How electricity works in Malta.
Malta electricity market 2026: Enemalta as sole DSO and supplier, regulated tariffs, smart meters, feed-in tariffs, REWS licensing, Italy interconnector and renewables.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Euro (EUR) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Malta energy at a glance.
Key figures for households in Malta. Each one links to its source on the full overview below.
Electricity price.
0.128 EUR per kWh for households, including taxes. Figures for 2025-H2.
Household use.
4,617 kWh a year for a typical household. Figures for 2024.
Renewable share.
11.2% of electricity from renewable sources. Figures for 2025.
Selling back to the grid.
Can homes export electricity? Yes. Details are in the export section below.
Four things to check in Malta.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Malta below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Malta requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Malta.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Malta, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Malta, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Malta.
The energy market in Malta, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 1 October 2026.
On this page22 sections
Malta has the smallest electricity system in the European Union and one of the most centralised. Enemalta plc is the only licensed distribution system operator and the only licensed supplier to final customers in Malta and Gozo. Malta uses EU derogations for small connected systems, so there is no third-party access to the network, no unbundling, no transmission system operator and, until at least July 2027, no free choice of supplier. Every household pays the same regulated tariff, set in law and overseen by the Regulator for Energy and Water Services (REWS).
Power comes from three main sources: gas-fired plants at Delimara run mostly by independent producers, imports from Sicily over the 225 MW Malta–Italy cable link, and about 270 MW of solar photovoltaics, nearly all on rooftops. In 2025 natural gas accounted for 58.3% of the electricity supplied from the grid, imports for 33.5% and grid-injected renewables for 7.7%. A second interconnector to Sicily is under construction, and a third link, utility-scale batteries and a floating offshore wind farm are being planned.
Household electricity is among the cheapest in the EU. Eurostat put the average household price at €0.1282/kWh in the second half of 2025, less than half the EU average, and regulated residential tariffs have not changed since March 2014. Rooftop solar is supported mainly through 20-year feed-in tariffs and REWS capital grants. Smart meters reach about 93% of household meters.
Energy snapshot.
Headline figures for electricity in Malta. Each shows its data year and links to its source.
- Population588,254 peopleSource 61 January 2026
- Households242,800 householdsSource 72025
- Average household size2.4 people/householdSource 82025
- Electricity use per household4,617 kWh/yrSource 122024
- Household price (EUR)0.128 EUR/kWhSource 12025-H2
- Renewable electricity share11.2%Source 152025
- Solar capacity0.269 GWSource 16end 2025
- Wind capacity0 GWSource 16end 2025
- Energy storage capacity31.6 MWhSource 16end 2025
- Smart-meter share92.9%Source 16end 2025
- Market structure
- Vertically integrated
- Homes can export to the grid
- Yes
- Home equipment in grid services
- No
- Regulator
- Regulator for Energy and Water Services (REWS)
- System operator
- Enemalta plc (single DSO; there is no TSO; the Italy link is operated with Terna)
- Distribution networks
- One national distribution system operated by Enemalta plc covering Malta, Gozo and Comino
- Currency
- Euro (EUR)
- Voltage and frequency
- 230 V / 50 Hz
Electricity prices in Malta.
- Household price (EUR)
- 0.128 EUR/kWh (2025-H2)Source 1Eurostat average household price for consumption band DC (2,500–4,999 kWh/yr), all taxes and levies included. Regulated residential band 1 rate is €0.1047/kWh (first 2,000 kWh) and band 2 is €0.1298/kWh, both including 5% VAT, plus a fixed annual service charge.
- Typical annual electricity bill
- 469.1 EUR/yr (2026 tariffs)Source 3Derived from the regulated residential tariff for 3,500 kWh a year on a single-phase supply: 2,000 kWh × €0.1047 + 1,500 kWh × €0.1298 + €65 service charge, VAT included. The eco-reduction, which many households qualify for, would lower this.
Household price trend (EUR per kWh).Source 1
| 2013-H2 | 0.1689 EUR/kWh |
|---|---|
| 2014-H1 | 0.1474 EUR/kWh |
| 2014-H2 | 0.1248 EUR/kWh |
| 2015-H2 | 0.1269 EUR/kWh |
| 2016-H2 | 0.1274 EUR/kWh |
| 2017-H2 | 0.1298 EUR/kWh |
| 2018-H2 | 0.1307 EUR/kWh |
| 2019-H2 | 0.1304 EUR/kWh |
| 2020-H2 | 0.1301 EUR/kWh |
| 2021-H2 | 0.1318 EUR/kWh |
| 2022-H2 | 0.1284 EUR/kWh |
| 2023-H2 | 0.1279 EUR/kWh |
| 2024-H1 | 0.1272 EUR/kWh |
| 2024-H2 | 0.1303 EUR/kWh |
| 2025-H1 | 0.1261 EUR/kWh |
| 2025-H2 | 0.1282 EUR/kWh |
How tariffs are set
Retail tariffs are written into the Electricity Connection and Supply Regulations (S.L. 545.41) and approved under the procedure in regulation 24 of those regulations, with REWS reviewing proposals. The residential and domestic rates now in force date from 31 March 2014 and did not change in 2025. There are no separate network tariffs: one bundled tariff covers distribution, generation, imports and supply. Household rates include 5% VAT and an excise duty of €0.0015/kWh. Eurostat data show VAT made up 4.8% of the Maltese household price in the second half of 2025, the lowest share in the EU.
Bands and the eco-reduction
Consumption bands are cumulative over a year and are applied pro rata to the days covered by each bimonthly bill. A household registered as a primary residence gets an “eco-reduction” if it uses little electricity. A single-person household using less than 2,000 kWh a year gets 25% off its consumption charge. In homes with two or more registered residents using no more than 1,750 kWh per person, 25% is taken off the first 1,000 kWh per person and 15% off the next 750 kWh. The number of residents must be registered with ARMS Ltd, and a person can only be registered at one address.
Larger supplies and businesses
Three-phase residential supplies rated above 60 A per phase also pay a maximum demand charge of €21.05 per kW per year. Non-residential premises have their own service fees and nine consumption bands from €0.1215/kWh down to €0.1080/kWh (excluding VAT). Very large users can choose kVAh billing or day/night rates.
Price level and trend
Because tariffs have been frozen, the Eurostat household price for the 2,500–4,999 kWh band has stayed between about €0.125 and €0.133/kWh since late 2014, after a cut in 2014. While European wholesale prices spiked in 2021–2023, Maltese regulated household tariffs did not change. Low-income and other eligible households also receive “energy benefit” payments, which the social policy department deducts directly from their bills.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | All households pay the regulated residential tariff in the Electricity Connection and Supply Regulations (S.L. 545.41): an annual service charge (€65 single-phase, €140 three-phase 40 A, €195 three-phase 60 A or more) plus five cumulative annual consumption bands, from €0.1047/kWh for the first 2,000 kWh up to €0.6076/kWh above 20,000 kWh, VAT included. |
| Other | Yes | “Domestic” tariffs apply to premises used domestically that are not registered as a primary residence, such as second homes. Rates are higher, from €0.1365/kWh in band 1 to €0.6860/kWh above 20,000 kWh. |
| Off-peak | Limited | Only for electric-vehicle charging through a separate EV meter: €0.1298/kWh from 00:00 to 05:59 and 12:00 to 15:59 (Monday–Saturday for domestic premises) and all day Sunday, with a €4/month single-phase meter charge. Outside these hours the normal residential bands apply. |
| Time-of-use | Limited | Day/night rates are available only to non-residential customers using more than 5 GWh (or 5.5 GVAh) a year. |
| Fixed | No | There are no competitive fixed-price offers because Enemalta is the only supplier. In effect, regulated prices have been fixed since 31 March 2014. |
| Dynamic | No | No dynamic price contracts exist. There is no organised wholesale market in Malta, and the energy component of bills does not follow wholesale prices. |
| Prepayment | No | Prepayment contracts are not available in Malta. |
Household prices compared with neighbouring countries (EUR per kWh).
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- 4,617 kWh/yr (2024)Source 12Derived: final electricity consumption of households in 2024 (1,086.3 GWh, Eurostat energy balance) divided by 235,300 private households in 2024 (Eurostat LFS).
- Average daily use per household
- 12.6 kWh/day (2024)Source 12Derived: 4,617 kWh per household per year divided by 365.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 1,892 kWh/person/yr (residential) (2024)Source 12Derived: household electricity consumption of 1,086.3 GWh in 2024 divided by the population on 1 January 2025 (574,250). World Bank puts total electricity use, all sectors, at 5,013 kWh per person in 2023.
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- 9,790 battery-electric cars registered (2025)Source 36Up from 7,301 in 2024. A further 5,243 plug-in hybrid cars were registered. Battery-electric cars made up 2,455 of 6,537 new car registrations in 2025 (37.6%, derived).
- Electric cooking
- Not identified from a reliable public source.
Households used 1,086 GWh of electricity in 2024, about 38% of final electricity consumption (2,864 GWh), according to the Eurostat energy balance. Household demand has risen from 855 GWh in 2019 as the population has grown. On average each household used about 4,600 kWh a year, which is high by EU standards. The system peak comes in summer, when cooling demand is highest.
There is no mains gas, so homes rely on electricity, bottled LPG and solar water heaters. The national peak is in summer: in 2025 it reached 636.6 MW at 17:00 on 25 July, 7.4% higher than in 2024 but still below the 2023 record. Enemalta forecasts annual demand rising from about 3.26 TWh in 2026 to 3.67 TWh in 2030.
Electric vehicles are increasing quickly. Battery-electric cars made up more than a third of new car registrations in 2025, and a dedicated EV meter gives home charging access to a cheaper off-peak rate.
Housing and households.
- Dwellings
- Not identified from a reliable public source.
- Owner-occupied
- 70.9 % of population (2025)Source 1050.9% own outright and 20.1% have a mortgage or loan (EU-SILC, share of people rather than households).
- Private rented
- 21.2 % of population (2025)Source 10Tenants paying market rent.
- Social or public housing
- 7.9 % of population (2025)Source 10Tenants at a reduced rent or rent-free. EU-SILC does not separate social housing, so this is the closest proxy.
- Houses
- 34.7 % of population (2025)Source 9Detached 3.1%; semi-detached or terraced 31.6%.
- Apartments and flats
- 65.2 % of population (2025)Source 952.6% in buildings with fewer than 10 flats and 12.6% in buildings with 10 or more.
- Urban population
- 95.7 % of population (2025)Source 11
Malta is one of the most densely populated countries in the world, and almost everyone lives in an urban area. According to EU-SILC, 65.2% of people live in flats, most of them in small blocks, and 34.7% in houses, almost all terraced or semi-detached. Detached houses are rare (3.1%).
Home ownership is high: 70.9% of people live in owner-occupied homes and half own outright. This matters for rooftop solar. Flat roofs are standard, but in apartment blocks the roof belongs to one owner or to the condominium, and roof space for each household is small. That is why most PV systems are small: 97.5% of grid-connected installations were 11 kWp or less at the end of 2025.
Electricity services are registered by premises type. A primary residence with registered occupants gets residential rates and the eco-reduction. Second homes and garages registered as domestic premises pay higher domestic rates, and everything else pays non-residential rates.
How the grid works in Malta.
- TransmissionEnemalta plc (with Terna S.p.A. on the Italy link)
- DistributionOne national distribution system operated by Enemalta plc covering Malta, Gozo and Comino
- MeteringARMS Ltd, Enemalta centralised metering and data system
- Supply1 or more retail suppliers
Physical flow
Electricity comes into the grid from the Delimara power station site in the south-east, from the Malta–Italy interconnector terminal at Magħtab and from tens of thousands of rooftop PV systems. Enemalta describes a four-level network at 132 kV, 33 kV, 11 kV and 400/230 V, with the 220 kV link to Sicily treated as part of the distribution system. The 132 kV cables feed distribution centres at Marsa, Kappara and Mosta, which feed 33 kV primary substations in Malta, Gozo and Comino. More than 1,580 11 kV substations then supply the low-voltage network. At the end of 2025 the network was 6,470 km long, including 113 km of submarine cable. Most of it is underground, but the low-voltage network is mostly overhead.
The link to Ragusa in Sicily, in service since April 2015, is a 200 MW HVAC 220 kV cable whose net transfer capacity was set at 225 MW all year from July 2024. A second 225 MW HVAC link of about 122 km is under construction. Its subsea cable finished factory testing in June 2026 and is ready to install. A third link, a 200 MW HVDC connection, is in the 2026 EU Ten-Year Network Development Plan, with commissioning envisaged for 2033.
Commercial flow
Malta has no organised wholesale market. Enemalta buys power from the two gas-fired independent producers, D3 Power Generation Ltd (DPS-3, 153 MW) and ElectroGas Malta Ltd (DPS-4, 215 MW), under long-term bilateral contracts. These two produced 58.5% of the electricity sent out in 2025. Enemalta also imports through the Italy link, mainly from the Italian day-ahead market, and buys exported renewable power at feed-in tariffs, contract-for-difference prices or the regulated “proxy of the market price”. Enemalta’s own gas-oil plants (175 MW) are kept as backup and produced 0.27% of the electricity sent out in 2025.
Retail and customer service
Enemalta then sells to all final customers at regulated tariffs. ARMS Ltd handles the customer side: applications for new services and changes of consumer, meter readings, bimonthly combined electricity and water bills, feed-in tariff credits and the online portal. Technical complaints go to Enemalta and billing complaints to ARMS. Unresolved disputes can go to REWS, which normally has to decide within four months.
Network performance
Losses fell from 7.70% in 2024 to 5.84% in 2025, mainly because non-technical losses fell. Average interruption time per customer (SAIDI) was 104.6 minutes in 2025, the best result in the last ten years. A new non-complex single-phase connection took 10.7 days on average, and small PV systems (under 41 kWp) took about 25 days to connect.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Ministry for Energy, the Environment and the Regeneration of the Grand Harbour | Responsible for energy policy, the National Energy and Climate Plan and the renewable support schemes under minister Miriam Dalli (renamed in June 2026; previously the Ministry for the Environment, Energy and Public Cleanliness). It is the contracting authority for renewable energy competitive bidding (ITBs). |
| Regulator | Regulator for Energy and Water Services (REWS) | Licenses generation, distribution and supply under the Electricity Regulations (S.L. 545.34). It approves tariffs, allocates feed-in tariffs, runs PV and battery grant schemes and the renewables one-stop shop, authorises electricians and EV charge-point operators, and settles disputes between customers and Enemalta. |
| DSO | Enemalta plc | Vertically integrated, state-owned company and the only distribution system operator. It runs the 6,470 km network at 220, 132, 33, 11 and 0.4 kV, operates the Malta–Italy cable link, balances the system, owns backup generation and installs and owns all meters. |
| System operator | Enemalta plc (with Terna S.p.A. on the Italy link) | Malta has no transmission system operator. Enemalta dispatches local plants, renewables and imports in merit order, giving renewables priority. It coordinates the 220 kV link with Terna, which treats Malta as a single virtual consumption and production point on the Italian grid. |
| Supplier | Enemalta plc | The only licensed supplier to final customers. Under Malta’s derogation from Article 4 of Directive (EU) 2019/944, a supply licence can only be given to the designated DSO, so customers cannot switch supplier. |
| Metering | ARMS Ltd | Automated Revenue Management Services Ltd is jointly owned by Enemalta and the Water Services Corporation. It reads meters, sends the combined electricity and water bill, collects debts and handles customer applications such as new services, change of consumer, PV connection and tariff changes. |
| Data hub / registry | Enemalta centralised metering and data system | Enemalta runs the national metering and data system and, through ARMS, acts as metered data administrator, metering point administrator and data access provider. Customers see hourly data for the last 30 days and monthly data for 13 months on the ARMS portal. |
| Exchange | Italian day-ahead market (via the Malta–Italy link) | Malta has no organised electricity market. Enemalta buys most imported power on the Italian day-ahead market. Local gas-fired independent producers (D3 Power Generation and ElectroGas Malta) sell to Enemalta under long-term bilateral contracts. |
Compared with the UK system.
| UK concept | Malta equivalent | How it works |
|---|---|---|
| DNO | Enemalta plc (single national DSO) | One DSO serves the whole country. Enemalta owns the network to the meter, provides new connections (applications go through ARMS) and deals with faults on 8000 2224. It is not legally unbundled from generation and supply, but must keep separate accounts for each activity. |
| National Grid/NESO | No TSO; Enemalta operates the system | There is no transmission system. Enemalta balances the system and is the only party responsible for balancing. Imbalances on the Italy link are settled under rules from the Italian regulator ARERA. |
| MPAN | ARMS account number + meter serial number | Malta has no separate supply-point number like the MPAN. A supply is identified by the ARMS account number together with the Enemalta meter serial number, which is the official “metering point identifier” in Malta’s EU data-access mapping. |
| MPRN | Not applicable | Malta has no piped gas grid and no gas supply points. LNG is used only for power generation at Delimara. Homes use bottled LPG. |
| Meter operator | Enemalta plc | Enemalta installs, owns, tests and replaces all meters, including PV generation, import/export and EV meters. ARMS handles meter readings and billing. |
| Supplier | Enemalta plc (regulated, no competition) | There is no retail competition, no switching and no price comparison. All customers have a deemed contract on the terms of the Enemalta Customer Charter and the S.L. 545.41 regulations. |
| Smart-meter infrastructure | Enemalta AMM system (PLC, second generation PLC + RF) | Enemalta runs one Automatic Metering Management system. Meters communicate over power-line carrier; second-generation meters (29.2% of installed meters at the end of 2025) switch to radio frequency when needed. There is no separate national communications body like DCC. |
How a supply point is identified.
Account no. 1000473856 / Meter no. 21B7C3MA410027734 (fictional)
Fictional example in the real format.
| Question | Answer |
|---|---|
| What is it called? | Electricity service account and meter serial number |
| Who issues it? | ARMS Ltd issues the account number when a service is registered to a consumer; Enemalta plc assigns the meter, whose serial number identifies the metering point |
| Format | Two identifiers are used together. The ARMS account number (“Nru. tal-kont / Account no.”) is numeric (10 digits on ARMS bill specimens). The meter serial number is set by the manufacturer and Enemalta; current smart meters use a 17-character alphanumeric serial, and older meters have shorter serials. |
| Length | Account number: 10 digits; meter serial: varies by meter (17 alphanumeric characters on current smart meters) |
| Stays with the property when you switch supplier? | No |
| Where to find it | Both numbers appear on the ARMS electricity and water bill. The account number is in the bill header and the meter number is in the meter readings section, which also gives the meter location address and consumer scheme (for example “Residential”). The meter serial is also printed on the meter. Both are shown in the ARMS online portal. |
| Electronic access | Customers log in to the ARMS portal with the national eID or an ARMS portal account and link their supply using the account and meter serial numbers. The portal shows hourly consumption for the last 30 days, monthly consumption for the last 13 months and bills back to 2010. |
| Third-party access | Malta’s 2025 national mapping under Implementing Regulation (EU) 2023/1162 lists no external eligible parties: Enemalta and ARMS hold every data role. Installers and grant applicants obtain the numbers from the customer’s bill. REWS grant and feed-in tariff applications require a copy of the ARMS bill for the site. |
| Who keeps the register | Enemalta plc keeps the national register of metering points and meters in its centralised metering and data system; ARMS Ltd keeps the customer and billing register (account holder, registered residents, tariff category). |
| Register scope | National |
How a supply is identified
Malta has never introduced a standard supply-point code such as an EAN or MPAN. In practice, the electricity “service” at a property is identified by the ARMS account number and the serial number of the Enemalta meter that serves it. In the national data-access mapping that REWS submitted to the European Commission, the metering point identifier is defined as the meter serial number, with examples in two formats: a 17-character alphanumeric serial for current smart meters and a shorter alphanumeric serial for older meters. ARMS forms such as the EV meter application ask for the “account number” and the “meter number of the existing electricity service”.
What happens when the occupier changes or the meter is replaced
Neither number is a permanent property code. When a property changes hands or tenants, the new occupier applies to ARMS with form F (“registration of change in consumer”). The previous account holder must settle all outstanding bills first, or the service cannot be transferred. The meter serial changes whenever Enemalta replaces the meter, for example during the current rollout of second-generation smart meters. The property address and meter location on the bill link the old and new records.
One building, one service
As a rule, buildings that are physically connected internally get only one electricity service unless otherwise authorised. A home can have extra meters on the same account: a PV generation meter and an import/export meter for a solar system, or a dedicated EV meter. Each has its own serial number, and ARMS bills them under the account.
Who holds the register
There is only one DSO and one supplier, so there is one national register. Enemalta keeps the technical metering point and meter data, and ARMS keeps the customer, tariff and billing records, including the number of registered residents, which sets the eco-reduction. Because there is no supplier switching, Malta does not need a central switching hub or a published supply-point code.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Yes |
| Net metering | Limited |
| Net billing | No |
| How exported electricity is paid | Regulated 20-year feed-in tariff for PV under 40 kWp (15c/kWh without a grant, 10.5c/kWh with a grant), paid on exports up to kWp × 1,600 kWh a year; otherwise the regulated proxy of the market price. Systems of 40 kW or more compete for two-way contracts for difference. |
| Is there net metering? | Only for PV systems connected before 10 September 2010. Those owners may keep it, but cannot enlarge their systems under it. Since August 2015 it has not been possible to switch from net metering to a feed-in tariff. All newer systems are paid feed-in tariffs or the proxy market price for metered exports. |
| What feed-in tariff is available in 2026? | For PV from 1 kWp to under 40 kWp approved between 1 January and 30 November 2026: €0.15/kWh for 20 years if no grant was received (8 MWp available), or €0.105/kWh for 20 years for systems that received a grant. The rate is fixed for the whole guarantee period once approved. |
| Is there a cap on paid exports? | Yes. For systems approved since 2013, the feed-in tariff is paid on up to kWp installed × 1,600 kWh a year. Units above the cap are paid at Enemalta’s proxy of the market price for that year. |
| What are “sell all” and “partial export”? | With sell all, Enemalta pays for every kWh measured by the PV generation meter, and the household pays for its total consumption. With partial export, the household uses its own solar power first and is paid only for the surplus measured on the import/export meter. Customers can change option with ARMS Form R, except for third-party installations, which must sell all. |
| How is the feed-in tariff paid? | For systems under 100 kWp the amount is set off against the electricity bill. If two consecutive actual-reading bills are in credit, Enemalta must pay the credit within 60 days. Feed-in income for households is exempt from income tax and VAT. |
| What happens when an old feed-in tariff expires? | Residential PV with a feed-in tariff approved before 2020 moves to €0.105/kWh after the original tariff ends, until 20 years of feed-in payments have been reached in total. |
| What technical rules apply? | Inverters must meet the Enemalta Network Code and the volt-var settings in regulation 11(3)(a) of S.L. 545.41 (power factor 0.85 lagging to leading), and LV interface protection must comply with MSA EN 50549-1 or an equivalent standard. Grid connection studies are free from 11 to 40 kWac and cost €150 to €2,500 above that. |
Connecting a home system.
- Check planning: the installation must either have Planning Authority permission, a Planning Authority confirmation that none is needed, or comply with the Development Notification Order 2016 and the PA’s PV design guidance (the applicant declares which).
- Apply to REWS through the online one-stop shop before installing, choosing the feed-in tariff scheme (or none) and either “sell all” (full export) or “partial export” (self-consume first).
- Up to 16 A per phase (3.68 kW single-phase, 11.04 kW three-phase), or 20 A per phase with volt-var capable inverters (4.6 kW / 13.8 kW), the system is only notified and REWS issues a feed-in tariff confirmation letter.
- Above those limits, the one-stop shop first arranges a preliminary grid connection study by Enemalta; once the applicant meets its conditions, Enemalta issues a No Objection Letter and REWS issues an Authorisation to Construct.
- A warranted electrical engineer commissions the system; the applicant submits Part 2 to REWS to obtain a Regulatory Clearance (and a licence to generate for authorised systems).
- The applicant applies to Enemalta (via the one-stop shop or the ARMS PV form) for connection; Enemalta installs a PV generation meter and an import/export meter, and ARMS starts crediting feed-in payments on the bill.
Households in Malta can export solar electricity, but under regulated arrangements rather than market contracts. Enemalta must buy all electricity exported by approved renewable generators: at the feed-in tariff for systems allocated one, or at the “proxy of the market price” otherwise. REWS sets this proxy each year as the estimated average variable cost of meeting demand from conventional generation and imports, and it is published by legal notice.
The standard metering set-up is a PV generation meter plus an import/export smart meter, both supplied by Enemalta. Bills show units generated, units exported and the money due from Enemalta. In 2025, 34.3% of renewable electricity was used on site rather than exported, and about 48% of producers had opted for partial export.
Network capacity is published on Enemalta’s quarterly low-voltage capacity map, which shows spare transformer capacity and remaining PV capacity at each substation. Larger systems, or those in congested areas, may need a grid study and reinforcement. From 2025, S.L. 545.34 also provides a framework for flexible connection agreements.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity | Up to 16 A per phase (20 A with volt-var): notification to REWS only. Above that: Authorisation to Construct before building and a licence to generate once built. | REWS (Electricity Regulations, S.L. 545.34) | Plants above 16 A per phase also need an Enemalta No Objection Letter based on a grid connection study. Renewable plants of 40 kW or more that want support must win a competitive ITB under S.L. 545.39. |
| Store electricity | Every energy storage facility must be notified to REWS, including when it is installed, changed, transferred, relocated or decommissioned. No fee is charged. | REWS; Enemalta for connection | Needs a declaration by a warranted electrical engineer. An Enemalta No Objection Letter is needed if the inverter AC rating exceeds 16 A on any phase. |
| Export to the grid | No separate licence. Export follows from the REWS notification or authorisation and an Enemalta connection with export metering. Enemalta must buy exported renewable power. | REWS; Enemalta; ARMS (billing) | Paid at the feed-in tariff, the CfD strike price (ITB winners) or the proxy of the market price. Generators can also sell to Enemalta under a power purchase agreement. |
| Supply (sell) electricity to consumers | Supply licence required, but it can only be issued to the designated DSO (Enemalta plc) under Malta’s derogation from free choice of supplier. | REWS | The derogation runs until 5 July 2027 and can be extended by up to eight years by the European Commission. Peer-to-peer sales to other customers are not possible. |
| Distribute electricity | Distribution licence held only by Enemalta plc, the single DSO. There is no third-party access to the network. | REWS | Malta is exempt from DSO and TSO unbundling and third-party access rules under Article 66 of Directive (EU) 2019/944. |
| Aggregate / operate a VPP | No aggregator licence or market role is in use. With no organised market and the DSO as sole balancing party, there is no route to sell aggregated flexibility. | REWS (S.L. 545.34) | The national data mapping lists no eligible third parties, such as aggregators, with access to metering data. |
| Trade wholesale electricity | No domestic wholesale market exists. Only Enemalta uses the Italy link, which is not open to third parties, and it trades on the Italian market. | REWS (REMIT monitoring); ARERA/Terna on the Italian side | Local independent producers sell to Enemalta under long-term contracts and report inside information under REMIT. |
| Balancing and grid services | Not open to distributed assets. The DSO alone has balancing responsibility, and there is no market for reserves or frequency services. | Enemalta plc | Enemalta balances in coordination with Terna. The planned utility-scale batteries at Delimara and Marsa are being developed by InterConnect Malta Ltd. |
| Remote control of assets | No licence regime. Enemalta’s smart meters support remote power limitation and connect/disconnect, but there is no framework for third-party control of household assets. | Enemalta plc | Smart meters deployed after 2019 support a Chain 2 near-real-time interface for in-home devices, but this was not yet in use in 2025. |
| Electrical installation work | Electricians need REWS Authorisation A (single-phase) or B (single-phase and three-phase up to 300 A per phase). Authorisation requires an exam and 12 or 24 months of supervised experience. | REWS (Electrical Installations Regulations, S.L. 545.24) | PV and battery systems must be commissioned or certified by a warranted electrical engineer for REWS approvals and grants. |
| Operate public EV charging points | Publicly accessible charging point operator (PCIO) authorisation needed. Private home chargers need no authorisation. | REWS (S.L. 545.38) | OCPP and OCPI are mandatory. The electricity part of the charging price is regulated; any service premium is set by the operator. |
Licensing in Malta reflects its derogations as a “small connected system” under the EU electricity directive. Generation is open: anyone can install rooftop PV, and more than 35,000 independent renewable producers are connected. However, distribution and supply licences can only go to Enemalta plc, and there is no third-party access to the grid. So an independent company cannot sell electricity to households, aggregate household batteries for market sale or trade power locally.
For small systems, the key threshold is 16 A per phase (3.68 kW single-phase or 11.04 kW three-phase), raised to 20 A per phase for inverters with volt-var control. At or below it, PV, micro-wind and CHP only need to be notified to REWS. Above it, an Authorisation to Construct and then a licence to generate are needed, along with Enemalta’s No Objection Letter. Every battery system, whatever its size, must be notified to REWS. Breaching the Electricity Regulations can lead to a fine of up to €69,000, or €1,300 for each day the offence continues.
Legal Notice 235 of 2025 brought EU electricity market design reform provisions into S.L. 545.34. These cover flexible connection agreements, supplier of last resort, fixed-price contract rights and DSO publication of network capacity. Some, including free choice of supplier, will only take practical effect if Malta’s derogation ends. Legal Notice 236 of 2025 provides that Enemalta’s obligation to buy all renewable exports ends once an organised market place becomes accessible.
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Wholesale energy market | No | — | No | Malta has no organised day-ahead or intraday market. Enemalta buys from independent producers under bilateral contracts and imports from the Italian day-ahead market. Distributed generators can only use their output on site or sell it to Enemalta. |
| Balancing and reserves | No | — | No | Enemalta plc. Only the DSO has balancing responsibility. Independent producers and active customers have no balancing role, and there is no procurement of balancing or ancillary services from third parties. |
| Local flexibility / congestion management | Developing | — | No | Enemalta plc. Since 2025, S.L. 545.34 includes a framework for flexible connection agreements, and Enemalta publishes low-voltage capacity by substation. No local flexibility market or tender exists yet. |
| Demand response via tariffs | Restricted | — | No | Enemalta plc / ARMS. The only time-based price signal for households is the off-peak rate for a dedicated EV meter, which includes a midday window when solar output peaks. |
Distributed assets in Malta cannot take part in flexibility markets because none exist. The system is run by one vertically integrated company that buys, dispatches and balances everything, and the EU network codes on capacity allocation, balancing and demand connection apply only partly or not at all. Household batteries, which reached about 31.6 MWh across 3,150 installations at the end of 2025, are used to increase self-consumption of rooftop solar, not to provide grid services.
The main sources of system flexibility are the Italy interconnectors, Enemalta’s backup gas-oil turbines and, in future, utility-scale batteries. Two battery systems at Delimara and Marsa, co-financed by the EU and promoted by the state company InterConnect Malta, received sixteen offers in their 2025 procurement and cleared State aid approval. They are meant to complement the second interconnector and reduce network bottlenecks.
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | Near-complete: 92.9% of household meters remotely read at the end of 2025; second-generation meters being installed |
| Reading interval | Hourly data shown to customers (last 30 days); billing on actual reads every two months |
| Remotely read meters (all customers) | 367,426 of 398,154 active meters (92.3%), end 2025 |
| Household meters remotely read | 316,689 of 340,940 (92.9%), end 2025 |
| Second-generation meters | 29.2% of installed meters at the end of 2025 (PLC with automatic RF fallback) |
| Meter owner / operator | Enemalta plc (meter models GEMIS, GETIS, GESIS from Gridspertise) |
| Data protocols | DLMS/COSEM (EN 62056); Chain 2 in-home interface (CLC TS 50568-4) |
| Customer access | ARMS portal: hourly (30 days), monthly (13 months); eID login |
Enemalta began replacing electricity meters with smart meters around 2010; the 2010 ARMS billing booklet said the free replacement would be completed by the end of 2012. Enemalta owns and operates all meters through one Automatic Metering Management system, and ARMS uses the data to bill. Meters record import and export, maximum demand and load profiles. They also support time-of-use registers, remote connection and disconnection, remote power limitation, voltage monitoring and self-diagnostics. Households with a remotely read meter get bimonthly bills based on actual readings; those without one get an actual reading at least every six months.
Enemalta is now installing second-generation meters, which use power-line carrier communication and switch to radio frequency when needed, to improve data reliability. Meters deployed after 2019 have a near-real-time Chain 2 interface for in-home devices, but in 2025 it was not yet activated for customers. Since 2021 smart meter data has also been used to calculate network losses, which fell to 5.84% in 2025.
Renewable electricity.
Electricity generation mix (2024).
- Natural gas: 84.3%
- Solar: 14.9%
- Bioenergy: 0.4%
- Oil: 0.4%
- Renewable electricity share
- 11.2% (2025)Source 15Share of gross electricity consumption from renewables (EU SHARES accounting, Eurostat). Used instead of the generation share because imports supplied 970 GWh in 2024; of domestic gross generation alone, 15.4% was renewable (336.0 of 2,185.9 GWh, 2024).
- Home solar
- 100.4 MW (AC), systems under 10 kW (2024)Source 14Eurostat solar PV capacity in the under-10 kW size class, a proxy for residential rooftop systems. 97.5% of all grid-connected PV installations were 11 kWp or smaller at the end of 2025.
- Solar added each year
- 14.1 MWp (2025)Source 160.345 MWp was decommissioned, giving a net increase of 5.4%.
- Solar PV
- 268.6 MWp (DC) (end 2025)Source 16250.4 MW AC. Largest single installation 5.4 MWp.
- Biogas CHP
- 2.823 MWe (end 2025)Source 16
- Micro wind
- 0.057 MW (end 2025)Source 16
Targets.
- Updated National Energy and Climate Plan (submitted January 2025): renewable share of gross final energy consumption of about 25% by 2030 (24.5% according to the European Environment Agency).
- Solar PV capacity of 350 MWp by 2030.
- Floating offshore wind farm under a 35-year concession and 25-year contract for difference (procurement under way).
Solar PV is almost the only renewable power source in Malta. There are no rivers for hydro, onshore wind has been held back by lack of space, and biogas is marginal. Total renewable generation was an estimated 363.75 GWh in 2025, up 8.0%. About a third of it was used where it was produced. Measured against domestic gross generation, renewables made up 15.4% in 2024. Measured against all electricity supplied, including imports, the share is lower: under EU accounting rules renewables covered 11.2% of gross electricity consumption in 2025.
Growth is limited by roof space and network capacity rather than sunshine, and annual PV additions have slowed to around 14 MWp. Larger projects of 40 kW or more compete in pay-as-bid auctions under S.L. 545.39 for 20-year two-way contracts for difference. In 2026 these were offered in three size bands: up to 2.5 MW at a 14c/kWh cap, 5 MW at 14c/kWh and 38 MW for projects of 1–10 MW.
The long-term plan for more domestic renewable power is offshore wind. InterConnect Malta received three pre-qualification submissions in July 2025 for a floating offshore wind farm and its grid connection, which was added to the 2026 EU Ten-Year Network Development Plan. The interconnectors also bring in electricity that is partly renewable: 9.8% of the imported mix in 2025.
Energy storage.
- Home batteries
- 31.6 MWh (end 2025)Source 163,150 installations, up from 15.1 MWh and 1,636 installations at the end of 2024.
- Grid-scale storage
- 2 MWh (2025)Source 16Only a 1 MW / 2 MWh research battery at Xewkija Distribution Centre (2021), not owned or operated by the DSO. Utility-scale systems at Delimara and Marsa are in procurement.
Batteries in Malta are almost all small household units paired with rooftop PV. Installed capacity has roughly doubled every year, from 6.7 MWh in 2023 to 15.1 MWh in 2024 and 31.6 MWh in 2025. Most of this growth was driven by REWS grants, including grants for owners of PV systems that have been connected for at least six years, many of whose feed-in tariffs are ending.
Every storage facility, whatever its size, must be notified to REWS with a warranted electrical engineer’s declaration. Larger inverters also need Enemalta’s No Objection Letter. Household batteries cannot earn money from grid services because there is no flexibility market, so their value comes from storing solar output for later use instead of exporting at the feed-in tariff or proxy price.
Storage projects.
- Delimara and Marsa battery energy storage systems: Two EU co-financed utility-scale BESS projects promoted by InterConnect Malta Ltd to complement the second interconnector and relieve network bottlenecks. The EPC tender closed in 2025 with sixteen offers, and the State aid procedure was concluded.
- Xewkija BESS (Gozo): 1 MW / 2 MWh battery installed in 2021 for research into grid interaction and flexibility.
- REWS household battery grants: Grants of 75% of battery costs (up to €6,000 per system and €600/kWh) in the 2026 scheme, which drove most household battery growth. The scheme closed to new applications in 2026.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| Enemalta plc | 100% (sole licensed supplier) | No | Limited | No | Yes |
Enemalta plc is the only electricity supplier. Billing, meter reading and customer service are done by ARMS Ltd on its behalf. Customers cannot switch supplier and there are no comparison tools, green tariffs or competitive offers. The fuel mix and CO₂ factor are the same for everyone: 364 g CO₂/kWh in 2025.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Regulator for Energy and Water Services (REWS) | Regulator | Energy and water regulator; schemes administrator; renewables one-stop shop | Publishes tariffs, feed-in tariff rules, grant schemes, licensing and notification procedures, and the annual national report on the electricity market. |
| Enemalta plc | Distribution | Single DSO, supplier, system operator and meter operator | Grid connection studies, No Objection Letters, the Network Code, the LV capacity map and all meters. |
| ARMS Ltd | Metering | Billing, meter reading and customer services for Enemalta and the Water Services Corporation | Where households apply for services, change of consumer, PV and EV meters, and see their consumption data. |
| InterConnect Malta Ltd | Transmission | State-owned promoter of the second and third Malta–Italy interconnectors, utility-scale batteries and the offshore wind grid connection | Delivers Malta’s strategic grid infrastructure projects. |
| Terna S.p.A. | Transmission | Italian TSO at the Sicilian end of the interconnector | Sets operating rules and transfer capacity for the Malta–Italy link with Enemalta. |
| Ministry for Energy, the Environment and the Regeneration of the Grand Harbour | Government | Energy policy, NECP and contracting authority for renewable auctions | Sets national energy targets and launches support schemes. |
| Institute for Sustainable Energy, University of Malta | Renewable Energy | Academic research and training in renewable energy | Malta’s main academic centre for solar and energy-system research. |
| Malta Competition and Consumer Affairs Authority (MCCAA) | Consumer | Consumer protection and product standards (Malta Standards Authority) | Publishes national adoptions of European standards (MSA EN), such as EN 50549-1, and handles consumer complaints. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Grid connection | Enemalta Network Code | Enemalta plc (DSO) | Sets the minimum technical rules for connecting generators, storage and customer equipment to the distribution system. |
| Interface protection / anti-islanding | MSA EN 50549-1 (or equivalent) | REWS via Electrical Installations Regulations (S.L. 545.24) | Required for generators connected at low voltage, which in practice means rooftop PV inverters. |
| Inverters (voltage support) | Volt-var settings, regulation 11(3)(a) of S.L. 545.41 | Enemalta / Government of Malta | Single-phase 0.8–4.6 kW and three-phase 0.8–41 kW inverters with volt-var: reactive power from 220 V to 210 V and absorption from 240 V to 250 V (single-phase). Power factor range 0.85 lagging to 0.85 leading. |
| Electrical installations | Electrical Installations Regulations (S.L. 545.24) | REWS | Wiring rules and the licensing of electricians (Authorisation A and B). New services must also comply with S.L. 545.41 and the Network Code. |
| Equipment registration | Government Notice 52 of 2010 (as amended) | REWS | PV modules, inverters and batteries must be on the REWS registered product list to qualify for grants, and must carry a 10-year warranty under the scheme terms. |
| Installer accreditation | Warranted electrical engineer commissioning | REWS (scheme and notification rules) | No national PV-installer certification scheme like MCS was identified. REWS requires commissioning certificates and declarations signed by a warranted electrical engineer, and work by authorised electricians. |
| Smart metering | DLMS/COSEM (EN 62056-5-3, -6-1, -6-2, -7-5); CLC TS 50568-4 | Enemalta plc | Meter data protocols and the Chain 2 PLC-C in-home interface on meters deployed after 2019. |
| EV charging | OCPP and OCPI (S.L. 545.38, regulation 11) | REWS | Mandatory for publicly accessible charging points and their back-end platforms. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Planning permission | Limited | National | Rooftop PV that meets the Development Notification Order 2016 and the Planning Authority’s design guidance needs no full permit. Otherwise a PA permit or a PA confirmation that none is needed must be provided to REWS. The Planning Authority may inspect grant-funded systems. |
| REWS notification (≤16 A/phase, ≤20 A with volt-var) | Yes | National | Made online through the REWS one-stop shop before installation, together with the feed-in tariff request where relevant. |
| REWS authorisation and licence to generate (>16 A/phase) | Limited | National | Authorisation to Construct before building and a generation licence after commissioning, for systems above the notification limits. |
| DSO grid study and No Objection Letter | Limited | National | Needed above 16 A per phase (20 A with volt-var) for generators, and for batteries with inverters above 16 A on any phase. Studies are free for 11–40 kWac and cost €150–€2,500 above that. A No Objection Letter is valid for one year. |
| Connection and metering application | Yes | National | Made to Enemalta via the one-stop shop or the ARMS PV form. Enemalta installs generation and import/export meters, which took about 25 days on average for systems under 41 kWp in 2025. |
| Battery notification | Yes | National | All energy storage facilities must be notified to REWS under S.L. 545.34, whatever their size. |
Permitting in Malta is national and centralised. There are no regional authorities or multiple DSOs to deal with. Applications go through the REWS one-stop shop, which brings together the feed-in tariff request, the notification or authorisation under the Electricity Regulations, Enemalta’s grid study where needed and the final connection request. A grant or feed-in tariff application requires the ARMS bill for the site, an equipment quotation and, after installation, invoices, photos of rating plates and a commissioning certificate from a warranted electrical engineer.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Feed-in tariff for PV under 40 kWp (no grant) | Active | Feed-in tariff | €0.15/kWh for 20 years for new PV from 1 kWp to under 40 kWp that received no capital grant. Paid on exports up to kWp × 1,600 kWh a year. 8 MWp is available in 2026 (LN 101 of 2026). | 1 January – 30 November 2026 (approval window) |
| Feed-in tariff for grant-aided residential PV | Active | Feed-in tariff | €0.105/kWh for 20 years for residential PV that received a grant. If a grant above 50% was received, the tariff is cut by 0.2c for each percentage point above 50%, but not below the proxy market price. | 1 January – 30 November 2026 (approval window) |
| 2026 Renewable Energy Sources (RES) grant scheme | Closed | Grant | PV with hybrid inverter: 65% up to €3,000 and €645/kWp. Hybrid inverter and battery, or battery only: 75% of battery cost up to €6,000 and €600/kWh. A further 5% was available for NZIA-compliant equipment. The battery-only options closed on 13 July 2026, and all applications closed from 12 September 2026. | 20 April – 11 September 2026 |
| Competitive bidding (ITB) for renewables of 40 kW–10 MW | Active | Contract for difference (auction) | Pay-as-bid auctions for 20-year two-way contracts for difference under S.L. 545.39. In 2026 there are two calls for 40 kW–1 MW, the second taking bids from 5 to 12 October 2026, and one call for 1–10 MW (38 MW), which closed on 1 July 2026. | 2026 calls |
| Extended feed-in tariff after expiry (pre-2020 residential PV) | Active | Feed-in tariff | Residential PV whose feed-in tariff was approved before 2020 receives €0.105/kWh after the original tariff ends, until 20 years of feed-in payments have been reached in total. | — |
| Proxy of the market price for surplus exports | Active | Export payment | Approved generators without a feed-in tariff, and exports above the feed-in cap, are paid Enemalta’s regulated proxy of the market price, set each year by legal notice. | — |
| Eco-reduction | Active | Tariff discount | 25% or 15% off the consumption charge for primary residences with low use per registered resident. | — |
| Net metering (pre-September 2010 PV) | Closed | Net metering | Closed to new systems since 10 September 2010. Existing users keep it but cannot enlarge their systems. | — |
Data and connectivity.
- Fixed broadband
- 100 % of households covered by very-high-capacity networks (2025)Source 38Fibre-to-the-premises coverage was 90.4% of households. Fixed broadband subscriptions were 44.5 per 100 people in 2024 (World Bank).
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- 100 % of households covered (2025)Source 38Coverage in the 3.4–3.8 GHz band was 40%.
Malta reached the EU’s 2030 targets for gigabit and 5G coverage early: very-high-capacity networks have covered every household since 2019, 5G since 2022, and the main fixed operator completed nationwide fibre in 2025, with its copper network due to be switched off in 2026.
Smart meters do not use public telecoms networks. They communicate with Enemalta’s head-end over power-line carrier, and second-generation meters switch to radio frequency when needed. Data uses the DLMS/COSEM standard. A Chain 2 in-home interface exists for future customer devices but had not yet been activated. Public EV charging must use OCPP and OCPI.
Grid conditions.
- National peak demand
- 0.637 GW (2025)Source 16Reached on 25 July 2025 at 17:00; met 52.8% by local fossil plants, 32.7% by imports and an estimated 14.6% by PV. Below the 2023 all-time high.
- Annual electricity demand
- 3.08 TWh (2025)Source 16Provisional figure for electricity sent out to the grid (3,082.69 GWh), including losses. It excludes 124.7 GWh of renewable electricity used on site.
- Generation capacity
- 0.874 GW (end 2025)Source 16Derived: 603 MW of local fossil plant (including 175 MW of Enemalta and 60 MW of UNEC backup) plus 271.5 MW of renewables (PV in MWp DC).
- Interconnection
- 0.225 GW (2025)Source 16Net transfer capacity of the 220 kV HVAC Malta–Italy link since 1 July 2024. A second 225 MW link is under construction.
- Curtailment
- Not identified from a reliable public source.
Malta’s system is small, with a summer peak of about 640 MW, and depends on the interconnector, which supplied a third of grid electricity in 2025. Security of supply rests on the gas-fired plants at Delimara (supplied by a floating LNG storage unit), the 225 MW link to Sicily and about 175 MW of Enemalta backup gas-oil turbines. Enemalta reported 15 major incidents in 2025 but cut average outage time per customer by 44%.
Rooftop PV covered an estimated 14.6% of demand even at the 17:00 peak in 2025. Enemalta’s quarterly capacity map shows where low-voltage substations can accept more PV. The second interconnector, utility-scale batteries and network reinforcement programmes are intended to absorb further growth. Enemalta forecasts demand rising about 3% a year to 2030.
Grid and capacity maps.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| Second Malta–Italy interconnector (IC2) | Upcoming | Under construction; cable ready to install from mid-2026 | A 225 MW HVAC link of about 122 km (99 km subsea, 245 kV) from Magħtab to Ragusa, alongside the existing cable. Factory testing of the cable was completed in June 2026, with onshore works continuing in Sicily and Malta. Co-financed by the ERDF 2021–2027. |
| Free choice of supplier derogation | Upcoming | 5 July 2027 (expiry unless extended) | Malta’s exemption from Article 4 of Directive (EU) 2019/944 runs until 5 July 2027 and can be extended by the European Commission for up to eight years. Until then only Enemalta can hold a supply licence. |
| Utility-scale batteries at Delimara and Marsa | Upcoming | Procurement concluded 2025; construction pending | Two EU co-financed battery systems developed by InterConnect Malta to complement IC2, relieve network bottlenecks and add flexibility. |
| Third interconnector (IC3) | Upcoming | Commissioning envisaged 2033 | A 200 MW bidirectional HVDC link at 320 kV to Sicily, included in the 2026 EU Ten-Year Network Development Plan and eligible for the 2027 Projects of Common Interest selection. |
| Floating offshore wind farm | Upcoming | Procurement continuing in 2026 | Three pre-qualification submissions were received in July 2025. The chosen developer will build and run the farm under a 35-year concession with a 25-year contract for difference, and build a state-owned offshore grid connection. |
| EU market design reform transposed | Current | 2025 (LN 235 and LN 236 of 2025) | Brought flexible connection agreements, supplier of last resort, fixed-price contract rights and DSO capacity publication into S.L. 545.34. Enemalta’s obligation to buy all renewable exports ends once an organised market place becomes accessible. |
| Electricity Connection and Supply Regulations | Current | 29 October 2024 | S.L. 545.41 (LN 282 of 2024) replaced the Electricity Supply Regulations. It sets the rules for connecting loads, generators and storage, metering, billing and tariffs, including volt-var requirements for inverters. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Low | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | Medium | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | Low | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | High | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | High | About 269 MWp of PV was connected by the end of 2025, almost all small rooftop systems (97.5% are 11 kWp or less), with more than 35,000 independent producers in a country of about 243,000 households. |
| Distributed energy market | Medium | Rooftop PV is widespread and household batteries doubled to 31.6 MWh in 2025, but storage is still small in absolute terms and all exports are sold to a single buyer at regulated rates. |
| Grid flexibility market | Low | There is no organised wholesale, balancing or flexibility market. The DSO alone balances the system, and no aggregator or third-party data access exists. |
| Energy storage adoption | Low | Household batteries total 31.6 MWh across 3,150 installations, and no utility-scale storage is operating apart from a 2 MWh research unit. The Delimara and Marsa BESS are in procurement. |
| Renewable growth environment | Low | Renewable generation grew 8% in 2025, but annual PV additions have slowed to about 14 MWp. Renewables are about 11% of gross electricity consumption, and no large wind capacity exists until offshore wind is built. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 42 sources
- Electricity prices for household consumers – bi-annual data (from 2007 onwards) [nrg_pc_204]. Eurostat, 2025. accessed 1 October 2026.
- Electricity price statistics. Eurostat Statistics Explained, 2026. accessed 1 October 2026.
- Regulated Electricity Tariffs. Regulator for Energy and Water Services, 2025. accessed 1 October 2026.
- Residential property services – tariffs. Enemalta plc. accessed 1 October 2026.
- Tariff prices. ARMS Ltd. accessed 1 October 2026.
- Population change – demographic balance and crude rates at national level [demo_gind]. Eurostat, 2026. accessed 1 October 2026.
- Number of private households by household composition [lfst_hhnhtych]. Eurostat, 2025. accessed 1 October 2026.
- Average household size – EU-SILC survey [ilc_lvph01]. Eurostat, 2025. accessed 1 October 2026.
- Distribution of population by degree of urbanisation, dwelling type and income group [ilc_lvho01]. Eurostat, 2025. accessed 1 October 2026.
- Distribution of population by tenure status, type of household and income group [ilc_lvho02]. Eurostat, 2025. accessed 1 October 2026.
- Urban population (% of total population) – Malta. World Bank, 2025. accessed 1 October 2026.
- Complete energy balances [nrg_bal_c] – electricity, final consumption households. Eurostat, 2024. accessed 1 October 2026.
- Gross and net production of electricity and derived heat by type of plant and operator [nrg_bal_peh]. Eurostat, 2024. accessed 1 October 2026.
- Electricity production capacities for renewables and wastes [nrg_inf_epcrw]. Eurostat, 2024. accessed 1 October 2026.
- Share of energy from renewable sources [nrg_ind_ren]. Eurostat, 2025. accessed 1 October 2026.
- 2026 National Report of the Regulator for Energy and Water Services to the European Commission on the Electricity and Natural Gas sectors in Malta. Regulator for Energy and Water Services, 2026. accessed 1 October 2026.
- 2026 Renewable Energy Sources Scheme. Regulator for Energy and Water Services, 2026. accessed 1 October 2026.
- Renewable Energy Systems Initiatives 2026 (leaflet). Regulator for Energy and Water Services, 2026. accessed 1 October 2026.
- Feed-in Tariff Schemes table (29 April 2026). Regulator for Energy and Water Services, 2026. accessed 1 October 2026.
- Feed-in Tariffs Schemes – Frequently Asked Questions. Regulator for Energy and Water Services, 2026. accessed 1 October 2026.
- Authorisation and Notification PV’s Feed In Tariff < 40 kWp. Regulator for Energy and Water Services, 2026. accessed 1 October 2026.
- Authorisation and Notification RES & CHP. Regulator for Energy and Water Services, 2026. accessed 1 October 2026.
- Energy Storage – Applications for Notification of an Energy Storage Facility. Regulator for Energy and Water Services, 2026. accessed 1 October 2026.
- Connection to the Electricity Distribution System. Regulator for Energy and Water Services, 2025. accessed 1 October 2026.
- FAQs relating to Electric Vehicle Charging. Regulator for Energy and Water Services, 2026. accessed 1 October 2026.
- Application to Become an Authorised Electrician. Regulator for Energy and Water Services, 2025. accessed 1 October 2026.
- Call for bids 2026. Regulator for Energy and Water Services, 2026. accessed 1 October 2026.
- About us – Our Network. Enemalta plc. accessed 1 October 2026.
- Grid-connected renewable energy systems. Enemalta plc, 2025. accessed 1 October 2026.
- Technical service specifications. Enemalta plc. accessed 1 October 2026.
- Becoming an Enemalta customer. Enemalta plc, 2026. accessed 1 October 2026.
- Available Capacity. Enemalta plc, 2025. accessed 1 October 2026.
- Malta – national practices report under Implementing Regulation (EU) 2023/1162 (metering and consumption data). EU DSO Entity / ENTSO-E (Repository of National Practices), 2025. accessed 1 October 2026.
- Your Residential Electricity and Water Bill Has Changed – information booklet (specimen bill). ARMS Ltd. accessed 1 October 2026.
- EV meter application form. ARMS Ltd, 2026. accessed 1 October 2026.
- Passenger cars, by type of motor energy [road_eqs_carpda]. Eurostat, 2025. accessed 1 October 2026.
- New passenger cars by type of motor energy [road_eqr_carpda]. Eurostat, 2025. accessed 1 October 2026.
- Digital Decade 2026 country report – Malta (SWD(2026) 155, Council doc. 10476/26 ADD 48). European Commission, 2026. accessed 1 October 2026.
- Nexans completes cable manufacturing for the Malta–Sicily second interconnector. Nexans, 2026. accessed 1 October 2026.
- Europe’s environment 2025 – Malta: renewable energy sources. European Environment Agency, 2025. accessed 1 October 2026.
- Government launches new €15 million renewable energy schemes for 2026. The Malta Independent, 2026. accessed 1 October 2026.
- Fixed broadband subscriptions (per 100 people) – Malta. World Bank, 2024. accessed 1 October 2026.
Questions about energy in Malta.
Eurostat puts the average household price at €0.1282/kWh in the second half of 2025, all taxes included. That is less than half the EU average (€0.2896/kWh) and the second-lowest in the EU. Regulated residential rates start at €0.1047/kWh for the first 2,000 kWh a year and rise through five bands to €0.6076/kWh above 20,000 kWh, plus an annual service charge of €65 for a single-phase supply. Rates have not changed since March 2014.
No. Enemalta plc is the only licensed electricity supplier, and Malta has an EU derogation from free choice of supplier until at least 5 July 2027. All customers pay the same regulated tariffs, and billing is handled by ARMS Ltd.
There is no equivalent single supply-point number. An electricity supply is identified by the ARMS account number together with the Enemalta meter serial number. Both are printed on the ARMS bill, and the meter serial is the official metering point identifier. Unlike an MPAN, neither is a permanent property code: the account changes when the consumer changes, and the serial changes when the meter is replaced.
Yes. Enemalta must buy exports from approved systems. In 2026, PV under 40 kWp without a grant can get a feed-in tariff of €0.15/kWh for 20 years, and grant-aided residential systems get €0.105/kWh. Payment covers up to 1,600 kWh per kWp a year, and any surplus beyond that is paid at the proxy market price. You can choose to sell all output or only the surplus.
Systems up to 16 A per phase (3.68 kW single-phase), or 20 A with volt-var inverters, only need to be notified to REWS through its one-stop shop before installation. Larger systems need an Enemalta grid study, a No Objection Letter, a REWS Authorisation to Construct and a licence to generate. Planning rules apply too, but rooftop PV meeting the Development Notification Order normally needs no full planning permit.
REWS ran a 2026 Renewable Energy Sources grant scheme covering 65% of PV-with-hybrid-inverter costs (up to €3,000) and 75% of battery costs (up to €6,000). The battery options closed in July 2026, and the whole scheme stopped taking applications from 12 September 2026. Schemes have been relaunched each year, so check REWS for the next call.
At the end of 2025, 316,689 of 340,940 active household meters (92.9%) were smart meters read remotely by Enemalta. Second-generation meters with power-line and radio communication made up 29.2% of all meters. Customers can see hourly data for the last 30 days on the ARMS portal.
In 2025, 58.3% of grid electricity came from local natural gas plants, 33.5% from imports through the cable link to Sicily, 7.7% from renewables fed into the grid (mainly rooftop solar) and 0.5% from oil-fired backup. A further 125 GWh of solar power was used directly by producers on site.