPNo specific licence. Load and feed-in control is covered by ElWG §63, and new generators of 3.68 kW and above must be controllable from 1 June 2026 (§76).DSOs; E-ControlThe DSO controls only grid-effective power at the connection point; optimisation behind the meter stays with the owner or their aggregator.

Austria does not license generation or supply at federal level. Electricity law is split between the federation, which sets framework law (the ElWG), and the nine Länder, which issue permits for power plants and grant DSO concessions under their own electricity acts. A household installing PV, a battery or a heat pump needs no licence: what matters is the DSO notification or network access contract, the building rules of the Land and municipality, and an offtake contract for any exported electricity.

Market roles are controlled through the balance-group system. Suppliers, traders and generators must belong to a balance group, and balance responsible parties register with APCS. The ElWG added new market roles and duties: aggregators, active customers who can trade peer-to-peer, energy communities with supplier-type duties above certain thresholds, and stricter risk-management requirements for suppliers.

Flexibility and grid services.

Aggregation of home equipment: Yes

Flexibility and grid services.
Market or serviceAccess for home equipmentMinimum sizeVia an aggregatorDetail
Frequency containment reserve (FCR)Yes—YesAPG. Procured through APG tenders after prequalification. Batteries and pooled units can take part.
Automatic frequency restoration reserve (aFRR)Yes—YesAPG (PICASSO platform). Capacity is procured by APG; activation is optimised across borders on PICASSO. Costs were very high on some days in the first half of 2025 until APG capped very expensive activations.
Manual frequency restoration reserve (mFRR)Yes1 MW (1 MW steps)YesAPG (MARI platform). Six 4-hour products; capacity bids from D-7 to D-1, energy bids up to 25 minutes before delivery. Several technical units can be pooled.
Redispatch and network reserveRestricted—LimitedAPG. Mostly large thermal and hydro plants contracted by APG. Redispatch was needed on 215 days in 2025 and cost €87.2 million.
Wholesale day-ahead and intradayYes—YesEXAA, EPEX SPOT. Households take part indirectly through dynamic supply contracts and aggregators. Quarter-hour day-ahead prices have applied since 1 October 2025.
DSO local flexibilityDeveloping—UnknownDSOs; joint flexibility platform (ElWG §142). The ElWG gives DSOs a legal basis for procuring flexibility and requires a joint platform. A national flexibility needs assessment is under way.
Energy communitiesYes—YesDSOs via EDA. Not a flexibility market as such, but more than 10,000 communities share local generation in 15-minute intervals. Members covered 31% of their consumption from shared energy in mid-2025.

Distributed assets can earn money in Austria mainly through the balancing reserve markets run by APG, which are open to pooled portfolios of generators, batteries and flexible loads after prequalification, and through dynamic tariffs that pass on quarter-hour wholesale prices. Austria has the most energy communities in Europe, which share local generation but are not yet a flexibility service for the grid.

The ElWG gives aggregation a clear legal basis for the first time: customers may sign an aggregation contract alongside their supply contract, independent aggregators do not need the supplier’s consent, and E-Control can regulate data exchange and compensation between aggregators and suppliers. DSO flexibility markets are still developing; the law requires APG and the larger DSOs to build a joint flexibility platform, and the controllability requirement for new generators will give DSOs direct control of grid-effective PV output over the next few years.

Flexibility and aggregation platforms.

Flexibility and aggregation platforms.
Platform or aggregatorWhat it does
APG balancing reserve tender platformTenders, prequalification documents and results for FCR, aFRR and mFRR.
EDA platformData exchange for switching, energy communities and metering data between DSOs, suppliers and other market participants.
Austrian Coordination Office for Energy CommunitiesGovernment-funded information point for setting up energy communities, run through the Climate and Energy Fund.

Smart meters.

Smart meters.
FactValue
Smart-meter rolloutDSO-led rollout; 96.9% of metering points smart by end 2024 (legal target 95%)
Reading interval15 minutes
Smart meters installed6.53 million of 6.74 million metering points (end 2024)
DSOs meeting the 95% target90 of 117 (end 2024)
Standard configurationDaily values sent to the DSO the next day (~5.17 million meters)
Opt-in to 15-minute data~760,000 meters (12.6%); ~472,000 also share them with the supplier
Opt-out127,800 meters (2.1%)
CommunicationsMostly power-line carrier to data concentrators (94%), then LTE or fibre; about 6% direct mobile connection
Customer accessDSO web portal (103 of 117 DSOs); EDA platform for authorised market parties

Who does what

In Austria smart meters are installed, owned and read by the distribution network operators, not by suppliers. The Intelligent Metering Introduction Ordinance (IME-VO) set a target of 95% of metering points by the end of 2024; the national average reached 96.9%, although 27 mostly small DSOs missed the target. Netz Burgenland, Netz Oberösterreich and Netz Niederösterreich were above 99.5%. Each DSO runs its own system, so there is no national communications company like the UK’s DCC.

Data configurations

Under the old rules, most meters stored daily values, which were sent to the DSO the next day. Customers could opt in to 15-minute values or opt out to a digital meter without remote reading. The ElWG (§54) makes 15-minute recording the default: smart meters must record all quarter-hour values for import and export. Households may object unless they have a dynamic contract, a heat pump, charger, battery or generator, or take part in an energy community. Daily-only transmission is allowed until the end of 2026 for customers using up to 5,000 kWh a year, and from 2027 only up to 1,500 kWh. The monthly maximum 15-minute demand is always read.

Access to data

Customers see their data in the DSO’s web portal (required by ElWOG §84 and the DAVID ordinance; 103 of 117 DSOs provided one). Suppliers, energy communities and other authorised parties receive data through EDA. From April 2026, customers billed annually can ask for a free monthly consumption and billing statement (ElWG §45). E-Control is revising the meter requirements ordinance (IMA-VO 2011) for the next generation of meters ("Smart Meter 2.0").

Renewable electricity.

Electricity generation mix (2025).

  • Hydro: 50.7%
  • Solar: 13.4%
  • Natural gas: 13%
  • Wind: 11.7%
  • Bioenergy: 6.4%
  • Coal products: 2.5%
  • Other fuels: 1.2%
  • Oil products: 0.9%
Source 10
Renewable electricity share
82.3% (2025)Source 10Share of domestic generation (60,200 of 73,129 GWh). 2024: 86.5%. Measured against gross consumption, E-Control put renewables at about 94% in 2024.
Home solar
546,436 PV installations (all sizes) (end 2025)Source 10Almost all are below 1 MW (545,988 installations with 8.3 GW). A separate household-only count was not identified.
Solar added each year
1.634 GW (2025)Source 4222% below 2024 (2,084 MW); the record was 2023. Figures from E-Control presented by PV Austria.
Hydro (run-of-river and storage)
15.8 GW (end 2025)Source 10Run-of-river 6.15 GW; storage and pumped-storage plants 9.61 GW.
Solar PV
9.94 GW (end 2025)Source 10
Wind
4.22 GW (end 2025)Source 10
Thermal (gas, biomass, other)
6.38 GW (end 2025)Source 10

Targets.

  • 100% of national electricity consumption from renewables (on annual balance) by 2030 (Renewable Expansion Act, EAG).
  • An additional 27 TWh of renewable electricity per year by 2030 compared with 2020 (EAG).
  • 5 TWh of domestically produced renewable gas by 2030 (EAG).

Hydropower is the backbone of Austria’s electricity system, but its output depends on rainfall and snowmelt. In the wet year 2024 hydro produced 49.4 TWh and renewables covered about 94% of gross consumption; in dry 2025 hydro output fell by a quarter to 37.1 TWh, renewables fell to 82.3% of generation, and gas-fired output rose by 25%.

Solar is growing fastest. Installed PV rose from 6.2 GW at the end of 2023 to 9.9 GW at the end of 2025, and PV produced 9.8 TWh in 2025, more than wind for the first time. Additions slowed to 1.6 GW in 2025 after the early end of the 0% VAT rate for small rooftop systems in April 2025. Wind capacity reached 4.2 GW, almost all in Lower Austria and Burgenland.

Most new renewable plants are supported under the EAG through market premiums (for larger plants) and investment grants (for PV and storage). About 3 TWh came from plants with an EAG market premium in 2024, and OeMAG bought about 4.6 TWh from older plants under the 2012 Green Electricity Act.

Energy storage.

Home batteries
Not identified from a reliable public source.
Grid-scale storage
Not identified from a reliable public source.

Austria’s main storage is Alpine pumped hydro, about 6 GW, plus large seasonal reservoirs. Battery storage is growing on two fronts. Home batteries are subsidised together with new PV through EAG investment grants, and the ElWG now treats storage clearly as a consumer when charging and a generator when discharging. Grid-scale batteries are at an early stage: the largest operating system had 24 MWh in 2025, but APG reported about 12 GW of battery projects asking for grid access, and E-Control consulted in 2025 on clearer connection and metering rules for storage and hybrid plants.

The ElWG also gives storage a role in grid planning: DSOs must offer flexible connection agreements, and storage that reduces peak feed-in can help PV owners stay within capped export limits.

Storage projects.

  • NGEN battery storage, Fürstenfeld (Styria): 12 MW / 24 MWh; described as Austria’s largest battery when it started operating in February 2025.
  • EVN battery storage, Theiß (Lower Austria): 70 MW / 140 MWh at the Theiß power-plant site, investment about €46 million, due in the third quarter of 2027.
  • Alpine pumped-storage plants: About 6 GW of pumped storage in the Alps (APG), used daily and seasonally to balance wind and solar in Austria and neighbouring countries.

Electricity suppliers.

Electricity suppliers.
SupplierMarket shareRenewable tariffTime of useDynamicExport tariff
Wien EnergieIncumbent supplier in ViennaUnknownUnknownUnknownUnknown
EVNIncumbent supplier in Lower AustriaUnknownUnknownUnknownUnknown
Energie AG OberösterreichIncumbent supplier in Upper AustriaUnknownUnknownUnknownUnknown
Energie SteiermarkIncumbent supplier in StyriaUnknownUnknownUnknownUnknown
KelagIncumbent supplier in CarinthiaUnknownUnknownUnknownUnknown
Salzburg AGIncumbent supplier in SalzburgUnknownUnknownUnknownUnknown
TIWAG-Tiroler WasserkraftIncumbent supplier in TyrolUnknownUnknownUnknownUnknown
Vorarlberger Kraftwerke (VKW, illwerke vkw)Incumbent supplier in VorarlbergUnknownUnknownUnknownUnknown
VerbundLargest generator (mainly hydro); nationwide retail supplierUnknownUnknownUnknownUnknown

Austria’s retail market is dominated by the former regional monopolies, mostly owned by the Länder and cities, which keep high market shares in their home network areas (E-Control and Federal Competition Authority task force, 2025). Up to 40 suppliers were active nationwide in 2025, compared with 56 before the energy crisis, and 5.4% of electricity customers switched supplier in 2025. Official market shares by supplier are not published.

Suppliers do not install or own meters in Austria: smart meters belong to the DSO, which is why every supplier above is marked "No" for smart meters. Product features change often, so availability of time-of-use, dynamic and buy-back products is marked "Unknown" here. The E-Control tariff calculator lists current offers for each postcode, including spot-market products.

Key organisations.

Key organisations.
OrganisationCategoryWhat it doesWhy it matters
Federal Ministry of Economy, Energy and Tourism (BMWET)GovernmentEnergy ministryResponsible for the ElWG, EAG support and ordinances on the feed-in levy and peak capping.
E-ControlRegulatorEnergy regulatorSets network charges and market rules, publishes smart-meter and market reports, and runs the tariff calculator.
Austrian Power Grid (APG)TransmissionTSO and control area managerRuns the transmission grid, balancing reserve markets and redispatch; publishes the network development plan.
Oesterreichs EnergieDistributionAssociation of the electricity industryRepresents utilities and DSOs, co-develops technical rules (TOR) and publishes the annual electricity statistics.
APCS Power Clearing and SettlementMarketBalance group coordinatorRegisters balance responsible parties and settles imbalances in the APG control area.
EXAA Energy Exchange AustriaMarketPower exchangeAustrian day-ahead exchange alongside EPEX SPOT.
OeMAG Abwicklungsstelle für ÖkostromRenewable EnergyGreen-power settlement and EAG funding agencyHandles EAG investment grants and market premiums and buys renewable electricity at a published monthly market price.
Photovoltaic & Battery Austria (PV Austria)SolarPV and storage industry associationPublishes market figures and a guide to permits for PV and storage in each Land.
IG WindkraftRenewable EnergyWind industry associationPublishes wind capacity statistics and represents wind developers.
Austrian Coordination Office for Energy CommunitiesConsumerGovernment information pointAdvises households, municipalities and businesses on setting up energy communities.
EDA Energiewirtschaftlicher DatenaustauschMeteringMarket data-exchange platformCarries switching, metering and energy-community data between DSOs and market parties.

Technical standards.

Technical standards.
AreaStandardIssued byNotes
Grid connection of generatorsTOR Erzeuger (Type A for small generators)E-Control / Oesterreichs Energie (technical and organisational rules)Type A covers small generators such as household PV and battery inverters and sets their grid-protection and grid-support behaviour.
Inverter conformityOVE Guideline R 25OVE (Austrian Electrotechnical Association)Test procedure for proving that inverters, including battery inverters, meet TOR Erzeuger Type A. DSOs expect a manufacturer certificate.
Grid connection (distribution, chargers)TOR Verteilernetzanschluss v1.3 (August 2025)E-ControlApplies to all charging points with a rated power above 3.68 kVA.
Power qualityTOR Netzrückwirkungen (2025)E-ControlReplaced TOR D2 in Q2 2025 with separate parts for low, medium and high voltage; treats generation and consumption equally.
ControllabilityElWG §76 standardised control interfaceFederal law; details in TORMandatory for new or substantially changed generation from 3.68 kW from 1 June 2026.
Plug-in PVVery small generators up to 0.8 kW (ElWG §6 Z 78, §77)Federal lawNo separate Zählpunkt or balance-group duties for plug-in systems up to 0.8 kW per connection.
Smart metersIMA-VO 2011, IME-VO, DAVID-VO 2012E-ControlMeter functions, rollout targets and customer data presentation. IMA-VO is being revised under the ElWG.
Installer qualificationTrade Act (Gewerbeordnung 1994), electrical engineering tradeFederal law; Austrian Economic ChamberElectrical installation work, including PV connection, must be carried out by a business licensed for the electrical engineering trade.

Permissions.

Permissions.
PermissionRequiredLevelDetail
Building permission for rooftop PVLimitedRegionalSet by each Land’s building code. Rooftop PV on homes is usually permit-free or needs only a notification; protected zones, heritage areas and large free-standing systems need notification or a permit.
Electricity-law permitLimitedRegionalEach Land’s electricity act sets the threshold; household systems are below it. Thresholds range from about 100 kWp to over 1,000 kWp (PV Austria guide, March 2026).
DSO connectionYesNationalNotification for renewable plants up to 20 kW, with a four-week deadline for the DSO; a network access contract above that (ElWG §96).
Co-owner consent in flatsLimitedNationalPV on a shared roof or façade needs the agreement of co-owners under the Condominium Act.
Spatial planning (ground-mounted PV)LimitedMixedFree-standing PV on green land needs a zoning designation or permit above Land-specific sizes.
Energy community registrationLimitedNationalOnly if the household joins an energy community: the community registers each member’s Zählpunkt with the DSO via EDA.

Permission for a household PV system or battery in Austria depends on the Land. Building, spatial-planning, electricity and nature-protection law are all Länder matters, so the rules differ between Vienna, Lower Austria, Tyrol and the other states. For a typical rooftop system on a house the practical steps are a DSO notification and, where required, a building notification to the municipality.

The federal ElWG standardises the grid side: renewable systems up to 20 kW connect on notification, and the DSO has four weeks to object on safety or technical grounds. It is always worth checking available grid capacity with the DSO first, because in some areas with high PV density feed-in may be capped.

Support schemes, taxes and incentives.

Support schemes, taxes and incentives.
SchemeStatusTypeDetailPeriod
EAG investment grant for PV and storageActiveGrant2026 rates: €150/kWp up to 10 kWp, €140/kWp for 10–20 kWp, up to €130/kWp for 20–100 kWp and up to €120/kWp for 100–1,000 kWp; storage up to 50 kW €150/kWh, only with new or expanded PV. A bonus applies for European-made components. Applications only during call windows, before commissioning.2026 calls: 23 Apr–11 May, 16–30 Jun, 8–22 Oct
Social tariff (supported price for eligible households)ActivePrice supportHouseholds exempt from the ORF broadcasting fee pay an energy price of 6 c/kWh net for the first 2,900 kWh a year, plus €52.50 extra allowance per additional person in households of more than three. About 290,000 households are eligible. Network charges and taxes still apply.From April 2026 (planned for ten years)
Electricity tax cut for householdsActiveTax reliefElektrizitätsabgabe for private households reduced from 1.5 c/kWh to 0.1 c/kWh, worth about €50 a year for an average household.1 Jan – 31 Dec 2026
Reduced network charges in energy communitiesActiveNetwork-charge reductionElectricity shared within renewable energy communities is exempt from the renewables support contribution and gets reduced network charges.—
OeMAG purchase at market priceActiveExport paymentOeMAG buys renewable electricity at a monthly market price (10.168 c/kWh for PV in September 2026).—
EAG market premiumActiveMarket premiumMarket premium for larger renewable plants under the Renewable Expansion Act, administered by OeMAG. About 3 TWh of electricity was supported this way in 2024, mainly wind, biogas and PV.—
0% VAT on small PV systemsClosedVAT reliefZero VAT on PV systems up to 35 kWp was abolished early from 1 April 2025; contracts signed before 7 March 2025 kept the 0% rate. Standard 20% VAT applies again.Ended 31 Mar 2025
Electricity price brake (Strompreisbremse)ClosedPrice subsidyFederal subsidy on household electricity introduced during the energy crisis; it expired at the end of 2024, which raised household energy costs at the start of 2025.Ended 31 Dec 2024

Data and connectivity.

Fixed broadband
95.5 % of households (2025)Source 52Households with internet access at home. Very-high-capacity fixed network coverage was 72.2% and fibre-to-the-premises 44.8% of households in 2024.
4G coverage
Not identified from a reliable public source.
5G coverage
99.5 % of populated areas (2024)Source 53Overall 5G coverage (Digital Decade KPI), up from 96.0% in 2023; EU average 94.3%.

Smart meters in Austria do not depend on home broadband: about 94% communicate over the power line (PLC) to data concentrators in substations, which then connect to the DSO over LTE, fibre or the 450 MHz radio network. About 6% connect directly by mobile network, and some small DSOs use radio mesh. PLC can be disturbed by inverters, wallboxes and other electronics, so some DSOs are testing other frequency bands and hybrid solutions.

Home energy devices use the household broadband or mobile network. Austria has near-universal 5G coverage but still lags the EU on fibre. For local data, many smart meters have a customer interface that can be activated by the DSO for energy-management systems, and the ElWG requires near-real-time non-validated data to be available (§52).

Grid conditions.

National peak demand
Not identified from a reliable public source.
Annual electricity demand
71.5 TWh (2025)Source 10Domestic consumption excluding pumped-storage pumping (77.2 TWh including it).
Generation capacity
36.3 GW (end 2025)Source 10Bottleneck capacity of all plants (hydro 15.8, PV 9.9, thermal 6.4, wind 4.2 GW).
Interconnection
Not identified from a reliable public source.
Curtailment
87.2 EUR million (redispatch costs) (2025)Source 11Redispatch on 215 days (203 in 2024). Curtailed renewable energy volumes are not published nationally; from 2027 DSOs must publish peak-capping events within 24 hours (ElWG §101).

Austria’s grid is under strain because renewable generation is concentrated in the east while large hydro and pumped storage are in the west, and transmission expansion has lagged. In 2025 APG used redispatch on 215 days at a cost of €87.2 million, and on a balance basis Austria imported electricity in eight months of the year. In the dull winter of 2025/26 imports reached 4,300 MW on 1 February 2026.

APG plans to invest €680 million in 2026 and about €9 billion by 2034. Distribution grids face the same pressure from PV: the Court of Audit (Rechnungshof) reported in May 2026 that PV and wind expansion had moved faster than grid adaptation and recommended that new tariffs reflect the costs each user causes. The ElWG responds with peak capping, flexible connection agreements, controllability of new generators and a new tariff structure from 2027.

Grid and capacity maps.

Regulatory changes.

Regulatory changes.
ChangeStatusDateDetail
Electricity Act (ElWG) in forceCurrent24 Dec 2025Largely replaces the ElWOG 2010 (BGBl. I Nr. 91/2025). Implements the EU electricity market directive with new customer rights (dynamic contracts, aggregation, peer-to-peer sharing), peak capping for PV, flexible grid access and new E-Control powers.
Social tariff and summer low-load network rateCurrent1 Apr 2026Supported price of 6 c/kWh net for 2,900 kWh a year for eligible households. On network level 7, network energy charges are 20% lower from 10:00 to 16:00 between April and September for customers with quarter-hour data.
Controllability of new generatorsCurrent1 Jun 2026New or substantially changed generation from 3.68 kW must have a control device with a standard interface (ElWG §76).
New rules for energy communitiesCurrent1 Oct 2026Energy communities above certain thresholds take on supplier-type information and billing duties; ElWG §66 on renewable energy communities applies.
Feed-in levy (Versorgungsinfrastrukturbeitrag)Upcoming1 Jan 2027Generators above 20 kW pay up to 0.05 c/kWh on electricity fed in, set yearly by ministerial ordinance (ElWG §75a).
New network-tariff structureUpcomingJan 2027Network charges move towards charging for load on the grid rather than annual consumption, under a new E-Control principles ordinance.
Peak capping for wind and 15-minute data defaultUpcoming1 Jan 2027DSOs may cap wind output by up to 1% of annual energy. Daily-only smart-meter data is then allowed only for customers using up to 1,500 kWh a year (down from 5,000 kWh).
End of the 2026 electricity tax cutUpcoming31 Dec 2026The household rate of 0.1 c/kWh is legislated for 2026 only; the standard rate returns unless extended.
24-hour supplier switchingUpcomingPending E-Control switching ordinanceEU law requires technical switches within 24 hours from 2026; E-Control is preparing a switching ordinance based on the ElWG.

Market indicators.

Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.

Market indicators.
IndicatorLevelBasis
Electricity costHighLow below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros).
Household electricity useHighLow below 2,500 kWh a year, high at 5,000 kWh or more (average use per household).
Renewable shareHighLow below 30%, high at 60% or more (renewable share of electricity).
Smart-meter adoptionHighLow below 30%, high at 80% or more (share of meters that are smart).
Home solar adoptionHigh546,436 PV installations and 9.9 GW at end 2025; 1.6 GW added in 2025; EAG investment grants of €120–150/kWp; simple notification up to 20 kW.
Distributed energy marketHighAbout 537,000 heat pumps (2024), 257,717 battery-electric cars (end 2025), more than 10,000 energy communities with about 150,000 members (2026).
Grid flexibility marketMediumAPG balancing markets are open to pooled assets from 1 MW, and the ElWG creates aggregator rights, but DSO flexibility markets and the joint flexibility platform are still being set up.
Energy storage adoptionMediumAbout 6 GW of pumped hydro and grant support for home batteries, but grid-scale batteries are small so far (largest operating 12 MW / 24 MWh in 2025) despite about 12 GW of grid-access requests.
Renewable growth environmentHighRenewables 82.3% of generation in 2025 and about 94% of consumption in 2024; PV capacity rose from 6.2 GW to 9.9 GW in two years; legal target of 100% renewable electricity by 2030.

Sources.

Public sources used for this profile, with the date each was accessed.

Show all 55 sources
  1. Population at the beginning of 2026 (press release). Statistik Austria, 2026. accessed 1 October 2026.
  2. Privathaushalte. Statistik Austria, 2025. accessed 1 October 2026.
  3. Electricity prices for household consumers – bi-annual data (nrg_pc_204). Eurostat, 2026. accessed 1 October 2026.
  4. Energieeinsatz der Haushalte. Statistik Austria, 2025. accessed 1 October 2026.
  5. Sanierungsmaßnahmen und Anzahl der Klimaanlagen 2018 bis 2024 (table). Statistik Austria, 2025. accessed 1 October 2026.
  6. Heizungen 2003 bis 2024 nach Bundesländern und verwendetem Energieträger (table). Statistik Austria, 2025. accessed 1 October 2026.
  7. Wohnen 2025 (press release). Statistik Austria, 2026. accessed 1 October 2026.
  8. Fahrzeugbestand 2025 (STATkompakt). Statistik Austria, 2026. accessed 1 October 2026.
  9. Kfz-Neuzulassungen 2025 (press release). Statistik Austria, 2026. accessed 1 October 2026.
  10. Stromstatistik – Kennzahlen 2025. Oesterreichs Energie, 2026. accessed 1 October 2026.
  11. Jahresanalyse 2025: Österreich wieder Stromimporteur. Austrian Power Grid, 2026. accessed 1 October 2026.
  12. Netzentwicklungsplan 2025 (presentation). Austrian Power Grid, 2026. accessed 1 October 2026.
  13. Tertiary Control – Manual Frequency Restoration Reserves (mFRR). Austrian Power Grid. accessed 1 October 2026.
  14. Tätigkeitsbericht 2026 (Berichtsjahr 2025). E-Control, 2026. accessed 1 October 2026.
  15. Bericht zur Einführung von intelligenten Messgeräten in Österreich 2025 (Berichtsjahr 2024). E-Control, 2025. accessed 1 October 2026.
  16. EAG-Monitoringbericht für 2025 veröffentlicht. WKO Kärnten (summary of E-Control report), 2025. accessed 1 October 2026.
  17. Transformation der Stromverteilernetze (press release). Rechnungshof Österreich, 2026. accessed 1 October 2026.
  18. Senkung der Elektrizitätsabgabe 2026. Parlament Österreich – Budgetdienst, 2025. accessed 1 October 2026.
  19. Erneuerbaren-Förderbeitragsverordnung 2026. WKO Oberösterreich, 2025. accessed 1 October 2026.
  20. Netzkosten steigen 2026 bei Strom leicht und bei Gas stark. ORF, 2025. accessed 1 October 2026.
  21. Sozialtarif für Strom startet im April. ORF, 2026. accessed 1 October 2026.
  22. ElWG: Zeitplan der Umsetzung. ORF, 2025. accessed 1 October 2026.
  23. E-Control: Energie ab Jänner kein Inflationstreiber mehr. ORF, 2025. accessed 1 October 2026.
  24. E-Control: Mehr als 420.000 Kunden wechselten Strom- oder Gasanbieter. vienna.at (APA), 2026. accessed 1 October 2026.
  25. Energieversorgung kam durch trüben Winter ans Limit. vienna.at (APA), 2026. accessed 1 October 2026.
  26. Elektrizitätswirtschaftsgesetz (ElWG). WKO, 2026. accessed 1 October 2026.
  27. Strommarktgesetze: ElWG beschlossen. WKO Oberösterreich, 2026. accessed 1 October 2026.
  28. § 96 ElWG – Vereinfachter Netzanschluss für kleine Anlagen. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  29. § 101 ElWG – Spitzenkappung. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  30. § 54 ElWG – Auslesung von intelligenten Messgeräten. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  31. § 109 ElWG – Zählpunkte. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  32. § 76 ElWG – Ansteuerbarkeit neuer Stromerzeugungsanlagen. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  33. § 75a ElWG – Versorgungsinfrastrukturbeitrag. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  34. § 36 ElWG – Gestützter Preis für begünstigte Haushalte. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  35. § 14 ElWG – Bilanzgruppenverantwortliche. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  36. § 147 ElWG – Regelreserve. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  37. § 142 ElWG – Gemeinsame Flexibilitätsplattform. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  38. § 78 ElWG – Pflichten der Lieferanten. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  39. § 77 ElWG – Kleinsterzeugungsanlagen. JUSLINE (consolidated ElWG text), 2026. accessed 1 October 2026.
  40. Zählpunktnummer / Zählpunktbezeichnung. durchblicker.at. accessed 1 October 2026.
  41. Ausfüllhilfe Datenblatt Photovoltaikanlage. Salzburg Netz. accessed 1 October 2026.
  42. Austria deploys 1.63 GW of solar in 2025. pv magazine, 2026. accessed 1 October 2026.
  43. Streichung der USt-Befreiung auf PV-Anlagen. WKO, 2025. accessed 1 October 2026.
  44. EAG-Investitionszuschuss 2026 für Photovoltaik und Stromspeicher. WKO, 2026. accessed 1 October 2026.
  45. Ergebnis 1. Fördercall 2026 Investitionszuschüsse Photovoltaik. EAG-Förderabwicklungsstelle (OeMAG), 2026. accessed 1 October 2026.
  46. Marktpreis. OeMAG, 2026. accessed 1 October 2026.
  47. Energiegemeinschaften – Wirkung in Österreich (fact sheet). Klima- und Energiefonds, 2026. accessed 1 October 2026.
  48. Innovative Energietechnologien in Österreich – Marktentwicklung 2024 (Kurzfassung). BMIMI / nachhaltigwirtschaften.at, 2025. accessed 1 October 2026.
  49. Leitfaden zur Anzeige- und Genehmigungspflicht von PV-Anlagen und Energiespeichern (Kurzversion, March 2026). PV Austria, 2026. accessed 1 October 2026.
  50. APCS – Power Clearing and Settlement. Europex. accessed 1 October 2026.
  51. Urban population (% of total population) – Austria. World Bank, 2025. accessed 1 October 2026.
  52. Level of internet access – households (tin00134). Eurostat, 2025. accessed 1 October 2026.
  53. Digital Decade 2025 country report – Austria. Council of the EU / European Commission, 2025. accessed 1 October 2026.
  54. Österreichs größter Batteriespeicher in Betrieb genommen. pv magazine, 2025. accessed 1 October 2026.
  55. Österreichs größter Batteriespeicher wird von EVN in Theiß errichtet. Land Niederösterreich, 2026. accessed 1 October 2026.

Questions about energy in Austria.

Talk to us about Olmack in Austria.Tell us about your home, housing portfolio or school estate in Austria. We'll explain what is possible there now.