How electricity works in Hungary.
Hungary electricity market 2026: regulated household prices, MVM Next, six DSOs, the 33-character POD, HMKE solar and gross billing, MAVIR balancing and reforms.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Hungarian forint (HUF) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Hungary energy at a glance.
Key figures for households in Hungary. Each one links to its source on the full overview below.
Electricity price.
42.315 HUF per kWh for households, including taxes. Figures for 2025-H2.
Household use.
3,184 kWh a year for a typical household. Figures for 2024.
Renewable share.
35.3% of electricity from renewable sources. Figures for 2025.
Selling back to the grid.
Can homes export electricity? Yes. Details are in the export section below.
Four things to check in Hungary.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Hungary below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Hungary requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Hungary.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Hungary, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Hungary, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Hungary.
The energy market in Hungary, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 1 October 2026.
On this page22 sections
Hungary has a liberalised wholesale electricity market and unbundled networks, but household supply is dominated by regulated prices. Since 30 June 2024 MVM Next, part of the state-owned MVM Group, has been the only universal-service supplier, and households on universal service pay a regulated price for consumption up to 2,523 kWh a year at each supply point, with a higher regulated price above that band. The transmission system operator is MAVIR and the regulator is the Hungarian Energy and Public Utility Regulatory Authority (MEKH).
Nuclear power from the four-unit Paks plant supplied 40% of domestic generation in 2025, and solar has grown faster than almost anywhere else in Europe: it reached 27.3% of generation in 2025, with around 8.2 GW installed. Hungary is also a structural net importer, bringing in about 9 TWh in 2025 against domestic generation of about 40 TWh.
Household solar is built as HMKE (háztartási méretű kiserőmű), small plants of up to 50 kVA on the low-voltage network. Annual net metering is closed to new systems: connection requests made after 7 September 2023 are settled on gross billing, and older systems move to gross billing ten years after commissioning. Following the April 2026 general election the new government has said regulated household prices will stay, and has announced a wind-power restart, dynamic tariffs and an independent aggregator framework.
Energy snapshot.
Headline figures for electricity in Hungary. Each shows its data year and links to its source.
- Population9,488,428 peopleSource 21 Jan 2026
- Households4,008,300 householdsSource 32025
- Average household size2.3 people/householdSource 42025
- Electricity use per household3,184 kWh/yrSource 52024
- Household price (HUF)42.3 HUF/kWhSource 12025-H2
- Household price (EUR)0.108 EUR/kWhSource 12025-H2
- Renewable electricity share35.3%Source 122025
- Solar capacity8.18 GWSource 122025
- Wind capacity0.32 GWSource 122025
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Partially liberalised
- Homes can export to the grid
- Yes
- Home equipment in grid services
- Restricted
- Regulator
- Hungarian Energy and Public Utility Regulatory Authority (MEKH)
- System operator
- MAVIR Zrt.
- Distribution networks
- Six regional DSOs: three in the E.ON group, two in the MVM group and OPUS TITÁSZ
- Currency
- Hungarian forint (HUF)
- Voltage and frequency
- 230 V / 50 Hz
Electricity prices in Hungary.
- Household price (HUF)
- 42.3 HUF/kWh (2025-H2)Source 1Eurostat average household price for the 2,500–4,999 kWh/yr band, all taxes and levies included. It blends the regulated price within the 2,523 kWh band with the higher regulated price above it.
- Household price (EUR)
- 0.108 EUR/kWh (2025-H2)Source 1Eurostat’s own EUR figure for the same band (all taxes), converted by Eurostat at its average exchange rate for the period; no separate conversion applied here.
- Typical annual electricity bill
- Not identified from a reliable public source.
Household price trend (HUF per kWh).Source 1
| 2019-H1 | 35.8898 HUF/kWh |
|---|---|
| 2019-H2 | 36.1969 HUF/kWh |
| 2020-H1 | 35.615 HUF/kWh |
| 2020-H2 | 36.0097 HUF/kWh |
| 2021-H1 | 36.1366 HUF/kWh |
| 2021-H2 | 36.0344 HUF/kWh |
| 2022-H1 | 35.5604 HUF/kWh |
| 2022-H2 | 44.1198 HUF/kWh |
| 2023-H1 | 44.0494 HUF/kWh |
| 2023-H2 | 43.3256 HUF/kWh |
| 2024-H1 | 42.6268 HUF/kWh |
| 2024-H2 | 41.3442 HUF/kWh |
| 2025-H1 | 42.0573 HUF/kWh |
| 2025-H2 | 42.3146 HUF/kWh |
Hungarian household bills are shaped mainly by the regulated price scheme known as rezsicsökkentés (utility cost reduction). In its current form, introduced in August 2022, the discounted regulated price covers only consumption up to 2,523 kWh a year at each supply point. Consumption above that band is charged at a separate, higher regulated residential price, which MVM Next quotes as 70.104 HUF/kWh gross for A1/A2 tariffs. That price includes system-use charges and 27% VAT.
The energy component of the regulated prices is set by ministerial decree, 4/2011 (I. 31.) NFM. The figures in its annex exclude VAT, excise duty and system-use charges, which are added separately. Network charges are regulated by MEKH and are uniform nationwide, so households pay the same tariff whichever of the six DSO areas they live in.
Price level and trend
Eurostat puts the average household price for the 2,500–4,999 kWh band at 42.31 HUF/kWh in the second half of 2025, or about €0.108/kWh. That is among the lowest in the EU. The price held at around 36 HUF/kWh from 2018 to the first half of 2022, rose to about 44 HUF/kWh once the band limit was introduced in late 2022, and has stayed between 41 and 44 HUF/kWh since. A household using less than the band pays well below this average, and a heavy user (for example one heating with electricity) pays considerably more.
Regulated prices are financed partly by the state: MVM received public support to maintain universal service. After the April 2026 election the Minister for Economy and Energy said the price scheme would remain for households.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | Universal service from MVM Next. Consumption up to 2,523 kWh a year at a supply point is charged at the discounted regulated price set in 4/2011 (I. 31.) NFM Decree. Above the band the residential A1/A2 price is 70.104 HUF/kWh gross, including system-use charges and 27% VAT. |
| Time-of-use | Yes | A2 is a two-rate tariff. The B (“vezérelt”, controlled) tariff supplies separately metered circuits, such as storage heaters and water heaters, that the DSO switches on during set periods. B has its own 2,523 kWh annual discounted band, and above it the price is 60.935 HUF/kWh gross. |
| Other | Limited | The H tariff is for separately metered heat pumps. It applies a lower regulated rate in the heating season (15 October to 15 April) only. |
| Dynamic | Limited | MVM Next “D árszabás”: customers have been able to apply since 1 September 2026, and it can start on 1 January 2027 at the earliest. Consumption up to the discounted band stays at the A1 price. Above it, each quarter-hour is priced at the HUPX price for that quarter-hour, converted at the MNB exchange rate, plus a trading fee. The tariff needs a remotely read meter with monthly time-series billing. |
| Variable | Limited | Households can buy from a licensed trader on market terms instead of universal service, but they then lose the regulated price. |
Household prices compared with neighbouring countries (EUR per kWh).
- Austria€0.327
- Romania€0.291
- Slovenia€0.212
- Slovakia€0.185
- Croatia€0.166
- Serbia€0.119
- Hungary€0.108
- Ukraine€0.085
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- 3,184 kWh/yr (2024)Source 5Derived: Eurostat household final electricity consumption of 12,876 GWh (2024) divided by 4,043.5 thousand households (Eurostat LFS, 2024). Not a published per-household statistic.
- Average daily use per household
- 8.7 kWh/day (2024)Source 5Derived: 3,184 kWh/yr (see household consumption) divided by 365.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 1,343 kWh/person/yr (2024)Source 5Residential only. Derived: household electricity consumption of 12,876 GWh divided by the population on 1 January 2024 (9,584,627). Total electricity demand per capita (all sectors) was 5.11 MWh in 2025 (Ember).
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- 86,372 battery-electric passenger cars (2025)Source 9Stock of battery-electric cars out of 4,374,763 registered passenger cars (Eurostat).
- Electric cooking
- Not identified from a reliable public source.
Hungarian households used 12,876 GWh of electricity in 2024 (Eurostat energy balance), up from 12,275 GWh in 2020. Spread across about 4.04 million households, that is roughly 3,200 kWh per household a year. The 2,523 kWh discounted band was set at about the average residential consumption, so a typical household sits close to the band limit.
Most homes are heated with natural gas, which also has a regulated household price band. Electricity demand is highest in winter and on very hot summer evenings: MAVIR recorded an all-time peak system load of 8,182 MW on 13 January 2026, and a summer record of 7,488 MW in summer 2026.
Transport electrification is still small but growing quickly: the battery-electric car fleet more than doubled from 41,212 in 2023 to 86,372 in 2025.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- 89.8 % of population (2025)Source 674.7% own outright and 15.1% have a mortgage or loan.
- Private rented
- 4.3 % of population (2025)Source 6Tenants paying market rent.
- Social or public housing
- 5.9 % of population (2025)Source 6Tenants paying reduced rent or living rent-free (Eurostat category). This includes municipal housing but is not limited to it.
- Houses
- 73.3 % of population (2025)Source 767.7% detached and 5.6% semi-detached or terraced.
- Apartments and flats
- 26.5 % of population (2025)Source 720.8% live in buildings with 10 or more dwellings.
- Urban population
- 70.7 % of population (2025)Source 11
Hungary is a country of owner-occupiers living in houses. Nearly 90% of people live in a home their household owns, among the highest rates in the EU, and almost three-quarters live in a house, most of them detached. Flats are concentrated in Budapest and the larger towns, including the large prefabricated estates (panelházak) built from the 1960s to the 1980s.
This housing stock suits rooftop solar, which is why HMKE systems have spread quickly on family homes. In blocks of flats each flat usually has its own supply point and meter, and shared roofs belong to the building’s condominium (társasház), which makes installations harder to organise.
How the grid works in Hungary.
- TransmissionMAVIR Zrt.
- DistributionSix regional DSOs: three in the E.ON group, two in the MVM group and OPUS TITÁSZ
- MeteringFEAK Zrt. (energy data-reporting platform)
- Supply1 or more retail suppliers
Electricity moves from large plants, chiefly the 2 GW Paks nuclear plant, gas-fired plants and utility-scale solar farms, through MAVIR’s 400/220 kV transmission grid to the six DSOs. They take it down to medium and low voltage for homes and businesses. Interconnectors with Austria, Slovakia, Ukraine, Romania, Serbia, Croatia and Slovenia carry the large net imports Hungary depends on: 9.0 TWh in 2025, against domestic generation of 40.2 TWh and demand of 49.2 TWh.
Commercially, generators sell through bilateral contracts and on HUPX, the day-ahead and intraday exchange that is coupled with neighbouring EU markets. Every market participant belongs to a balance group (mérlegkör) whose balance-responsible party settles imbalances with MAVIR. MVM Next buys wholesale power to supply universal-service customers at regulated prices, and the state covers part of the cost.
Household connections are organised entirely through the local DSO. It connects the property, installs and reads the meter, assigns the 33-character POD, and approves any HMKE solar system before it is connected.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry for Economy and Energy | Sets energy policy, including the regulated household price scheme and support programmes. After the April 2026 election energy is part of the economy portfolio. |
| Regulator | Hungarian Energy and Public Utility Regulatory Authority (MEKH) | Independent regulator under Act XXII of 2013. It issues licences, sets network and system-use charges, approves the network codes (including the Distribution Code) and supervises consumer protection. |
| TSO | MAVIR Zrt. | State-owned transmission system operator and system operator. It runs the high-voltage grid, balancing and ancillary services (FCR, aFRR, mFRR) and cross-border capacity, and from 1 October 2026 Hungary takes part in the European aFRR platform PICASSO. |
| DSO | ELMŰ Hálózati Kft. (E.ON group) | Distribution network for Budapest and most of Pest county. |
| DSO | E.ON Észak-dunántúli Áramhálózati Zrt. | Distribution network for northern Transdanubia. |
| DSO | E.ON Dél-dunántúli Áramhálózati Zrt. | Distribution network for southern Transdanubia. |
| DSO | MVM Émász Áramhálózati Kft. | North-east and north: Nógrád, Borsod-Abaúj-Zemplén, Heves and parts of Pest and Jász-Nagykun-Szolnok counties. About 22,000 km of network, more than 400 settlements and 740,000 customers. |
| DSO | MVM Démász Áramhálózati Kft. | Distribution network for south-east Hungary. |
| DSO | OPUS TITÁSZ Zrt. | East and north-east (formerly E.ON Tiszántúli). About 26,177 km of network across nearly 400 settlements and more than 772,000 homes and workplaces. |
| Supplier | MVM Next Energiakereskedelmi Zrt. | Sole universal-service supplier of electricity and gas since E.ON Áramszolgáltató merged into it on 30 June 2024. Supplies almost all households. |
| Exchange | HUPX (Hungarian Power Exchange) | Day-ahead and intraday power exchange, coupled with neighbouring EU markets. Its quarter-hourly prices are the reference for the new dynamic household tariff. |
| Data hub / registry | FEAK Zrt. (energy data-reporting platform) | Runs the energy data-reporting platform that HMKE inverters must be compatible with. Under DSO rules, from 1 August 2026 only inverters on the FEAK-compliant list are accepted for new or extended HMKE. |
Compared with the UK system.
| UK concept | Hungary equivalent | How it works |
|---|---|---|
| DNO | Elosztói engedélyes (licensed DSO) | Six regional DSOs, each a licensed monopoly in its area: ELMŰ Hálózati, E.ON Észak-dunántúli and E.ON Dél-dunántúli (E.ON group), MVM Émász and MVM Démász (MVM group), and OPUS TITÁSZ. Unlike UK DNOs they also own and read the meters, and they handle connection and HMKE approvals directly with the customer. Network charges are set nationally by MEKH and do not vary by region. |
| National Grid/NESO | MAVIR Zrt. | A single state-owned company owns the transmission grid and is also the system operator, combining roles that in Great Britain are split between National Grid Electricity Transmission and NESO. MAVIR buys balancing reserves and accredits units, including aggregated portfolios, to provide them. |
| MPAN | Mérési pont azonosító (POD) | A 33-character alphanumeric code starting with HU, assigned by the DSO that operates the metering point. Its fixed positions encode the operator, voltage level, metering type and connection type, followed by a 20-character operator-defined part. It is printed on every bill and is the reference for switching supplier and for HMKE applications. |
| MPRN | Gas POD (separate system) | Gas supply points have their own identifiers, issued by the gas DSOs. Gas and electricity identifiers are separate, as in the UK. |
| Meter operator | DSO (elosztói engedélyes) | There is no competitive meter-operator market. The DSO owns, installs, replaces and reads the meter, including the bidirectional meter needed for HMKE and the smart meters funded by the EU Recovery and Resilience Facility (RRF). |
| Supplier | Egyetemes szolgáltató / villamosenergia-kereskedő | Households eligible for universal service are supplied by MVM Next at regulated prices. Licensed traders can supply households on market terms, but the household then loses the regulated price, so in practice the household market is not competitive. Business customers buy mainly from licensed traders. |
| Smart-meter infrastructure | DSO-led smart metering (no DCC equivalent) | There is no central communications body like the DCC. Each DSO procures, installs and runs its own smart meters and head-end systems, with RRF-funded programmes run by E.ON and MVM. MAVIR’s Mérési Központ portal gives power plants and balance-responsible parties access to settlement metering data, but it is not a household data hub. |
How a supply point is identified.
HU000210F111S00000000000000123456 (fictional)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Mérési pont azonosító (POD) |
| Who issues it? | The operator of the metering point: in practice the local DSO for households (MAVIR for transmission-level points). |
| Format | Positions 1–2: country code “HU”. Positions 3–8: metering-point operator code (for example 000110 E.ON Észak-dunántúli, 000120 E.ON Dél-dunántúli, 000130 the former E.ON Tiszántúli network now run by OPUS TITÁSZ, 000210 ELMŰ Hálózati, 000220 ÉMÁSZ, 000310 DÉMÁSZ, 001000 MAVIR). Position 9: voltage level (F = 0.4 kV low voltage). Position 10: metering type (1 = main meter). Position 11: reading type. Position 12: connection type (1 = main network connection). Position 13: type of the remaining identifier (U, E = coordinate-based, S = serial number). Positions 14–33: a 20-character string chosen by the operator. Only A–Z and 0–9 are used, and “-” may fill undefined positions. |
| Length | 33 alphanumeric characters |
| Stays with the property when you switch supplier? | Yes |
| Where to find it | Printed on every electricity bill and in the supplier’s and DSO’s online customer portals, usually next to the user ID (felhasználó azonosító) and the address of the supply point (felhasználási hely). |
| Electronic access | Customers see the POD and their consumption in the DSO and supplier portals. Owners of remotely read and smart meters can see interval data where the DSO provides it. There is no single national consumer data portal. |
| Third-party access | The POD is how the DSO and the supplier exchange customer, metering and settlement data. A new trader, or an installer applying for an HMKE connection, uses the POD with the customer’s written authorisation (meghatalmazás). |
| Who keeps the register | Each DSO keeps the register of the metering points it operates. Assignment rules are set in the Distribution Code (Elosztói Szabályzat, annex 20), which MEKH approves. |
| Register scope | Per DSO |
Every Hungarian electricity connection point has a mérési pont azonosító, or POD, which the Distribution Code defines as the unique identifier of the connection point. DSOs and traders use it to exchange customer information, metering data and settlement data. The code is unique nationwide, but each DSO issues and records the PODs on its own network, so there is no central register like the UK’s MPAS.
How the code is built
Unlike the mostly numeric MPAN, the Hungarian POD is a 33-character alphanumeric string with a structure set in annex 20 of the Distribution Code. It begins with HU and a six-digit code identifying the operator of the metering point. The next four characters describe the voltage level (F for 0.4 kV), the type of measurement, the reading role and the type of connection. The 13th character says how the final 20 characters are formed: as a serial number (S), from coordinates (E), or another scheme. A household on the ELMŰ network might therefore have a POD such as HU000210F111S00000000000000123456 (fictional). Operator codes reflect the original companies, so some PODs still carry the codes of DSOs that have since been renamed, such as the former E.ON Tiszántúli network now run by OPUS TITÁSZ.
What it is used for
The POD belongs to the connection point, not the customer, so it stays the same when the occupier or the supplier changes. Households need it to switch trader, to apply for the B or H tariffs, and to start an HMKE application, where the DSO assesses the connection by POD. The regulated 2,523 kWh discounted band is also counted per supply point, and the separately metered B circuit has its own band.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Yes |
| Net metering | Limited |
| Net billing | Yes |
| How exported electricity is paid | Gross billing: all grid consumption is billed at the household’s tariff with full system-use charges, and the HMKE operator invoices the trader monthly for all energy exported, at the feed-in price in their contract. For universal-service households MVM Next prices exports under the rules of 4/2011 NFM Decree, and for non-residential customers at 1 HUF/kWh. Annual net metering continues only for older systems until ten years after commissioning. |
| What size counts as a household system? | An HMKE is a small plant on the low-voltage network whose connection capacity does not exceed 50 kVA at one connection point (Electricity Act, section 3, point 24). It does not need a generation licence. |
| Who can still use annual net metering? | Only HMKE whose connection request was made by 7 September 2023 and that were commissioned before 1 January 2026, and only until ten years after commissioning. Systems commissioned before 1 January 2014 have already moved to gross billing. |
| Are there grid-capacity limits on new solar? | Yes. From 1 November 2022 new HMKE feed-in was suspended on low-voltage circuits that had reached capacity. Partial lifting began on 1 January 2024, and by April 2025 more than 93% of circuits had reopened, but around 6,500 applicants faced waits beyond 2027. |
| Which technical rules apply to inverters? | Inverters must meet annex 6/B of the Distribution Code and be on the DSO’s approved list. Requirements include EU Regulation 2016/631 (RfG) and MSZ EN 50549-1, MSZ EN 62109-1/-2 and MSZ EN 62116. |
| Does exporting change how the meter works? | Yes. The DSO replaces or reprograms the meter so that it measures imports and exports separately. Under gross billing both are settled monthly, and surplus cannot be carried over to later months or other sites. |
Connecting a home system.
- Check that the planned inverter is on the DSO’s list of approved inverters. From 1 August 2026 it must be FEAK-compliant.
- Submit an HMKE connection request (igénybejelentés) to the DSO online, with authorisation if an installer applies on the owner’s behalf.
- The DSO examines the technical conditions and replies within 30 days.
- A professional with design authorisation prepares the connection documentation, and an extract (CSDK) is sent to the DSO within 90 days.
- The DSO approves the plan or asks for changes within 15 days. The approved plan is valid for 365 days, and installation may start only after approval.
- After installation, submit the completion statement and the electrical safety (érintésvédelmi) test report. A registered installer checks the meter position.
- The DSO sends an amended network-use contract within 15 days, replaces or reprograms the meter to measure both directions, and commissions the system.
- Sign a gross-billing contract with the trader; without it, exported energy is not paid for.
Hungary’s rooftop solar boom was built on generous annual net metering (éves szaldó), under which exports offset imports over a whole year. The government changed the rules in September 2023. Since 1 January 2024 new systems, and any system more than ten years old, have been on gross billing (bruttó elszámolás), set out in MEKH Decree 13/2023 and Government Decree 273/2007. Imports and exports are counted separately each month: imports are billed at the household’s tariff with full system-use charges, and exports are paid at a feed-in price in the contract with the trader.
Under gross billing the HMKE operator legally makes a separate sale of electricity, so the household issues an invoice (or accepts the trader’s self-billing statement) for its monthly exports. Constitutional complaints against the transition were filed, and in 2024–2025 the Constitutional Court annulled the cut-off date for applications made between 8 and 12 September 2023 and asked the government to reconsider it.
The change makes self-consumption much more valuable than export, which has driven interest in home batteries and in shifting loads such as hot water and heat pumps into solar hours.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity | No licence for HMKE (up to 50 kVA on low voltage) or for plants below 0.5 MW. A combined small-power-plant licence (kiserőművi összevont engedély) covers construction and operation from 0.5 MW to under 50 MW. A full generation licence is needed from 50 MW. | MEKH | All grid-connected plants still need a DSO or TSO connection agreement. Self-supply units that do not feed the public grid can get a separate self-supply generator (önellátó termelő) licence. |
| Store electricity | Storage is defined in the Electricity Act (section 3, point 70a). Behind-the-meter household storage needs no licence but must be included in the DSO connection approval. Grid-scale storage of 0.5 MW or more follows the generation licensing and connection regime. | MEKH / DSO / MAVIR | Storage of at least 0.5 MW commissioned after 1 January 2024 with aFRR accreditation qualifies for a reduced transmission charge. |
| Export to the grid | No licence for HMKE. A gross-billing contract with the trader is needed to be paid for exports. | DSO (connection); trader (contract) | Each HMKE export is a separate sale for VAT and invoicing purposes. |
| Sell / supply electricity to consumers | Electricity trading licence (villamosenergia-kereskedelmi engedély). Universal service is a separately designated activity, now carried out only by MVM Next. | MEKH | Selling to households on market terms means they leave the regulated price. |
| Wholesale trading | Electricity trading licence, plus HUPX membership for exchange trading and a balance-group arrangement. | MEKH; HUPX | Traders also register under EU REMIT. |
| Aggregate | Aggregators are recognised market actors (Electricity Act, section 3, point 3a). To provide reserves they need MAVIR accreditation of the aggregated portfolio and a balance-group arrangement. An independent aggregator framework is being legislated. | MAVIR (accreditation); MEKH | Aggregators already operate portfolios of several hundred MW in aFRR. |
| Balancing / grid services | MAVIR prequalification (accreditation) for each product (FCR, aFRR, mFRR). The minimum bid is 1 MW, and pooling is allowed. | MAVIR | From 1 October 2026 accredited aFRR providers can offer energy through the European PICASSO platform. |
| Virtual power plant / remote control of assets | No separate licence, but the portfolio is accredited by MAVIR as an aggregated unit. Household devices must use approved inverters and must not breach DSO connection conditions. | MAVIR; DSO | From 1 August 2026 new HMKE inverters must be compatible with the FEAK data-reporting platform. |
Licensing is set by Act LXXXVI of 2007 on electricity (VET) and administered by MEKH. The key thresholds are 50 kVA, below which a low-voltage system is a household plant (HMKE) handled only by the DSO, and 0.5 MW, above which a generation licence is needed. Between 0.5 MW and 50 MW a single combined licence covers construction and operation.
The law also recognises the active customer (aktív felhasználó, section 3, point 17a): a consumer who produces or stores renewable energy on site and sells surplus without this being their main business. Market roles such as trading, universal service and system operation need MEKH licences, while participation in balancing markets depends on MAVIR technical accreditation rather than a licence.
Flexibility and grid services.
Aggregation of home equipment: Yes
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Frequency Containment Reserve (FCR) | Yes | 1 MW | Yes | MAVIR. Capacity procured by MAVIR from accredited units and aggregated portfolios. |
| Automatic Frequency Restoration Reserve (aFRR) | Yes | 1 MW | Yes | MAVIR / PICASSO. Grid-scale batteries, gas plants and aggregated solar portfolios are accredited. Hungary joins PICASSO from 1 October 2026, opening cross-border aFRR energy activation. |
| Manual Frequency Restoration Reserve (mFRR) | Yes | 1 MW | Yes | MAVIR. Capacity and energy bids from accredited units and portfolios. |
| Day-ahead and intraday wholesale | Restricted | — | Limited | HUPX. Open to licensed traders and balance groups. Households take part only indirectly, through the dynamic tariff from 2027. |
| Household demand response | Developing | — | No | The main household flexibility tools are the DSO-switched B tariff and, from 2027, the HUPX-linked dynamic tariff. No household flexibility market operated by a DSO was identified. |
Hungary’s flexibility market is the TSO’s reserve market. MAVIR procures FCR, aFRR and mFRR from accredited units, with a 1 MW minimum bid, and aggregated portfolios of smaller units are allowed. Rapid solar growth has increased the need for balancing, and new grid-scale batteries are being accredited for aFRR.
Household assets are not yet active in these markets. Distributed flexibility has been limited by regulated household prices, the absence of a dynamic tariff until 2027 and limited smart metering. The government elected in 2026 has listed dynamic tariffs, an independent aggregator framework and wider smart-meter deployment among its legislative priorities.
Flexibility and aggregation platforms.
| Platform or aggregator | What it does |
|---|---|
| PICASSO | European aFRR energy platform. MAVIR connects from 1 October 2026. |
| HUPX | Hungarian day-ahead and intraday power exchange. |
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | DSO-led, partly funded by the EU Recovery and Resilience Facility (RRF); no national mandate for all homes |
| Reading interval | 15 minutes for the dynamic tariff; most households are still read annually |
| E.ON smart meters before April 2024 | 432,000 |
| E.ON RRF programme | 165,000+ new smart meters, HUF 10.1 billion |
| MVM RRF first phase | 89,000+ smart meters, over HUF 5 billion EU support |
| MVM 2030 goal | 650,000 smart meters |
| Meter owner | Local DSO |
Smart metering in Hungary is the responsibility of the DSOs, which own and read all meters. The E.ON group, which runs ELMŰ Hálózati and the two Transdanubian networks, had installed 432,000 smart meters before April 2024 and was adding more than 165,000 under an RRF-funded programme. The two MVM DSOs began a first phase of more than 89,000 meters in 2024 and aim for 650,000 by 2030.
Most households still have conventional meters read once a year, with monthly bills based on estimates or self-reading. HMKE owners get a bidirectional meter, and the dynamic tariff needs a remotely read meter with monthly time-series billing, for which the DSO may charge an installation fee.
Renewable electricity.
Electricity generation mix (2025).
- Nuclear: 40%
- Solar: 27.3%
- Gas: 20.3%
- Bioenergy: 5.9%
- Coal: 3.4%
- Wind: 1.5%
- Other fossil: 1%
- Hydro: 0.6%
- Renewable electricity share
- 35.3% (2025)Source 12Share of domestic generation (solar 27.29%, bioenergy 5.94%, wind 1.49%, hydro 0.57%). Including nuclear, low-carbon sources were 75.32%. The EU directive-based RES-E share of consumption was 28.3% (Eurostat).
- Home solar
- 2,733 MW (April 2025)Source 24300,562 HMKE systems in operation in early April 2025, more than a third of 7,712 MW total solar (MAVIR data cited by the Ministry of Energy).
- Solar added each year
- 1.4 GW (2024)Source 25Hungarian Photovoltaic Industry Association figure reported by pv magazine.
- Solar
- 8.18 GW (2025)Source 12
- Nuclear
- 2.03 GW (2025)Source 12
- Gas
- 4.18 GW (2025)Source 12
- Coal
- 1.01 GW (2025)Source 12
- Bioenergy
- 0.62 GW (2025)Source 12
- Wind
- 0.32 GW (2025)Source 12
- Hydro
- 0.06 GW (2025)Source 12
Targets.
- Wind: from about 330 MW to around 4 GW by 2030, through annual competitive auctions. The first tender was raised to nearly 1,000 MW and was expected to be published by the end of August 2026.
- Battery storage: 1 GW of discharge capacity by 2030 under the National Energy and Climate Plan.
Hungary’s electricity mix rests on nuclear and solar. Paks supplied 40% of generation in 2025, and solar produced 10.98 TWh, or 27.3%, up from 24.2% in 2024. Wind has barely grown since the mid-2010s because of strict siting rules. Gas supplies about a fifth of generation, and coal is down to 3.4%.
Solar growth has been driven by utility-scale plants and by more than 300,000 household HMKE systems: the 100,000th was connected in 2021, the 200,000th in 2023 and the 300,000th in March 2025. On 13 June 2025 solar output peaked at about 6.2 GW, close to the whole system load at that moment.
Wind is restarting. Since 1 January 2026 the Electricity Act has allowed turbines with hub heights of up to 199 metres in designated simplified zones, and the government elected in April 2026 has announced annual auctions aimed at about 4 GW by 2030.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
Grid-scale storage in Hungary is mostly lithium-ion batteries built for MAVIR’s balancing markets and for arbitrage, much of it co-funded through Recovery and Resilience Facility calls. Storage of at least 0.5 MW commissioned after 2024 that holds aFRR accreditation qualifies for a reduced transmission charge.
Home batteries became more attractive once gross billing made exported solar worth much less than self-consumed solar. The 2026 home storage programme (Otthoni Energiatároló Program) drew 132,000 applications, but it was suspended on 16 March 2026, and as of late August 2026 the new government had not confirmed how it would continue.
Storage projects.
- Buj Battery and Buj Energy Storage (Szabolcs-Szatmár-Bereg): Two adjacent 49.9 MW / 144.288 MWh battery systems (99.8 MW / 288.6 MWh in total), both commissioned in June 2026 and described by the developer as Hungary’s largest. Their aFRR capability was accredited by MAVIR, and they were co-funded under the RRF-6.5.1-23 grid-scale storage call.
- RRF-6.5.1-23 grid-scale storage call: An EU Recovery Facility call funding storage that can take part in balancing energy and capacity markets.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| MVM Next Energiakereskedelmi Zrt. | Sole universal-service supplier since 30 June 2024, serving almost all households | Unknown | Yes | Limited | Yes |
In practice the household market has one supplier. MVM Next took over E.ON’s universal-service business on 30 June 2024 and is now the only universal-service supplier of electricity and gas. A household can contract with a licensed trader instead, but would lose the regulated price.
Business customers are supplied mainly by licensed traders on market terms, and micro-enterprises can still use universal service, with a discounted band of 4,606 kWh a year.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| MEKH | Regulator | Energy and utilities regulator | Licensing, network tariffs, network codes and HMKE grid-capacity information. |
| MAVIR Zrt. | Transmission | Transmission and system operator | System data, balancing-market accreditation and the Mérési Központ metering-data portal. |
| E.ON Hungária group (ELMŰ Hálózati, E.ON Észak-dunántúli, E.ON Dél-dunántúli) | Distribution | DSOs for Budapest, Pest and Transdanubia | HMKE connection process, approved inverter list and distribution code. |
| MVM Émász and MVM Démász Áramhálózati | Distribution | DSOs for the north-east and south-east | Connections and smart-meter rollout in the MVM network areas. |
| OPUS TITÁSZ Zrt. | Distribution | DSO for eastern Hungary | Connections and HMKE approvals in the Tiszántúl region. |
| HUPX | Market | Power exchange | Day-ahead and intraday reference prices, used by the dynamic tariff. |
| FEAK Zrt. | Metering | Energy data-reporting platform | Inverter compatibility needed for new HMKE from August 2026. |
| Magyar Napelem Napkollektor Szövetség (MANAP) | Solar | Solar industry association | Industry data on solar deployment. |
| MVM Next | Consumer | Universal-service supplier | Regulated household tariffs, gross billing and the dynamic tariff. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Grid connection (generators) | EU Regulation 2016/631 (RfG); Distribution Code annex 6/B | European Commission; DSOs (approved by MEKH) | HMKE must meet the RfG requirements for generating units and the DSO’s inverter requirements. |
| Inverters | MSZ EN 50549-1; MSZ EN 62109-1/-2; MSZ EN 61000-6-x | Hungarian Standards Institution (MSZT), adopting CENELEC/IEC | Only inverters on the DSO’s approved list may be used. From 1 August 2026 the list is limited to FEAK-compliant devices, and hybrid inverters are marked. |
| Anti-islanding | MSZ EN 62116 | MSZT / IEC | The approved list also shows whether an inverter can run in island mode and what disconnection device it needs. |
| Installation and safety | Electrical safety (érintésvédelmi) inspection; registered meter-point installer | DSOs; Distribution Code | A first safety inspection is needed before commissioning, and the meter position must be checked by a DSO-registered installer. |
| Design | Connection documentation (CSDK) by a designer with design authorisation | DSOs | Required for every HMKE application. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| DSO approval for HMKE | Yes | National | A connection request followed by DSO approval of the connection documentation is needed before installation. The approved plan is valid for 365 days. |
| Generation licence | No | National | Not needed for HMKE (up to 50 kVA) or plants under 0.5 MW. |
| Grid capacity | Limited | Regional | Feed-in may be refused or deferred on low-voltage circuits that have reached capacity. Most circuits have reopened since 2024, but waiting lists remain in some areas. |
| Supplier contract for export | Yes | National | A gross-billing contract with the trader is needed to be paid for exports. |
For a household, the main approval is the DSO’s: the connection request, approval of the connection documentation, commissioning and replacement of the meter. Large ground-mounted plants and wind turbines also need building and environmental permits from the government offices (kormányhivatalok), as well as MEKH licences above 0.5 MW.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Regulated discounted price band (rezsicsökkentés) | Active | Regulated price | Universal-service households pay the discounted regulated price for up to 2,523 kWh a year per supply point, with a separate band for B-tariff circuits. Consumption above the band is charged at 70.104 HUF/kWh gross. | — |
| HMKE gross billing (export payment) | Active | Export payment | Monthly payment for all exported energy at the feed-in price in the contract with the trader. Older systems keep annual net metering until ten years after commissioning. | From 1 January 2024 |
| Otthoni Energiatároló Program (home energy storage programme) | Closed | Grant | Grants of up to HUF 2.5 million for home solar with storage, prioritising households that have left annual net metering. Applications were taken from 2 February to 15 March 2026 (132,000 applied, budget HUF 105.5 billion), and the programme was suspended on 16 March 2026. As of late August 2026 the government intended to continue it with changes, but no details had been published. | Applications 2 Feb – 15 Mar 2026 |
| Napenergia Plusz Program | Closed | Grant | A 2024 grant scheme of up to HUF 5 million per home for residential solar with storage. The budget was HUF 75.8 billion plus HUF 30 billion added in July 2024. | 2024 |
| RRF smart-meter programmes | Active | Grant (to DSOs) | EU Recovery and Resilience Facility funding for DSO smart-meter installations, run by E.ON and MVM. | — |
Data and connectivity.
- Fixed broadband
- 93.9 % of households (2025)Source 8Households with internet access (Eurostat).
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
Almost all Hungarian households have internet access, which supports app-based monitoring of inverters and batteries. From August 2026, inverters for new HMKE must be compatible with the FEAK energy data-reporting platform, which brings generation data from household systems into a common reporting system.
Grid conditions.
- National peak demand
- 8.182 GW (13 Jan 2026)Source 23All-time record gross system load recorded by MAVIR.
- Annual electricity demand
- 49.2 TWh (2025)Source 12
- Generation capacity
- 16.9 GW (2025)Source 12Derived: sum of Ember clean (11.23 GW) and fossil (5.64 GW) capacity.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
The Hungarian grid combines a large, inflexible baseload source (Paks), very fast solar growth and heavy reliance on imports. Midday solar can nearly cover the whole system load in summer, while the evening peak depends on gas, imports and the reserve market.
Summer 2026 showed how exposed the system is. During a heatwave from late July, record-low Danube levels limited Paks’s cooling water. Units were cut back and shut down, and by 4 August 2026 only one 240 MW turbine was running. Supply was maintained through imports and demand appeals from network companies, and the units were restarted once the river rose.
At distribution level, some low-voltage circuits reached their limits for solar feed-in in 2022, which led to HMKE connection suspensions that have mostly been lifted since 2024.
Grid and capacity maps.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Annual net metering closed to new HMKE; gross billing | Current | 1 January 2024 | New systems, and systems ten years after commissioning, are settled monthly on gross billing (MEKH Decree 13/2023, Government Decree 273/2007). |
| Wind siting rules eased | Current | 1 January 2026 | Turbines with hub heights of up to 199 m are allowed in designated simplified zones. |
| FEAK-compliant inverters only | Current | 1 August 2026 | DSOs accept only FEAK-compliant inverters for new or extended HMKE and inverter replacements. |
| Hungary joins PICASSO | Current | 1 October 2026 | MAVIR connects to the European aFRR platform, so accredited providers can offer balancing energy across borders. |
| Household dynamic tariff (MVM Next D tariff) | Upcoming | 1 January 2027 | Quarter-hourly HUPX-linked pricing above the discounted band for customers with remotely read meters. Applications have been open since 1 September 2026. |
| Wind auctions towards 4 GW by 2030 | Upcoming | 2026 onwards | Annual competitive auctions, the first of nearly 1,000 MW, alongside planned legislation on dynamic tariffs, independent aggregators, renewable permitting and smart meters. |
| Future of the home energy storage programme | Upcoming | Not announced | Suspended since 16 March 2026. The government has said it intends to continue it with changes. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Low | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | Medium | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | Medium | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | High | 300,562 household systems with 2,733 MW in operation in April 2025, on a housing stock where 73% of people live in houses. |
| Distributed energy market | Medium | Strong rooftop solar, but net metering has closed, some low-voltage circuits have been restricted, and household storage and EV numbers are still modest. |
| Grid flexibility market | Medium | TSO reserve markets are open to aggregated portfolios (1 MW minimum) and PICASSO accession starts in October 2026, but there is no household flexibility market and no dynamic tariff until 2027. |
| Energy storage adoption | Low | Grid-scale batteries are only now coming online (the largest site, Buj, has two 49.9 MW units commissioned in June 2026), there is no national storage statistic, and the home storage grant has been suspended. |
| Renewable growth environment | High | Solar rose from 24.2% to 27.3% of generation between 2024 and 2025, and wind auctions aim for about 4 GW by 2030. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 37 sources
- Electricity prices for household consumers — bi-annual data (nrg_pc_204). Eurostat, 2025. accessed 1 October 2026.
- Population on 1 January (tps00001). Eurostat, 2026. accessed 1 October 2026.
- Number of private households by household composition (lfst_hhnhtych). Eurostat, 2025. accessed 1 October 2026.
- Average household size — EU-SILC (ilc_lvph01). Eurostat, 2025. accessed 1 October 2026.
- Complete energy balances — households, electricity (nrg_bal_c). Eurostat, 2024. accessed 1 October 2026.
- Distribution of population by tenure status (ilc_lvho02). Eurostat, 2025. accessed 1 October 2026.
- Distribution of population by degree of urbanisation and dwelling type (ilc_lvho01). Eurostat, 2025. accessed 1 October 2026.
- Level of internet access — households (isoc_ci_in_h). Eurostat, 2025. accessed 1 October 2026.
- Passenger cars by type of motor energy (road_eqs_carpda). Eurostat, 2025. accessed 1 October 2026.
- Share of energy from renewable sources (nrg_ind_ren). Eurostat, 2025. accessed 1 October 2026.
- Urban population (% of total population) — Hungary. World Bank, 2025. accessed 1 October 2026.
- Yearly electricity data (generation, capacity, demand, imports) — Hungary. Ember, 2025. accessed 1 October 2026.
- Részletes információk — áram (regulated band, residential market prices). MVM Next. accessed 1 October 2026.
- Szeptembertől igényelhető az MVM új, dinamikus áramtarifája. MVM Next, 2026. accessed 1 October 2026.
- D árszabás. MVM Next, 2026. accessed 1 October 2026.
- Bruttó HMKE elszámolás. MVM Next. accessed 1 October 2026.
- 4/2011. (I. 31.) NFM rendelet a villamos energia egyetemes szolgáltatás árképzéséről. Nemzeti Jogszabálytár, 2026. accessed 1 October 2026.
- 2007. évi LXXXVI. törvény a villamos energiáról (VET). Wolters Kluwer Jogtár, 2026. accessed 1 October 2026.
- Tájékoztatás a háztartási méretű kiserőművek (HMKE) bruttó elszámolásáról. E.ON Hungária. accessed 1 October 2026.
- Háztartási méretű kiserőművek (HMKE) hálózatra kapcsolási folyamata. E.ON Hungária. accessed 1 October 2026.
- HMKE-kben alkalmazható inverterek listája. E.ON Hungária, 2026. accessed 1 October 2026.
- Elosztói Szabályzat — mellékletek (20. sz. melléklet: a mérési pont azonosító felépítése). E.ON Hungária, 2021. accessed 1 October 2026.
- Az egekben az áramfogyasztás. Infostart (MAVIR data), 2026. accessed 1 October 2026.
- Rég várt adat a lakossági napelemekről. Infostart (Ministry of Energy, MAVIR data), 2025. accessed 1 October 2026.
- Hungary’s solar capacity nears 8 GW. pv magazine, 2025. accessed 1 October 2026.
- Hungary expected to surpass 300,000 residential solar installations. pv magazine, 2024. accessed 1 October 2026.
- Napelemes csatlakozási tilalom (HMKE). Világgazdaság, 2025. accessed 1 October 2026.
- MVM: leáll az áramszámlázás — az E.ON Áramszolgáltató beolvad az MVM Nextbe. Economx, 2024. accessed 1 October 2026.
- Szintet lép az E.ON Hungária. Infostart, 2024. accessed 1 October 2026.
- Nagy bejelentést tett az MVM. Infostart, 2024. accessed 1 October 2026.
- Battery energy storage facility with a nominal power capacity of 49.9 MW has been established in Buj. Greenvolt Power, 2026. accessed 1 October 2026.
- Energiatárolási piaci helyzetkép. KPMG Hungary, 2025. accessed 1 October 2026.
- Otthoni Energiatároló Program — állami támogatás, Tisza-kormány. Economx, 2026. accessed 1 October 2026.
- Kapitány István a parlamenti bizottság előtt. Infostart, 2026. accessed 1 October 2026.
- Hungary lifts wind power expansion freeze, targets more than tenfold capacity increase by 2030. Renewable Energy Industry, 2026. accessed 1 October 2026.
- Successful PICASSO accreditation at ALTEO. BCSDH (ALTEO member news), 2026. accessed 1 October 2026.
- Paksi erőmű: Duna-vízszint, az utolsó turbina. Economx, 2026. accessed 1 October 2026.
Questions about energy in Hungary.
Eurostat puts the average household price at 42.31 HUF/kWh (about €0.108/kWh) in the second half of 2025, including all taxes, one of the lowest in the EU. Universal-service households pay a discounted regulated price for up to 2,523 kWh a year, and 70.104 HUF/kWh gross above that.
The mérési pont azonosító (POD), a 33-character alphanumeric code starting with HU. The DSO assigns it to the connection point, and it is printed on every electricity bill. It encodes the network operator, voltage level and connection type, and stays with the property when the occupier changes.
Yes. Household systems of up to 50 kVA (HMKE) can export after DSO approval. Systems requested after 7 September 2023 are on gross billing: all imports are billed and all exports are paid monthly at the feed-in price in your contract with the trader. Older systems keep annual net metering until ten years after commissioning.
MAVIR runs the transmission grid and the system as a whole. Six regional DSOs run the local networks: ELMŰ Hálózati, E.ON Észak-dunántúli and E.ON Dél-dunántúli (E.ON group), MVM Émász and MVM Démász (MVM group), and OPUS TITÁSZ. MEKH regulates the sector.
Legally yes, but households that leave universal service lose the regulated price, so almost all households are supplied by MVM Next, the only universal-service supplier since June 2024.
From 1 January 2027 MVM Next offers a dynamic D tariff. Consumption above the discounted band is priced every quarter-hour from HUPX exchange prices, and the tariff needs a remotely read meter. Applications opened on 1 September 2026.
No generation licence is needed for household systems of up to 50 kVA or plants under 0.5 MW, but the DSO must approve the connection documentation before installation, and the inverter must be on the DSO’s approved list.