How electricity works in Panama.
Panama electricity market 2026: ASEP-regulated tariffs, EDEMET, ENSA and EDECHI, the CND/ETESA system operator, net-metered self-consumption and the FET subsidy.
This overview covers what electricity costs, how much a typical household uses, how the grid is run and regulated, and whether homes can send electricity back to the grid. Figures are shown in Panamanian balboa (at par with the US dollar) (PAB) where they relate to prices.
Each important figure links to its public source and states the year it refers to. Where no reliable public figure was found, the page says so. Unfamiliar terms are explained in our glossary.
Panama energy at a glance.
Key figures for households in Panama. Each one links to its source on the full overview below.
Electricity price.
0.176 PAB per kWh for households, including taxes. Figures for Sep–Dec 2026.
Renewable share.
68% of electricity from renewable sources. Figures for 2024.
Selling back to the grid.
Can homes export electricity? Yes. Details are in the export section below.
Four things to check in Panama.
Rules and schemes change. Use this page as a starting point, then confirm the details that matter to you.
Check the local rules.
Read the connection, export and permission rules for Panama below, and ask your local grid operator if anything is unclear.
Choose a qualified installer.
Look for an installer listed on an official register, with the certifications Panama requires for the work.
Look at current schemes.
Check which support schemes are open now. Closed or scheduled schemes are labelled as such.
Talk to your energy supplier.
Ask how new equipment, such as solar or a battery, could affect your tariff and any export payments.
Schemes, rules and certifications in Panama.
The full detail sits in the sections below. Each item shows its status and links to the official source.
Support schemes.
Grants, tax relief and export payments in Panama, each labelled Active, Scheduled or Closed.
Connection and export.
How equipment is connected to the grid in Panama, and the steps to export electricity.
Standards and certifications.
The technical standards and installer certifications that apply to energy equipment in Panama.
The energy market in Panama, in detail.
Each figure shows the year it refers to and a numbered link to its public source, listed at the end of the page.
Profile last updated 9 October 2026.
On this page22 sections
Panama’s electricity sector was restructured by Law 6 of 1997 into separate generation, transmission and distribution businesses. Generation is competitive: private and mixed-ownership companies sell energy and capacity in a wholesale market, mostly through long-term contracts with the distributors and partly in a spot (occasional) market. The state-owned Empresa de Transmisión Eléctrica, S.A. (ETESA) owns the national transmission network, runs the tenders through which distributors buy energy and capacity, and houses the Centro Nacional de Despacho (CND), which dispatches the system and operates the wholesale market.
Households buy electricity from one of three distribution companies, each with an exclusive concession area: EDEMET (Panama City west and the central provinces) and EDECHI (Chiriquí), both operated under the Naturgy brand, and ENSA (Elektra Noreste, the east of Panama City, Colón and the north-east). In August 2026 the three served 1,342,179 customers between them. Tariffs are set by the regulator, the Autoridad Nacional de los Servicios Públicos (ASEP), and are heavily subsidised for small consumers through the state Tariff Stabilisation Fund (FET).
Hydropower is the backbone of supply, producing just over half of Panama’s electricity in 2024, with natural gas, oil and coal plants, and fast-growing solar and wind, making up the rest. Customers can install renewable generation for their own use and offset it against their bills under ASEP’s self-consumption procedure; the government’s 2026 energy-plan diagnosis counted more than 7,000 such customers with 196 MW of distributed generation by 2025.
Energy snapshot.
Headline figures for electricity in Panama. Each shows its data year and links to its source.
- Population4,571,189 peopleSource 12025
- Households1,201,809 householdsSource 52023
- Average household size3.34 people/householdSource 72023
- Electricity use per householdNot identified from a reliable public source.
- Household price (PAB)0.176 PAB/kWhSource 9Sep–Dec 2026
- Household price (EUR)0.157 EUR/kWhSource 18Sep–Dec 2026
- Renewable electricity share68%Source 192024
- Solar capacity0.973 GWSource 202025
- Wind capacity0.336 GWSource 8August 2026
- Energy storage capacityNot identified from a reliable public source.
- Smart-meter shareNot identified from a reliable public source.
- Market structure
- Partially liberalised
- Homes can export to the grid
- Yes
- Home equipment in grid services
- No
- Regulator
- ASEP (Autoridad Nacional de los Servicios Públicos); the Secretaría Nacional de Energía sets policy
- System operator
- Centro Nacional de Despacho (CND), part of the state transmission company ETESA
- Distribution networks
- Three concession-holding distributors: EDEMET and EDECHI (Naturgy) and ENSA
- Currency
- Panamanian balboa (at par with the US dollar) (PAB)
- Voltage and frequency
- 120 V and 120/240 V / 60 Hz
Electricity prices in Panama.
- Household price (PAB)
- 0.176 PAB/kWh (Sep–Dec 2026)Source 9EDEMET simple low-voltage tariff (BTS), energy charge for kWh 11–300, valid 1 September to 31 December 2026; the first 10 kWh are covered by a fixed charge of B/.3.17 a month. ENSA charges B/.0.17737 and EDECHI B/.0.19175 for the same band. Before the monthly fuel-cost adjustment (CVC, −B/.0.00993/kWh for EDEMET in September 2026) and before the FET subsidy credit, which reduces the bill of EDEMET households using up to 300 kWh by between about 31% and 49% depending on the consumption band.
- Household price (EUR)
- 0.157 EUR/kWh (Sep–Dec 2026)Source 18Converted from B/.0.17624/kWh (the balboa is at par with the US dollar) at the ECB reference rate of USD 1.1206 per euro on 9 October 2026.
- Typical annual electricity bill
- 651.4 PAB/yr (Sep–Dec 2026 tariffs (annualised))Source 9Illustrative, derived: an EDEMET household on tariff BTS using 300 kWh a month pays the B/.3.17 fixed charge (first 10 kWh) plus 290 kWh × B/.0.17624 = B/.54.28 a month, × 12. Excludes the fuel adjustment (CVC), the FET subsidy credit (about −31% at this level of use) and any other bill items. 300 kWh is an illustrative level, not an official average.
Household price trend (PAB per kWh).Source 12
| 2023 H1 | 0.15141 PAB/kWh |
|---|---|
| 2023 Q3 | 0.15141 PAB/kWh |
| 2023 Q4 | 0.15394 PAB/kWh |
| 2024 H1 | 0.14796 PAB/kWh |
| 2024 Jul–Oct | 0.14413 PAB/kWh |
| 2024 Oct–Dec | 0.14413 PAB/kWh |
| 2025 H1 | 0.14718 PAB/kWh |
| 2025 H2 | 0.1617 PAB/kWh |
| 2026 H1 | 0.15693 PAB/kWh |
| 2026 Jul–Aug | 0.15693 PAB/kWh |
| 2026 Sep–Dec | 0.17624 PAB/kWh |
How tariffs are set
ASEP approves a tariff schedule (pliego tarifario) for each distributor for a multi-year tariff period, covering distribution and commercialisation costs, and passes through the cost of the energy and capacity the distributor buys under its supply contracts and in the spot market. Naturgy states that its 2023–2026 schedule ran from 1 July 2023 to 30 June 2026, with updates every six months by the consumer price index. ASEP publishes the resulting tariffs for regulated customers for each period; the current schedule runs from 1 September to 31 December 2026.
Fuel prices are passed through separately by a monthly fuel-cost adjustment (variación por combustible, CVC) for each tariff. For September and October 2026 it reduced EDEMET’s BTS price by B/.0.00993 and B/.0.00882 per kWh, added B/.0.00009 at ENSA and reduced EDECHI’s by B/.0.00492 and B/.0.01175.
Subsidies
The state Tariff Stabilisation Fund (Fondo de Estabilización Tarifaria, FET) credits a percentage of the bill to eligible customers so that, under Cabinet Resolution 60 of 23 June 2015, they keep paying the average reference price of the first half of 2015. For September–December 2026 the FET credit for EDEMET homes ranges from 30.62% to 48.68% for consumption up to 300 kWh and from 5.52% to 10.30% for 301–750 kWh; for ENSA homes up to 300 kWh it ranges from 26.61% to 46.19%; at EDECHI it is larger still. The fuel-cost adjustment is not covered by the FET. The 2026 energy-plan diagnosis puts the cumulative electricity subsidy over the decade reviewed at 1,590 million balboas.
ENSA’s tariff dispute
ASEP’s July–August 2026 tariff notice stated that, following a suspension ordered by the Third Chamber of the Supreme Court of ASEP’s 2023 approval of ENSA’s schedule (Resolution AN 18702-Elec), the previous ENSA schedule (Resolution AN 13039-Elec) had applied provisionally since 23 October 2024 under Resolution AN 19632-Elec. That note does not appear in the September–December 2026 notice.
Differences between areas
EDECHI, which serves Chiriquí, has the highest BTS energy charges but also the largest subsidy credits. ENSA’s higher-consumption bands are dearer than EDEMET’s.
Tariff types.
| Tariff | Available | Detail |
|---|---|---|
| Regulated | Yes | Simple low-voltage tariff BTS for customers with maximum demand up to 15 kW. Sep–Dec 2026: a fixed charge for the first 10 kWh (EDEMET B/.3.17, ENSA B/.2.76, EDECHI B/.3.04), then kWh 11–300 at B/.0.17624 / 0.17737 / 0.19175, kWh 301–750 at B/.0.23177 / 0.24666 / 0.25341 and above 750 kWh at B/.0.25027 / 0.27005 / 0.27486 (EDEMET / ENSA / EDECHI). |
| Time-of-use | Limited | BTSH, the simple tariff with time blocks, is available on request to customers up to 15 kW and needs a meter that records by period. Sep–Dec 2026 prices for EDEMET are B/.0.39247/kWh at peak, B/.0.19878 in the medium off-peak block and B/.0.11612 in the low off-peak block (ENSA B/.0.30790 / 0.22812 / 0.14833). The FET subsidy does not apply to BTSH at EDEMET or ENSA. |
| Prepayment | Limited | Prepaid tariff for residential customers using up to 300 kWh a month in coverage areas approved by ASEP: B/.0.16337/kWh at EDEMET, B/.0.18927 at ENSA and B/.0.16527 at EDECHI (Sep–Dec 2026), with FET credits of 29.57% to 50.14%. Credit is bought as a 20-digit code typed into an indoor keypad. |
| Other | Yes | Customers above 15 kW move to the demand tariff BTD or the time-of-use demand tariff BTH; medium- and high-voltage customers have their own MTD/MTH and ATD/ATH tariffs. |
| Dynamic | No | No residential tariff linked to the wholesale (spot) price was identified. Changes in fuel costs reach customers through a monthly fuel-cost adjustment (CVC) published by ASEP for each tariff. |
| Fixed | No | There is no retail competition and no fixed-price contract offer; prices are reset by ASEP several times a year. |
Household prices compared with neighbouring countries (EUR per kWh).
- Colombia€0.231
- Honduras€0.215
- Guatemala€0.209
- El Salvador€0.168
- Nicaragua€0.158
- Panama€0.157
- Costa Rica€0.114
Household prices including taxes, converted to euros as stated on each country page.
Household electricity use.
- Electricity use per household
- Not identified from a reliable public source.
- Average daily use per household
- Not identified from a reliable public source.
- Typical household peak demand
- Not identified from a reliable public source.
- Electricity use per person
- 2,242 kWh/person/yr (2024)Source 3Electric power consumption per person, all sectors (World Bank indicator EG.USE.ELEC.KH.PC).
- Heat pumps
- Not identified from a reliable public source.
- Air conditioning
- Not identified from a reliable public source.
- Electric vehicles
- Not identified from a reliable public source.
- Electric cooking
- 1.01 % of homes (2023)Source 7Derived: 12,174 of 1,201,809 occupied private dwellings cook mainly with electricity; 1,102,863 use gas (LPG) and 72,179 firewood.
Homes are a growing share of Panama’s electricity use: the 2026 energy-plan diagnosis reports that the residential sector’s share of consumption rose from 32.5% in 2015 to 39% in 2025, and government from 12% to 14%.
Demand peaks in the hot, dry months and in mid-year. ASEP’s statistics show monthly maximum demand on the national system rising from 1,778 MW in January 2026 to 2,170 MW in July 2026.
Almost all households cook with subsidised bottled gas, so electricity use in homes is driven mainly by cooling, refrigeration, lighting and appliances.
Housing and households.
- Dwellings
- 1,201,809 dwellings (2023)Source 5Occupied private dwellings.
- Owner-occupied
- 81.6% (2023)Source 6Derived: owned outright (763,183) plus mortgaged (217,227) as a share of 1,201,809 occupied private dwellings. A further 4.2% are lent (cedida), and small numbers are in succession/litigation or occupied without title.
- Private rented
- 13.1% (2023)Source 6Derived: 157,657 rented dwellings. The census does not separate private from public landlords.
- Social or public housing
- Not identified from a reliable public source.
- Houses
- 86.5% (2023)Source 7Derived: 1,039,294 individual houses. A further 0.6% are improvised dwellings and 0.8% rooms in tenement houses.
- Apartments and flats
- 12.1% (2023)Source 7Derived: 145,472 apartments.
- Urban population
- 66.2 % of population (2025)Source 2
Most Panamanian households live in individual houses, and more than four in five own their home. Apartments, 12% of dwellings in 2023, are concentrated in Panama City, where most have concrete-slab roofs; nearly all houses have metal roofs.
The 2023 census found 1,082,313 dwellings lit by electricity from a distribution company, 49,206 using their own solar panels and smaller numbers using community or private generators, candles or torches. The government’s energy-plan diagnosis reports that about 58,000 homes still had no electricity, while the electrification rate rose from 88.0% in 2014 to 96.0% in 2024.
The population is concentrated in the provinces of Panamá (448,402 households) and Panamá Oeste (199,081), followed by Chiriquí (142,806).
How the grid works in Panama.
- TransmissionEmpresa de Transmisión Eléctrica, S.A. (ETESA), Centro Nacional de Despacho (CND), part of ETESA
- DistributionThree concession-holding distributors: EDEMET and EDECHI (Naturgy) and ENSA
- MeteringNot identified from a reliable public source.
- Supply3 or more retail suppliers
Physical flow
In August 2026 Panama had 5,107 MW of installed capacity: 1,848 MW of hydro (620 MW reservoir and 1,228 MW run-of-river), 1,051 MW gas, 581 MW bunker oil, 221 MW diesel, 300 MW coal, 771 MW solar and 336 MW wind. Power flows over ETESA’s high-voltage network to the three distribution networks. Panama is connected to Costa Rica and the rest of Central America through the regional transmission network; ASEP’s statistics show exports of 101–143 GWh a month between September 2025 and May 2026 and almost none from June to August 2026.
Commercial flow
Generators sell to distributors mainly through long-term contracts awarded in public tenders run by ETESA, and trade differences in the spot (occasional) market operated by the CND. Distributors pass the cost of these purchases, plus regulated network and commercialisation charges, to customers through ASEP tariffs. In August 2026 the system marginal cost averaged B/.65.14/MWh.
Who does what.
| Role | Organisation | What it does |
|---|---|---|
| Ministry | Secretaría Nacional de Energía (SNE) | Sets energy policy and is preparing the National Energy Plan 2026–2040. Receives information on larger self-consumption plants and storage systems. |
| Regulator | Autoridad Nacional de los Servicios Públicos (ASEP) | Approves distributors’ tariff schedules and publishes regulated tariffs, issues technical and commercial rules (metering, self-consumption, storage, EV charging), handles concessions and licences and settles disputes between customers and distributors. |
| TSO | Empresa de Transmisión Eléctrica, S.A. (ETESA) | State-owned owner of the national transmission system. Also runs the public tenders (actos de concurrencia) through which energy and capacity are bought for the distributors. |
| System operator | Centro Nacional de Despacho (CND), part of ETESA | Dispatches the national interconnected system (SIN), operates the wholesale market and supervises larger self-consumption plants through the distributors. |
| DSO | EDEMET (Empresa de Distribución Eléctrica Metro-Oeste), Naturgy | Largest distributor: 603,175 customers in August 2026, serving western Panama City and the central and western provinces. |
| DSO | ENSA (Elektra Noreste, S.A.) | 550,142 customers in August 2026, serving eastern Panama City, Colón and the north-east of the country. |
| DSO | EDECHI (Empresa de Distribución Eléctrica Chiriquí), Naturgy | 188,862 customers in August 2026 in the province of Chiriquí. |
Compared with the UK system.
| UK concept | Panama equivalent | How it works |
|---|---|---|
| DNO | Empresa distribuidora (EDEMET, ENSA or EDECHI) | Each distributor holds an exclusive concession for its area and both runs the network and sells electricity to the customers in it. It connects new customers, installs and reads the meter and signs interconnection agreements with self-consumers. |
| National Grid/NESO | ETESA and its Centro Nacional de Despacho (CND) | ETESA owns the transmission network and its CND unit dispatches generation and runs the wholesale market, so transmission ownership and system operation sit in the same state company. |
| MPAN | Número de cliente (customer/account number) | Each supply is identified by the distributor’s customer number, which ASEP’s rules use when distributors report self-consumers and storage systems. There is no national meter-point numbering scheme and no common format between distributors. |
| MPRN | No equivalent | There is no piped gas network for homes; households cook mainly with bottled LPG. |
| Meter operator | The distributor | The distributor supplies and reads the meter under ASEP’s metering standard (Resolution AN 5999-Elec of 13 March 2013) and installs a bidirectional meter at its own cost for self-consumers. There is no separate metering market. |
| Supplier | The same distributor (no retail choice for households) | Households buy from the distributor in whose area they live, at ASEP’s regulated tariffs. Only large customers qualified as Grandes Clientes can buy in the wholesale market instead. |
| Smart-meter infrastructure | Distributor systems; no national programme | No national smart-meter roll-out or central data hub was identified. Smart, communicating meters are required by ASEP rules only in specific cases, such as three-phase self-consumers with demand above 100 kW. |
How a supply point is identified.
| Question | Answer |
|---|---|
| What is it called? | Número de cliente (número de identificación de cuenta de servicio eléctrico) |
| Who issues it? | The local distributor (EDEMET, ENSA or EDECHI) |
| Format | A numeric customer/account number assigned by the distributor when the supply contract is signed. Each distributor uses its own numbering, and no public specification of its structure was found. |
| Length | Not published |
| Stays with the property when you switch supplier? | Not identified from a reliable public source. |
| Where to find it | On the electricity bill: Naturgy explains that the bill shows reference and customer numbers that locate the contract and identify the customer, together with the supply address. |
| Electronic access | Through each distributor’s online customer office (for example Naturgy’s oficina virtual) after registration, where customers can view and pay bills. |
| Third-party access | No regulated third-party data-access scheme was identified. Distributors report self-consumers to ASEP monthly by customer number. |
| Who keeps the register | Each distributor keeps its own customer register; ASEP receives monthly lists of self-consumers from each distributor. |
| Register scope | Per DSO |
In Panama a household’s electricity supply is identified by its contract with the local distributor rather than by a national meter-point number. When a home is connected, the distributor opens a supply contract linked to an address and a meter and assigns a customer number. ASEP’s self-consumption procedure requires the interconnection agreement to record the customer’s identification number and the property’s land-registry number (finca), district and province, and distributors must report each self-consumer to ASEP by name and customer number every month.
ASEP’s 2024 battery-storage procedure likewise refers to the “identification numbers of the electricity service account” of the customers a storage system supplies, confirming that the account number is the reference used by the regulator.
Because each of the three distributors runs its own billing system, a customer who moves between concession areas (for example from ENSA’s area in eastern Panama City to EDEMET’s in the west) takes out a new contract with a different company. Whether a customer number stays with the property when the occupant changes was not stated in the sources reviewed.
No fictional example is given because no distributor publishes the structure or length of its customer numbers.
Sending electricity to the grid.
| Question | Answer |
|---|---|
| Can homes export electricity? | Yes |
| Net metering | Yes |
| Net billing | Limited |
| How exported electricity is paid | Monthly net metering with kWh credits; credits left at the end of the year or half-year are paid at the distributor’s average contract energy purchase cost, up to 25% of the customer’s historical consumption |
| How big can a system be? | The procedure has no single cap but sets three bands: up to 500 kW (Electrical Installations Regulation, RIE, only), over 500 kW to 2,500 kW (also remote supervision and remote disconnection by the distributor and supervision by the CND), and above 2,500 kW (also the applicable grid code). Capacity is measured in kW AC after the inverter. |
| How is surplus credited? | Each billing period (28–32 days) the bidirectional meter is netted. If the customer exported more than it imported, the fixed charge is billed and the net export is stored as kWh credits used in following months. |
| Is surplus paid for? | Yes, within limits. Customers choose annual or half-yearly settlement; remaining credits are paid by cheque, bank transfer (ACH) or account credit at the distributor’s average purchase cost under its energy contracts, up to a maximum of 25% of the customer’s historical consumption recorded in the interconnection agreement. Annual credits are paid before 16 February of the following year. |
| Is there a network-wide limit? | The initial general limit is that the total installed capacity of self-consumers in a concession area must not exceed 10% of the distributor’s forecast annual maximum demand (MW) or 2% of its annual energy consumption (GWh). ASEP is to review the limit every three years, and distributors and ASEP must publish the remaining capacity. |
| Can I sell to a neighbour or a third party? | No. Self-consumers cannot take part in the wholesale market or sell energy to third parties, and equipment suppliers cannot sell energy to the customer, because selling electricity to final customers is reserved to the distributors. |
| Can I generate without exporting? | Yes. Customers who do not join the procedure can self-supply with the distributor’s authorisation if their system disconnects from the grid while generating or uses zero-export devices. |
Connecting a home system.
- Send the distributor a letter requesting connection, with the electrical design approved by the Fire Service (Cuerpo de Bomberos) and municipal engineering, the plant’s capacity and the technical specifications of all equipment.
- The distributor replies in writing within 15 working days (plants up to 500 kW) or 20 working days (larger plants), with its consent or observations and a copy of the interconnection agreement.
- Sign the interconnection agreement, install the system and obtain the inspections and permits from the competent authorities.
- Notify the distributor, which carries out tests within 5 working days (up to 500 kW) or 10 working days (larger plants).
- The distributor issues written approval within 10 working days of the tests and installs a bidirectional meter at its own cost; parallel operation may start only after this approval.
The rules are set out in ASEP’s Procedure for Self-Consumption with New, Renewable and Clean Sources, approved by Resolution AN 10206-Elec of 11 July 2016 and amended by Resolution AN 10299-Elec of 10 August 2016, which ASEP publishes as its current self-consumption procedure. It applies to customers of the distributors connected at low or medium voltage, but not to large customers qualified to buy in the wholesale market.
The customer pays for a separate generation meter (accuracy ±2% or better), while the distributor installs the bidirectional meter at its own cost. Any network reinforcement needed only because of the plant is paid by the customer and is not refundable. The distributor may require a lockable visible-break disconnect switch, and for low-voltage systems below 500 kW the main switch can serve as the disconnect device by written agreement.
Owners of plants above 100 kW must send their location, approved design, capacity and interconnection agreement to the SNE, the CND and ASEP within five working days of signing. Distributors report every self-consumer to ASEP each month, including energy injected and credits paid. By 2025, according to the energy-plan diagnosis, more than 7,000 customers had 196 MW of distributed generation.
Licensing and approvals.
Requirements depend on the activity. The table sets out what each activity needs and who grants it.
| Activity | Licence or registration | Authority | Notes |
|---|---|---|---|
| Generate electricity for own use | No generation licence under the self-consumption procedure; an interconnection agreement with the distributor and Fire Service and municipal approval of the design are needed | Distributor, under ASEP rules | Plants above 500 kW need remote supervision and disconnection; above 2,500 kW the grid code also applies. |
| Generate electricity for sale to the wholesale market | Concession or licence from ASEP under the electricity law (Law 6 of 1997) | ASEP | Sales are made through contracts with distributors or large customers and in the spot market operated by the CND. Size thresholds were not verified. |
| Self-generation and cogeneration outside the procedure | Governed by ASEP’s regulation of self-generation and cogeneration activities (Resolution AN 5046-Elec) | ASEP | Details not reviewed. |
| Store energy | No general framework for customer-owned grid-connected storage identified; ASEP’s 2024 procedure covers only distributor-owned batteries for public critical-load customers | ASEP and distributors | Those systems may be used only for reliability, not demand management; NFPA 855 and the RIE apply. |
| Export surplus | Interconnection agreement under the self-consumption procedure; compensation only from the local distributor | Distributor; ASEP resolves disputes | Paid surplus is capped at 25% of historical consumption. |
| Supply electricity to final customers | Distribution concession for a defined area; sales to regulated customers are exclusive to the distributors | ASEP | Three concession holders: EDEMET, ENSA and EDECHI. |
| Aggregate DER | No aggregator role identified in the regulations reviewed | ASEP | Self-consumers may not sell to third parties or participate in the wholesale market. |
| Wholesale trading and balancing | Participation as a registered agent of the wholesale market (generators, distributors, large customers) | ASEP and the CND | Self-consumers under the procedure are excluded. |
| Remote control of assets / VPP | No licence regime identified; distributors must be able to disconnect self-consumption plants above 500 kW remotely | Distributor and CND | No virtual power plant framework identified. |
Panama separates the competitive wholesale business, open to licensed generators and qualified large customers, from the regulated distribution and supply business, which is reserved to the three concession holders. Households and small businesses therefore have one route to generate: the self-consumption procedure, under which they deal only with their distributor.
Installations must comply with the Electrical Installations Regulation of the Republic of Panama (RIE). Designs are approved by the Fire Service and municipal engineering, and protection tests are carried out by a technician who meets the requirements of the Technical Board of Engineering and Architecture (JTIA).
Flexibility and grid services.
Aggregation of home equipment: No
| Market or service | Access for home equipment | Minimum size | Via an aggregator | Detail |
|---|---|---|---|---|
| Wholesale spot (occasional) and contract markets | No | — | No | CND (ETESA). Open to registered agents such as generators, distributors and qualified large customers; customers under the self-consumption procedure are explicitly excluded. |
| Time-of-use tariffs | Yes | — | No | Distributors. BTSH and demand-based time-of-use tariffs reward shifting consumption away from the peak; they are tariffs, not a market. |
| Regional electricity market (MER) | No | — | No | CND with the regional operator. Panama exports and imports through the Central American regional market; small resources do not take part. |
No flexibility or aggregation market for distributed resources exists in Panama. The 2026 energy-plan diagnosis lists system flexibility (reserves, storage and demand management) among the persistent gaps the 2026–2040 plan needs to address.
Smart meters.
| Fact | Value |
|---|---|
| Smart-meter rollout | No national smart-meter programme identified; prepayment meters in parts of the network |
| Reading interval | Not published for household meters; 15-minute data required for three-phase self-consumers above 100 kW |
| Metering standard | Resolution AN 5999-Elec, 13 March 2013 |
| Self-consumer meter | Bidirectional meter installed by the distributor at its cost |
| Naturgy prepayment customers | More than 5,500 |
| Prepayment top-up | 20-digit code entered on an indoor keypad |
Meters are owned and read by the distributors under ASEP’s metering standard for regulated customers. ASEP’s self-consumption procedure requires that three-phase self-consumers with maximum demand above 100 kW get a bidirectional meter with mass memory recording voltages, currents and power-quality data every 15 minutes, communicating with the distributor’s operations centre through a smart metering system with a real-time SCADA interface.
Prepayment metering is governed by a separate ASEP procedure (2019). Naturgy’s prepayment service uses an outdoor meter and an indoor keypad display showing energy bought and available.
Renewable electricity.
Electricity generation mix (2024).
- Hydro: 53.1%
- Gas: 20.9%
- Oil: 7.5%
- Solar: 7.4%
- Wind: 7.2%
- Coal: 3.7%
- Bioenergy: 0.4%
- Renewable electricity share
- 68% (2024)Source 19Share of electricity generation from hydro (53.09%), solar (7.37%), wind (7.15%) and bioenergy (0.37%), Ember data via Our World in Data. Panama was a net exporter in 2024 (generation 13.43 TWh against demand of 13.29 TWh), so the generation share is used.
- Home solar
- 0.196 GW (2025)Source 23All distributed generation (more than 7,000 customers), not only residential.
- Solar added each year
- Not identified from a reliable public source.
- Total installed capacity
- 5.107 GW (August 2026)Source 8
- Hydro (reservoir and run-of-river)
- 1.848 GW (August 2026)Source 8620 MW reservoir plus 1,227.57 MW run-of-river (derived by addition).
- Solar PV (wholesale-market plants)
- 0.771 GW (August 2026)Source 8
- Wind
- 0.336 GW (August 2026)Source 8
Targets.
- The National Energy Plan 2026–2040 is being prepared by the Secretaría Nacional de Energía; regional consultation forums were held in September 2026 and no new targets had been published.
- The plan diagnosis sets a target range of 10–14% for electricity losses, against about 19.5% today.
Hydropower dominates Panama’s generation, but most of it is run-of-river, so output depends heavily on rainfall; the energy-plan diagnosis highlights resilience to droughts as a persistent gap. Natural gas has become the main thermal fuel, and coal and oil plants provide the rest.
Solar has grown quickly: ASEP lists 770.65 MW of photovoltaic plants in the wholesale market in August 2026, and IRENA reports 0.973 GW of total solar capacity for 2025, which includes distributed systems. The 2023 census also recorded 49,206 homes, mostly rural, that rely on their own solar panels for lighting.
Energy storage.
- Home batteries
- Not identified from a reliable public source.
- Grid-scale storage
- Not identified from a reliable public source.
Panama’s only specific storage rule is ASEP’s Procedure for the Incorporation of Battery Storage Systems in Final Customers with Critical Load (Resolution AN 19360-Elec of 2 July 2024). It lets distributors install batteries, which they own and recover through tariffs, to keep supply going to public critical-load customers such as state hospitals and health centres, blood banks, prisons and police. The batteries may be used only to improve reliability, not for demand management, and must meet the RIE and NFPA 855, with Fire Service approval and CND approval above 2,500 kW.
Where such a customer also has a self-consumption system, the two are treated separately, each with its own inverter, and the battery can be charged from the solar plant or the grid.
Electricity suppliers.
| Supplier | Market share | Renewable tariff | Time of use | Dynamic | Export tariff |
|---|---|---|---|---|---|
| EDEMET (Naturgy) | 45% of customers and 50% of sales (August 2026) | No | Limited | No | Limited |
| ENSA (Elektra Noreste) | 41% of customers and 40% of sales (August 2026) | No | Limited | No | Limited |
| EDECHI (Naturgy) | 14% of customers and 10% of sales (August 2026) | No | Limited | No | Limited |
The three distributors are both network operators and the only suppliers to regulated customers in their areas, so a household’s supplier is fixed by its address. In August 2026 they sold 769.4 GWh and billed B/.155.6 million: EDEMET 359.5 GWh, ENSA 319.9 GWh and EDECHI 90.0 GWh.
“Export tariff: Limited” reflects net metering with paid surplus capped at 25% of historical consumption. “Time-of-use: Limited” reflects that BTSH is available on request and needs a suitable meter.
Key organisations.
| Organisation | Category | What it does | Why it matters |
|---|---|---|---|
| Secretaría Nacional de Energía (SNE) | Government | Energy policy and planning | Leads the National Energy Plan 2026–2040 and receives data on larger self-consumption and storage systems. |
| ASEP | Regulator | Public services regulator | Sets tariffs, self-consumption, metering and storage rules and publishes monthly market statistics. |
| ETESA | Transmission | Transmission owner and energy procurement for distributors | Owns the national grid, runs the supply tenders and houses the system operator. |
| Centro Nacional de Despacho (CND) | Market | System and wholesale market operator | Dispatches the national system and operates the wholesale and spot markets. |
| Naturgy Panamá (EDEMET and EDECHI) | Distribution | Distributors | Serve almost six in ten customers, including the west of Panama City and Chiriquí. |
| ENSA | Distribution | Distributor | Serves eastern Panama City, Colón and the north-east. |
| Instituto Nacional de Estadística y Censo (INEC) | Consumer | National statistics office | Publishes census data on housing, lighting sources and cooking fuels. |
Technical standards.
| Area | Standard | Issued by | Notes |
|---|---|---|---|
| Electrical installations | Reglamento de Instalaciones Eléctricas de la República de Panamá (RIE) | Panamanian authorities; inspected by the Fire Service and municipal engineering | Applies to all self-consumption plants and storage systems under ASEP procedures. |
| Grid connection (self-consumption) | Procedure for Self-Consumption with New, Renewable and Clean Sources (Resolutions AN 10206-Elec and AN 10299-Elec, 2016) | ASEP | Requires automatic disconnection when grid supply fails, trip settings for voltage and frequency, and a power factor above 0.90 when output exceeds 10% of rating. |
| Grid codes for large solar and wind | Código de Redes Fotovoltaico and Código de Redes Eólico (2017) | ASEP | Apply to self-consumption plants above 2,500 kW (except metering). |
| Metering | Norma de Medición for regulated customers (Resolution AN 5999-Elec, 2013) | ASEP | Specifies the bidirectional meters used for self-consumers. |
| Battery storage fire safety | NFPA 855 | National Fire Protection Association, required by ASEP Resolution AN 19360-Elec | Required for critical-load battery systems, with Fire Service approval. |
| Installer competence | Technical Board of Engineering and Architecture (JTIA) requirements | JTIA | Protection tests for self-consumption plants must be carried out by a technician meeting JTIA requirements. |
| EV charging | Procedure for operating electric-vehicle charging stations (2025) | ASEP | Details not reviewed. |
Permissions.
| Permission | Required | Level | Detail |
|---|---|---|---|
| Fire Service and municipal engineering approval | Yes | Mixed | The electrical design must be approved before applying to the distributor, and the installed plant inspected and certified before parallel operation. |
| Distributor interconnection agreement | Yes | Mixed | Needed for any self-consumption plant that operates in parallel with the grid; written approval after testing is required before operation. |
| Distributor authorisation for zero-export systems | Yes | Mixed | Customers outside the procedure may self-supply only with the distributor’s authorisation and zero-export or automatic-disconnection devices. |
| Notification to SNE, CND and ASEP | Limited | National | Only for plants above 100 kW, within five working days of signing the agreement. |
For a typical home system, the steps are the design approval by the Fire Service and municipal engineering, the distributor’s written consent and interconnection agreement, inspections, the distributor’s tests and its written approval. Disagreements with the distributor can be referred to ASEP, which can apply the sanctions in Law 6 of 1997.
Support schemes, taxes and incentives.
| Scheme | Status | Type | Detail | Period |
|---|---|---|---|---|
| Net metering for self-consumption | Active | Net metering | Monthly netting with kWh credits; credits left at the end of the year or half-year paid at the distributor’s average contract purchase cost, up to 25% of historical consumption. | Since 2016 (Resolutions AN 10206-Elec and AN 10299-Elec) |
| Tariff Stabilisation Fund (FET) subsidy | Active | Bill subsidy | State-funded credit on bills, largest for low consumption: for EDEMET homes up to 300 kWh it was 30.62–48.68% in September–December 2026. | Current: 1 September – 31 December 2026 |
| Residential time-of-use tariff (BTSH) | Active | Tariff | Lower prices in the off-peak blocks for customers up to 15 kW; EDEMET’s low off-peak price is B/.0.11612/kWh in September–December 2026. | — |
Data and connectivity.
- Fixed broadband
- 18.1 fixed subscriptions per 100 people (2023)Source 4
- 4G coverage
- Not identified from a reliable public source.
- 5G coverage
- Not identified from a reliable public source.
Smart-meter communications are chosen by each distributor. ASEP’s self-consumption rules require larger three-phase self-consumers to have meters that communicate with the distributor’s operations centre through a smart metering system interfaced with SCADA, and plants above 500 kW to be remotely supervised by the distributor and, through it, by the CND.
Grid conditions.
- National peak demand
- 2.17 GW (July 2026)Source 8Highest monthly maximum demand between September 2025 and August 2026 (2,170 MW). The energy-plan diagnosis cites a maximum demand of 2,235 MW against 5,120 MW of capacity.
- Annual electricity demand
- 13.3 TWh (2024)Source 21Ember data via Our World in Data; generation was 13.43 TWh.
- Generation capacity
- 5.107 GW (August 2026)Source 8Firm capacity was 3,051 MW.
- Interconnection
- Not identified from a reliable public source.
- Curtailment
- Not identified from a reliable public source.
Installed capacity is more than double peak demand, but the energy-plan diagnosis notes that firmness depends on plant availability, hydrology and transmission constraints, and that reliability should be treated as a question of flexibility rather than capacity alone. Electricity losses, mostly in distribution and including non-technical losses, are about 19.5%.
Self-consumption capacity in each concession area is limited to 10% of the distributor’s forecast maximum demand or 2% of its annual energy, and the distributors and ASEP must publish the remaining capacity.
Regulatory changes.
| Change | Status | Date | Detail |
|---|---|---|---|
| September–December 2026 tariffs | Current | 1 September 2026 | New regulated tariffs for EDEMET, ENSA and EDECHI; EDEMET’s BTS energy charge for kWh 11–300 rose from B/.0.15693 to B/.0.17624. |
| Battery storage for critical-load customers (AN 19360-Elec) | Current | 2 July 2024 | Allows distributor-owned batteries to improve reliability at state hospitals, police and similar sites. |
| National Energy Plan 2026–2040 | Upcoming | 2026–2027 | In preparation by the SNE, with a diagnosis published and regional consultation forums held in September 2026; policy formulation and publication are still to come. |
Market indicators.
Neutral descriptions of the market, each with the evidence behind it. They do not rank countries.
| Indicator | Level | Basis |
|---|---|---|
| Electricity cost | Medium | Low below €0.15 per kWh, high at €0.30 or more (household price including taxes, converted to euros). |
| Household electricity use | — | Low below 2,500 kWh a year, high at 5,000 kWh or more (average use per household). |
| Renewable share | High | Low below 30%, high at 60% or more (renewable share of electricity). |
| Smart-meter adoption | — | Low below 30%, high at 80% or more (share of meters that are smart). |
| Home solar adoption | Medium | More than 7,000 customers had 196 MW of distributed generation by 2025 (SNE), under a net-metering scheme in place since 2016. |
| Distributed energy market | Medium | A complete interconnection procedure with deadlines and paid surplus exists, but paid surplus is capped at 25% of consumption and total self-consumption per area is limited to 10% of peak demand. |
| Grid flexibility market | Low | Self-consumers are excluded from the wholesale market and no aggregator role exists; only time-of-use tariffs are available. |
| Energy storage adoption | Low | No storage in ASEP capacity statistics; the only storage rule (2024) covers distributor-owned batteries for critical public sites. |
| Renewable growth environment | Medium | Solar capacity reached about 0.97 GW in 2025 (IRENA) and 771 MW of solar plants are in the wholesale market, but the renewable share of generation (68% in 2024) still depends heavily on rainfall. |
Sources.
Public sources used for this profile, with the date each was accessed.
Show all 27 sources
- Population, total: Panama. World Bank, 2025. accessed 9 October 2026.
- Urban population (% of total population): Panama. World Bank, 2025. accessed 9 October 2026.
- Electric power consumption (kWh per capita): Panama. World Bank, 2024. accessed 9 October 2026.
- Fixed broadband subscriptions (per 100 people): Panama. World Bank, 2023. accessed 9 October 2026.
- Censo 2023, Cuadro 1: Viviendas particulares ocupadas y población, por provincia y comarca indígena (Censos 2010 y 2023). Instituto Nacional de Estadística y Censo (INEC), 2023. accessed 9 October 2026.
- Censo 2023, Cuadro 3: Viviendas particulares ocupadas por tenencia de la vivienda. Instituto Nacional de Estadística y Censo (INEC), 2023. accessed 9 October 2026.
- Censo 2023, Cuadro 4: Viviendas particulares ocupadas por tipo de vivienda, según algunas características de la vivienda. Instituto Nacional de Estadística y Censo (INEC), 2023. accessed 9 October 2026.
- Estadística del Mercado Eléctrico Panameño: agosto 2026. ASEP, 2026. accessed 9 October 2026.
- Tarifas de electricidad para clientes regulados, vigentes del 1 de septiembre al 31 de diciembre de 2026. ASEP, 2026. accessed 9 October 2026.
- Tarifas de electricidad para clientes regulados, vigentes del 1 de julio al 31 de agosto de 2026. ASEP, 2026. accessed 9 October 2026.
- Variación por combustible para clientes regulados, segundo semestre 2026. ASEP, 2026. accessed 9 October 2026.
- Tarifas del Sector Eléctrico: año 2023–2026 (tariff notices by period). ASEP, 2026. accessed 9 October 2026.
- Descripción y condiciones de aplicación de las tarifas. ASEP, 2026. accessed 9 October 2026.
- Procedimiento para autoconsumo con fuentes nuevas, renovables y limpias (Resoluciones AN 10206-Elec y AN 10299-Elec de 2016). ASEP, 2016. accessed 9 October 2026.
- Procedimiento para la incorporación de sistemas de almacenamiento con baterías en clientes finales con carga crítica (Resolución AN 19360-Elec). ASEP, 2024. accessed 9 October 2026.
- Reglamentaciones y normas técnicas de electricidad. ASEP, 2026. accessed 9 October 2026.
- Norma de medición aplicable a los clientes regulados (Resolución AN 5999-Elec). ASEP, 2013. accessed 9 October 2026.
- ECB euro reference exchange rate: US dollar (USD), 9 October 2026. European Central Bank, 2026. accessed 9 October 2026.
- Share of electricity production by source: Panama (Ember). Our World in Data, 2024. accessed 9 October 2026.
- Installed solar capacity: Panama (IRENA). Our World in Data, 2025. accessed 9 October 2026.
- Electricity demand: Panama (Ember). Our World in Data, 2024. accessed 9 October 2026.
- Plan Energético Nacional 2026–2040. Secretaría Nacional de Energía, 2026. accessed 9 October 2026.
- Resumen diagnóstico del Plan Energético Nacional 2026–2040. Secretaría Nacional de Energía, 2026. accessed 9 October 2026.
- Tarifas (hogar). Naturgy Panamá, 2026. accessed 9 October 2026.
- Medición de prepago. Naturgy Panamá, 2026. accessed 9 October 2026.
- Conoce tu factura. Naturgy Panamá, 2026. accessed 9 October 2026.
- ETESA: transmisión, compras de energía y Centro Nacional de Despacho. Empresa de Transmisión Eléctrica, S.A., 2026. accessed 9 October 2026.
Questions about energy in Panama.
For September–December 2026 an EDEMET household on the simple tariff pays a B/.3.17 fixed charge for the first 10 kWh and B/.0.17624 per kWh up to 300 kWh, rising to B/.0.23177 for 301–750 kWh and B/.0.25027 above that. ENSA and EDECHI charge slightly more. Households using up to 300 kWh then receive a state subsidy credit (FET), which in this period is about 27–49% at EDEMET and ENSA and larger at EDECHI.
Your local distributor, which you cannot choose: EDEMET or EDECHI (both Naturgy) or ENSA, depending on where you live. ASEP sets their tariffs.
Yes, through your distributor only. Under ASEP’s self-consumption procedure exports are netted against consumption each month and stored as credits; unused credits are paid at the distributor’s average energy purchase cost, up to 25% of your historical consumption.
The customer (account) number given by your distributor, shown on your bill. There is no national meter-point number; each distributor has its own numbering.
About 68% of generation was renewable in 2024, mainly hydropower (53%), with solar and wind around 7% each (Ember). Gas, oil and coal supplied the rest.
Yes. The design must be approved by the Fire Service and municipal engineering, and you must sign an interconnection agreement with your distributor, which tests the system and gives written approval before it can operate.
Yes. Customers up to 15 kW can ask for the BTSH tariff with peak and off-peak blocks; at EDEMET the low off-peak price is B/.0.11612 per kWh against B/.0.39247 at peak (September–December 2026).