Countries

Energy in Dominica, explained.

How electricity works in Dominica: prices, the grid and local rules. Olmack status: Not yet available. Information last checked 10 October 2026.

Olmack in Dominica: Not yet available.Olmack is not offered in Dominica yet. The market information on this page is provided for reference. Information last checked 10 October 2026.
Energy-market overview

How electricity works in Dominica.

Dominica electricity 2026: DOMLEC sole utility regulated by the IRC, prices near US$0.33/kWh, new 10 MW geothermal plant, AMI meters and a new time-of-use tariff.

This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in East Caribbean dollar (XCD) where they relate to prices.

Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.

At a glance

Dominica energy at a glance.

Key figures for households in Dominica. Each one links to its source on the full overview below.

  • Electricity price.

    0.33 USD per kWh for households, including taxes. Figures for 2022.

  • Household use.

    1,437 kWh a year for a typical household. Figures for 2016.

  • Renewable share.

    20.3% of electricity from renewable sources. Figures for 2021.

  • Selling back to the grid.

    Can homes export electricity? Limited. Details are in the export section below.

Before you start

Four things to check in Dominica.

Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.

  1. Check the local rules.

    Read the connection, export and permission rules for Dominica below, and ask your local grid operator if anything is unclear.

  2. Choose a qualified installer.

    Look for an installer listed on an official register, with the certifications Dominica requires for the work.

  3. Look at current schemes.

    Check which support schemes are open now. Closed or scheduled schemes are labelled as such.

  4. Talk to your energy supplier.

    Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.

Local detail

Schemes, rules and certifications in Dominica.

The full detail sits in the sections below. Each item shows its status and links to the official source.

  • Support schemes.

    Grants, tax relief and export payments in Dominica, each labelled Active, Scheduled or Closed.

  • Connection and export.

    How equipment is connected to the grid in Dominica, and the steps to export electricity.

  • Standards and certifications.

    The technical standards and installer certifications that apply to energy equipment in Dominica.

Full overview

The energy market in Dominica, in detail.

Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.

Profile last updated 10 October 2026.

On this page22 sections

The Commonwealth of Dominica has a single island grid run by Dominica Electricity Services Ltd (DOMLEC), which holds a 25-year exclusive licence to transmit, distribute and supply electricity and a 25-year non-exclusive generation licence, both from 1 January 2014. The sector is regulated by the Independent Regulatory Commission (IRC), set up under the Electricity Supply Act No. 10 of 2006, which came into force on 1 March 2007. In March 2022 the Government owned 52% of DOMLEC, Dominica Social Security 20% and private shareholders 28%.

Until 2026 electricity came from diesel and run-of-river hydro. In 2022 DOMLEC had 25.52 MW of installed capacity (18.88 MW diesel at Fond Cole and Sugar Loaf, 6.64 MW hydro in the Roseau Valley), generated 89 GWh and met a peak demand of 16.35 MW, according to the World Bank. Retail prices were around US$0.33/kWh. A 10 MW geothermal plant owned by an independent power producer reached commercial operation on 31 July 2026 and sells to DOMLEC under a power purchase agreement; a 6 MW / 6 MWh battery system supports the grid.

Government and IRC policy aims for 100% renewable electricity by 2030. The IRC completed a DOMLEC rate review in 2026, and a new tariff with an off-peak (time-of-use) option took effect on 1 October 2026. A new framework for distributed renewable generation such as rooftop solar is being prepared.

Energy snapshot.

Headline figures for electricity in Dominica. Each shows its data year and links to its source.

  • Population65,871 peopleSource 12025
  • HouseholdsNot identified from a reliable public source.
  • Average household sizeNot identified from a reliable public source.
  • Electricity use per household1,437 kWh/yrSource 102016
  • Household price (XCD)0.33 USD/kWhSource 62022
  • Household price (EUR)0.295 EUR/kWhSource 322022
  • Renewable electricity share20.3%Source 32021
  • Solar capacityNot identified from a reliable public source.
  • Wind capacityNot identified from a reliable public source.
  • Energy storage capacity6 MWhSource 312025
  • Smart-meter shareNot identified from a reliable public source.
Market structure
Vertically integrated
Homes can export to the grid
Limited
Home equipment in grid services
No
Regulator
Independent Regulatory Commission (IRC)
System operator
DOMLEC (operates the single island grid; no separate system operator)
Distribution networks
One utility, DOMLEC, holds the exclusive transmission, distribution and supply licence for the whole island
Currency
East Caribbean dollar (XCD)
Voltage and frequency
Not confirmed from an official source

Electricity prices in Dominica.

Household price (XCD)
0.33 USD/kWh (2022)Source 6The World Bank states that electricity tariffs reached around 33 US cents/kWh, reflecting high diesel prices in 2022; it gave the same level for December 2016. Tariffs are billed in East Caribbean dollars; the current residential rate schedule (from 1 October 2026) could not be read from an official page.
Household price (EUR)
0.295 EUR/kWh (2022)Source 32Converted from US$0.33/kWh at the ECB reference rate of USD 1.1206 per euro on 9 October 2026.
Typical annual electricity bill
474 USD/yr (Derived (2016 consumption, 2022 price))Source 10Derived: 1,437 kWh a year (average domestic sales per DOMLEC domestic customer, CSO 2016) × about US$0.33/kWh (World Bank, 2022). Illustrative only; excludes VAT on consumption above 100 kWh a month.

Household price trend (XCD per kWh).Source 6

0.330.830.33Dec 2016 (approx.)2022 (approx.)
Dominica household electricity price, XCD per kWh
Dec 2016 (approx.)0.33 XCD/kWh
2022 (approx.)0.33 XCD/kWh

How tariffs are set

The Independent Regulatory Commission determines DOMLEC’s tariffs from its revenue requirement, which covers operating and financing costs and the cost of any obligations imposed by the government. The tariff regime dates from an IRC decision of 13 May 2010. The 2026 rate review was based on a cost-of-service study with a 2023 test year; DOMLEC filed for a 4% increase. Because the IRC was without a Board of Commissioners for a period, DOMLEC questioned the Executive Director’s authority to approve tariffs; a five-member board chaired by Kevin Julien was announced on 12 August 2026.

What is on a bill

Bills combine regulated energy charges with a fuel surcharge that passes through DOMLEC’s diesel costs. VAT at 15% is charged only on consumption above the first 100 units each month. Meters are read and bills issued monthly. A new domestic account needs a minimum deposit of $125, on which interest is paid.

Why prices are high and what may change

Diesel has supplied most electricity, so bills have tracked oil prices: the World Bank reports tariffs of around 33 US cents/kWh in 2022, when DOMLEC’s fuel costs rose by 54%. Geothermal power from the new 10 MW plant is expected by the World Bank to cost about 12 US cents/kWh, and the IRC has said it expects geothermal generation to be reflected in lower monthly bills; it is monitoring bills and DOMLEC’s revenues from August to the end of 2026.

Tariff types.

Tariff types.
TariffAvailableDetail
RegulatedYesDOMLEC’s tariffs are set by the IRC from the utility’s revenue requirement. The IRC published DOMLEC’s cost-of-service and revised rate proposal (a 4% filing, 2023 test year) on 2 April 2026, consulted in April and May, and a new tariff took effect on 1 October 2026.
Time-of-useYesThe tariff effective 1 October 2026 introduces an off-peak pricing option so that customers can shift electricity-intensive activities to lower-rate periods. Period times and rates were not published on the pages read.
PrepaymentYesDOMLEC’s Pay-As-You-Go (PAUG) service runs on its AMI meters. The unit price is the same for prepaid and post-paid accounts; the meter beeps when credit falls to 30 units or below.
OtherYesA fuel surcharge is added, calculated as gallons of fuel used × average fuel cost ÷ total units sold. VAT of 15% applies only to consumption above 100 units (kWh) a month.
DynamicNoThere is no wholesale market, so no market-linked tariffs exist.
FixedNoDOMLEC is the sole supplier, so there is no choice of supplier or fixed-price contract.

Household prices compared with neighbouring countries (EUR per kWh).

Household prices including taxes, converted to euros as stated on each country page.

Household electricity use.

Electricity use per household
1,437 kWh/yr (2016)Source 10Derived: domestic sales of 45,847.3 MWh ÷ 31,913 domestic customers at year end (Central Statistics Office, 2016). Average per domestic account, not per household. 2016 is the last full year before Hurricane Maria.
Average daily use per household
3.9 kWh/day (2016)Source 10Derived: 1,437 kWh a year per domestic customer ÷ 365.
Typical household peak demand
Not identified from a reliable public source.
Electricity use per person
Not identified from a reliable public source.
Heat pumps
Not identified from a reliable public source.
Air conditioning
Not identified from a reliable public source.
Electric vehicles
Not identified from a reliable public source.
Electric cooking
Not identified from a reliable public source.

Households are DOMLEC’s largest customer group. In 2016 domestic customers bought 45,847 MWh of the 99,384 MWh sold, and numbered 31,913 out of 36,467 customers (Central Statistics Office). The World Bank reports that in 2022 about 47% of the 89 GWh generated was sold to households, 43% to commercial customers and 10% to industry, hotels and street lighting.

Hurricane Maria in September 2017 sharply reduced demand: CSO figures show total sales falling from 99,384 MWh in 2016 to 77,597 MWh in 2017. The World Bank estimates the storm damaged 90% of housing and caused US$33 million of damage to the power system. Some businesses also run their own diesel generators; the World Bank estimates about 15 MW of self-generation capacity.

Housing and households.

Dwellings
Not identified from a reliable public source.
Owner-occupied
Not identified from a reliable public source.
Private rented
Not identified from a reliable public source.
Social or public housing
Not identified from a reliable public source.
Houses
Not identified from a reliable public source.
Apartments and flats
Not identified from a reliable public source.
Urban population
74 % of population (2025)Source 2World Bank estimate (73.99%).

Dominica is an island of 754 km², and its housing is highly exposed to hurricanes: the World Bank reports that Hurricane Maria damaged about 90% of the housing stock in 2017, and a World Bank housing recovery project followed. Official tenure and dwelling-type figures were not available in a readable form.

To connect a home, DOMLEC asks for proof of ownership, identification and an electrical fitness certificate for the wiring, which links electrical safety inspection to the supply connection.

How the grid works in Dominica.

  1. TransmissionDOMLEC, DOMLEC
  2. DistributionOne utility, DOMLEC, holds the exclusive transmission, distribution and supply licence for the whole island
  3. MeteringDOMLEC
  4. Supply1 or more retail suppliers

Physical structure

In 2022 the World Bank recorded 25.52 MW of installed capacity on DOMLEC’s system: 18.88 MW of diesel at Fond Cole and Sugar Loaf and 6.64 MW from three run-of-river hydro plants in the Roseau Valley. DOMLEC commissioned 4.8 MW of leased generation in May 2025 and a 6 MW / 6 MWh battery system. A 10 MW geothermal plant (two 5 MW units) entered commercial operation on 31 July 2026.

To connect the plant, the World Bank-financed Geothermal Risk Mitigation II project (US$38.5 million IDA credit, approved January 2024) funds a 69 kV overhead line of about 7.6 km and a 33 kV underground line of about 11 km to Fond Cole, an 11 kV line to Laudat, and new substations at Fond Cole (69/33/11 kV), New Trafalgar and Padu.

Security of supply

The IRC has explained that if one geothermal unit trips, the battery can hold the grid stable for about two and a half hours while DOMLEC starts backup engines. Losing both units at once is the one event identified as able to cause an island-wide outage, and the IRC, DOMLEC and the plant operator are working on it. Managing low demand in the early morning, when geothermal output is high relative to load, is another open issue.

Commercial flow

There is no wholesale market. DOMLEC generates from its own plant and buys geothermal output under a power purchase agreement with the independent power producer, then sells to all customers at IRC-approved tariffs. Generation licences for other parties are issued by the IRC; in January 2024 it approved the transfer of a generation licence from the Dominica Geothermal Development Company (DGDC), the state-owned developer, to GPCD.

Who does what.

Who does what.
RoleOrganisationWhat it does
RegulatorIndependent Regulatory Commission (IRC)Established by the Electricity Supply Act 2006. Licenses generation, transmission, distribution and supply, sets DOMLEC’s tariffs, sets quality-of-service standards with compensation payments, handles customer appeals and publishes grid codes and interconnection policies.
SupplierDominica Electricity Services Ltd (DOMLEC)The island’s only utility. Holds a 25-year exclusive transmission, distribution and supply licence and a 25-year non-exclusive generation licence from 1 January 2014. Owned 52% by the Government, 20% by Dominica Social Security and 28% by private shareholders (March 2022). About 37,000 customers (2022).
TSODOMLECOwns and runs the island network, including new 69 kV and 33 kV lines and substations built under the World Bank-financed Geothermal Risk Mitigation II project to connect the geothermal plant to Fond Cole.
DSODOMLECSole distribution network operator. Transmission and distribution losses were 8.2% in 2022.
System operatorDOMLECDispatches its diesel and hydro units, the battery system and the geothermal plant, and runs backup engines if a geothermal unit trips.
MeteringDOMLECOwns all meters; operates an Advanced Metering Infrastructure (AMI) system with remote reading and reconnection, and the Pay-As-You-Go prepaid service.

Compared with the UK system.

Compared with the UK system.
UK conceptDominica equivalentHow it works
DNODOMLECThere is no separate network company. DOMLEC holds the single, island-wide exclusive licence to transmit, distribute and supply electricity.
National Grid/NESODOMLECDominica has one isolated grid with no interconnection to neighbouring islands. DOMLEC balances it with diesel, hydro, a battery system and power bought from the geothermal plant.
MPANDOMLEC account number (and meter number)A connection is identified by the account number DOMLEC assigns, printed on the bill, together with the meter at the premises. There is no national supply-point register separate from DOMLEC’s billing system.
MPRNNo equivalentThere is no piped gas network.
Meter operatorDOMLECDOMLEC installs, owns and reads all meters; there is no competitive metering market.
SupplierDOMLECCustomers cannot switch supplier. Tariffs are approved by the IRC, and complaints go to DOMLEC first and then to the IRC on appeal.
Smart-meter infrastructureDOMLEC AMIDOMLEC rolled out its own AMI system around 2011–2012 rather than a national programme with a central data hub. It supports remote reading, remote reconnection after payment and prepaid metering.

How a supply point is identified.

Illustrative only: DOMLEC account 0123456, meter 98765432 (fictional; real formats are not published)

Fictional example in the real format.

How a supply point is identified.
QuestionAnswer
What is it called?DOMLEC account number (with meter number) (Account no.)
Who issues it?DOMLEC, when a new service connection is set up
FormatA numeric account (customer) number in DOMLEC’s billing system, linked to the AMI meter installed at the premises. The numbering format is not published.
LengthNot published
Stays with the property when you switch supplier?Not identified from a reliable public source.
Where to find itPrinted towards the upper and bottom right sections of the DOMLEC electricity bill; prepaid customers also have a meter-specific PAUG card and tokens.
Electronic accessCustomers can view balances, bills and payment history in the DOMLEC MyAccount portal (myaccount.domlec.dm) and top up prepaid meters online (topup.domlec.dm).
Third-party accessNo open data hub or third-party data access framework identified. Installers obtain account and meter details from the customer or through DOMLEC.
Who keeps the registerDOMLEC’s customer and metering records; there is no separate national register.
Register scopeNational

What identifies a connection

Dominica has a single utility for the whole island, so a connection is identified by the account number DOMLEC opens for the customer and the meter installed at the premises. DOMLEC’s billing and AMI system is in effect the national register of supply points. There is no supplier switching, so no industry-wide identifier like an MPAN is needed.

Getting a connection

To open a new service, DOMLEC requires proof of ownership of the property, identification and an electrical fitness certificate. Installation normally takes seven days, or the same day if payment is made before noon. Domestic accounts need a minimum deposit of $125, refunded with interest when the service is disconnected and all balances are settled. DOMLEC does not publish whether the account number stays with the property when the occupier changes.

Prepaid accounts

Under Pay-As-You-Go, customers buy tokens that are specific to their meter and cannot be transferred to another meter. The unit price is the same as for post-paid accounts; a lost card costs EC$10 to replace.

Fictional example

A household in Roseau might hold DOMLEC account 0123456 with meter 98765432. Both numbers are invented: DOMLEC does not publish its numbering format.

Sending electricity to the grid.

Sending electricity to the grid.
QuestionAnswer
Can homes export electricity?Limited
Net meteringUnknown
Net billingUnknown
How exported electricity is paidSet under the IRC’s Distributed Renewable Energy Generation (DRE) policy (2016); the compensation terms could not be read from the published document. A new DRE framework is being prepared.
Do I need a licence for rooftop solar?Systems under 20 kW need a licence only if they connect directly or indirectly to the national grid; systems of 20 kW and over always need one. The IRC publishes the applications it receives from self-generators over 20 kW (more than 70 listed).
Is there a net metering or net billing scheme?The IRC issued a Distributed Renewable Energy Generation Interconnection Policy (May 2016) and a Distributed Renewable Energy Generation Policy decision (August 2016), but their compensation terms could not be confirmed. In 2026 the IRC said it is drafting a new interconnection policy and DRE framework under which customers and the utility will be incentivised to adopt such systems.
Is there a limit on solar on the grid?No published cap was identified. The IRC notes that low demand in the early morning is already an operational issue with geothermal on the grid.

Connecting a home system.

  1. Apply to the IRC for a generation licence: required for any generator of 20 kW or more, and for smaller systems that will connect directly or indirectly to the grid. The IRC publishes separate forms for solar systems and for self-generators.
  2. The IRC decides within 90 days of accepting the application.
  3. Agree interconnection and metering arrangements with DOMLEC under the IRC’s DRE interconnection policy and the Transmission, Distribution and Supply Code.
  4. Have the installation certified as electrically fit before connection.

Grid-connected self-generation is allowed but licensed: Dominica’s threshold for mandatory licensing is 20 kW, and smaller systems also need a licence if they export or otherwise connect to the grid. Interconnection rules date from 2016 and are being revised as part of the IRC’s 2026–2027 work programme, alongside a review of the grid codes and codes for new technologies.

Licensing and approvals.

Requirements depend on the activity. The table sets out what each activity needs and who grants it.

Licensing and approvals.
ActivityLicence or registrationAuthorityNotes
Generate electricityLicence from the IRC for generation of 20 kW or more, and for smaller generation that connects directly or indirectly to the grid.Independent Regulatory CommissionDOMLEC holds a 25-year non-exclusive generation licence from 1 January 2014. In January 2024 the IRC approved the transfer of a generation licence from DGDC to GPCD.
Self-generation (rooftop solar)No licence for off-grid systems under 20 kW; a licence is needed for any grid-connected system and any system of 20 kW or more.IRC; interconnection with DOMLECSeparate IRC forms for solar systems and self-generators.
Store electricityNo separate storage licence category identified; batteries are not mentioned in the IRC licensing guidance.Not identifiedDOMLEC operates a 6 MW / 6 MWh battery system.
Export to the gridRequires a generation licence and interconnection under the IRC’s DRE interconnection policy.IRC / DOMLECSee export section.
Transmit, distribute or supply electricityLicence from the IRC; DOMLEC holds an exclusive 25-year transmission, distribution and supply licence from 1 January 2014.Independent Regulatory CommissionNo other supplier can sell to customers during the exclusive period.
Electrical contracting and installationThe IRC has published a policy on certifying and licensing electrical contractors, electricians and engineers (2020); connections need an electrical fitness certificate.IRCA national Code of Practice for Low-Voltage Electrical Installations was announced in July 2026.
Aggregate, trade, wholesale, balancing, grid services, VPP, remote control of assetsNo licence category exists because there is no wholesale, balancing or aggregation market.Not applicableDOMLEC balances the grid itself.

The Electricity Supply Act No. 10 of 2006 gives the IRC power to license electricity generation, transmission, and distribution and supply. The IRC’s procedures are set out in its Licensing Procedures decision (2009/001/D) and a decision on Adding Capacity to the Public Supply System (2008/002/D), and it must decide on an application within 90 days of accepting it. DOMLEC has notified the IRC that it intends to renegotiate its current licence.

Flexibility and grid services.

Aggregation of home equipment: No

Flexibility and grid services.
Market or serviceAccess for home equipmentMinimum sizeVia an aggregatorDetail
Wholesale marketNo—NoNone exists; DOMLEC buys geothermal output under a bilateral power purchase agreement.
Frequency control and reservesNo—NoDOMLEC. Provided by DOMLEC’s diesel units and its 6 MW / 6 MWh battery, which can stabilise the grid for about two and a half hours if a geothermal unit trips.
Demand responseNo—NoNo demand response programme identified; the new off-peak tariff option is the only price signal for shifting demand.

There are no flexibility markets and no framework for aggregating distributed assets. Balancing is DOMLEC’s responsibility. The time-of-use option introduced on 1 October 2026 gives households a first incentive to shift consumption to off-peak periods.

Smart meters.

Smart meters.
FactValue
Smart-meter rolloutUtility-led AMI rollout by DOMLEC around 2011–2012 (more than 19,000 meters installed, completion expected Q1 2012); no current penetration figure published
Reading intervalNot published (meters are read for billing once a month)
ProgrammeDOMLEC Advanced Metering Infrastructure
Meters installed (as reported)More than 19,000; completion expected Q1 2012
FunctionsRemote reading, remote reconnection within minutes of payment, power-quality monitoring
PrepaidPay-As-You-Go (PAUG) on AMI meters
Customer accessMyAccount portal for bills and payment history
Third-party data accessNo framework identified

Dominica has no national smart-meter programme or data hub: DOMLEC installed its own Advanced Metering Infrastructure. DOMLEC reports that the system works across the island’s terrain, including communities without road access, and lets it reconnect customers remotely within minutes of payment, monitor voltage and spot incorrect or dangerous meter installations. AMI also underpins the Pay-As-You-Go prepaid service, whose take-up increased with the new meters. Data intervals and current meter numbers were not published.

Renewable electricity.

Electricity generation mix (2021).

  • Diesel: 79.7%
  • Hydro: 20.3%
Source 3
Renewable electricity share
20.3% (2021)Source 3Renewable (hydro) share of electricity output, World Bank WDI. The World Bank put it at 21% in 2022 and expects about 85% once the 10 MW geothermal plant (commercial operation 31 July 2026) is fully integrated; no post-geothermal figure has yet been published.
Home solar
Not identified from a reliable public source.
Solar added each year
Not identified from a reliable public source.
Diesel (DOMLEC)
18.9 MW (2022)Source 6
Hydro (run-of-river)
6.64 MW (2022)Source 6
Geothermal
10 MW (2026)Source 20Two 5 MW units; commercial operation 31 July 2026.
Battery storage
6 MW / 6 MWh (2025)Source 31

Targets.

  • 100% renewable electricity by 2030 (cited by the World Bank and the IRC)
  • NDC: greenhouse gas emissions 45% below 2014 levels by 2030
  • Renewable share of generation of 85% by February 2029 (World Bank Geothermal Risk Mitigation II results target)

Before geothermal

Hydro has been the only significant renewable source. The World Bank’s data series shows its share of output varying between about 20% and 38% from 2014 to 2021 with rainfall and storm damage, and 21% in 2022. The rest came from diesel, burning about 224 g of fuel per kWh in 2022.

Geothermal

Geothermal exploration and drilling were financed by the World Bank’s Geothermal Risk Mitigation Project (approved 2019), and transmission by its successor (approved 2024). The 10 MW plant, estimated by the World Bank to cost US$57 million, cleared its final reliability test in July 2026 and entered commercial operation on 31 July 2026. The World Bank expects it to displace more than 60% of diesel generation and lift the renewable share to about 85%. It cites geothermal resource potential of up to 100 MW.

Other renewables

DOMLEC states that wind, geothermal and biogas have been researched for some time with varying success. No official data on grid-connected solar capacity were identified.

Energy storage.

Home batteries
Not identified from a reliable public source.
Grid-scale storage
6 MWh (2025)Source 316 MW / 6 MWh BESS reported in DOMLEC’s 2025 annual report summary, funded by a UAE grant.

Battery storage on Dominica is utility-owned. The IRC describes the battery as the first line of defence when one geothermal unit goes offline, holding the grid stable for about two and a half hours depending on its state of charge. No regulation on storage licensing or home batteries was identified.

Storage projects.

Electricity suppliers.

Electricity suppliers.
SupplierMarket shareRenewable tariffTime of useDynamicExport tariff
Dominica Electricity Services Ltd (DOMLEC)Sole supplier; about 37,000 customers (2022)NoYesNoUnknown

DOMLEC is the only electricity supplier and describes itself as such. Its exclusive supply licence runs for 25 years from 1 January 2014, so there is no retail competition.

Key organisations.

Key organisations.
OrganisationCategoryWhat it doesWhy it matters
Independent Regulatory Commission (IRC)RegulatorElectricity sector regulatorLicenses generators and DOMLEC, sets tariffs, handles complaints on appeal and sets interconnection and grid code rules.
Dominica Electricity Services Ltd (DOMLEC)DistributionSole utilityGenerates, transmits, distributes and supplies electricity across the island.
Dominica Geothermal Development Company (DGDC)Renewable EnergyState-owned geothermal developerWholly government-owned company that led geothermal development with World Bank support.
Central Statistics OfficeGovernmentNational statistics officePublishes electricity generation, sales and customer statistics and the census.
World Bank – Dominica Geothermal Risk Mitigation IIRenewable EnergyDevelopment lenderFinances the transmission lines and substations that connect the geothermal plant.

Technical standards.

Technical standards.
AreaStandardIssued byNotes
Grid connectionElectricity Sector Transmission, Distribution & Supply Code (2016); Distributed Renewable Energy Generation Interconnection Policy (2016)IRCUnder review; a new interconnection policy is being drafted.
Electrical installationsCode of Practice for Low-Voltage Electrical InstallationsCommonwealth of Dominica / IRCAnnounced July 2026; nationally developed, replacing reliance on the UK IET wiring standards.
Installer accreditationCertifying and Licensing of Electrical Contractors, Electricians and Engineers (policy, 2020)IRCDetails of the scheme could not be read.
Quality of supplyQuality of Service Standards for Electricity Supply (2009)IRCInclude compensation payments to customers for breaches.

Permissions.

Permissions.
PermissionRequiredLevelDetail
IRC generation licenceLimitedNationalRequired for generation of 20 kW or more and for any smaller system connected to the grid.
DOMLEC interconnectionYesNationalAny grid-connected system must be connected by DOMLEC.
Electrical fitness certificateYesNationalDOMLEC requires one before connecting a new service.
Building or planning approvalLimitedNationalNo specific rules for rooftop solar identified from official sources.

For a household, the main steps are an IRC licence for a grid-connected system, DOMLEC’s interconnection, and certification that the wiring is fit. No separate planning rules for rooftop solar or home batteries were identified.

Support schemes, taxes and incentives.

Support schemes, taxes and incentives.
SchemeStatusTypeDetailPeriod
VAT relief on the first 100 kWhActiveVAT reliefThe first 100 units of monthly consumption are free of VAT; 15% VAT applies to consumption above that.—
Off-peak tariff optionActiveTime-of-use tariffIntroduced with the new DOMLEC tariff from 1 October 2026 to reward shifting electricity-intensive activities to off-peak periods.From 1 Oct 2026
Dominica Geothermal Risk Mitigation II (World Bank)ActiveDonor-funded utility investmentUS$38.5 million IDA credit for transmission to connect the 10 MW geothermal plant.Jan 2024 – Feb 2029

Data and connectivity.

Fixed broadband
Not identified from a reliable public source.
4G coverage
Not identified from a reliable public source.
5G coverage
Not identified from a reliable public source.

According to the World Bank, 82.1% of people used the internet in 2024. DOMLEC’s AMI meters communicate with the utility’s own system, including in communities without road access; the communications technology is not published.

Grid conditions.

National peak demand
0.016 GW (2022)Source 616.35 MW.
Annual electricity demand
0.089 TWh (2022)Source 689 GWh generated by DOMLEC.
Generation capacity
0.026 GW (2022)Source 618.88 MW diesel + 6.64 MW hydro. Since then 4.8 MW of leased generation (2025) and 10 MW of geothermal (2026) have been added.
Interconnection
0 GWIsolated island grid with no interconnection.
Curtailment
Not identified from a reliable public source.

The grid is small and isolated: 89 GWh generated and a 16.35 MW peak in 2022, with transmission and distribution losses of 8.2%. Hurricane Maria in 2017 caused about US$30 million of damage to the transmission and distribution network. With 10 MW of geothermal against a peak of about 16 MW, the loss of both geothermal units is the main single risk to supply, and low early-morning demand creates operating challenges.

Regulatory changes.

Regulatory changes.
ChangeStatusDateDetail
New DOMLEC tariff with off-peak optionCurrent1 October 2026Outcome of the 2026 rate review; the IRC is monitoring bills to the end of 2026.
Geothermal plant in commercial operationCurrent31 July 202610 MW independent power producer selling to DOMLEC under a power purchase agreement.
Low-Voltage Electrical Installations Code of PracticeCurrentJuly 2026Nationally developed code; application guidance to follow.
New Distributed Renewable Energy Generation framework and interconnection policyUpcomingLate 2026 – early 2027The IRC is consulting solar owners, installers and investors on rules that incentivise customers and DOMLEC to adopt distributed renewables, alongside a review of grid codes.
DOMLEC performance standards (KPIs)Upcoming2026–2027Key performance indicators for DOMLEC to follow the tariff approval.
100% renewable electricity targetUpcoming2030National goal cited by the IRC and the World Bank.

Market indicators.

Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.

Market indicators.
IndicatorLevelBasis
Electricity costMediumLow below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros).
Household electricity useLowLow below 2,500 kWh a year, high at 5,000 kWh or more (average use per household).
Renewable shareLowLow below 30%, high at 60% or more (renewable share of electricity).
Smart-meter adoption—Low below 30%, high at 80% or more (share of meters that are smart).
Home solar adoptionLowNo official data on rooftop solar; DOMLEC says private solar is used mainly for water heating, and grid-connected systems need an IRC licence.
Distributed energy marketLowSupply is dominated by DOMLEC and one geothermal IPP; distributed generation is limited to licensed self-generators and a 2016 interconnection policy now under review.
Grid flexibility marketLowNo wholesale, balancing or demand-response markets; a time-of-use option began in October 2026.
Energy storage adoptionLowOne utility battery of 6 MW / 6 MWh; no data on home batteries.
Renewable growth environmentHigh10 MW geothermal entered operation in July 2026 against a 16.35 MW peak (2022); the World Bank targets an 85% renewable share from about 21% in 2022.

Sources.

Public sources used for this profile, with the date each was accessed.

Show all 32 sources
  1. Population, total – Dominica (SP.POP.TOTL). World Bank, 2025. accessed 10 October 2026.
  2. Urban population (% of total) – Dominica (SP.URB.TOTL.IN.ZS). World Bank, 2025. accessed 10 October 2026.
  3. Renewable electricity output (% of total) – Dominica (EG.ELC.RNEW.ZS). World Bank, 2021. accessed 10 October 2026.
  4. Access to electricity (% of population) – Dominica (EG.ELC.ACCS.ZS). World Bank, 2024. accessed 10 October 2026.
  5. Individuals using the Internet – Dominica (IT.NET.USER.ZS). World Bank, 2024. accessed 10 October 2026.
  6. Project Appraisal Document – Dominica Second Geothermal Risk Mitigation Project (P179845). World Bank, 2023. accessed 10 October 2026.
  7. Project Appraisal Document – Dominica Geothermal Risk Mitigation Project (P162149). World Bank, 2019. accessed 10 October 2026.
  8. Implementation Status and Results Report – Dominica Geothermal Risk Mitigation II (Seq. 2). World Bank, 2024. accessed 10 October 2026.
  9. Projects API – World Bank projects in Dominica. World Bank, 2026. accessed 10 October 2026.
  10. Electricity Generation, Sales and Consumers 2003 to 2017. Central Statistics Office, Commonwealth of Dominica, 2017. accessed 10 October 2026.
  11. Central Statistics Office – home (population 2017). Central Statistics Office, Commonwealth of Dominica, 2017. accessed 10 October 2026.
  12. Understanding Licensing. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  13. Self-Generators Applications. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  14. Decision Papers. Independent Regulatory Commission, Dominica, 2024. accessed 10 October 2026.
  15. Administrative, Policy, Etc.. Independent Regulatory Commission, Dominica, 2020. accessed 10 October 2026.
  16. Final Consultation of DOMLEC’s Rates Review. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  17. New Electricity Tariff Takes Effect October 1: What Customers Should Know. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  18. Geothermal Is Now in Commercial Operation: What It Means for Dominica. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  19. Geothermal Plant Clears Final Reliability Test, Commercial Operations Near. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  20. Dominica’s Electricity Grid Faces a Remaining Geothermal Challenge. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  21. How Dominica’s Grid Responds to a Geothermal Interruption. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  22. From Renewable Energy to Efficiency: What’s Ahead for the IRC. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  23. Building the Future Grid: IRC Outlines Its Next Priorities. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  24. IRC Welcomes New Board and a Return to Full Regulatory Operations. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  25. New Code of Practice Signals a Major Step for Electrical Safety in Dominica. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  26. FAQs. Independent Regulatory Commission, Dominica, 2026. accessed 10 October 2026.
  27. FAQs. Dominica Electricity Services Ltd (DOMLEC), 2026. accessed 10 October 2026.
  28. Advanced Metering Infrastructure (AMI). Dominica Electricity Services Ltd (DOMLEC), 2012. accessed 10 October 2026.
  29. About Us. Dominica Electricity Services Ltd (DOMLEC), 2026. accessed 10 October 2026.
  30. Generation Department. Dominica Electricity Services Ltd (DOMLEC), 2026. accessed 10 October 2026.
  31. Investor Relations (2025 Annual Report summary). Dominica Electricity Services Ltd (DOMLEC), 2025. accessed 10 October 2026.
  32. ECB euro reference exchange rate: US dollar (USD). European Central Bank, 2026. accessed 10 October 2026.

Questions about energy in Dominica.

Talk to us about Olmack in Dominica.Tell us about your home, housing portfolio or school estate in Dominica. We'll explain what is possible there now.